US Army Corps of Engineers
BUILDING STRONG®
October 29, 2015
USACE - New York District
Peter Weppler
Chief, Environmental Analysis Branch
Planning Division
Jamaica Bay Activities Update
US Army Corps of Engineers
BUILDING STRONG®
BUILDING STRONG®
Hudson-Raritan Estuary (HRE)
Restoration Feasibility Study
Marsh Island Recommendations
• Currently Preparing Conceptual Designs
o Designs can be utilized for Operations &
Maintenance Alternative Placement
sites (100% Non-Fed for incremental
cost increase)
• Recommendation will be based on Cost
and Constructability
• Draft Feasibility Report/Environmental
Assessment – Summer 2016
• New Construction Authorization pending
approval of Final Report - Winter 2017
• 65% Fed / 35 % Non-Fed Cost-Share
BUILDING STRONG®
 NY/NJ Harbor Deepening Project
► Anchorage Channel
• Tested material (survey estimate being reviewed internally
now)
• Approximately 85% sand with rest fine grained material.
► Maintenance Dredging of Ambrose and Anchorage
Reaches – have not been scheduled as of today
4
Upcoming Beneficial Reuse
Opportunities within Jamaica Bay
BUILDING STRONG®
 East Rockaway Inlet – Material has been
traditionally used for shore protection in
Rockaway
 Rockaway Inlet (Jamaica Bay entrance channel)
► Not scheduled to be dredged in FY16. Ops will initiate
E&D in case there is a need/appropriation/request by
others (with non-federal $$) to dredge and place.
 Regional Dredging Team will be scheduling a
meeting to discuss upcoming opportunities
throughout Harbor
5
Upcoming Beneficial Reuse
Opportunities within Jamaica Bay
BUILDING STRONG®
6
SEC. 2037, WRDA’07 – “Regional
Sediment Management”
 Amends Sec 204 WRDA ’92, and
other…
► $ for Corps participation in State RSM planning
► $ for Corps development of regional plans
► Annual limits:
 $30M annual appropriations limit; up from $15M
 $5M cap for federal share of project
BUILDING STRONG®
7
SEC. 2037, WRDA 2007 –
Implementation Guidance
 Guidance Memo, 8 Apr ‘08
► RSM is presented as planning for Beneficial Use
► Acknowledges that RSM is broader; and that this
“broader system approach” is addressed in guidance
under development (RSM ER/EC)
• BU - just one aspect of RSM in the CW program;
• RSM involves a system-based approach to managing
sediment resources
 through regional strategies that address integrated
sediment needs and opportunities;
 Leverage other authorities and funding to accomplish
comprehensive, integrated regional sediment
management goals
BUILDING STRONG®
8
Corps Participation in RSM
Planning
 Section 204(e) Authority, as per Section 2037 of WRDA
2007, which authorizes up to $5,000,000 per fiscal year
for USACE to cooperate with the State in the preparation
of a comprehensive State or regional sediment
management plans and to encourage the State
participation in the implementation of the plan – State led
 Cooperate with Federal, state, regional and local
agencies to develop RSM plans at Federal expense, for
sediment obtained through construction, operation, or
maintenance of authorized Federal water resources
projects
► Work w/state or other on the scope of the work and the proposed
Federal involvement; based on this, request Sec 204 funds.
BUILDING STRONG®
http://www.nan.usace.army.mil/Home.aspxhttp://www.nan.usace.army.mil/Home.aspx
For More InformationFor More Information
Peter WepplerPeter Weppler
Chief – Environmental Analysis BranchChief – Environmental Analysis Branch
917-790-8634917-790-8634
Peter.m.weppler@usace.army.milPeter.m.weppler@usace.army.mil
Lisa Baron (HRE, Jamaica Bay)Lisa Baron (HRE, Jamaica Bay)
917-790-8306917-790-8306
Lisa.a.Baron@usace.army.milLisa.a.Baron@usace.army.mil
Dan Falt (Rockaway Reformulation)Dan Falt (Rockaway Reformulation)
917-790-8614917-790-8614
Daniel.t.Falt@usace.army.milDaniel.t.Falt@usace.army.mil
BUILDING STRONG®
http://www.nan.usace.army.mil/Home.aspxhttp://www.nan.usace.army.mil/Home.aspx
For More InformationFor More Information
Peter WepplerPeter Weppler
Chief – Environmental Analysis BranchChief – Environmental Analysis Branch
917-790-8634917-790-8634
Peter.m.weppler@usace.army.milPeter.m.weppler@usace.army.mil
Lisa Baron (HRE, Jamaica Bay)Lisa Baron (HRE, Jamaica Bay)
917-790-8306917-790-8306
Lisa.a.Baron@usace.army.milLisa.a.Baron@usace.army.mil
Dan Falt (Rockaway Reformulation)Dan Falt (Rockaway Reformulation)
917-790-8614917-790-8614
Daniel.t.Falt@usace.army.milDaniel.t.Falt@usace.army.mil

Weppler jamaica bay task force 29 oct15_sand

  • 1.
    US Army Corpsof Engineers BUILDING STRONG® October 29, 2015 USACE - New York District Peter Weppler Chief, Environmental Analysis Branch Planning Division Jamaica Bay Activities Update
  • 2.
    US Army Corpsof Engineers BUILDING STRONG®
  • 3.
    BUILDING STRONG® Hudson-Raritan Estuary(HRE) Restoration Feasibility Study Marsh Island Recommendations • Currently Preparing Conceptual Designs o Designs can be utilized for Operations & Maintenance Alternative Placement sites (100% Non-Fed for incremental cost increase) • Recommendation will be based on Cost and Constructability • Draft Feasibility Report/Environmental Assessment – Summer 2016 • New Construction Authorization pending approval of Final Report - Winter 2017 • 65% Fed / 35 % Non-Fed Cost-Share
  • 4.
    BUILDING STRONG®  NY/NJHarbor Deepening Project ► Anchorage Channel • Tested material (survey estimate being reviewed internally now) • Approximately 85% sand with rest fine grained material. ► Maintenance Dredging of Ambrose and Anchorage Reaches – have not been scheduled as of today 4 Upcoming Beneficial Reuse Opportunities within Jamaica Bay
  • 5.
    BUILDING STRONG®  EastRockaway Inlet – Material has been traditionally used for shore protection in Rockaway  Rockaway Inlet (Jamaica Bay entrance channel) ► Not scheduled to be dredged in FY16. Ops will initiate E&D in case there is a need/appropriation/request by others (with non-federal $$) to dredge and place.  Regional Dredging Team will be scheduling a meeting to discuss upcoming opportunities throughout Harbor 5 Upcoming Beneficial Reuse Opportunities within Jamaica Bay
  • 6.
    BUILDING STRONG® 6 SEC. 2037,WRDA’07 – “Regional Sediment Management”  Amends Sec 204 WRDA ’92, and other… ► $ for Corps participation in State RSM planning ► $ for Corps development of regional plans ► Annual limits:  $30M annual appropriations limit; up from $15M  $5M cap for federal share of project
  • 7.
    BUILDING STRONG® 7 SEC. 2037,WRDA 2007 – Implementation Guidance  Guidance Memo, 8 Apr ‘08 ► RSM is presented as planning for Beneficial Use ► Acknowledges that RSM is broader; and that this “broader system approach” is addressed in guidance under development (RSM ER/EC) • BU - just one aspect of RSM in the CW program; • RSM involves a system-based approach to managing sediment resources  through regional strategies that address integrated sediment needs and opportunities;  Leverage other authorities and funding to accomplish comprehensive, integrated regional sediment management goals
  • 8.
    BUILDING STRONG® 8 Corps Participationin RSM Planning  Section 204(e) Authority, as per Section 2037 of WRDA 2007, which authorizes up to $5,000,000 per fiscal year for USACE to cooperate with the State in the preparation of a comprehensive State or regional sediment management plans and to encourage the State participation in the implementation of the plan – State led  Cooperate with Federal, state, regional and local agencies to develop RSM plans at Federal expense, for sediment obtained through construction, operation, or maintenance of authorized Federal water resources projects ► Work w/state or other on the scope of the work and the proposed Federal involvement; based on this, request Sec 204 funds.
  • 9.
    BUILDING STRONG® http://www.nan.usace.army.mil/Home.aspxhttp://www.nan.usace.army.mil/Home.aspx For MoreInformationFor More Information Peter WepplerPeter Weppler Chief – Environmental Analysis BranchChief – Environmental Analysis Branch 917-790-8634917-790-8634 Peter.m.weppler@usace.army.milPeter.m.weppler@usace.army.mil Lisa Baron (HRE, Jamaica Bay)Lisa Baron (HRE, Jamaica Bay) 917-790-8306917-790-8306 Lisa.a.Baron@usace.army.milLisa.a.Baron@usace.army.mil Dan Falt (Rockaway Reformulation)Dan Falt (Rockaway Reformulation) 917-790-8614917-790-8614 Daniel.t.Falt@usace.army.milDaniel.t.Falt@usace.army.mil
  • 10.
    BUILDING STRONG® http://www.nan.usace.army.mil/Home.aspxhttp://www.nan.usace.army.mil/Home.aspx For MoreInformationFor More Information Peter WepplerPeter Weppler Chief – Environmental Analysis BranchChief – Environmental Analysis Branch 917-790-8634917-790-8634 Peter.m.weppler@usace.army.milPeter.m.weppler@usace.army.mil Lisa Baron (HRE, Jamaica Bay)Lisa Baron (HRE, Jamaica Bay) 917-790-8306917-790-8306 Lisa.a.Baron@usace.army.milLisa.a.Baron@usace.army.mil Dan Falt (Rockaway Reformulation)Dan Falt (Rockaway Reformulation) 917-790-8614917-790-8614 Daniel.t.Falt@usace.army.milDaniel.t.Falt@usace.army.mil