1. Weekly Report
Date: from 09/01/16 to 14/01/16 SeniorSite Engineer:Houssam Slika (ID: 1953)
Zone Area: D (Z3B, Z4B) Site Engineer:Md. Shah Faisal (ID: 2747)
Site Supervisor:Talaat Elsherbini (ID: 2607)
Area boundary as highlighted between axes (G-W, 1B-9)
2. COMPLETED WORKS:
A- Fire Alarm System
1. Work done and inspectedfor FAS pointon slab of Z4B, B1 , AREA-5 between
axes
(K, L)- (3, 4). Refer:(IR-PDM-B1-T00025-FAS)
2. Work done and inspectedfor extensionPVCconduitfor FAS points on Z3B, B2,
Area-9 betweenaxes(S-U),(3-5).Refer:(IR-PDM-B2-T00042-FAS)
3. 3. Cleaningand preparation slab couplingfoam for FAS work at stair core case in
Z3B, B2, Area-9 betweenaxis(S-U),(3-5)
4. Cleaningand preparation slab coupling foam for FAS work at Ramp core case in
Z4B, B2, part-5 betweenaxes(1A-4), (N-P).
4. B- Data Network System
1. Workdone andinspectedforDNSpointsonslabofZ4B,B1, AREA-5 betweenaxes
(K, L)-(3, 4). Refer: (IR-PDM-B1-T00026-DNS)
2. Work done and inspectedfor extensionPVCconduitfor DNS points on Z3B, B2,
Area-9 betweenaxes(S-U),(3-5).Refer:(IR-PDM-B2-T00043-DNS)
5. Work in Progress:
1. Marking for ELV work on the ramp slab of Z4B, B2, part-5 betweenaxes(1A-4),
(N-P).
6. Material installed
PVC 25mm Lm(M) PVC 32mm Lm(M)
51m 0 m
Look ahead:
1. 1 FAS pointon Concrete core wall in Z3B, B2, part-9 betweenaxes(R-S),(3-4)
2. 1 FAS pointon Concrete column in Z4B, 01, part-5 betweenaxes(K, 3-4).
3. 1 FAS pointon Concrete Column inZ4B, B1M, part-5 betweenaxes(L-5).
4. 6 FAS pointsand 2 DNS points on 2 concrete column in Z4B, B2, part-5 betweenaxes
(N-Q),(7-9).
5. 1 FAS pointon Concrete column in Z4B, B1, part-5 betweenaxes(G-H),(3-5).
6. ELV work on slab in Z4B, GF/UGF/MGF,part-5betweenaxes(G-P),(4-7).