SlideShare a Scribd company logo
1 of 1
Download to read offline
Volume IV Issue No. 4


                                                                                           The Global Leader in Managing Construction Risk
                                                       The Saga of Concurrent Delay

  When delays occur on a construction                         completion of design which under                1.     If the effect of Employer delay on
  project it is not uncommon for each party to                the Contract is a Contractor                           the completion date is longer than
  attempt to use concurrent delays in defense                 responsibility and late access to                      that of the Contractor’s, then the
  against the opposing party’s delay damages:                 site which is the Employer’s
                                                                                                                     Contractor would potentially be
  Employers often cite concurrent delays by                   responsibility.
  the Contractor as a reason for awarding an                                                                         entitled to recover damage for a
  extension of time without compensation;                2.   Impacts to more than one critical                      period equivalent to the difference
  whereas, Contractor’s claims usually ignore                 path in which one path is affected                     between the effects of the two
  the concurrent delay from the claimed                                                                              delayed periods.
                                                              by an Employer delay, and the
  delays in order to claim the full prolongation
  costs stemming from the Employer delays                     other being affected by a
                                                              Contractor delay.                               2.     If the effect of the Employer’s and
  and to prevent exposure to liquidated                                                                              Contractor’s delay’s on the
  damages.                                                                                                           completion       date   are     felt
                                                     Evaluation/Identification of Concurrent                         concurrently, the Contractor may
  Providing a clear definition of concurrent         Delays                                                          recover additional costs only if it
  delays and how they affect the Contractor’s        A meaningful evaluation of concurrency and                      was able to separate its incurred
  entitlement to additional costs along with         how it affects the Contractor’s potential                       additional costs from those of the
  guidelines to an independent delay analysis        entitlements requires a totally independent                     Employer.
  methodology may assist parties to settle           and objective delay analysis approach. For
  disputes in relation to concurrent delays.         this, I recommend Time Impact Analysis             Finally, the Employer would be entitled to
                                                     undertaken in short windows of time.               apply liquidated damages if the effect of
  The Definition of Concurrent Delay                                                                    Contractor caused delay on the completion
  Concurrent delays are experienced when             In this instance, Hill has established and         date is longer than that of the Employer’s.
  two or more independent critical delays,           effectively employed on a number of                The period to which the damages are
  one caused by the Employer and one                 assignments, predefined steps which in             applied should be equivalent to the
  caused by the Contractor occur at                  addition to providing total auditability           difference between the effects of the two
  approximate the same time period, each             enhances the objectivity of the results            delays.
  having the ability to delay the Time for           thereby assisting the parties in resolving
  Completion.                                        disputes in relation to concurrent delays. -        - Jad Chouman, Associate Director of
                                                     Following these steps systematically allows
  For delays to be concurrent, the following         the identification of delay events,                 Hill International, Claims Group
  key factors should exist:                          assessment of delay responsibility and
                                                     determination of their impact within the
       1.    They should critically impact the       defined windows of time while taking into
             Time for Completion, and not            consideration any mitigation measures
             simply absorb float;                    taken to reduce the delays. This approach
                                                     mainly depends on the availability adequate
       2.    They should be independent and          programme updates and contemporaneous
             not caused indirectly by the other      project records.
             parties delay; and
                                                     Effect of Concurrency on Entitlement to an
       3.    They should occur approximately                                                                       Hill   International,   with   3,200
                                                     Extension of Time
                                                                                                                   employees in 110 offices worldwide,
             at the same time period and their       Barring any Contractual provision to the
                                                                                                                   provides     program    management,
             impact should be concurrent but         contrary, the Contractor’s concurrent
                                                                                                                   project management, construction
             not necessary identical.                delay(s) should not impact its entitlement to
                                                                                                                   management and construction claims
                                                     an Extension of Time due to the actions of                    and consulting services. Engineering
       Accordingly, there are two possible           the Employer                                                  News - Record magazine recently
       scenarios when considering the
                                                                                                                   ranked Hill as the 11th largest
       impacts of concurrent delays:                  Effect of Concurrency on Entitlement to                      construction management firm in the
       1. Impacts to the same critical path,          Compensation                                                 United States.
           at least one of which is                   As for Contractor’s entitlement for
           attributable to each party. For            compensation in case of concurrent delays,                   For more information on Hill, please
           example, the commencement of               there are two possible scenarios:                            visit our website at www.hillintl.com.
           works is delayed by the late

David Brodie-Stedman                                     David Merritt
                                                                                                         Disclaimer: This article does not constitute advice, legal or
Senior Vice President & Managing Director                Senior Vice President & Managing Director       otherwise,     and     is    provided    only     as   general
Asia, Middle East and Africa                             Middle East and Africa                          commentary. Appropriate professional advice should always
                                                                                                         be obtained before taking or refraining from taking any
Abu Dhabi Office                                         Sultan Business Centre                          action in relation to such information and/or the application
Butti Al Otaiba Bldg., Suite 1601 & 1602                 5th Floor, Suite 501                            of applicable law. This article and the materials contained in
Sh. Khalifa St., P.O. Box: 5201, Abu Dhabi – U.A.E       P.O. Box: 71467, Dubai - U.A.E.                 it are provided on the basis that all liability for any loss or
                                                                                                         damage, whether direct or indirect, arising out of or in
Tel : +971 – 2 – 627 2855                                Tel. : +971 - 4 - 337 2145                      connection with any use or reliance upon this article is
Fax: +971 – 2 – 627 2042                                 Fax : +971 - 4 - 335 6077                       excluded to the fullest extent permitted by law.
E-mail: auh@hillintl.com                                 E-mail : dxb@hillintl.com

More Related Content

Similar to The saga of concurrent delay vol. iv issue no. 4

DELAYS TEST - Copy (2).pptx
DELAYS    TEST - Copy (2).pptxDELAYS    TEST - Copy (2).pptx
DELAYS TEST - Copy (2).pptxAshar Gill
 
Professional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOTProfessional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOTYee Len Wan
 
Importance of Taking Over Certificate (TOC)
Importance of Taking Over Certificate (TOC)Importance of Taking Over Certificate (TOC)
Importance of Taking Over Certificate (TOC)Sadeeq Ullah Khan
 
Literature review on_ extension of time
Literature review on_ extension of timeLiterature review on_ extension of time
Literature review on_ extension of timeJoseph Sangpang
 
PP2 - Seminar Presentation
PP2 - Seminar Presentation PP2 - Seminar Presentation
PP2 - Seminar Presentation Lin Hui
 
Liquidated damages contracts
Liquidated damages   contractsLiquidated damages   contracts
Liquidated damages contractsBhushan Goyal
 
Wind primerapril2011
Wind primerapril2011Wind primerapril2011
Wind primerapril2011Don Threewitt
 
Professional practice 2
Professional practice 2Professional practice 2
Professional practice 2ahmong4
 
المحاضرة 160 بعنوان البرنامج الزمنى فى عقود التشيد
المحاضرة 160 بعنوان البرنامج الزمنى فى عقود التشيدالمحاضرة 160 بعنوان البرنامج الزمنى فى عقود التشيد
المحاضرة 160 بعنوان البرنامج الزمنى فى عقود التشيدEgyptian Engineers Association
 
Covid-19-and-NEC4.pdf
Covid-19-and-NEC4.pdfCovid-19-and-NEC4.pdf
Covid-19-and-NEC4.pdfShingFaatWong
 
IRJET- Delay in Construction its Causes and Mitigation: A Review
IRJET-  	  Delay in Construction its Causes and Mitigation: A ReviewIRJET-  	  Delay in Construction its Causes and Mitigation: A Review
IRJET- Delay in Construction its Causes and Mitigation: A ReviewIRJET Journal
 
Construction claims, disputes and project closure
Construction claims, disputes and project closureConstruction claims, disputes and project closure
Construction claims, disputes and project closuresrinivas2036
 
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...IJMER
 
Episode 28 : Project Management Contract
Episode 28 : Project Management ContractEpisode 28 : Project Management Contract
Episode 28 : Project Management ContractSAJJAD KHUDHUR ABBAS
 
A Fresh Take on Project Forensics
A Fresh Take on Project ForensicsA Fresh Take on Project Forensics
A Fresh Take on Project ForensicsAcumen
 
Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...IRJET Journal
 

Similar to The saga of concurrent delay vol. iv issue no. 4 (20)

DELAYS TEST - Copy (2).pptx
DELAYS    TEST - Copy (2).pptxDELAYS    TEST - Copy (2).pptx
DELAYS TEST - Copy (2).pptx
 
Professional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOTProfessional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOT
 
Importance of Taking Over Certificate (TOC)
Importance of Taking Over Certificate (TOC)Importance of Taking Over Certificate (TOC)
Importance of Taking Over Certificate (TOC)
 
Literature review on_ extension of time
Literature review on_ extension of timeLiterature review on_ extension of time
Literature review on_ extension of time
 
PP2 - Seminar Presentation
PP2 - Seminar Presentation PP2 - Seminar Presentation
PP2 - Seminar Presentation
 
Liquidated damages contracts
Liquidated damages   contractsLiquidated damages   contracts
Liquidated damages contracts
 
Wind primerapril2011
Wind primerapril2011Wind primerapril2011
Wind primerapril2011
 
Professional practice 2
Professional practice 2Professional practice 2
Professional practice 2
 
Liquidated damages
Liquidated damagesLiquidated damages
Liquidated damages
 
المحاضرة 160 بعنوان البرنامج الزمنى فى عقود التشيد
المحاضرة 160 بعنوان البرنامج الزمنى فى عقود التشيدالمحاضرة 160 بعنوان البرنامج الزمنى فى عقود التشيد
المحاضرة 160 بعنوان البرنامج الزمنى فى عقود التشيد
 
Covid-19-and-NEC4.pdf
Covid-19-and-NEC4.pdfCovid-19-and-NEC4.pdf
Covid-19-and-NEC4.pdf
 
IRJET- Delay in Construction its Causes and Mitigation: A Review
IRJET-  	  Delay in Construction its Causes and Mitigation: A ReviewIRJET-  	  Delay in Construction its Causes and Mitigation: A Review
IRJET- Delay in Construction its Causes and Mitigation: A Review
 
Construction claims, disputes and project closure
Construction claims, disputes and project closureConstruction claims, disputes and project closure
Construction claims, disputes and project closure
 
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...
 
Episode 28 : Project Management Contract
Episode 28 : Project Management ContractEpisode 28 : Project Management Contract
Episode 28 : Project Management Contract
 
A Fresh Take on Project Forensics
A Fresh Take on Project ForensicsA Fresh Take on Project Forensics
A Fresh Take on Project Forensics
 
Chapter 1 [compatibility mode]
Chapter 1 [compatibility mode]Chapter 1 [compatibility mode]
Chapter 1 [compatibility mode]
 
Chapter 1 [compatibility mode]
Chapter 1 [compatibility mode]Chapter 1 [compatibility mode]
Chapter 1 [compatibility mode]
 
Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...
 
Newsletter TE&A
Newsletter TE&ANewsletter TE&A
Newsletter TE&A
 

The saga of concurrent delay vol. iv issue no. 4

  • 1. Volume IV Issue No. 4 The Global Leader in Managing Construction Risk The Saga of Concurrent Delay When delays occur on a construction completion of design which under 1. If the effect of Employer delay on project it is not uncommon for each party to the Contract is a Contractor the completion date is longer than attempt to use concurrent delays in defense responsibility and late access to that of the Contractor’s, then the against the opposing party’s delay damages: site which is the Employer’s Contractor would potentially be Employers often cite concurrent delays by responsibility. the Contractor as a reason for awarding an entitled to recover damage for a extension of time without compensation; 2. Impacts to more than one critical period equivalent to the difference whereas, Contractor’s claims usually ignore path in which one path is affected between the effects of the two the concurrent delay from the claimed delayed periods. by an Employer delay, and the delays in order to claim the full prolongation costs stemming from the Employer delays other being affected by a Contractor delay. 2. If the effect of the Employer’s and and to prevent exposure to liquidated Contractor’s delay’s on the damages. completion date are felt Evaluation/Identification of Concurrent concurrently, the Contractor may Providing a clear definition of concurrent Delays recover additional costs only if it delays and how they affect the Contractor’s A meaningful evaluation of concurrency and was able to separate its incurred entitlement to additional costs along with how it affects the Contractor’s potential additional costs from those of the guidelines to an independent delay analysis entitlements requires a totally independent Employer. methodology may assist parties to settle and objective delay analysis approach. For disputes in relation to concurrent delays. this, I recommend Time Impact Analysis Finally, the Employer would be entitled to undertaken in short windows of time. apply liquidated damages if the effect of The Definition of Concurrent Delay Contractor caused delay on the completion Concurrent delays are experienced when In this instance, Hill has established and date is longer than that of the Employer’s. two or more independent critical delays, effectively employed on a number of The period to which the damages are one caused by the Employer and one assignments, predefined steps which in applied should be equivalent to the caused by the Contractor occur at addition to providing total auditability difference between the effects of the two approximate the same time period, each enhances the objectivity of the results delays. having the ability to delay the Time for thereby assisting the parties in resolving Completion. disputes in relation to concurrent delays. - - Jad Chouman, Associate Director of Following these steps systematically allows For delays to be concurrent, the following the identification of delay events, Hill International, Claims Group key factors should exist: assessment of delay responsibility and determination of their impact within the 1. They should critically impact the defined windows of time while taking into Time for Completion, and not consideration any mitigation measures simply absorb float; taken to reduce the delays. This approach mainly depends on the availability adequate 2. They should be independent and programme updates and contemporaneous not caused indirectly by the other project records. parties delay; and Effect of Concurrency on Entitlement to an 3. They should occur approximately Hill International, with 3,200 Extension of Time employees in 110 offices worldwide, at the same time period and their Barring any Contractual provision to the provides program management, impact should be concurrent but contrary, the Contractor’s concurrent project management, construction not necessary identical. delay(s) should not impact its entitlement to management and construction claims an Extension of Time due to the actions of and consulting services. Engineering Accordingly, there are two possible the Employer News - Record magazine recently scenarios when considering the ranked Hill as the 11th largest impacts of concurrent delays: Effect of Concurrency on Entitlement to construction management firm in the 1. Impacts to the same critical path, Compensation United States. at least one of which is As for Contractor’s entitlement for attributable to each party. For compensation in case of concurrent delays, For more information on Hill, please example, the commencement of there are two possible scenarios: visit our website at www.hillintl.com. works is delayed by the late David Brodie-Stedman David Merritt Disclaimer: This article does not constitute advice, legal or Senior Vice President & Managing Director Senior Vice President & Managing Director otherwise, and is provided only as general Asia, Middle East and Africa Middle East and Africa commentary. Appropriate professional advice should always be obtained before taking or refraining from taking any Abu Dhabi Office Sultan Business Centre action in relation to such information and/or the application Butti Al Otaiba Bldg., Suite 1601 & 1602 5th Floor, Suite 501 of applicable law. This article and the materials contained in Sh. Khalifa St., P.O. Box: 5201, Abu Dhabi – U.A.E P.O. Box: 71467, Dubai - U.A.E. it are provided on the basis that all liability for any loss or damage, whether direct or indirect, arising out of or in Tel : +971 – 2 – 627 2855 Tel. : +971 - 4 - 337 2145 connection with any use or reliance upon this article is Fax: +971 – 2 – 627 2042 Fax : +971 - 4 - 335 6077 excluded to the fullest extent permitted by law. E-mail: auh@hillintl.com E-mail : dxb@hillintl.com