SlideShare a Scribd company logo
1 of 56
Session 5: Site-specific case
studies
Burgess Farm, Salford
350 homes on a greenfield site was allowed by the
SoS against the inspector's advice. Despite the
permanent loss of an area of open countryside and
the fact that the development would seriously degrade
the character and appearance of the area. SoS
considered that this was outweighed by the
scheme's contribution to reducing the significant
shortfall of some 4,000 homes (2.5 years supply)
against the five year housing land requirement.
DCS Number 100-078-099
Barnet & Chase Farm:
APP/Q5300/A/07/2043798/NWF
• The Inspector stated that:
‘the appropriate test is that the value generated
by the scheme should exceed the value of the
site in its current use. The logic is that, if the
converse were the case, then sites would not
come forward for development’.
Clay Farm, Cambridge - 07/0621/OUT
• Residential development of up to 2,300 new mixed-
tenure dwellings and accompanying provision of
community facilities; sports and recreation facilities and
landscaped open spaces including 49 ha. of public open
space in the green corridor
• Provision for education facilities; and all related
infrastructure including: all roads and associated
infrastructure, alternative locations for Cambridgeshire
guided bus stops, alternative location for CGB
Landscape Ecological Mitigation Area, attenuation ponds
including alternative location for Addenbrookes's Access
Road pond, cycleways, footways and crossings of
Hobson's Brook.
Clay Farm, Cambridge - 07/0621/OUT
The SoS agrees with the Inspector that the appellants’ approach
to assessing viability has the effect of protecting historic land
values as well as insulating the developer against a risk for
which he is already indemnified by profit margins and that
this would be at the expense of affordable housing levels. He
therefore also agrees with the Inspector that the residual land
value (RLV) approach used by the Council is the appropriate
methodology for evaluating the economics of these
developments…he is concerned that there is nowhere else to
accommodate the affordable housing at the levels intended for
these sites in the development plan. The SoS attaches very
substantial weight to this matter and considers that it
outweighs the shortfall in the Council's five year supply of
developable sites.
Bath Road, Bristol:
APP/P0119/A/08/2069226
Bath Road, Bristol:
APP/P0119/A/08/2069226
• McCarthy & Stone – 29 sheltered apartments for the elderly
including associated communal facilities and car parking.
• A main issue at appeal was whether the proposal would make
suitable provision for affordable housing. Policy seeks 33.3%
affordable housing. On-site not suitable therefore parties
agreed that an off-site contribution was acceptable subject to
viability.
• At the Inquiry appellant stated viability of the proposal would
only allow a contribution of £115,000 which would fund only 1
or 2 affordable units, and is well below the target of 33.3%.
The LPA were seeking circa £414k based on previous
successful appeal decisions.
Bath Road, Bristol:
APP/P0119/A/08/2069226
• Both parties conducted appraisals using the old Housing
Corporation model. There were differences between
the parties on BCIS construction costs, finance
costs, contingency, developers profit, build rates
and CfSH. Resulting in different residual values from
LPA and appellant.
• LPA argued that the appellant had inflated costs of the
scheme. LPA used a comparable site from another
appeal. Inspector placed little weight on this approach as
that comparable scheme had not yet come forward.
Further he felt the appellants assumptions were
reasonable and evidenced.
Bath Road, Bristol:
APP/P0119/A/08/2069226
• ‘the difference between the Residual Land Value
(RLV) and the existing site value provides a basis
for ascertaining the viability of contributing towards
affordable housing’.
• “Any reservations that I may have about the
balance of viability arguments are outweighed by
what I consider are clear benefits of the
proposal.” (due to lack of sheltered housing locally).
Beckenham: APP/G5180/A/08/2084559
Beckenham: APP/G5180/A/08/2084559
Beckenham: APP/G5180/A/08/2084559
• Change of use of office to residential and
enlargement to comprise 55 dwellings including key
worker and affordable housing. Elevational
alterations and part seventh/eighth floor extensions,
screened roof terrace
• Main issues – whether the proposed development
meets development plan policies concerning the
provision of affordable housing or a payment in lieu
thereof and, whether there are any other material
planning considerations relevant to the determination
of the case.
Beckenham: APP/G5180/A/08/2084559
• At the Inquiry a SoCG was submitted agreeing the
residual site value with no affordable housing
(£2.773 million), the residual value with affordable
housing (£1.9223 million) and the existing use value
of the site (£2.482 million). These agreed values
determine that without an affordable housing
contribution, the scheme will only yield less than
12% above the existing use value, 8% below the
generally accepted margin necessary to induce
such development to proceed. Self-evidently, with
a 35% AH target, such a scheme must also be, in
the view of the appellant, considered non-viable.
Beckenham: APP/G5180/A/08/2084559
• …when the agreed residual value of the site,
incorporating 35% affordable housing is set against
CUV, the development becomes unviable. Having
carefully weighed the matter, I conclude the
viability report convincingly demonstrates that
the proposals cannot support any affordable
housing; accordingly they are not in
contravention of LBB and LP affordable housing
policy.
Oxford Street, Woodstock:
APP/D3125/A/09/2104658
Oxford Street, Woodstock:
APP/D3125/A/09/2104658
• Multiple appeals due to alterations
• Demolition of Youngs Garage and 6 Hensington Road,
erection of 36 dwellings, health centre and retail unit.
Associated parking, roads and footpaths. Alterations to
6,8 and 10 Oxford Street and minor alterations to Punch
Bowl Cottage.
• Appeals made under section 78 of the Town and Country
Planning Act 1990 against a refusal to grant planning
permission and under section 20 and 74 of the Planning
(Listed Buildings and Conservation Areas) Act 1990
against a refusal to grant listed building consent.
Oxford Street, Woodstock:
APP/D3125/A/09/2104658
• This case focuses on the margin required over and above the
Existing Use Value in order to achieve a change of use of the
land:
• ‘The main parties valuations of the current existing value of
the land are not dissimilar but the Appellant has sought to add
a 10% premium. Though the site is owned by the Appellants it
must be assumed, for valuation purposes, that the land is
being acquired now. It is unreasonable to assume that an
existing owner and user of the land would not require a
premium over the actual value of the land to offset
inconvenience and assist with relocation. The Appellants
addition of the 10% premium is not unreasonable in these
circumstances.’
Oxenholme Road, Kendal, Cumbria
APP/M0933/A/13/2193338
Oxenholme Road
Background and main issues
• Appeal for outline planning permission for the
construction of 148 no. dwellings at land to the west of
Oxenholme Road, Kendal, Cumbria (6.95 hectares at
the edge of the built-up area of Kendal)
• Main issue is if there is less than a five year supply of
developable housing land
• Also the provision of affordable housing; the effect on
highway and transport infrastructure; the suitability of the
site for residential development, in particular the effect on
the Green Gap between Kendal and Oxenholme.
Oxenholme Road
16. …requirement for 35% affordable housing
18. …appellants dispute the viability implications
21. The concept of a ‘competitive return’ is not further
defined by the NPPF, and could be the subject of differing
interpretations by the parties involved in any particular
development. The assessment of a competitive return will
involve an element of judgement. Clearly, however,
excessively ambitious predictions must be tempered by
comparison with industry norms and local circumstances.
Oxenholme Road
22. …it is common ground that a competitive return for the
developer can be taken as a profit of 18-20% of GDV
23. …The issue therefore becomes the achievement of a
competitive return for the land owner.
24. …the Council proposes the margin settled upon by the
consultants who prepared the recent Viability Study in support of
the Local Plan. At an EUV of £50,000/hectare, to reflect higher
value ‘paddock’ use at the urban fringe rather than basic
agricultural value, with a margin of 20% plus £400,000/hectare
the site value would amount to £3,197,000 [£246,873/net
developable acre]
Oxenholme Road
25. However, the RICS guidance note on viability
points out concerns about the potential inaccuracy of
the EUV plus margin method, and does not
recommend it. The Harman report on viability testing of
plans also points out the weakness of this approach
when dealing with agricultural land at the urban edge.
In the present case, the figures adapted from the
LADPD Viability Study are broad brush, and the
precise rationale for the £400,000 margin is not
open to interrogation.
Oxenholme Road
25. …Furthermore, I note that representations made for
the Local Plan on behalf of the Cumbria House Builder
Group in response to the Viability Study are firmly of the
view that the level proposed would not encourage
landowners to bring forward sites for development. The
figure of £246,873 would be well below the £500,000/net
developable acre proposed by the House Builder Group
and favoured by the appellants in this appeal.
Oxenholme Road
26. Therefore, although I note that the EUV plus
margin method has been accepted in other situations,
such as the examination of the London CIL charging
schedule, and may be useful at an area-wide level, in
this case I consider that greater weight must be
given to the residual method of determining the
site value, which has also been followed by the
appellants.
Oxenholme Road
27. … The appellants’ single appraisal seeks to
demonstrate that, at their preferred lower sales values and
the same benchmark land value, the scheme without any
affordable housing would result in a surplus of £335,000the
appellants’ conclusion is that this amount would allow 10%
affordable housing provision, subject to some ‘flex’ by the
parties on their level of return and on the tenure of the
housing.
Oxenholme Road
• The Council and appellant differed on build costs
and sale prices
• Inspector accepted evidence from QS that costs
were reasonable
• The Council claimed the lower market values taken
from their LADPD viability study were cautious ‘worst
case’ approach. However, without enough available
comparables the Inspector sides with the appellant
stating the Council’s values would be uncompetitive,
harm cash flow and could affect buyers’ ability to
access borrowing i.e. he used a reality check!
Oxenholme Road
• On land value the Council defended it’s
£4000,000/net developable acres (backed by the
LADPD viability study) vs. the appellants
£500,000/net developable acre (backed by the
Cumbria House Builder Group)
• Various comparables were used in favour of each
benchmark land value level.
Oxenholme Road
47. The parties refer to an appeal decision for land at
Shinfield, Berkshire, which is quoted in the LADPD
Viability Study. However, little weight can be given to
that decision in the present case, as the nature of the
site was quite different, being partly previously
developed, and the positions taken by the parties on
the proportion of uplift in site value that should be
directed to the provision of affordable housing were at
odds with those now proposed. There is no reason in
the present case to assume that either 100% or 50% of
the uplift in site value is the correct proportion to fund
community benefits.
Oxenholme Road
51. …I am unable to conclude that a higher benchmark
value than £400,000/net developable acre should be
accepted in this appeal. The evidence for the higher figure
proposed by the appellants is not conclusive, being based
largely on one small comparator site of a different quality
and on a relatively broad brush method of checking land
value against GDV. Although contested, the LADPD
Viability Study suggests that not all owners have
expectations in excess of the £400,000 level ...the
expectations of one land owner are not critical in the
determination of a benchmark level, which relates to the
reasonable expectation of a typical owner.
Oxenholme Road
52. …I consider that there are grounds to conclude that a
lower benchmark figure would be reasonable. I conclude
that the need to set a benchmark land value of
£500,000/net developable acre, on which the appellants’
case is based, has not been conclusively demonstrated.
53. The appellants’ viability appraisal shows that with no
affordable housing, the scheme could generate a surplus of
£335,000 at the higher benchmark land value, which the
appellants state could support an affordable housing
provision of 10%. It is clear that a lower land value would
generate a larger surplus, which would thus support a
higher proportion of affordable housing…which would
equate to more than £400,000/net developable acre.
Oxenholme Road
57. …in the absence of clear evidence that the proposal
could not generate a competitive return for both developer
and landowner at the policy approved level of provision, I
conclude that a condition requiring 35% affordable housing
would be reasonable and necessary and would comply with
the guidance of the NPPF and meet the tests of Circular
11/95
95. The acute need for affordable housing is accepted. It
has not been shown that the development requires a
proportion of affordable housing below the policy minimum
of 35% in order to generate a competitive return.
Shinfield
• APP/X0360/A/12/2179141
• Reading University
• Wokingham Council
• 8th January 2013
Site and scheme
• 8.5 ha, 5 km south of Reading
• Was National Institute for Research into
Dairying (closed in 1980s)
• 4.5 ha within development limits – with
buildings etc
• 4 ha beyond development limits – pasture
• To clear site and build 126 new dwellings
within development limits – remainder to be
open space etc
History
• Long history
• 18,766m2 of B1 in 1992
• 2001 identified as being suitable for 80
dwellings by Local Plan inspector
• 2003 part of site developed
• The principle of development was not
contested.
Main Issues
‘The main issues are: (i) whether the proposals
make adequate provision for mitigating any
adverse impact they would have upon local
services and infrastructure; and (ii) whether the
proposed amount of affordable housing would
be appropriate in the context of the viability of
the development, the National Planning Policy
Framework, development plan policy and all
other material planning considerations.’
The problem
The Council wanted…
• £2,028,920 in developer
contributions
• 40% affordable housing
(policy says subject to
viability)
• Higher sales prices
• Lower developers profit
• Different Benchmark land
value / site value
The Developer offered…
• £2,312,569 in developer
contributions
• 2% affordable housing
Developers Profit
The appellants supported their calculations by providing
letters and emails from six national housebuilders who
set out their net profit margin targets for residential
developments. The figures ranged from a minimum of
17% to 28%, with the usual target being in the range 20-
25%. Those that differentiated between market and
affordable housing in their correspondence did not set
different profit margins. Due to the level and nature of
the supporting evidence, I give great weight it. I
conclude that the national housebuilders’ figures are to
be preferred and that a figure of 20% of GDV, which is
at the lower end of the range, is reasonable.
Benchmark land value
There is a significant difference in the figures produced
by the parties. The Council calculated a Benchmark
Land Value of £1,984,000 (reduced to about
£1,865,000 when decontamination costs were agreed);
the appellants calculate it to be £2,325,000. During the
Inquiry reference was made to Current Use Value
(CUV) and Existing Use Value (EUV) but it was agreed
that these definitions are interchangeable in respect of
the calculations used for this site.
The Appellant’s approach
The appellants’ valuation of the site is
£2,325,000 based upon 8 acres of commercial
open storage/ industrial land and buildings at
£250,000 per acre and 13 acres of settlement
fringe at £25,000 per acre. The figure of
£250,000 per acre seems reasonable in the light
of the recent sale value achieved at the smaller
site at Paddock Road (£330,000 per acre).
The Council’s approach
The Council did not use comparators; instead it relied
upon a valuation based upon a substantial office
scheme on the appeal site. This was based upon the
outline planning permission for offices on the site in
2003 that was renewed in 2006 but which has since
lapsed...I am concerned about this approach in that
the Council has failed to demonstrate that there is any
market for such a substantial office development here.
Indeed, the only recently completed (2009) office
development of comparable scale, The Blade in
Reading, is still largely vacant.
Competitive Return
Determining what constitutes a competitive return
inevitably involves making a subjective judgement
based upon the evidence. Two very different
viewpoints were put forward at the Inquiry with the
appellants seeking a land value of £4,750,000 which is
roughly the mid-point between the EUV/CUV and the
RLV with planning permission for housing and no
obligations. This ties in with the 50:50 split between the
community and the landowner sought by the
appellants. The Council considered that a sum of
£1.865m would ensure a competitive return; that is to
say the Council’s calculation of the EUV/CUV.
Competitive Return
Paragraph 173 of the Framework says that the costs of
any requirements should provide competitive returns to
a willing landowner and willing developer to enable the
development to be deliverable. The paragraph heading
is “Ensuring viability and deliverability”; it is clear that
its objective is to ensure that land comes forward for
development.
Competitive Return
I am not convinced that a land value that equates to the
EUV/CUV would provide any incentive to the landowner to
sell the site...such a conclusion would not provide any
incentive to the landowner to carry out any remediation
work. There would be no incentive to sell the land and so
such a low return would fail to achieve the delivery of this
site for housing development. In these circumstances, and
given the fact that in this case only two very different
viewpoints on what constitutes a competitive return have
been put forward, the appellants’ conclusions are to be
preferred. In the scenario preferred by the Council, I do not
consider that the appellants would be a willing vendor.
Viable amount of affordable
The RICS GN says that any planning obligations
imposed on a development will need to be paid out of
the uplift in the value of the land but it cannot use up the
whole of the difference, other than in exceptional
circumstances, as that would remove the likelihood of
land being released for development. That is exactly
what is at issue here in that the Council’s valuation
witness, in cross examination, stated that a landowner
should be content to receive what the land is worth, that
is to say the SV. In his opinion this stands at £1.865m. I
accept that, if this figure was agreed (and it is not), it
would mean that the development would be viable.
Viable amount of affordable
However, it would not result in the land being released
for development. Not only is this SV well below that
calculated by the appellants, there is no incentive to sell.
In short, the appellants would not be willing landowners.
If a site is not willingly delivered, development will not
take place. The appellants, rightly in my opinion, say that
this would not represent a competitive return. They
argue that the uplift in value should be split 50:50
between the landowner and the Council. This would, in
this instance, represent the identified s106 requirements
being paid as well as a contribution of 2% of the
dwellings as affordable housing.
And finally
I conclude on this issue that, allowing the
landowner a competitive return of 50% of the
uplift in value, the calculations in the
development appraisal allowing for 2%
affordable housing are reasonable and
demonstrate that at this level of affordable
housing the development would be viable
(Document 26). The only alterations to these
calculations are the relatively minor…
Case study: South Lakeland
Shinfield Test
• We do not accept that Shinfield is an
authoritative precedent for Plan wide viability
testing
• Under the Shinfield principles the uplift from
granting planning consent is shared 50:50
between the landowner and the local authority.
£1,000,000 viability Threshold
Table 10.3 Residual Value compared to £1,000,000/ha Viability Threshold (£/net ha)
Alternativ
e Land
Value
Viability
Threshol
d
Affordable %
0% 25% 30% 35% 40%
Site 1 Urban Edge 1 Kendal 25,000
1,000,00
0 1,443,027 1,148,255 1,083,908 1,017,109 948,778
Site 2 Urban Edge 2 Kendal 25,000
1,000,00
0 1,455,240 1,130,680 1,059,830 986,281 911,045
Site 3 Office re-development Kendal 400,000
1,000,00
0 732,148 412,529 346,134 272,991 198,171
Site 4 Estate Infill Kendal 50,000
1,000,00
0 1,716,295 1,404,668 1,333,530 1,258,469 1,182,385
Site 5 LSC Infill Arnside 50,000
1,000,00
0 1,089,497 860,561 808,331 754,112 698,649
Site 6 LSC Infill Grange 50,000
1,000,00
0 1,315,092 1,015,954 950,654 882,866 813,524
Site 7 Cleared Urban Ulverston 300,000
1,000,00
0 399,698 153,528 100,147 43,821 -13,273
Site 8 KSC Urban Edge Milnthorpe 25,000
1,000,00
0 1,319,627 1,034,413 971,956 908,733 841,158
Site 9 LSC Edge Allithwaite 50,000
1,000,00
0 1,879,318 1,474,114 1,385,383 1,307,848 1,210,926
Site 10 LSC Edge Endmoor 50,000
1,000,00
0 1,266,331 1,000,000 949,065 889,158 825,151
Site 11 LSC Paddock Penny Bridge 50,000
1,000,00
0 1,648,636 1,320,890 1,245,698 1,169,586 1,088,227
1,000,00
EUV + 20% + £400,000/ha on greenfield
Table 10.4 Residual Value compared to 20% + £400,000/ha Uplift Viability Threshold (£/net ha)
Alternative
Land
Value
Viability
Threshold
Affordable %
0% 25% 30% 35% 40%
Site 1 Urban Edge 1 Kendal 25,000 430,000 1,443,027 1,148,255 1,083,908 1,017,109 948,778
Site 2 Urban Edge 2 Kendal 25,000 430,000 1,455,240 1,130,680 1,059,830 986,281 911,045
Site 3
Office re-
development Kendal 400,000 480,000 732,148 412,529 346,134 272,991 198,171
Site 4 Estate Infill Kendal 50,000 460,000 1,716,295 1,404,668 1,333,530 1,258,469 1,182,385
Site 5 LSC Infill Arnside 50,000 460,000 1,089,497 860,561 808,331 754,112 698,649
Site 6 LSC Infill Grange 50,000 460,000 1,315,092 1,015,954 950,654 882,866 813,524
Site 7 Cleared Urban Ulverston 300,000 360,000 399,698 153,528 100,147 43,821 -13,273
Site 8 KSC Urban Edge Milnthorpe 25,000 430,000 1,319,627 1,034,413 971,956 908,733 841,158
Site 9 LSC Edge Allithwaite 50,000 460,000 1,879,318 1,474,114 1,385,383 1,307,848 1,210,926
Site 10 LSC Edge Endmoor 50,000 460,000 1,266,331 1,000,000 949,065 889,158 825,151
Site 11 LSC Paddock Penny Bridge 50,000 460,000 1,648,636 1,320,890 1,245,698 1,169,586 1,088,227
Site 12 Small Village Lune Valley 50,000 460,000 1,952,203 1,952,203 1,952,203 1,952,203 1,952,203
Site 13 Ex Garage Site Central SLDC 400,000 480,000 457,674 212,560 159,053 103,507 46,688
Site 14 Village Infill Cartmel Peninsula 50,000 460,000 1,522,498 1,203,186 1,130,073 1,056,066 976,954
Site 15 Village Infill Eastern Area 50,000 460,000 552,018 552,018 552,018 552,018 552,018
Site 16 Rural House Rural west 50,000 310,000 75,454 75,454 75,454 75,454 75,454
Castle Green Road Kendal 25,000 430,000 1,098,652 858,474 806,045 751,618 695,942
Quarry Lane Storth 25,000 430,000 1,175,868 866,671 799,175 729,108 663,665
South Ulverston Ulverston 25,000 430,000 852,535 623,926 573,994 522,158 469,132
Ulverston Canal
Head Ulverston 300,000 360,000 928,748 625,484 559,283 495,210 424,244
Developers Profit 20% and 25% GDV
Table 10.5 Residual Value compared to 20% + £400,000/ha Uplift Viability Threshold (£/net ha)
Developers’ return of 20% and 25%
20% GDV 25% GDV
Site 1 Urban Edge 1 Kendal 25,000 430,000 1,017,109 831,087
Site 2 Urban Edge 2 Kendal 25,000 430,000 986,281 772,718
Site 3 Office re-development Kendal 400,000 480,000 272,991 30,763
Site 4 Estate Infill Kendal 50,000 460,000 1,258,469 988,341
Site 5 LSC Infill Arnside 50,000 460,000 754,112 565,668
Site 6 LSC Infill Grange 50,000 460,000 882,866 694,863
Site 7 Cleared Urban Ulverston 300,000 360,000 43,821 -262,517
Site 8 KSC Urban Edge Milnthorpe 25,000 430,000 908,733 712,529
Site 9 LSC Edge Allithwaite 50,000 460,000 1,307,848 1,060,360
Site 10 LSC Edge Endmoor 50,000 460,000 889,158 703,008
Site 11 LSC Paddock Penny Bridge 50,000 460,000 1,169,586 960,717
Site 12 Small Village Lune Valley 50,000 460,000 1,952,203 1,677,952
Site 13 Ex Garage Site Central SLDC 400,000 480,000 103,507 -73,964
Site 14 Village Infill Cartmel Peninsula 50,000 460,000 1,056,066 854,394
Site 15 Village Infill Eastern Area 50,000 460,000 552,018 455,105
Site 16 Rural House Rural west 50,000 310,000 75,454 58,142
Castle Green Road Kendal 25,000 430,000 751,618 615,149
Quarry Lane Storth 25,000 430,000 729,108 538,318
South Ulverston Ulverston 25,000 430,000 522,158 343,462
Ulverston Canal Head Ulverston 300,000 360,000 495,210 259,067
£500,000/ha Viability Threshold
Table 10.6 Residual Value compared to £500,000/ha Viability Threshold (£/net ha)
Alternativ
e Land
Value
Viability
Threshol
d
Affordable %
0% 25% 30% 35% 40%
Site 1 Urban Edge 1 Kendal 25,000 500,000 1,443,027 1,148,255 1,083,908 1,017,109 948,778
Site 2 Urban Edge 2 Kendal 25,000 500,000 1,455,240 1,130,680 1,059,830 986,281 911,045
Site 3
Office re-
development Kendal 400,000 500,000 732,148 412,529 346,134 272,991 198,171
Site 4 Estate Infill Kendal 50,000 500,000 1,716,295 1,404,668 1,333,530 1,258,469 1,182,385
Site 5 LSC Infill Arnside 50,000 500,000 1,089,497 860,561 808,331 754,112 698,649
Site 6 LSC Infill Grange 50,000 500,000 1,315,092 1,015,954 950,654 882,866 813,524
Site 7 Cleared Urban Ulverston 300,000 500,000 399,698 153,528 100,147 43,821 -13,273
Site 8 KSC Urban Edge Milnthorpe 25,000 500,000 1,319,627 1,034,413 971,956 908,733 841,158
Site 9 LSC Edge Allithwaite 50,000 500,000 1,879,318 1,474,114 1,385,383 1,307,848 1,210,926
Site 10 LSC Edge Endmoor 50,000 500,000 1,266,331 1,000,000 949,065 889,158 825,151
Site 11 LSC Paddock Penny Bridge 50,000 500,000 1,648,636 1,320,890 1,245,698 1,169,586 1,088,227
Site 12 Small Village Lune Valley 50,000 500,000 1,952,203 1,952,203 1,952,203 1,952,203 1,952,203
Site 13 Ex Garage Site Central SLDC 400,000 500,000 457,674 212,560 159,053 103,507 46,688
Site 14 Village Infill Cartmel Peninsula 50,000 500,000 1,522,498 1,203,186 1,130,073 1,056,066 976,954
Site 15 Village Infill Eastern Area 50,000 500,000 552,018 552,018 552,018 552,018 552,018
Site 16 Rural House Rural west 50,000 500,000 75,454 75,454 75,454 75,454 75,454
Castle Green Road Kendal 25,000 500,000 1,098,652 858,474 806,045 751,618 695,942
Quarry Lane Storth 25,000 500,000 1,175,868 866,671 799,175 729,108 663,665
South Ulverston Ulverston 25,000 500,000 852,535 623,926 573,994 522,158 469,132
Ulverston Canal
Head Ulverston 300,000 500,000 928,748 625,484 559,283 495,210 424,244
Viability Threshold = 25% of GDV
Table 10.7 Residual Value compared to Viability Threshold of 25% of GDV
GDV % GDV Residual % of GDV
Site 1 Urban Edge 1 Kendal 27,652,629 6,913,157 5,339,823 19%
Site 2 Urban Edge 2 Kendal 34,474,092 8,618,523 5,720,430 17%
Site 3 Office re-development Kendal 1,751,290 437,822 84,627 5%
Site 4 Estate Infill Kendal 1,945,866 486,466 377,541 19%
Site 5 LSC Infill Arnside 4,812,189 1,203,047 754,112 16%
Site 6 LSC Infill Grange 7,144,640 1,786,160 1,324,299 19%
Site 7 Cleared Urban Ulverston 1,786,127 446,532 10,955 1%
Site 8 KSC Urban Edge Milnthorpe 13,091,105 3,272,776 2,271,833 17%
Site 9 LSC Edge Allithwaite 4,578,328 1,144,582 980,886 21%
Site 10 LSC Edge Endmoor 2,273,993 568,498 444,579 20%
Site 11 LSC Paddock Penny Bridge 3,733,644 933,411 818,710 22%
Site 12 Small Village Lune Valley 1,002,000 250,500 292,831 29%
Site 13 Ex Garage Site Central SLDC 827,808 206,952 20,701 3%
Site 14 Village Infill Cartmel Peninsula 1,970,884 492,721 422,426 21%
Site 15 Village Infill Eastern Area 684,750 171,188 165,605 24%
Site 16 Rural House Rural west 390,000 97,500 75,454 19%
Castle Green Road Kendal 11,024,904 2,756,226 2,314,982 21%
Quarry Lane Storth 7,045,698 1,761,425 1,035,333 15%
South Ulverston Ulverston 111,430,801 27,857,700 11,581,459 10%
Ulverston Canal Head Ulverston 12,225,882 3,056,471 955,755 8%
Shinfield Test
Existing Use
Value
Residual - No
affordable, no
developer
contributions
Shinfield
Threshold
Residual -
Base
Modelled
Site 1 Urban Edge 1 Kendal 25,000 1,043,694 534,347 711,976
Site 2 Urban Edge 2 Kendal 25,000 1,049,780 537,390 686,726
Site 3 Office re-development Kendal 400,000 797,456 598,728 272,991
Site 4 Estate Infill Kendal 50,000 1,239,640 644,820 878,002
Site 5 LSC Infill Arnside 50,000 1,038,143 544,071 685,556
Site 6 LSC Infill Grange 50,000 1,020,043 535,022 662,150
Site 7 Cleared Urban Ulverston 300,000 475,187 387,594 43,821
Site 8 KSC Urban Edge Milnthorpe 25,000 898,153 461,576 597,851
Site 9 LSC Edge Allithwaite 50,000 1,445,461 747,731 980,886
Site 10 LSC Edge Endmoor 50,000 936,945 493,472 635,113
Site 11 LSC Paddock Penny Bridge 50,000 1,274,754 662,377 880,333
Site 12 Small Village Lune Valley 50,000 1,494,704 772,352 1,464,153
Site 13 Ex Garage Site Central SLDC 400,000 496,992 448,496 103,507
Site 14 Village Infill Cartmel Peninsular 50,000 780,162 415,081 528,033
Site 15 Village Infill Eastern Area 50,000 567,592 308,796 552,018
Site 16 Rural House Rural west 50,000 77,027 63,513 75,454
Full Policy + Developer Contributions
Table 10.9 Impact of different Developer Contributions
Alternative
Use Value
Viability
Threshold
Developer Contributions. £/ unit (market and affordable)
£/ha £/ha £1,500 £2,500 £5,000 £7,500 £10,000
Site 1 Urban Edge 1 Kendal 25,000 430,000 1,017,109 985,133 905,194 825,255 745,315
Site 2 Urban Edge 2 Kendal 25,000 430,000 986,281 951,307 863,874 776,440 689,006
Site 3
Office re-
development
Kendal 400,000 480,000
272,991
229,023 119,103 9,184 -100,736
Site 4 Estate Infill Kendal 50,000 460,000 1,258,469 1,217,735 1,115,898 1,014,061 912,225
Site 5 LSC Infill Arnside 50,000 460,000 754,112 718,807 630,544 542,282 458,364
Site 6 LSC Infill Grange 50,000 460,000 882,866 852,889 777,946 703,003 634,013
Site 7 Cleared Urban Ulverston 300,000 360,000 43,821 -6,505 -132,321 -258,137 -385,862
Site 8 KSC Urban Edge Milnthorpe 25,000 430,000 908,733 878,356 802,414 726,471 650,529
Site 9 LSC Edge Allithwaite 50,000 460,000 1,307,848 1,275,569 1,194,872 1,114,175 1,033,478
Site 10 LSC Edge Endmoor 50,000 460,000 889,158 858,607 782,230 705,852 629,475
Site 11 LSC Paddock Penny Bridge 50,000 460,000 1,169,586 1,139,324 1,063,671 988,017 912,364
Site 12 Small Village Lune Valley 50,000 460,000 1,952,203 1,925,047 1,857,156 1,789,265 1,721,374
Site 13 Ex Garage Site Central SLDC 400,000 480,000 103,507 77,296 11,767 -53,763 -119,292
Site 14 Village Infill Cartmel Peninsula 50,000 460,000 1,056,066 1,030,607 966,959 903,311 839,663
Site 15 Village Infill Eastern Area 50,000 460,000 552,018 541,636 515,680 489,724 463,768
Site 16 Rural House Rural west 50,000 310,000 75,454 74,406 71,785 69,163 66,542
Contact us
Simon Drummond-Hay
Email simon@drummond-hay.co.uk
Phone 015242 76205 / 07989 975 977
David Carlisle
Email david.a.carlisle@aecom.com
Phone 020 7821 4194 / 07827353558

More Related Content

What's hot

East Open House - East At-Grade (Pharmacy - Ionview Stops) to Kennedy Station...
East Open House - East At-Grade (Pharmacy - Ionview Stops) to Kennedy Station...East Open House - East At-Grade (Pharmacy - Ionview Stops) to Kennedy Station...
East Open House - East At-Grade (Pharmacy - Ionview Stops) to Kennedy Station...Crosstown TO
 
RACER_casestudy_buickcity_0115
RACER_casestudy_buickcity_0115RACER_casestudy_buickcity_0115
RACER_casestudy_buickcity_0115Bernadette Grafton
 
MAPC sPARKing New Ideas Parking Symposium: Presentation by Meghan Jop
MAPC sPARKing New Ideas Parking Symposium: Presentation by Meghan JopMAPC sPARKing New Ideas Parking Symposium: Presentation by Meghan Jop
MAPC sPARKing New Ideas Parking Symposium: Presentation by Meghan JopMetropolitan Area Planning Council
 
NJ Future Forum 2012 Dealing With Reality Antonicello
NJ Future Forum 2012 Dealing With Reality AntonicelloNJ Future Forum 2012 Dealing With Reality Antonicello
NJ Future Forum 2012 Dealing With Reality AntonicelloNew Jersey Future
 
30th Street Industrial Corridor
30th Street Industrial Corridor30th Street Industrial Corridor
30th Street Industrial Corridorhebham
 
Brbc video bpt mktg cmpgn ec dev june 2010
Brbc video bpt mktg cmpgn ec dev june 2010Brbc video bpt mktg cmpgn ec dev june 2010
Brbc video bpt mktg cmpgn ec dev june 2010GMSolis
 
Public Presentation V: Draft Master Plan
Public Presentation V: Draft Master PlanPublic Presentation V: Draft Master Plan
Public Presentation V: Draft Master Planawweiss
 
Travis Armbrister Thesis project (2016 Department of Architecture alumni)
Travis Armbrister Thesis project (2016 Department of Architecture alumni)Travis Armbrister Thesis project (2016 Department of Architecture alumni)
Travis Armbrister Thesis project (2016 Department of Architecture alumni)Kwesi Daniels
 
Central- West Open House - April 2018
Central- West Open House - April 2018Central- West Open House - April 2018
Central- West Open House - April 2018Crosstown TO
 
El Paso City Council 09.09.14 Agenda Item 14.1: TxDOT Billboard Amendment
El Paso City Council 09.09.14 Agenda Item 14.1: TxDOT Billboard AmendmentEl Paso City Council 09.09.14 Agenda Item 14.1: TxDOT Billboard Amendment
El Paso City Council 09.09.14 Agenda Item 14.1: TxDOT Billboard Amendmentepdevelopment
 
Nethermayne Site Planning Application
Nethermayne Site Planning ApplicationNethermayne Site Planning Application
Nethermayne Site Planning Applicationheppellf
 
2015 - Oakridge Transit Centre Policy Statement
2015 - Oakridge Transit Centre Policy Statement2015 - Oakridge Transit Centre Policy Statement
2015 - Oakridge Transit Centre Policy StatementBen Johnson
 
Mosman Parks & Bushland Association objection to Sydney Harbour Trust privati...
Mosman Parks & Bushland Association objection to Sydney Harbour Trust privati...Mosman Parks & Bushland Association objection to Sydney Harbour Trust privati...
Mosman Parks & Bushland Association objection to Sydney Harbour Trust privati...savemiddlehead
 
Qadri motion re: Bradley-Craig barn relocation
Qadri motion re: Bradley-Craig barn relocationQadri motion re: Bradley-Craig barn relocation
Qadri motion re: Bradley-Craig barn relocationStittsvilleCentral.ca
 
Cheshire RESI: Sebastian Tibenham, executive director + Neil Culkin, senior ...
Cheshire RESI: Sebastian Tibenham, executive director + Neil Culkin, senior  ...Cheshire RESI: Sebastian Tibenham, executive director + Neil Culkin, senior  ...
Cheshire RESI: Sebastian Tibenham, executive director + Neil Culkin, senior ...Place North West
 
Township of Langley - Regional Growth Strategy Presentation
Township of Langley - Regional Growth Strategy PresentationTownship of Langley - Regional Growth Strategy Presentation
Township of Langley - Regional Growth Strategy Presentationjgabateman
 
120420 Aph Cv
120420 Aph Cv120420 Aph Cv
120420 Aph Cveboroil
 

What's hot (20)

East Open House - East At-Grade (Pharmacy - Ionview Stops) to Kennedy Station...
East Open House - East At-Grade (Pharmacy - Ionview Stops) to Kennedy Station...East Open House - East At-Grade (Pharmacy - Ionview Stops) to Kennedy Station...
East Open House - East At-Grade (Pharmacy - Ionview Stops) to Kennedy Station...
 
RACER_casestudy_buickcity_0115
RACER_casestudy_buickcity_0115RACER_casestudy_buickcity_0115
RACER_casestudy_buickcity_0115
 
MAPC sPARKing New Ideas Parking Symposium: Presentation by Meghan Jop
MAPC sPARKing New Ideas Parking Symposium: Presentation by Meghan JopMAPC sPARKing New Ideas Parking Symposium: Presentation by Meghan Jop
MAPC sPARKing New Ideas Parking Symposium: Presentation by Meghan Jop
 
NJ Future Forum 2012 Dealing With Reality Antonicello
NJ Future Forum 2012 Dealing With Reality AntonicelloNJ Future Forum 2012 Dealing With Reality Antonicello
NJ Future Forum 2012 Dealing With Reality Antonicello
 
30th Street Industrial Corridor
30th Street Industrial Corridor30th Street Industrial Corridor
30th Street Industrial Corridor
 
Brbc video bpt mktg cmpgn ec dev june 2010
Brbc video bpt mktg cmpgn ec dev june 2010Brbc video bpt mktg cmpgn ec dev june 2010
Brbc video bpt mktg cmpgn ec dev june 2010
 
Chimney Hill Applicant Presentation
Chimney Hill Applicant PresentationChimney Hill Applicant Presentation
Chimney Hill Applicant Presentation
 
Public Presentation V: Draft Master Plan
Public Presentation V: Draft Master PlanPublic Presentation V: Draft Master Plan
Public Presentation V: Draft Master Plan
 
Travis Armbrister Thesis project (2016 Department of Architecture alumni)
Travis Armbrister Thesis project (2016 Department of Architecture alumni)Travis Armbrister Thesis project (2016 Department of Architecture alumni)
Travis Armbrister Thesis project (2016 Department of Architecture alumni)
 
Central- West Open House - April 2018
Central- West Open House - April 2018Central- West Open House - April 2018
Central- West Open House - April 2018
 
El Paso City Council 09.09.14 Agenda Item 14.1: TxDOT Billboard Amendment
El Paso City Council 09.09.14 Agenda Item 14.1: TxDOT Billboard AmendmentEl Paso City Council 09.09.14 Agenda Item 14.1: TxDOT Billboard Amendment
El Paso City Council 09.09.14 Agenda Item 14.1: TxDOT Billboard Amendment
 
Chaper 40 R Presentation
Chaper 40 R PresentationChaper 40 R Presentation
Chaper 40 R Presentation
 
Nethermayne Site Planning Application
Nethermayne Site Planning ApplicationNethermayne Site Planning Application
Nethermayne Site Planning Application
 
2015 - Oakridge Transit Centre Policy Statement
2015 - Oakridge Transit Centre Policy Statement2015 - Oakridge Transit Centre Policy Statement
2015 - Oakridge Transit Centre Policy Statement
 
Mosman Parks & Bushland Association objection to Sydney Harbour Trust privati...
Mosman Parks & Bushland Association objection to Sydney Harbour Trust privati...Mosman Parks & Bushland Association objection to Sydney Harbour Trust privati...
Mosman Parks & Bushland Association objection to Sydney Harbour Trust privati...
 
Qadri motion re: Bradley-Craig barn relocation
Qadri motion re: Bradley-Craig barn relocationQadri motion re: Bradley-Craig barn relocation
Qadri motion re: Bradley-Craig barn relocation
 
Cheshire RESI: Sebastian Tibenham, executive director + Neil Culkin, senior ...
Cheshire RESI: Sebastian Tibenham, executive director + Neil Culkin, senior  ...Cheshire RESI: Sebastian Tibenham, executive director + Neil Culkin, senior  ...
Cheshire RESI: Sebastian Tibenham, executive director + Neil Culkin, senior ...
 
Township of Langley - Regional Growth Strategy Presentation
Township of Langley - Regional Growth Strategy PresentationTownship of Langley - Regional Growth Strategy Presentation
Township of Langley - Regional Growth Strategy Presentation
 
120420 Aph Cv
120420 Aph Cv120420 Aph Cv
120420 Aph Cv
 
City Hall Site Selection
City Hall Site SelectionCity Hall Site Selection
City Hall Site Selection
 

Viewers also liked

Cost of Ownership for Hadoop Implementation - Hadoop Summit 2014
Cost of Ownership for Hadoop Implementation - Hadoop Summit 2014Cost of Ownership for Hadoop Implementation - Hadoop Summit 2014
Cost of Ownership for Hadoop Implementation - Hadoop Summit 2014aziksa
 
Supportin Farm Viability through the Agricultural Systems Approach - Municipa...
Supportin Farm Viability through the Agricultural Systems Approach - Municipa...Supportin Farm Viability through the Agricultural Systems Approach - Municipa...
Supportin Farm Viability through the Agricultural Systems Approach - Municipa...Carolyn Puterbough
 
Pas viability conference york rebecca housam 7th july 2015
Pas viability conference york rebecca housam 7th july 2015Pas viability conference york rebecca housam 7th july 2015
Pas viability conference york rebecca housam 7th july 2015PAS_Team
 
Lect 7 pavement materials
Lect 7 pavement materialsLect 7 pavement materials
Lect 7 pavement materialsM Firdaus
 
S106 ATLAS
S106 ATLASS106 ATLAS
S106 ATLASPAS_Team
 

Viewers also liked (6)

Cost of Ownership for Hadoop Implementation - Hadoop Summit 2014
Cost of Ownership for Hadoop Implementation - Hadoop Summit 2014Cost of Ownership for Hadoop Implementation - Hadoop Summit 2014
Cost of Ownership for Hadoop Implementation - Hadoop Summit 2014
 
Supportin Farm Viability through the Agricultural Systems Approach - Municipa...
Supportin Farm Viability through the Agricultural Systems Approach - Municipa...Supportin Farm Viability through the Agricultural Systems Approach - Municipa...
Supportin Farm Viability through the Agricultural Systems Approach - Municipa...
 
Pas viability conference york rebecca housam 7th july 2015
Pas viability conference york rebecca housam 7th july 2015Pas viability conference york rebecca housam 7th july 2015
Pas viability conference york rebecca housam 7th july 2015
 
Lect 7 pavement materials
Lect 7 pavement materialsLect 7 pavement materials
Lect 7 pavement materials
 
S106 ATLAS
S106 ATLASS106 ATLAS
S106 ATLAS
 
Build Features, Not Apps
Build Features, Not AppsBuild Features, Not Apps
Build Features, Not Apps
 

Similar to Viability Session 5: Site-specific case studies

Planning Review 2009
Planning Review 2009Planning Review 2009
Planning Review 2009Graham Gover
 
Griffith Avenue SHD ncac presentation 21 01-2019
Griffith Avenue SHD ncac presentation 21 01-2019Griffith Avenue SHD ncac presentation 21 01-2019
Griffith Avenue SHD ncac presentation 21 01-2019Naoise
 
Letter to council 31 may 2011
Letter to council 31 may 2011Letter to council 31 may 2011
Letter to council 31 may 2011Natalie Foo
 
Planning and Environmental Law Update
Planning and Environmental Law UpdatePlanning and Environmental Law Update
Planning and Environmental Law Update39 Essex Chambers
 
S106 viability york july 2015
S106 viability york july 2015S106 viability york july 2015
S106 viability york july 2015PAS_Team
 
Jim Cliffe - Viability
Jim Cliffe - Viability Jim Cliffe - Viability
Jim Cliffe - Viability PAS_Team
 
2014 planning case law update 180214 [2]
2014 planning case law update 180214 [2]2014 planning case law update 180214 [2]
2014 planning case law update 180214 [2]JRidley12
 
Understanding viability
Understanding viabilityUnderstanding viability
Understanding viabilityPAS_Team
 
Strategic Estate Planning - case studies
Strategic Estate Planning - case studiesStrategic Estate Planning - case studies
Strategic Estate Planning - case studiesAmbercycle Consulting
 
39578899 1
39578899 139578899 1
39578899 1PAS_Team
 
13351_sitematch_zcard
13351_sitematch_zcard13351_sitematch_zcard
13351_sitematch_zcardSamuel Blake
 
Public matters newsletter, July 2014
Public matters newsletter, July 2014Public matters newsletter, July 2014
Public matters newsletter, July 2014Browne Jacobson LLP
 
Planning and Environmental Law Update - Leeds
Planning and Environmental Law Update - LeedsPlanning and Environmental Law Update - Leeds
Planning and Environmental Law Update - Leeds39 Essex Chambers
 
Andrew Parkinson, Landmark Chambers - Section 106 Case Law Update
Andrew Parkinson, Landmark Chambers - Section 106 Case Law UpdateAndrew Parkinson, Landmark Chambers - Section 106 Case Law Update
Andrew Parkinson, Landmark Chambers - Section 106 Case Law UpdatePAS_Team
 
Planning & Environment Law Update
Planning & Environment Law UpdatePlanning & Environment Law Update
Planning & Environment Law Update39 Essex Chambers
 
Compulsory Purchase Update - Ludlow, 5 February 2015
Compulsory Purchase Update - Ludlow, 5 February 2015Compulsory Purchase Update - Ludlow, 5 February 2015
Compulsory Purchase Update - Ludlow, 5 February 2015Charles Cowap
 

Similar to Viability Session 5: Site-specific case studies (20)

Planning Review 2009
Planning Review 2009Planning Review 2009
Planning Review 2009
 
Griffith Avenue SHD ncac presentation 21 01-2019
Griffith Avenue SHD ncac presentation 21 01-2019Griffith Avenue SHD ncac presentation 21 01-2019
Griffith Avenue SHD ncac presentation 21 01-2019
 
Letter to council 31 may 2011
Letter to council 31 may 2011Letter to council 31 may 2011
Letter to council 31 may 2011
 
Planning and Environmental Law Update
Planning and Environmental Law UpdatePlanning and Environmental Law Update
Planning and Environmental Law Update
 
S106 viability york july 2015
S106 viability york july 2015S106 viability york july 2015
S106 viability york july 2015
 
Jim Cliffe - Viability
Jim Cliffe - Viability Jim Cliffe - Viability
Jim Cliffe - Viability
 
2014 planning case law update 180214 [2]
2014 planning case law update 180214 [2]2014 planning case law update 180214 [2]
2014 planning case law update 180214 [2]
 
Understanding viability
Understanding viabilityUnderstanding viability
Understanding viability
 
Synopsis_Solar Farms 25-04-16
Synopsis_Solar Farms 25-04-16Synopsis_Solar Farms 25-04-16
Synopsis_Solar Farms 25-04-16
 
Community Access Project re Wayne Apartments Project May 2012
Community Access Project re Wayne Apartments Project May 2012Community Access Project re Wayne Apartments Project May 2012
Community Access Project re Wayne Apartments Project May 2012
 
Strategic Estate Planning - case studies
Strategic Estate Planning - case studiesStrategic Estate Planning - case studies
Strategic Estate Planning - case studies
 
Winchester final slides
Winchester final slidesWinchester final slides
Winchester final slides
 
Gaap info
Gaap infoGaap info
Gaap info
 
39578899 1
39578899 139578899 1
39578899 1
 
13351_sitematch_zcard
13351_sitematch_zcard13351_sitematch_zcard
13351_sitematch_zcard
 
Public matters newsletter, July 2014
Public matters newsletter, July 2014Public matters newsletter, July 2014
Public matters newsletter, July 2014
 
Planning and Environmental Law Update - Leeds
Planning and Environmental Law Update - LeedsPlanning and Environmental Law Update - Leeds
Planning and Environmental Law Update - Leeds
 
Andrew Parkinson, Landmark Chambers - Section 106 Case Law Update
Andrew Parkinson, Landmark Chambers - Section 106 Case Law UpdateAndrew Parkinson, Landmark Chambers - Section 106 Case Law Update
Andrew Parkinson, Landmark Chambers - Section 106 Case Law Update
 
Planning & Environment Law Update
Planning & Environment Law UpdatePlanning & Environment Law Update
Planning & Environment Law Update
 
Compulsory Purchase Update - Ludlow, 5 February 2015
Compulsory Purchase Update - Ludlow, 5 February 2015Compulsory Purchase Update - Ludlow, 5 February 2015
Compulsory Purchase Update - Ludlow, 5 February 2015
 

More from PAS_Team

231121 SP slides - PAS workshop November 2023.pdf
231121 SP slides - PAS workshop November 2023.pdf231121 SP slides - PAS workshop November 2023.pdf
231121 SP slides - PAS workshop November 2023.pdfPAS_Team
 
So you want to apply for the Planning Skills Delivery Fund PAS Events August ...
So you want to apply for the Planning Skills Delivery Fund PAS Events August ...So you want to apply for the Planning Skills Delivery Fund PAS Events August ...
So you want to apply for the Planning Skills Delivery Fund PAS Events August ...PAS_Team
 
PAS BNG in Local Plans slides June 2023
PAS BNG in Local Plans slides June 2023PAS BNG in Local Plans slides June 2023
PAS BNG in Local Plans slides June 2023PAS_Team
 
Guildford BC BNG Policy June 2023.pdf
Guildford BC BNG Policy June 2023.pdfGuildford BC BNG Policy June 2023.pdf
Guildford BC BNG Policy June 2023.pdfPAS_Team
 
BNG at Salford City Council_June 2023.pdf
BNG at Salford City Council_June 2023.pdfBNG at Salford City Council_June 2023.pdf
BNG at Salford City Council_June 2023.pdfPAS_Team
 
PAS LNRS and role of Supporting Authorities_23_05_23_PAS slides.pptx
PAS LNRS and role of Supporting Authorities_23_05_23_PAS slides.pptxPAS LNRS and role of Supporting Authorities_23_05_23_PAS slides.pptx
PAS LNRS and role of Supporting Authorities_23_05_23_PAS slides.pptxPAS_Team
 
Leeds Beckett Lecture Career Advice.pptx
Leeds Beckett Lecture Career Advice.pptxLeeds Beckett Lecture Career Advice.pptx
Leeds Beckett Lecture Career Advice.pptxPAS_Team
 
Infrastructure Levy Technical Consultation (Workshop 3 Delivering Affordable ...
Infrastructure Levy Technical Consultation (Workshop 3 Delivering Affordable ...Infrastructure Levy Technical Consultation (Workshop 3 Delivering Affordable ...
Infrastructure Levy Technical Consultation (Workshop 3 Delivering Affordable ...PAS_Team
 
Infrastructure Levy Technical Consultation (Workshop 2 Spending the levy and ...
Infrastructure Levy Technical Consultation (Workshop 2 Spending the levy and ...Infrastructure Levy Technical Consultation (Workshop 2 Spending the levy and ...
Infrastructure Levy Technical Consultation (Workshop 2 Spending the levy and ...PAS_Team
 
Infrastructure Levy Technical Consultation (Workshop 1 Setting rates and char...
Infrastructure Levy Technical Consultation (Workshop 1 Setting rates and char...Infrastructure Levy Technical Consultation (Workshop 1 Setting rates and char...
Infrastructure Levy Technical Consultation (Workshop 1 Setting rates and char...PAS_Team
 
PAS Natural England Biodiversity Net Gain update 18_04_23
PAS Natural England Biodiversity Net Gain update 18_04_23PAS Natural England Biodiversity Net Gain update 18_04_23
PAS Natural England Biodiversity Net Gain update 18_04_23PAS_Team
 
EOR Webinar PAS presentation slidesFINAL.pptx
EOR Webinar PAS presentation slidesFINAL.pptxEOR Webinar PAS presentation slidesFINAL.pptx
EOR Webinar PAS presentation slidesFINAL.pptxPAS_Team
 
230329 IL Technical Consultation - launch event.pptx
230329 IL Technical Consultation - launch event.pptx230329 IL Technical Consultation - launch event.pptx
230329 IL Technical Consultation - launch event.pptxPAS_Team
 
PAS Pre-App March 2023.pdf
PAS Pre-App March 2023.pdfPAS Pre-App March 2023.pdf
PAS Pre-App March 2023.pdfPAS_Team
 
CBC Monitoring Review.pptx
CBC Monitoring  Review.pptxCBC Monitoring  Review.pptx
CBC Monitoring Review.pptxPAS_Team
 
PAS Salford Pre App Journey March 2023 JC.pptx
PAS Salford Pre App Journey March 2023 JC.pptxPAS Salford Pre App Journey March 2023 JC.pptx
PAS Salford Pre App Journey March 2023 JC.pptxPAS_Team
 
PAS BNG and Nature Recovery Autumn 2022 Events Evaluation.pdf
PAS BNG and Nature Recovery Autumn 2022 Events Evaluation.pdfPAS BNG and Nature Recovery Autumn 2022 Events Evaluation.pdf
PAS BNG and Nature Recovery Autumn 2022 Events Evaluation.pdfPAS_Team
 
PAS NERC guidance events Nov 22 web.pptx
PAS NERC guidance events Nov 22 web.pptxPAS NERC guidance events Nov 22 web.pptx
PAS NERC guidance events Nov 22 web.pptxPAS_Team
 
PAS Nature Recovery for LAs 8 Dec Post Event.pptx
PAS Nature Recovery for LAs 8 Dec Post Event.pptxPAS Nature Recovery for LAs 8 Dec Post Event.pptx
PAS Nature Recovery for LAs 8 Dec Post Event.pptxPAS_Team
 
PAS BNG and NR policy and strategy
PAS BNG and NR policy and strategy PAS BNG and NR policy and strategy
PAS BNG and NR policy and strategy PAS_Team
 

More from PAS_Team (20)

231121 SP slides - PAS workshop November 2023.pdf
231121 SP slides - PAS workshop November 2023.pdf231121 SP slides - PAS workshop November 2023.pdf
231121 SP slides - PAS workshop November 2023.pdf
 
So you want to apply for the Planning Skills Delivery Fund PAS Events August ...
So you want to apply for the Planning Skills Delivery Fund PAS Events August ...So you want to apply for the Planning Skills Delivery Fund PAS Events August ...
So you want to apply for the Planning Skills Delivery Fund PAS Events August ...
 
PAS BNG in Local Plans slides June 2023
PAS BNG in Local Plans slides June 2023PAS BNG in Local Plans slides June 2023
PAS BNG in Local Plans slides June 2023
 
Guildford BC BNG Policy June 2023.pdf
Guildford BC BNG Policy June 2023.pdfGuildford BC BNG Policy June 2023.pdf
Guildford BC BNG Policy June 2023.pdf
 
BNG at Salford City Council_June 2023.pdf
BNG at Salford City Council_June 2023.pdfBNG at Salford City Council_June 2023.pdf
BNG at Salford City Council_June 2023.pdf
 
PAS LNRS and role of Supporting Authorities_23_05_23_PAS slides.pptx
PAS LNRS and role of Supporting Authorities_23_05_23_PAS slides.pptxPAS LNRS and role of Supporting Authorities_23_05_23_PAS slides.pptx
PAS LNRS and role of Supporting Authorities_23_05_23_PAS slides.pptx
 
Leeds Beckett Lecture Career Advice.pptx
Leeds Beckett Lecture Career Advice.pptxLeeds Beckett Lecture Career Advice.pptx
Leeds Beckett Lecture Career Advice.pptx
 
Infrastructure Levy Technical Consultation (Workshop 3 Delivering Affordable ...
Infrastructure Levy Technical Consultation (Workshop 3 Delivering Affordable ...Infrastructure Levy Technical Consultation (Workshop 3 Delivering Affordable ...
Infrastructure Levy Technical Consultation (Workshop 3 Delivering Affordable ...
 
Infrastructure Levy Technical Consultation (Workshop 2 Spending the levy and ...
Infrastructure Levy Technical Consultation (Workshop 2 Spending the levy and ...Infrastructure Levy Technical Consultation (Workshop 2 Spending the levy and ...
Infrastructure Levy Technical Consultation (Workshop 2 Spending the levy and ...
 
Infrastructure Levy Technical Consultation (Workshop 1 Setting rates and char...
Infrastructure Levy Technical Consultation (Workshop 1 Setting rates and char...Infrastructure Levy Technical Consultation (Workshop 1 Setting rates and char...
Infrastructure Levy Technical Consultation (Workshop 1 Setting rates and char...
 
PAS Natural England Biodiversity Net Gain update 18_04_23
PAS Natural England Biodiversity Net Gain update 18_04_23PAS Natural England Biodiversity Net Gain update 18_04_23
PAS Natural England Biodiversity Net Gain update 18_04_23
 
EOR Webinar PAS presentation slidesFINAL.pptx
EOR Webinar PAS presentation slidesFINAL.pptxEOR Webinar PAS presentation slidesFINAL.pptx
EOR Webinar PAS presentation slidesFINAL.pptx
 
230329 IL Technical Consultation - launch event.pptx
230329 IL Technical Consultation - launch event.pptx230329 IL Technical Consultation - launch event.pptx
230329 IL Technical Consultation - launch event.pptx
 
PAS Pre-App March 2023.pdf
PAS Pre-App March 2023.pdfPAS Pre-App March 2023.pdf
PAS Pre-App March 2023.pdf
 
CBC Monitoring Review.pptx
CBC Monitoring  Review.pptxCBC Monitoring  Review.pptx
CBC Monitoring Review.pptx
 
PAS Salford Pre App Journey March 2023 JC.pptx
PAS Salford Pre App Journey March 2023 JC.pptxPAS Salford Pre App Journey March 2023 JC.pptx
PAS Salford Pre App Journey March 2023 JC.pptx
 
PAS BNG and Nature Recovery Autumn 2022 Events Evaluation.pdf
PAS BNG and Nature Recovery Autumn 2022 Events Evaluation.pdfPAS BNG and Nature Recovery Autumn 2022 Events Evaluation.pdf
PAS BNG and Nature Recovery Autumn 2022 Events Evaluation.pdf
 
PAS NERC guidance events Nov 22 web.pptx
PAS NERC guidance events Nov 22 web.pptxPAS NERC guidance events Nov 22 web.pptx
PAS NERC guidance events Nov 22 web.pptx
 
PAS Nature Recovery for LAs 8 Dec Post Event.pptx
PAS Nature Recovery for LAs 8 Dec Post Event.pptxPAS Nature Recovery for LAs 8 Dec Post Event.pptx
PAS Nature Recovery for LAs 8 Dec Post Event.pptx
 
PAS BNG and NR policy and strategy
PAS BNG and NR policy and strategy PAS BNG and NR policy and strategy
PAS BNG and NR policy and strategy
 

Recently uploaded

Postal Ballots-For home voting step by step process 2024.pptx
Postal Ballots-For home voting step by step process 2024.pptxPostal Ballots-For home voting step by step process 2024.pptx
Postal Ballots-For home voting step by step process 2024.pptxSwastiRanjanNayak
 
Climate change and safety and health at work
Climate change and safety and health at workClimate change and safety and health at work
Climate change and safety and health at workChristina Parmionova
 
2024: The FAR, Federal Acquisition Regulations - Part 28
2024: The FAR, Federal Acquisition Regulations - Part 282024: The FAR, Federal Acquisition Regulations - Part 28
2024: The FAR, Federal Acquisition Regulations - Part 28JSchaus & Associates
 
The U.S. Budget and Economic Outlook (Presentation)
The U.S. Budget and Economic Outlook (Presentation)The U.S. Budget and Economic Outlook (Presentation)
The U.S. Budget and Economic Outlook (Presentation)Congressional Budget Office
 
Zechariah Boodey Farmstead Collaborative presentation - Humble Beginnings
Zechariah Boodey Farmstead Collaborative presentation -  Humble BeginningsZechariah Boodey Farmstead Collaborative presentation -  Humble Beginnings
Zechariah Boodey Farmstead Collaborative presentation - Humble Beginningsinfo695895
 
The Economic and Organised Crime Office (EOCO) has been advised by the Office...
The Economic and Organised Crime Office (EOCO) has been advised by the Office...The Economic and Organised Crime Office (EOCO) has been advised by the Office...
The Economic and Organised Crime Office (EOCO) has been advised by the Office...nservice241
 
Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...
Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...
Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...Dipal Arora
 
Top Rated Pune Call Girls Dapodi ⟟ 6297143586 ⟟ Call Me For Genuine Sex Serv...
Top Rated  Pune Call Girls Dapodi ⟟ 6297143586 ⟟ Call Me For Genuine Sex Serv...Top Rated  Pune Call Girls Dapodi ⟟ 6297143586 ⟟ Call Me For Genuine Sex Serv...
Top Rated Pune Call Girls Dapodi ⟟ 6297143586 ⟟ Call Me For Genuine Sex Serv...Call Girls in Nagpur High Profile
 
PPT Item # 4 - 231 Encino Ave (Significance Only)
PPT Item # 4 - 231 Encino Ave (Significance Only)PPT Item # 4 - 231 Encino Ave (Significance Only)
PPT Item # 4 - 231 Encino Ave (Significance Only)ahcitycouncil
 
EDUROOT SME_ Performance upto March-2024.pptx
EDUROOT SME_ Performance upto March-2024.pptxEDUROOT SME_ Performance upto March-2024.pptx
EDUROOT SME_ Performance upto March-2024.pptxaaryamanorathofficia
 
(TARA) Call Girls Chakan ( 7001035870 ) HI-Fi Pune Escorts Service
(TARA) Call Girls Chakan ( 7001035870 ) HI-Fi Pune Escorts Service(TARA) Call Girls Chakan ( 7001035870 ) HI-Fi Pune Escorts Service
(TARA) Call Girls Chakan ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
(NEHA) Bhosari Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(NEHA) Bhosari Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(NEHA) Bhosari Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(NEHA) Bhosari Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
Cunningham Road Call Girls Bangalore WhatsApp 8250192130 High Profile Service
Cunningham Road Call Girls Bangalore WhatsApp 8250192130 High Profile ServiceCunningham Road Call Girls Bangalore WhatsApp 8250192130 High Profile Service
Cunningham Road Call Girls Bangalore WhatsApp 8250192130 High Profile ServiceHigh Profile Call Girls
 
Top Rated Pune Call Girls Bhosari ⟟ 6297143586 ⟟ Call Me For Genuine Sex Ser...
Top Rated  Pune Call Girls Bhosari ⟟ 6297143586 ⟟ Call Me For Genuine Sex Ser...Top Rated  Pune Call Girls Bhosari ⟟ 6297143586 ⟟ Call Me For Genuine Sex Ser...
Top Rated Pune Call Girls Bhosari ⟟ 6297143586 ⟟ Call Me For Genuine Sex Ser...Call Girls in Nagpur High Profile
 
Human-AI Collaboration for Virtual Capacity in Emergency Operation Centers (E...
Human-AI Collaborationfor Virtual Capacity in Emergency Operation Centers (E...Human-AI Collaborationfor Virtual Capacity in Emergency Operation Centers (E...
Human-AI Collaboration for Virtual Capacity in Emergency Operation Centers (E...Hemant Purohit
 
Call Girls Nanded City Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Nanded City Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Nanded City Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Nanded City Call Me 7737669865 Budget Friendly No Advance Bookingroncy bisnoi
 
Artificial Intelligence in Philippine Local Governance: Challenges and Opport...
Artificial Intelligence in Philippine Local Governance: Challenges and Opport...Artificial Intelligence in Philippine Local Governance: Challenges and Opport...
Artificial Intelligence in Philippine Local Governance: Challenges and Opport...CedZabala
 
Night 7k to 12k Call Girls Service In Navi Mumbai 👉 BOOK NOW 9833363713 👈 ♀️...
Night 7k to 12k  Call Girls Service In Navi Mumbai 👉 BOOK NOW 9833363713 👈 ♀️...Night 7k to 12k  Call Girls Service In Navi Mumbai 👉 BOOK NOW 9833363713 👈 ♀️...
Night 7k to 12k Call Girls Service In Navi Mumbai 👉 BOOK NOW 9833363713 👈 ♀️...aartirawatdelhi
 
Incident Command System xxxxxxxxxxxxxxxxxxxxxxxxx
Incident Command System xxxxxxxxxxxxxxxxxxxxxxxxxIncident Command System xxxxxxxxxxxxxxxxxxxxxxxxx
Incident Command System xxxxxxxxxxxxxxxxxxxxxxxxxPeter Miles
 
Climate change and occupational safety and health.
Climate change and occupational safety and health.Climate change and occupational safety and health.
Climate change and occupational safety and health.Christina Parmionova
 

Recently uploaded (20)

Postal Ballots-For home voting step by step process 2024.pptx
Postal Ballots-For home voting step by step process 2024.pptxPostal Ballots-For home voting step by step process 2024.pptx
Postal Ballots-For home voting step by step process 2024.pptx
 
Climate change and safety and health at work
Climate change and safety and health at workClimate change and safety and health at work
Climate change and safety and health at work
 
2024: The FAR, Federal Acquisition Regulations - Part 28
2024: The FAR, Federal Acquisition Regulations - Part 282024: The FAR, Federal Acquisition Regulations - Part 28
2024: The FAR, Federal Acquisition Regulations - Part 28
 
The U.S. Budget and Economic Outlook (Presentation)
The U.S. Budget and Economic Outlook (Presentation)The U.S. Budget and Economic Outlook (Presentation)
The U.S. Budget and Economic Outlook (Presentation)
 
Zechariah Boodey Farmstead Collaborative presentation - Humble Beginnings
Zechariah Boodey Farmstead Collaborative presentation -  Humble BeginningsZechariah Boodey Farmstead Collaborative presentation -  Humble Beginnings
Zechariah Boodey Farmstead Collaborative presentation - Humble Beginnings
 
The Economic and Organised Crime Office (EOCO) has been advised by the Office...
The Economic and Organised Crime Office (EOCO) has been advised by the Office...The Economic and Organised Crime Office (EOCO) has been advised by the Office...
The Economic and Organised Crime Office (EOCO) has been advised by the Office...
 
Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...
Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...
Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...
 
Top Rated Pune Call Girls Dapodi ⟟ 6297143586 ⟟ Call Me For Genuine Sex Serv...
Top Rated  Pune Call Girls Dapodi ⟟ 6297143586 ⟟ Call Me For Genuine Sex Serv...Top Rated  Pune Call Girls Dapodi ⟟ 6297143586 ⟟ Call Me For Genuine Sex Serv...
Top Rated Pune Call Girls Dapodi ⟟ 6297143586 ⟟ Call Me For Genuine Sex Serv...
 
PPT Item # 4 - 231 Encino Ave (Significance Only)
PPT Item # 4 - 231 Encino Ave (Significance Only)PPT Item # 4 - 231 Encino Ave (Significance Only)
PPT Item # 4 - 231 Encino Ave (Significance Only)
 
EDUROOT SME_ Performance upto March-2024.pptx
EDUROOT SME_ Performance upto March-2024.pptxEDUROOT SME_ Performance upto March-2024.pptx
EDUROOT SME_ Performance upto March-2024.pptx
 
(TARA) Call Girls Chakan ( 7001035870 ) HI-Fi Pune Escorts Service
(TARA) Call Girls Chakan ( 7001035870 ) HI-Fi Pune Escorts Service(TARA) Call Girls Chakan ( 7001035870 ) HI-Fi Pune Escorts Service
(TARA) Call Girls Chakan ( 7001035870 ) HI-Fi Pune Escorts Service
 
(NEHA) Bhosari Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(NEHA) Bhosari Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(NEHA) Bhosari Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(NEHA) Bhosari Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
Cunningham Road Call Girls Bangalore WhatsApp 8250192130 High Profile Service
Cunningham Road Call Girls Bangalore WhatsApp 8250192130 High Profile ServiceCunningham Road Call Girls Bangalore WhatsApp 8250192130 High Profile Service
Cunningham Road Call Girls Bangalore WhatsApp 8250192130 High Profile Service
 
Top Rated Pune Call Girls Bhosari ⟟ 6297143586 ⟟ Call Me For Genuine Sex Ser...
Top Rated  Pune Call Girls Bhosari ⟟ 6297143586 ⟟ Call Me For Genuine Sex Ser...Top Rated  Pune Call Girls Bhosari ⟟ 6297143586 ⟟ Call Me For Genuine Sex Ser...
Top Rated Pune Call Girls Bhosari ⟟ 6297143586 ⟟ Call Me For Genuine Sex Ser...
 
Human-AI Collaboration for Virtual Capacity in Emergency Operation Centers (E...
Human-AI Collaborationfor Virtual Capacity in Emergency Operation Centers (E...Human-AI Collaborationfor Virtual Capacity in Emergency Operation Centers (E...
Human-AI Collaboration for Virtual Capacity in Emergency Operation Centers (E...
 
Call Girls Nanded City Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Nanded City Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Nanded City Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Nanded City Call Me 7737669865 Budget Friendly No Advance Booking
 
Artificial Intelligence in Philippine Local Governance: Challenges and Opport...
Artificial Intelligence in Philippine Local Governance: Challenges and Opport...Artificial Intelligence in Philippine Local Governance: Challenges and Opport...
Artificial Intelligence in Philippine Local Governance: Challenges and Opport...
 
Night 7k to 12k Call Girls Service In Navi Mumbai 👉 BOOK NOW 9833363713 👈 ♀️...
Night 7k to 12k  Call Girls Service In Navi Mumbai 👉 BOOK NOW 9833363713 👈 ♀️...Night 7k to 12k  Call Girls Service In Navi Mumbai 👉 BOOK NOW 9833363713 👈 ♀️...
Night 7k to 12k Call Girls Service In Navi Mumbai 👉 BOOK NOW 9833363713 👈 ♀️...
 
Incident Command System xxxxxxxxxxxxxxxxxxxxxxxxx
Incident Command System xxxxxxxxxxxxxxxxxxxxxxxxxIncident Command System xxxxxxxxxxxxxxxxxxxxxxxxx
Incident Command System xxxxxxxxxxxxxxxxxxxxxxxxx
 
Climate change and occupational safety and health.
Climate change and occupational safety and health.Climate change and occupational safety and health.
Climate change and occupational safety and health.
 

Viability Session 5: Site-specific case studies

  • 2. Burgess Farm, Salford 350 homes on a greenfield site was allowed by the SoS against the inspector's advice. Despite the permanent loss of an area of open countryside and the fact that the development would seriously degrade the character and appearance of the area. SoS considered that this was outweighed by the scheme's contribution to reducing the significant shortfall of some 4,000 homes (2.5 years supply) against the five year housing land requirement. DCS Number 100-078-099
  • 3. Barnet & Chase Farm: APP/Q5300/A/07/2043798/NWF • The Inspector stated that: ‘the appropriate test is that the value generated by the scheme should exceed the value of the site in its current use. The logic is that, if the converse were the case, then sites would not come forward for development’.
  • 4. Clay Farm, Cambridge - 07/0621/OUT • Residential development of up to 2,300 new mixed- tenure dwellings and accompanying provision of community facilities; sports and recreation facilities and landscaped open spaces including 49 ha. of public open space in the green corridor • Provision for education facilities; and all related infrastructure including: all roads and associated infrastructure, alternative locations for Cambridgeshire guided bus stops, alternative location for CGB Landscape Ecological Mitigation Area, attenuation ponds including alternative location for Addenbrookes's Access Road pond, cycleways, footways and crossings of Hobson's Brook.
  • 5. Clay Farm, Cambridge - 07/0621/OUT The SoS agrees with the Inspector that the appellants’ approach to assessing viability has the effect of protecting historic land values as well as insulating the developer against a risk for which he is already indemnified by profit margins and that this would be at the expense of affordable housing levels. He therefore also agrees with the Inspector that the residual land value (RLV) approach used by the Council is the appropriate methodology for evaluating the economics of these developments…he is concerned that there is nowhere else to accommodate the affordable housing at the levels intended for these sites in the development plan. The SoS attaches very substantial weight to this matter and considers that it outweighs the shortfall in the Council's five year supply of developable sites.
  • 7. Bath Road, Bristol: APP/P0119/A/08/2069226 • McCarthy & Stone – 29 sheltered apartments for the elderly including associated communal facilities and car parking. • A main issue at appeal was whether the proposal would make suitable provision for affordable housing. Policy seeks 33.3% affordable housing. On-site not suitable therefore parties agreed that an off-site contribution was acceptable subject to viability. • At the Inquiry appellant stated viability of the proposal would only allow a contribution of £115,000 which would fund only 1 or 2 affordable units, and is well below the target of 33.3%. The LPA were seeking circa £414k based on previous successful appeal decisions.
  • 8. Bath Road, Bristol: APP/P0119/A/08/2069226 • Both parties conducted appraisals using the old Housing Corporation model. There were differences between the parties on BCIS construction costs, finance costs, contingency, developers profit, build rates and CfSH. Resulting in different residual values from LPA and appellant. • LPA argued that the appellant had inflated costs of the scheme. LPA used a comparable site from another appeal. Inspector placed little weight on this approach as that comparable scheme had not yet come forward. Further he felt the appellants assumptions were reasonable and evidenced.
  • 9. Bath Road, Bristol: APP/P0119/A/08/2069226 • ‘the difference between the Residual Land Value (RLV) and the existing site value provides a basis for ascertaining the viability of contributing towards affordable housing’. • “Any reservations that I may have about the balance of viability arguments are outweighed by what I consider are clear benefits of the proposal.” (due to lack of sheltered housing locally).
  • 12. Beckenham: APP/G5180/A/08/2084559 • Change of use of office to residential and enlargement to comprise 55 dwellings including key worker and affordable housing. Elevational alterations and part seventh/eighth floor extensions, screened roof terrace • Main issues – whether the proposed development meets development plan policies concerning the provision of affordable housing or a payment in lieu thereof and, whether there are any other material planning considerations relevant to the determination of the case.
  • 13. Beckenham: APP/G5180/A/08/2084559 • At the Inquiry a SoCG was submitted agreeing the residual site value with no affordable housing (£2.773 million), the residual value with affordable housing (£1.9223 million) and the existing use value of the site (£2.482 million). These agreed values determine that without an affordable housing contribution, the scheme will only yield less than 12% above the existing use value, 8% below the generally accepted margin necessary to induce such development to proceed. Self-evidently, with a 35% AH target, such a scheme must also be, in the view of the appellant, considered non-viable.
  • 14. Beckenham: APP/G5180/A/08/2084559 • …when the agreed residual value of the site, incorporating 35% affordable housing is set against CUV, the development becomes unviable. Having carefully weighed the matter, I conclude the viability report convincingly demonstrates that the proposals cannot support any affordable housing; accordingly they are not in contravention of LBB and LP affordable housing policy.
  • 16. Oxford Street, Woodstock: APP/D3125/A/09/2104658 • Multiple appeals due to alterations • Demolition of Youngs Garage and 6 Hensington Road, erection of 36 dwellings, health centre and retail unit. Associated parking, roads and footpaths. Alterations to 6,8 and 10 Oxford Street and minor alterations to Punch Bowl Cottage. • Appeals made under section 78 of the Town and Country Planning Act 1990 against a refusal to grant planning permission and under section 20 and 74 of the Planning (Listed Buildings and Conservation Areas) Act 1990 against a refusal to grant listed building consent.
  • 17. Oxford Street, Woodstock: APP/D3125/A/09/2104658 • This case focuses on the margin required over and above the Existing Use Value in order to achieve a change of use of the land: • ‘The main parties valuations of the current existing value of the land are not dissimilar but the Appellant has sought to add a 10% premium. Though the site is owned by the Appellants it must be assumed, for valuation purposes, that the land is being acquired now. It is unreasonable to assume that an existing owner and user of the land would not require a premium over the actual value of the land to offset inconvenience and assist with relocation. The Appellants addition of the 10% premium is not unreasonable in these circumstances.’
  • 18. Oxenholme Road, Kendal, Cumbria APP/M0933/A/13/2193338
  • 19. Oxenholme Road Background and main issues • Appeal for outline planning permission for the construction of 148 no. dwellings at land to the west of Oxenholme Road, Kendal, Cumbria (6.95 hectares at the edge of the built-up area of Kendal) • Main issue is if there is less than a five year supply of developable housing land • Also the provision of affordable housing; the effect on highway and transport infrastructure; the suitability of the site for residential development, in particular the effect on the Green Gap between Kendal and Oxenholme.
  • 20. Oxenholme Road 16. …requirement for 35% affordable housing 18. …appellants dispute the viability implications 21. The concept of a ‘competitive return’ is not further defined by the NPPF, and could be the subject of differing interpretations by the parties involved in any particular development. The assessment of a competitive return will involve an element of judgement. Clearly, however, excessively ambitious predictions must be tempered by comparison with industry norms and local circumstances.
  • 21. Oxenholme Road 22. …it is common ground that a competitive return for the developer can be taken as a profit of 18-20% of GDV 23. …The issue therefore becomes the achievement of a competitive return for the land owner. 24. …the Council proposes the margin settled upon by the consultants who prepared the recent Viability Study in support of the Local Plan. At an EUV of £50,000/hectare, to reflect higher value ‘paddock’ use at the urban fringe rather than basic agricultural value, with a margin of 20% plus £400,000/hectare the site value would amount to £3,197,000 [£246,873/net developable acre]
  • 22. Oxenholme Road 25. However, the RICS guidance note on viability points out concerns about the potential inaccuracy of the EUV plus margin method, and does not recommend it. The Harman report on viability testing of plans also points out the weakness of this approach when dealing with agricultural land at the urban edge. In the present case, the figures adapted from the LADPD Viability Study are broad brush, and the precise rationale for the £400,000 margin is not open to interrogation.
  • 23. Oxenholme Road 25. …Furthermore, I note that representations made for the Local Plan on behalf of the Cumbria House Builder Group in response to the Viability Study are firmly of the view that the level proposed would not encourage landowners to bring forward sites for development. The figure of £246,873 would be well below the £500,000/net developable acre proposed by the House Builder Group and favoured by the appellants in this appeal.
  • 24. Oxenholme Road 26. Therefore, although I note that the EUV plus margin method has been accepted in other situations, such as the examination of the London CIL charging schedule, and may be useful at an area-wide level, in this case I consider that greater weight must be given to the residual method of determining the site value, which has also been followed by the appellants.
  • 25. Oxenholme Road 27. … The appellants’ single appraisal seeks to demonstrate that, at their preferred lower sales values and the same benchmark land value, the scheme without any affordable housing would result in a surplus of £335,000the appellants’ conclusion is that this amount would allow 10% affordable housing provision, subject to some ‘flex’ by the parties on their level of return and on the tenure of the housing.
  • 26. Oxenholme Road • The Council and appellant differed on build costs and sale prices • Inspector accepted evidence from QS that costs were reasonable • The Council claimed the lower market values taken from their LADPD viability study were cautious ‘worst case’ approach. However, without enough available comparables the Inspector sides with the appellant stating the Council’s values would be uncompetitive, harm cash flow and could affect buyers’ ability to access borrowing i.e. he used a reality check!
  • 27. Oxenholme Road • On land value the Council defended it’s £4000,000/net developable acres (backed by the LADPD viability study) vs. the appellants £500,000/net developable acre (backed by the Cumbria House Builder Group) • Various comparables were used in favour of each benchmark land value level.
  • 28. Oxenholme Road 47. The parties refer to an appeal decision for land at Shinfield, Berkshire, which is quoted in the LADPD Viability Study. However, little weight can be given to that decision in the present case, as the nature of the site was quite different, being partly previously developed, and the positions taken by the parties on the proportion of uplift in site value that should be directed to the provision of affordable housing were at odds with those now proposed. There is no reason in the present case to assume that either 100% or 50% of the uplift in site value is the correct proportion to fund community benefits.
  • 29. Oxenholme Road 51. …I am unable to conclude that a higher benchmark value than £400,000/net developable acre should be accepted in this appeal. The evidence for the higher figure proposed by the appellants is not conclusive, being based largely on one small comparator site of a different quality and on a relatively broad brush method of checking land value against GDV. Although contested, the LADPD Viability Study suggests that not all owners have expectations in excess of the £400,000 level ...the expectations of one land owner are not critical in the determination of a benchmark level, which relates to the reasonable expectation of a typical owner.
  • 30. Oxenholme Road 52. …I consider that there are grounds to conclude that a lower benchmark figure would be reasonable. I conclude that the need to set a benchmark land value of £500,000/net developable acre, on which the appellants’ case is based, has not been conclusively demonstrated. 53. The appellants’ viability appraisal shows that with no affordable housing, the scheme could generate a surplus of £335,000 at the higher benchmark land value, which the appellants state could support an affordable housing provision of 10%. It is clear that a lower land value would generate a larger surplus, which would thus support a higher proportion of affordable housing…which would equate to more than £400,000/net developable acre.
  • 31. Oxenholme Road 57. …in the absence of clear evidence that the proposal could not generate a competitive return for both developer and landowner at the policy approved level of provision, I conclude that a condition requiring 35% affordable housing would be reasonable and necessary and would comply with the guidance of the NPPF and meet the tests of Circular 11/95 95. The acute need for affordable housing is accepted. It has not been shown that the development requires a proportion of affordable housing below the policy minimum of 35% in order to generate a competitive return.
  • 32. Shinfield • APP/X0360/A/12/2179141 • Reading University • Wokingham Council • 8th January 2013
  • 33. Site and scheme • 8.5 ha, 5 km south of Reading • Was National Institute for Research into Dairying (closed in 1980s) • 4.5 ha within development limits – with buildings etc • 4 ha beyond development limits – pasture • To clear site and build 126 new dwellings within development limits – remainder to be open space etc
  • 34. History • Long history • 18,766m2 of B1 in 1992 • 2001 identified as being suitable for 80 dwellings by Local Plan inspector • 2003 part of site developed • The principle of development was not contested.
  • 35. Main Issues ‘The main issues are: (i) whether the proposals make adequate provision for mitigating any adverse impact they would have upon local services and infrastructure; and (ii) whether the proposed amount of affordable housing would be appropriate in the context of the viability of the development, the National Planning Policy Framework, development plan policy and all other material planning considerations.’
  • 36. The problem The Council wanted… • £2,028,920 in developer contributions • 40% affordable housing (policy says subject to viability) • Higher sales prices • Lower developers profit • Different Benchmark land value / site value The Developer offered… • £2,312,569 in developer contributions • 2% affordable housing
  • 37. Developers Profit The appellants supported their calculations by providing letters and emails from six national housebuilders who set out their net profit margin targets for residential developments. The figures ranged from a minimum of 17% to 28%, with the usual target being in the range 20- 25%. Those that differentiated between market and affordable housing in their correspondence did not set different profit margins. Due to the level and nature of the supporting evidence, I give great weight it. I conclude that the national housebuilders’ figures are to be preferred and that a figure of 20% of GDV, which is at the lower end of the range, is reasonable.
  • 38. Benchmark land value There is a significant difference in the figures produced by the parties. The Council calculated a Benchmark Land Value of £1,984,000 (reduced to about £1,865,000 when decontamination costs were agreed); the appellants calculate it to be £2,325,000. During the Inquiry reference was made to Current Use Value (CUV) and Existing Use Value (EUV) but it was agreed that these definitions are interchangeable in respect of the calculations used for this site.
  • 39. The Appellant’s approach The appellants’ valuation of the site is £2,325,000 based upon 8 acres of commercial open storage/ industrial land and buildings at £250,000 per acre and 13 acres of settlement fringe at £25,000 per acre. The figure of £250,000 per acre seems reasonable in the light of the recent sale value achieved at the smaller site at Paddock Road (£330,000 per acre).
  • 40. The Council’s approach The Council did not use comparators; instead it relied upon a valuation based upon a substantial office scheme on the appeal site. This was based upon the outline planning permission for offices on the site in 2003 that was renewed in 2006 but which has since lapsed...I am concerned about this approach in that the Council has failed to demonstrate that there is any market for such a substantial office development here. Indeed, the only recently completed (2009) office development of comparable scale, The Blade in Reading, is still largely vacant.
  • 41. Competitive Return Determining what constitutes a competitive return inevitably involves making a subjective judgement based upon the evidence. Two very different viewpoints were put forward at the Inquiry with the appellants seeking a land value of £4,750,000 which is roughly the mid-point between the EUV/CUV and the RLV with planning permission for housing and no obligations. This ties in with the 50:50 split between the community and the landowner sought by the appellants. The Council considered that a sum of £1.865m would ensure a competitive return; that is to say the Council’s calculation of the EUV/CUV.
  • 42. Competitive Return Paragraph 173 of the Framework says that the costs of any requirements should provide competitive returns to a willing landowner and willing developer to enable the development to be deliverable. The paragraph heading is “Ensuring viability and deliverability”; it is clear that its objective is to ensure that land comes forward for development.
  • 43. Competitive Return I am not convinced that a land value that equates to the EUV/CUV would provide any incentive to the landowner to sell the site...such a conclusion would not provide any incentive to the landowner to carry out any remediation work. There would be no incentive to sell the land and so such a low return would fail to achieve the delivery of this site for housing development. In these circumstances, and given the fact that in this case only two very different viewpoints on what constitutes a competitive return have been put forward, the appellants’ conclusions are to be preferred. In the scenario preferred by the Council, I do not consider that the appellants would be a willing vendor.
  • 44. Viable amount of affordable The RICS GN says that any planning obligations imposed on a development will need to be paid out of the uplift in the value of the land but it cannot use up the whole of the difference, other than in exceptional circumstances, as that would remove the likelihood of land being released for development. That is exactly what is at issue here in that the Council’s valuation witness, in cross examination, stated that a landowner should be content to receive what the land is worth, that is to say the SV. In his opinion this stands at £1.865m. I accept that, if this figure was agreed (and it is not), it would mean that the development would be viable.
  • 45. Viable amount of affordable However, it would not result in the land being released for development. Not only is this SV well below that calculated by the appellants, there is no incentive to sell. In short, the appellants would not be willing landowners. If a site is not willingly delivered, development will not take place. The appellants, rightly in my opinion, say that this would not represent a competitive return. They argue that the uplift in value should be split 50:50 between the landowner and the Council. This would, in this instance, represent the identified s106 requirements being paid as well as a contribution of 2% of the dwellings as affordable housing.
  • 46. And finally I conclude on this issue that, allowing the landowner a competitive return of 50% of the uplift in value, the calculations in the development appraisal allowing for 2% affordable housing are reasonable and demonstrate that at this level of affordable housing the development would be viable (Document 26). The only alterations to these calculations are the relatively minor…
  • 47. Case study: South Lakeland
  • 48. Shinfield Test • We do not accept that Shinfield is an authoritative precedent for Plan wide viability testing • Under the Shinfield principles the uplift from granting planning consent is shared 50:50 between the landowner and the local authority.
  • 49. £1,000,000 viability Threshold Table 10.3 Residual Value compared to £1,000,000/ha Viability Threshold (£/net ha) Alternativ e Land Value Viability Threshol d Affordable % 0% 25% 30% 35% 40% Site 1 Urban Edge 1 Kendal 25,000 1,000,00 0 1,443,027 1,148,255 1,083,908 1,017,109 948,778 Site 2 Urban Edge 2 Kendal 25,000 1,000,00 0 1,455,240 1,130,680 1,059,830 986,281 911,045 Site 3 Office re-development Kendal 400,000 1,000,00 0 732,148 412,529 346,134 272,991 198,171 Site 4 Estate Infill Kendal 50,000 1,000,00 0 1,716,295 1,404,668 1,333,530 1,258,469 1,182,385 Site 5 LSC Infill Arnside 50,000 1,000,00 0 1,089,497 860,561 808,331 754,112 698,649 Site 6 LSC Infill Grange 50,000 1,000,00 0 1,315,092 1,015,954 950,654 882,866 813,524 Site 7 Cleared Urban Ulverston 300,000 1,000,00 0 399,698 153,528 100,147 43,821 -13,273 Site 8 KSC Urban Edge Milnthorpe 25,000 1,000,00 0 1,319,627 1,034,413 971,956 908,733 841,158 Site 9 LSC Edge Allithwaite 50,000 1,000,00 0 1,879,318 1,474,114 1,385,383 1,307,848 1,210,926 Site 10 LSC Edge Endmoor 50,000 1,000,00 0 1,266,331 1,000,000 949,065 889,158 825,151 Site 11 LSC Paddock Penny Bridge 50,000 1,000,00 0 1,648,636 1,320,890 1,245,698 1,169,586 1,088,227 1,000,00
  • 50. EUV + 20% + £400,000/ha on greenfield Table 10.4 Residual Value compared to 20% + £400,000/ha Uplift Viability Threshold (£/net ha) Alternative Land Value Viability Threshold Affordable % 0% 25% 30% 35% 40% Site 1 Urban Edge 1 Kendal 25,000 430,000 1,443,027 1,148,255 1,083,908 1,017,109 948,778 Site 2 Urban Edge 2 Kendal 25,000 430,000 1,455,240 1,130,680 1,059,830 986,281 911,045 Site 3 Office re- development Kendal 400,000 480,000 732,148 412,529 346,134 272,991 198,171 Site 4 Estate Infill Kendal 50,000 460,000 1,716,295 1,404,668 1,333,530 1,258,469 1,182,385 Site 5 LSC Infill Arnside 50,000 460,000 1,089,497 860,561 808,331 754,112 698,649 Site 6 LSC Infill Grange 50,000 460,000 1,315,092 1,015,954 950,654 882,866 813,524 Site 7 Cleared Urban Ulverston 300,000 360,000 399,698 153,528 100,147 43,821 -13,273 Site 8 KSC Urban Edge Milnthorpe 25,000 430,000 1,319,627 1,034,413 971,956 908,733 841,158 Site 9 LSC Edge Allithwaite 50,000 460,000 1,879,318 1,474,114 1,385,383 1,307,848 1,210,926 Site 10 LSC Edge Endmoor 50,000 460,000 1,266,331 1,000,000 949,065 889,158 825,151 Site 11 LSC Paddock Penny Bridge 50,000 460,000 1,648,636 1,320,890 1,245,698 1,169,586 1,088,227 Site 12 Small Village Lune Valley 50,000 460,000 1,952,203 1,952,203 1,952,203 1,952,203 1,952,203 Site 13 Ex Garage Site Central SLDC 400,000 480,000 457,674 212,560 159,053 103,507 46,688 Site 14 Village Infill Cartmel Peninsula 50,000 460,000 1,522,498 1,203,186 1,130,073 1,056,066 976,954 Site 15 Village Infill Eastern Area 50,000 460,000 552,018 552,018 552,018 552,018 552,018 Site 16 Rural House Rural west 50,000 310,000 75,454 75,454 75,454 75,454 75,454 Castle Green Road Kendal 25,000 430,000 1,098,652 858,474 806,045 751,618 695,942 Quarry Lane Storth 25,000 430,000 1,175,868 866,671 799,175 729,108 663,665 South Ulverston Ulverston 25,000 430,000 852,535 623,926 573,994 522,158 469,132 Ulverston Canal Head Ulverston 300,000 360,000 928,748 625,484 559,283 495,210 424,244
  • 51. Developers Profit 20% and 25% GDV Table 10.5 Residual Value compared to 20% + £400,000/ha Uplift Viability Threshold (£/net ha) Developers’ return of 20% and 25% 20% GDV 25% GDV Site 1 Urban Edge 1 Kendal 25,000 430,000 1,017,109 831,087 Site 2 Urban Edge 2 Kendal 25,000 430,000 986,281 772,718 Site 3 Office re-development Kendal 400,000 480,000 272,991 30,763 Site 4 Estate Infill Kendal 50,000 460,000 1,258,469 988,341 Site 5 LSC Infill Arnside 50,000 460,000 754,112 565,668 Site 6 LSC Infill Grange 50,000 460,000 882,866 694,863 Site 7 Cleared Urban Ulverston 300,000 360,000 43,821 -262,517 Site 8 KSC Urban Edge Milnthorpe 25,000 430,000 908,733 712,529 Site 9 LSC Edge Allithwaite 50,000 460,000 1,307,848 1,060,360 Site 10 LSC Edge Endmoor 50,000 460,000 889,158 703,008 Site 11 LSC Paddock Penny Bridge 50,000 460,000 1,169,586 960,717 Site 12 Small Village Lune Valley 50,000 460,000 1,952,203 1,677,952 Site 13 Ex Garage Site Central SLDC 400,000 480,000 103,507 -73,964 Site 14 Village Infill Cartmel Peninsula 50,000 460,000 1,056,066 854,394 Site 15 Village Infill Eastern Area 50,000 460,000 552,018 455,105 Site 16 Rural House Rural west 50,000 310,000 75,454 58,142 Castle Green Road Kendal 25,000 430,000 751,618 615,149 Quarry Lane Storth 25,000 430,000 729,108 538,318 South Ulverston Ulverston 25,000 430,000 522,158 343,462 Ulverston Canal Head Ulverston 300,000 360,000 495,210 259,067
  • 52. £500,000/ha Viability Threshold Table 10.6 Residual Value compared to £500,000/ha Viability Threshold (£/net ha) Alternativ e Land Value Viability Threshol d Affordable % 0% 25% 30% 35% 40% Site 1 Urban Edge 1 Kendal 25,000 500,000 1,443,027 1,148,255 1,083,908 1,017,109 948,778 Site 2 Urban Edge 2 Kendal 25,000 500,000 1,455,240 1,130,680 1,059,830 986,281 911,045 Site 3 Office re- development Kendal 400,000 500,000 732,148 412,529 346,134 272,991 198,171 Site 4 Estate Infill Kendal 50,000 500,000 1,716,295 1,404,668 1,333,530 1,258,469 1,182,385 Site 5 LSC Infill Arnside 50,000 500,000 1,089,497 860,561 808,331 754,112 698,649 Site 6 LSC Infill Grange 50,000 500,000 1,315,092 1,015,954 950,654 882,866 813,524 Site 7 Cleared Urban Ulverston 300,000 500,000 399,698 153,528 100,147 43,821 -13,273 Site 8 KSC Urban Edge Milnthorpe 25,000 500,000 1,319,627 1,034,413 971,956 908,733 841,158 Site 9 LSC Edge Allithwaite 50,000 500,000 1,879,318 1,474,114 1,385,383 1,307,848 1,210,926 Site 10 LSC Edge Endmoor 50,000 500,000 1,266,331 1,000,000 949,065 889,158 825,151 Site 11 LSC Paddock Penny Bridge 50,000 500,000 1,648,636 1,320,890 1,245,698 1,169,586 1,088,227 Site 12 Small Village Lune Valley 50,000 500,000 1,952,203 1,952,203 1,952,203 1,952,203 1,952,203 Site 13 Ex Garage Site Central SLDC 400,000 500,000 457,674 212,560 159,053 103,507 46,688 Site 14 Village Infill Cartmel Peninsula 50,000 500,000 1,522,498 1,203,186 1,130,073 1,056,066 976,954 Site 15 Village Infill Eastern Area 50,000 500,000 552,018 552,018 552,018 552,018 552,018 Site 16 Rural House Rural west 50,000 500,000 75,454 75,454 75,454 75,454 75,454 Castle Green Road Kendal 25,000 500,000 1,098,652 858,474 806,045 751,618 695,942 Quarry Lane Storth 25,000 500,000 1,175,868 866,671 799,175 729,108 663,665 South Ulverston Ulverston 25,000 500,000 852,535 623,926 573,994 522,158 469,132 Ulverston Canal Head Ulverston 300,000 500,000 928,748 625,484 559,283 495,210 424,244
  • 53. Viability Threshold = 25% of GDV Table 10.7 Residual Value compared to Viability Threshold of 25% of GDV GDV % GDV Residual % of GDV Site 1 Urban Edge 1 Kendal 27,652,629 6,913,157 5,339,823 19% Site 2 Urban Edge 2 Kendal 34,474,092 8,618,523 5,720,430 17% Site 3 Office re-development Kendal 1,751,290 437,822 84,627 5% Site 4 Estate Infill Kendal 1,945,866 486,466 377,541 19% Site 5 LSC Infill Arnside 4,812,189 1,203,047 754,112 16% Site 6 LSC Infill Grange 7,144,640 1,786,160 1,324,299 19% Site 7 Cleared Urban Ulverston 1,786,127 446,532 10,955 1% Site 8 KSC Urban Edge Milnthorpe 13,091,105 3,272,776 2,271,833 17% Site 9 LSC Edge Allithwaite 4,578,328 1,144,582 980,886 21% Site 10 LSC Edge Endmoor 2,273,993 568,498 444,579 20% Site 11 LSC Paddock Penny Bridge 3,733,644 933,411 818,710 22% Site 12 Small Village Lune Valley 1,002,000 250,500 292,831 29% Site 13 Ex Garage Site Central SLDC 827,808 206,952 20,701 3% Site 14 Village Infill Cartmel Peninsula 1,970,884 492,721 422,426 21% Site 15 Village Infill Eastern Area 684,750 171,188 165,605 24% Site 16 Rural House Rural west 390,000 97,500 75,454 19% Castle Green Road Kendal 11,024,904 2,756,226 2,314,982 21% Quarry Lane Storth 7,045,698 1,761,425 1,035,333 15% South Ulverston Ulverston 111,430,801 27,857,700 11,581,459 10% Ulverston Canal Head Ulverston 12,225,882 3,056,471 955,755 8%
  • 54. Shinfield Test Existing Use Value Residual - No affordable, no developer contributions Shinfield Threshold Residual - Base Modelled Site 1 Urban Edge 1 Kendal 25,000 1,043,694 534,347 711,976 Site 2 Urban Edge 2 Kendal 25,000 1,049,780 537,390 686,726 Site 3 Office re-development Kendal 400,000 797,456 598,728 272,991 Site 4 Estate Infill Kendal 50,000 1,239,640 644,820 878,002 Site 5 LSC Infill Arnside 50,000 1,038,143 544,071 685,556 Site 6 LSC Infill Grange 50,000 1,020,043 535,022 662,150 Site 7 Cleared Urban Ulverston 300,000 475,187 387,594 43,821 Site 8 KSC Urban Edge Milnthorpe 25,000 898,153 461,576 597,851 Site 9 LSC Edge Allithwaite 50,000 1,445,461 747,731 980,886 Site 10 LSC Edge Endmoor 50,000 936,945 493,472 635,113 Site 11 LSC Paddock Penny Bridge 50,000 1,274,754 662,377 880,333 Site 12 Small Village Lune Valley 50,000 1,494,704 772,352 1,464,153 Site 13 Ex Garage Site Central SLDC 400,000 496,992 448,496 103,507 Site 14 Village Infill Cartmel Peninsular 50,000 780,162 415,081 528,033 Site 15 Village Infill Eastern Area 50,000 567,592 308,796 552,018 Site 16 Rural House Rural west 50,000 77,027 63,513 75,454
  • 55. Full Policy + Developer Contributions Table 10.9 Impact of different Developer Contributions Alternative Use Value Viability Threshold Developer Contributions. £/ unit (market and affordable) £/ha £/ha £1,500 £2,500 £5,000 £7,500 £10,000 Site 1 Urban Edge 1 Kendal 25,000 430,000 1,017,109 985,133 905,194 825,255 745,315 Site 2 Urban Edge 2 Kendal 25,000 430,000 986,281 951,307 863,874 776,440 689,006 Site 3 Office re- development Kendal 400,000 480,000 272,991 229,023 119,103 9,184 -100,736 Site 4 Estate Infill Kendal 50,000 460,000 1,258,469 1,217,735 1,115,898 1,014,061 912,225 Site 5 LSC Infill Arnside 50,000 460,000 754,112 718,807 630,544 542,282 458,364 Site 6 LSC Infill Grange 50,000 460,000 882,866 852,889 777,946 703,003 634,013 Site 7 Cleared Urban Ulverston 300,000 360,000 43,821 -6,505 -132,321 -258,137 -385,862 Site 8 KSC Urban Edge Milnthorpe 25,000 430,000 908,733 878,356 802,414 726,471 650,529 Site 9 LSC Edge Allithwaite 50,000 460,000 1,307,848 1,275,569 1,194,872 1,114,175 1,033,478 Site 10 LSC Edge Endmoor 50,000 460,000 889,158 858,607 782,230 705,852 629,475 Site 11 LSC Paddock Penny Bridge 50,000 460,000 1,169,586 1,139,324 1,063,671 988,017 912,364 Site 12 Small Village Lune Valley 50,000 460,000 1,952,203 1,925,047 1,857,156 1,789,265 1,721,374 Site 13 Ex Garage Site Central SLDC 400,000 480,000 103,507 77,296 11,767 -53,763 -119,292 Site 14 Village Infill Cartmel Peninsula 50,000 460,000 1,056,066 1,030,607 966,959 903,311 839,663 Site 15 Village Infill Eastern Area 50,000 460,000 552,018 541,636 515,680 489,724 463,768 Site 16 Rural House Rural west 50,000 310,000 75,454 74,406 71,785 69,163 66,542
  • 56. Contact us Simon Drummond-Hay Email simon@drummond-hay.co.uk Phone 015242 76205 / 07989 975 977 David Carlisle Email david.a.carlisle@aecom.com Phone 020 7821 4194 / 07827353558