SlideShare a Scribd company logo
CHECK LIST FOR OHE MAST GROUTING REV-00
1 | Pa g e
In case of any doubt or corrections please mail to : v.gopal21@gmail.com
1. Check the copy of approved CSD, LOP and the DPR of foundation and JVR for
mast
2. Check the span on both sides, Implantation, step distance, type of foundation,
type of mast, gradient and super elevation.
3. Check type of foundation casted, type of mast / upright erected are as per
approved CSD, LOP and DPR for foundation. If any change observed the same
shall be brought to the notice of in-charge before proceeding further.
4. Check confirmation of changes are recorded the proceed further activity
5. Check for proper tools such as crow bars, shovel, trowel, iron sheet, mortar
hoe, mud pan, water bucket, measuring cup, measurement box, wooden
wedges, measuring tapes, plumb bob/plummet, nylon string and safety items
including nylon/manila ropes of 25 mm diameter.
6. Check use of suitable shutters with proper dimensions as per type of foundation
used while casting the muffs for proper shape and finish.
7. Check for availability of main contractor engineer and safety engineer during
execution
8. Check Permission is obtained in advance from division officers/Staff of TrD,
Engineering and Operating department as applicable.
9. Check Information is given Local Permanent way , TrD, RPF and both side
SM/SS before starting work and all staff , supervisor, engineer are aware of
G&S Rules, safety procedures, applicable instructions and JP issued by
division
10.Check all persons engaged are wearing Personal Protective Equipment.
11.Check for whistle / Flag man on either side to alert the gang for movement of
train
12.Check visually for mast type, make/marking, band ,galvanisation coating, holes,
injury of galvanisation due to transportation / handling, defects, damages,
deformity including bend, twist and inspection mark/seal etc.
13.Check and ensure adequate protection is provided to avoid the mast lean
towards trackside/alongside of track, while adjusting.
14.Check the mast /upright is placed in proper position (implantation, embedded
length, orientation and height of opposite upright in case of portal) by verifying
the web side and bottom portion is in the core hole.
15.Check the embedded length of mast in the core hole is 1.35 metre for individual
mast and 1.45 metre for TTU and Portal up-rights from top of the foundation.
(Cutting length in HLPF and High bank in cutting area should be ensured )
CHECK LIST FOR OHE MAST GROUTING REV-00
2 | Pa g e
In case of any doubt or corrections please mail to : v.gopal21@gmail.com
16.Check the step distance, if it is more than 50cm, Mast should be lifted and
grouted to get adequate height and Super block should be casted on the top of
the foundation. Ex. If step distance is found 60 cm, then mast should be lifted
by10 cm and super block of 10 cm to be casted on the top of foundation to get
required embedded length.
17.Check and adjust the deflection as specified in CSD (particularly at curves),
implantation at platform, yard, obligatory location and verify span and
implantation near signal mast and span near bridges, culverts and OLS
18.Check the wooden wedges are placed firmly after adjusting the mast ensure
the dimensional tolerance on span is +/- 50 mm and the implantation is +/- 20
mm
19.Check following material for grouting at site are approved for M 15 mix:
a. Cement for Make/ brand, Grade, ISI no, batch no & Manufacturing date.
b. Size and quality and quantity of coarse aggregates (20 mm), fine
aggregates (4.75 mm) & Cement shall be of OPC as per IS 12269 Gr 43
or 53.
20.Check and ensure mixing of the dry concrete uniformly i.e. Cement, coarse
aggregates, fine aggregates
21.Check and ensure the required quantity is added with measuring container in
concrete.
22.Check the mixing is done thoroughly for around two minutes to get the
homogenous concrete.
23.Check and ensure Concrete is placed within 15 to 20 minutes of pouring water.
24.Check the concrete is poured uniformly in the core hole.
25.Check proper compaction of the concrete is done to remove air from the
concrete. If compaction is not well, it creates voids/honeycomb in concrete
resulting in reduction of the strength.
26.Check and ensure the compaction is done for every 30 Cm layer of concrete.
27.Check all anchor blocks and foundations of structures carrying overhead
equipment shall be provided with concrete muffs. The top of these muffs shall
be above the level of ground the track formation and of adequate height of not
less than 15 cm for protection during rainy weather
CHECK LIST FOR OHE MAST GROUTING REV-00
3 | Pa g e
In case of any doubt or corrections please mail to : v.gopal21@gmail.com
28.Check for protection done to avoid anyone to disturb muff surface till the
concrete gets hardened (Initial setting)
29.Check and ensure muffs are casted at the same day. The top of such
foundations shall be given a slope of 1 in 50 towards the edge to ensure that
water does not collect at the base of the structure.
30.Check the exposed surfaces of concrete shall be kept continuously in damp or
wet condition by ponding or by covering with a layer of sacking, canvas,
31.hessian or similar material and kept constantly wet for at least seven days from
the date of placing concrete.
32.Check the area is cleaned by removing items such as : balance concrete, pit
cover, empty cement bags, trash items (used for food packaging, preparation,
consuming), plastic items and balance aggregates if any
33.Check the samples of aggregates (fine & coarse), and water from the site
periodically (once in a month) and send it to govt. approved lab for testing as
per approved FQP/Specification and record in sample test register
34.Check and record the, Location Number, date, type of mast, actual implantation
and deflection
35.Check and ensure the DPR is submitted in office within next two days and
update site diary with relevant information which will be subjected to audit
36.Sample Concrete calculation is attached in Annexure 1
CHECK LIST FOR OHE MAST GROUTING REV-00
4 | Pa g e
In case of any doubt or corrections please mail to : v.gopal21@gmail.com
Note : If M15 concrete is used for foundation in locations like HRB , M20 mix to be done for grouting
Annexure :1
Calculation for M15 Concrete (1:2:4)
During concreting when we place wet concrete, it gets harden after certain standard
time. Initial Setting Time : 30 minutes ,Final Setting Time : 10 Hours
Volume of dry Concrete = 1.54 to 1.57 times Volume of wet concrete.
For One cubic metre Concrete work of ratio 1:2:4 ; Sum = 1+2+4=7
Total volume of wet concrete required is: 1.57 Cubic metre
1. Volume of cement = (1/7) x 1.57 = 0.224 Cubic metre; 0.224 x1440 = 323kg
(6.46 bag of 50 kg cement is required for I cubic metre)
2. Volume of fine aggregate or M. Sand required (>.07 to 4.7 mm) = (2/7) x 1.57 =
0.448 Cubic metre
3. Volume of coarse aggregate required (20mm) = (4/7) x 1.57 = 0.896 Cubic
metre.
4. Water cement ratio is maximum 0.6, for one cubic metre concrete quantity of
water required is = 323x0.6 = 193.8 kg or litre.
Use measurement box for correct mixing.
***********************************************************************************************
Relevant Indian Standard Specifications for reference
1. IS 383-1970 Specification for coarse and fine aggregate from Natural Source for
Concrete.
2. IS 456-1978 Code of practice for plain and reinforced concrete.
3. IS 516-1959 Method of test for strength of concrete
4. IS 1199-1959 Method of sampling and analysis of concrete
5. IS 2386-1963 Method of test for aggregate for concrete work. a) Pt. I Particle size
and shape b) Pt. II Estimation of deleterious materials ii organic impurities c) Pt. IIi
Specific gravity, density, (km and bulking. d) Pt. IV Mechanical properties.
IS 12269 Specification for ordinary Portland Cement
****End of check sheet****

More Related Content

What's hot

Revised ppt High rise OHE (1).pptx
Revised ppt High rise OHE (1).pptxRevised ppt High rise OHE (1).pptx
Revised ppt High rise OHE (1).pptx
HimanshuTekwani1
 
Traction OHE 30.07.2019.ppt
Traction OHE 30.07.2019.pptTraction OHE 30.07.2019.ppt
Traction OHE 30.07.2019.ppt
Ashish585772
 
Overhead railway traction
Overhead railway tractionOverhead railway traction
Overhead railway traction
Probodh Mallick
 
Design and construction of underground cable transmission line
Design and construction of underground cable transmission lineDesign and construction of underground cable transmission line
Design and construction of underground cable transmission line
Fazlur Rahman
 
33kv substation
33kv substation33kv substation
33kv substation
Abhishek Dawachya
 
UNIT - 06 TRANSMISSION LINES AND SUBSTATIONS
UNIT - 06 TRANSMISSION LINES AND SUBSTATIONSUNIT - 06 TRANSMISSION LINES AND SUBSTATIONS
UNIT - 06 TRANSMISSION LINES AND SUBSTATIONS
PremanandDesai
 
Distribution system 2
Distribution system  2Distribution system  2
Distribution system 2
Engr Numan Sarwar
 
Guidelines for electrical wiring in residential buildings
Guidelines for electrical wiring in residential buildings Guidelines for electrical wiring in residential buildings
Guidelines for electrical wiring in residential buildings Vijay Kumar
 
132 33kv substation documentation
132 33kv substation documentation132 33kv substation documentation
132 33kv substation documentation
Rajashekar Gurrala
 
Railway Electrification - Traction
Railway Electrification - TractionRailway Electrification - Traction
Railway Electrification - Traction
SUDIN BISWAS
 
Electric traction system
Electric traction systemElectric traction system
Electric traction system
AmitKumar6931
 
Underground cables
Underground cablesUnderground cables
Underground cables
Anu71
 
Transmisiion line design concept
Transmisiion line design conceptTransmisiion line design concept
Transmisiion line design conceptKumar VEL
 
Substations
Substations Substations
Substations
Engr Muhammad Imran
 
Current transformer ieema
Current transformer  ieemaCurrent transformer  ieema
Current transformer ieema
Niraj Agrawal
 
STC-TrD-03-c-Safety rules for OHE.pptx
STC-TrD-03-c-Safety rules for OHE.pptxSTC-TrD-03-c-Safety rules for OHE.pptx
STC-TrD-03-c-Safety rules for OHE.pptx
ShashankMudholkar
 
St pantograph
St pantographSt pantograph
St pantograph
Shubham Tiwari ST
 
ppt on summer training on uppcl
ppt on summer training on uppclppt on summer training on uppcl
ppt on summer training on uppcl
Sunny Daksh
 
Power transformer testing and commissioning guidelines r
Power transformer testing and commissioning guidelines rPower transformer testing and commissioning guidelines r
Power transformer testing and commissioning guidelines r
Ashish Patel
 

What's hot (20)

Revised ppt High rise OHE (1).pptx
Revised ppt High rise OHE (1).pptxRevised ppt High rise OHE (1).pptx
Revised ppt High rise OHE (1).pptx
 
Traction OHE 30.07.2019.ppt
Traction OHE 30.07.2019.pptTraction OHE 30.07.2019.ppt
Traction OHE 30.07.2019.ppt
 
Overhead railway traction
Overhead railway tractionOverhead railway traction
Overhead railway traction
 
Design and construction of underground cable transmission line
Design and construction of underground cable transmission lineDesign and construction of underground cable transmission line
Design and construction of underground cable transmission line
 
33kv substation
33kv substation33kv substation
33kv substation
 
UNIT - 06 TRANSMISSION LINES AND SUBSTATIONS
UNIT - 06 TRANSMISSION LINES AND SUBSTATIONSUNIT - 06 TRANSMISSION LINES AND SUBSTATIONS
UNIT - 06 TRANSMISSION LINES AND SUBSTATIONS
 
Dog Conductor
Dog ConductorDog Conductor
Dog Conductor
 
Distribution system 2
Distribution system  2Distribution system  2
Distribution system 2
 
Guidelines for electrical wiring in residential buildings
Guidelines for electrical wiring in residential buildings Guidelines for electrical wiring in residential buildings
Guidelines for electrical wiring in residential buildings
 
132 33kv substation documentation
132 33kv substation documentation132 33kv substation documentation
132 33kv substation documentation
 
Railway Electrification - Traction
Railway Electrification - TractionRailway Electrification - Traction
Railway Electrification - Traction
 
Electric traction system
Electric traction systemElectric traction system
Electric traction system
 
Underground cables
Underground cablesUnderground cables
Underground cables
 
Transmisiion line design concept
Transmisiion line design conceptTransmisiion line design concept
Transmisiion line design concept
 
Substations
Substations Substations
Substations
 
Current transformer ieema
Current transformer  ieemaCurrent transformer  ieema
Current transformer ieema
 
STC-TrD-03-c-Safety rules for OHE.pptx
STC-TrD-03-c-Safety rules for OHE.pptxSTC-TrD-03-c-Safety rules for OHE.pptx
STC-TrD-03-c-Safety rules for OHE.pptx
 
St pantograph
St pantographSt pantograph
St pantograph
 
ppt on summer training on uppcl
ppt on summer training on uppclppt on summer training on uppcl
ppt on summer training on uppcl
 
Power transformer testing and commissioning guidelines r
Power transformer testing and commissioning guidelines rPower transformer testing and commissioning guidelines r
Power transformer testing and commissioning guidelines r
 

Similar to VG Check list for OHE mast grouting rev 00

VG check list for OHE foundation
VG check list for OHE foundation VG check list for OHE foundation
VG check list for OHE foundation
Varadharajalu Gopal
 
Lining in tunnels
Lining in tunnelsLining in tunnels
Lining in tunnels
Himanshu Batra
 
Construction basic SIP
Construction basic SIPConstruction basic SIP
Construction basic SIP
Mkh Nantu
 
detailed specification for cement concrete
detailed specification for cement concretedetailed specification for cement concrete
detailed specification for cement concrete
vivek gami
 
sample.pptx
sample.pptxsample.pptx
sample.pptx
HirenThakkar31
 
Buildingmaterialslabmanuallab01 161125043012
Buildingmaterialslabmanuallab01 161125043012Buildingmaterialslabmanuallab01 161125043012
Buildingmaterialslabmanuallab01 161125043012
Vijay Patidar
 
Buildingmaterialslabmanuallab01 161125043012 (1)
Buildingmaterialslabmanuallab01 161125043012 (1)Buildingmaterialslabmanuallab01 161125043012 (1)
Buildingmaterialslabmanuallab01 161125043012 (1)
Vijay Patidar
 
Building materials lab_manual lab 01
Building materials lab_manual  lab 01Building materials lab_manual  lab 01
Building materials lab_manual lab 01
Engr. Umair Razzaq
 
GOOD CONSTRUCTION PRACTICE.pptx
GOOD CONSTRUCTION PRACTICE.pptxGOOD CONSTRUCTION PRACTICE.pptx
GOOD CONSTRUCTION PRACTICE.pptx
HirenThakkar31
 
Specifications of rcc foundation
Specifications of rcc foundation Specifications of rcc foundation
Specifications of rcc foundation
Prabhat chhirolya
 
Construction practices and quality control
Construction practices and quality controlConstruction practices and quality control
Construction practices and quality control
SIBENDU SURAJEET JENA
 
selfcompactingconcretescc-160316004923.pptx
selfcompactingconcretescc-160316004923.pptxselfcompactingconcretescc-160316004923.pptx
selfcompactingconcretescc-160316004923.pptx
ARUNKUMARC39
 
publication_1580218342.pdf
publication_1580218342.pdfpublication_1580218342.pdf
publication_1580218342.pdf
PradeepPokhrel5
 
Subgrade, ETB and Asphalt Site Organisation construction procedure-2.pptx
Subgrade, ETB and Asphalt Site Organisation construction procedure-2.pptxSubgrade, ETB and Asphalt Site Organisation construction procedure-2.pptx
Subgrade, ETB and Asphalt Site Organisation construction procedure-2.pptx
EricNikorido1
 
Work check list
Work check listWork check list
Technical specifications for Phase 1 Wastewater Network tank interceptors
Technical specifications for Phase 1 Wastewater Network tank interceptorsTechnical specifications for Phase 1 Wastewater Network tank interceptors
Technical specifications for Phase 1 Wastewater Network tank interceptorsLaith Abdel Nabi
 
B.3. Arch 561 LEC-10 detail spec example.pdf
B.3. Arch 561  LEC-10 detail spec example.pdfB.3. Arch 561  LEC-10 detail spec example.pdf
B.3. Arch 561 LEC-10 detail spec example.pdf
Rahul Chandra Deb Nath
 
IRJET - Effect of Silica Fume on Properties of Concrete
IRJET -  	  Effect of Silica Fume on Properties of ConcreteIRJET -  	  Effect of Silica Fume on Properties of Concrete
IRJET - Effect of Silica Fume on Properties of Concrete
IRJET Journal
 
Road pavements-of-cement-concrete
Road pavements-of-cement-concreteRoad pavements-of-cement-concrete
Road pavements-of-cement-concreteMylene Delmoro
 
Road pavements-of-cement-concrete
Road pavements-of-cement-concreteRoad pavements-of-cement-concrete
Road pavements-of-cement-concreteMylene Delmoro
 

Similar to VG Check list for OHE mast grouting rev 00 (20)

VG check list for OHE foundation
VG check list for OHE foundation VG check list for OHE foundation
VG check list for OHE foundation
 
Lining in tunnels
Lining in tunnelsLining in tunnels
Lining in tunnels
 
Construction basic SIP
Construction basic SIPConstruction basic SIP
Construction basic SIP
 
detailed specification for cement concrete
detailed specification for cement concretedetailed specification for cement concrete
detailed specification for cement concrete
 
sample.pptx
sample.pptxsample.pptx
sample.pptx
 
Buildingmaterialslabmanuallab01 161125043012
Buildingmaterialslabmanuallab01 161125043012Buildingmaterialslabmanuallab01 161125043012
Buildingmaterialslabmanuallab01 161125043012
 
Buildingmaterialslabmanuallab01 161125043012 (1)
Buildingmaterialslabmanuallab01 161125043012 (1)Buildingmaterialslabmanuallab01 161125043012 (1)
Buildingmaterialslabmanuallab01 161125043012 (1)
 
Building materials lab_manual lab 01
Building materials lab_manual  lab 01Building materials lab_manual  lab 01
Building materials lab_manual lab 01
 
GOOD CONSTRUCTION PRACTICE.pptx
GOOD CONSTRUCTION PRACTICE.pptxGOOD CONSTRUCTION PRACTICE.pptx
GOOD CONSTRUCTION PRACTICE.pptx
 
Specifications of rcc foundation
Specifications of rcc foundation Specifications of rcc foundation
Specifications of rcc foundation
 
Construction practices and quality control
Construction practices and quality controlConstruction practices and quality control
Construction practices and quality control
 
selfcompactingconcretescc-160316004923.pptx
selfcompactingconcretescc-160316004923.pptxselfcompactingconcretescc-160316004923.pptx
selfcompactingconcretescc-160316004923.pptx
 
publication_1580218342.pdf
publication_1580218342.pdfpublication_1580218342.pdf
publication_1580218342.pdf
 
Subgrade, ETB and Asphalt Site Organisation construction procedure-2.pptx
Subgrade, ETB and Asphalt Site Organisation construction procedure-2.pptxSubgrade, ETB and Asphalt Site Organisation construction procedure-2.pptx
Subgrade, ETB and Asphalt Site Organisation construction procedure-2.pptx
 
Work check list
Work check listWork check list
Work check list
 
Technical specifications for Phase 1 Wastewater Network tank interceptors
Technical specifications for Phase 1 Wastewater Network tank interceptorsTechnical specifications for Phase 1 Wastewater Network tank interceptors
Technical specifications for Phase 1 Wastewater Network tank interceptors
 
B.3. Arch 561 LEC-10 detail spec example.pdf
B.3. Arch 561  LEC-10 detail spec example.pdfB.3. Arch 561  LEC-10 detail spec example.pdf
B.3. Arch 561 LEC-10 detail spec example.pdf
 
IRJET - Effect of Silica Fume on Properties of Concrete
IRJET -  	  Effect of Silica Fume on Properties of ConcreteIRJET -  	  Effect of Silica Fume on Properties of Concrete
IRJET - Effect of Silica Fume on Properties of Concrete
 
Road pavements-of-cement-concrete
Road pavements-of-cement-concreteRoad pavements-of-cement-concrete
Road pavements-of-cement-concrete
 
Road pavements-of-cement-concrete
Road pavements-of-cement-concreteRoad pavements-of-cement-concrete
Road pavements-of-cement-concrete
 

Recently uploaded

WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
AafreenAbuthahir2
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
AmarGB2
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
gerogepatton
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
MdTanvirMahtab2
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
AhmedHussein950959
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
Jayaprasanna4
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
manasideore6
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
bakpo1
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
karthi keyan
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
VENKATESHvenky89705
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
Massimo Talia
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
TeeVichai
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
fxintegritypublishin
 
English lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdfEnglish lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdf
BrazilAccount1
 

Recently uploaded (20)

WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
 
English lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdfEnglish lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdf
 

VG Check list for OHE mast grouting rev 00

  • 1. CHECK LIST FOR OHE MAST GROUTING REV-00 1 | Pa g e In case of any doubt or corrections please mail to : v.gopal21@gmail.com 1. Check the copy of approved CSD, LOP and the DPR of foundation and JVR for mast 2. Check the span on both sides, Implantation, step distance, type of foundation, type of mast, gradient and super elevation. 3. Check type of foundation casted, type of mast / upright erected are as per approved CSD, LOP and DPR for foundation. If any change observed the same shall be brought to the notice of in-charge before proceeding further. 4. Check confirmation of changes are recorded the proceed further activity 5. Check for proper tools such as crow bars, shovel, trowel, iron sheet, mortar hoe, mud pan, water bucket, measuring cup, measurement box, wooden wedges, measuring tapes, plumb bob/plummet, nylon string and safety items including nylon/manila ropes of 25 mm diameter. 6. Check use of suitable shutters with proper dimensions as per type of foundation used while casting the muffs for proper shape and finish. 7. Check for availability of main contractor engineer and safety engineer during execution 8. Check Permission is obtained in advance from division officers/Staff of TrD, Engineering and Operating department as applicable. 9. Check Information is given Local Permanent way , TrD, RPF and both side SM/SS before starting work and all staff , supervisor, engineer are aware of G&S Rules, safety procedures, applicable instructions and JP issued by division 10.Check all persons engaged are wearing Personal Protective Equipment. 11.Check for whistle / Flag man on either side to alert the gang for movement of train 12.Check visually for mast type, make/marking, band ,galvanisation coating, holes, injury of galvanisation due to transportation / handling, defects, damages, deformity including bend, twist and inspection mark/seal etc. 13.Check and ensure adequate protection is provided to avoid the mast lean towards trackside/alongside of track, while adjusting. 14.Check the mast /upright is placed in proper position (implantation, embedded length, orientation and height of opposite upright in case of portal) by verifying the web side and bottom portion is in the core hole. 15.Check the embedded length of mast in the core hole is 1.35 metre for individual mast and 1.45 metre for TTU and Portal up-rights from top of the foundation. (Cutting length in HLPF and High bank in cutting area should be ensured )
  • 2. CHECK LIST FOR OHE MAST GROUTING REV-00 2 | Pa g e In case of any doubt or corrections please mail to : v.gopal21@gmail.com 16.Check the step distance, if it is more than 50cm, Mast should be lifted and grouted to get adequate height and Super block should be casted on the top of the foundation. Ex. If step distance is found 60 cm, then mast should be lifted by10 cm and super block of 10 cm to be casted on the top of foundation to get required embedded length. 17.Check and adjust the deflection as specified in CSD (particularly at curves), implantation at platform, yard, obligatory location and verify span and implantation near signal mast and span near bridges, culverts and OLS 18.Check the wooden wedges are placed firmly after adjusting the mast ensure the dimensional tolerance on span is +/- 50 mm and the implantation is +/- 20 mm 19.Check following material for grouting at site are approved for M 15 mix: a. Cement for Make/ brand, Grade, ISI no, batch no & Manufacturing date. b. Size and quality and quantity of coarse aggregates (20 mm), fine aggregates (4.75 mm) & Cement shall be of OPC as per IS 12269 Gr 43 or 53. 20.Check and ensure mixing of the dry concrete uniformly i.e. Cement, coarse aggregates, fine aggregates 21.Check and ensure the required quantity is added with measuring container in concrete. 22.Check the mixing is done thoroughly for around two minutes to get the homogenous concrete. 23.Check and ensure Concrete is placed within 15 to 20 minutes of pouring water. 24.Check the concrete is poured uniformly in the core hole. 25.Check proper compaction of the concrete is done to remove air from the concrete. If compaction is not well, it creates voids/honeycomb in concrete resulting in reduction of the strength. 26.Check and ensure the compaction is done for every 30 Cm layer of concrete. 27.Check all anchor blocks and foundations of structures carrying overhead equipment shall be provided with concrete muffs. The top of these muffs shall be above the level of ground the track formation and of adequate height of not less than 15 cm for protection during rainy weather
  • 3. CHECK LIST FOR OHE MAST GROUTING REV-00 3 | Pa g e In case of any doubt or corrections please mail to : v.gopal21@gmail.com 28.Check for protection done to avoid anyone to disturb muff surface till the concrete gets hardened (Initial setting) 29.Check and ensure muffs are casted at the same day. The top of such foundations shall be given a slope of 1 in 50 towards the edge to ensure that water does not collect at the base of the structure. 30.Check the exposed surfaces of concrete shall be kept continuously in damp or wet condition by ponding or by covering with a layer of sacking, canvas, 31.hessian or similar material and kept constantly wet for at least seven days from the date of placing concrete. 32.Check the area is cleaned by removing items such as : balance concrete, pit cover, empty cement bags, trash items (used for food packaging, preparation, consuming), plastic items and balance aggregates if any 33.Check the samples of aggregates (fine & coarse), and water from the site periodically (once in a month) and send it to govt. approved lab for testing as per approved FQP/Specification and record in sample test register 34.Check and record the, Location Number, date, type of mast, actual implantation and deflection 35.Check and ensure the DPR is submitted in office within next two days and update site diary with relevant information which will be subjected to audit 36.Sample Concrete calculation is attached in Annexure 1
  • 4. CHECK LIST FOR OHE MAST GROUTING REV-00 4 | Pa g e In case of any doubt or corrections please mail to : v.gopal21@gmail.com Note : If M15 concrete is used for foundation in locations like HRB , M20 mix to be done for grouting Annexure :1 Calculation for M15 Concrete (1:2:4) During concreting when we place wet concrete, it gets harden after certain standard time. Initial Setting Time : 30 minutes ,Final Setting Time : 10 Hours Volume of dry Concrete = 1.54 to 1.57 times Volume of wet concrete. For One cubic metre Concrete work of ratio 1:2:4 ; Sum = 1+2+4=7 Total volume of wet concrete required is: 1.57 Cubic metre 1. Volume of cement = (1/7) x 1.57 = 0.224 Cubic metre; 0.224 x1440 = 323kg (6.46 bag of 50 kg cement is required for I cubic metre) 2. Volume of fine aggregate or M. Sand required (>.07 to 4.7 mm) = (2/7) x 1.57 = 0.448 Cubic metre 3. Volume of coarse aggregate required (20mm) = (4/7) x 1.57 = 0.896 Cubic metre. 4. Water cement ratio is maximum 0.6, for one cubic metre concrete quantity of water required is = 323x0.6 = 193.8 kg or litre. Use measurement box for correct mixing. *********************************************************************************************** Relevant Indian Standard Specifications for reference 1. IS 383-1970 Specification for coarse and fine aggregate from Natural Source for Concrete. 2. IS 456-1978 Code of practice for plain and reinforced concrete. 3. IS 516-1959 Method of test for strength of concrete 4. IS 1199-1959 Method of sampling and analysis of concrete 5. IS 2386-1963 Method of test for aggregate for concrete work. a) Pt. I Particle size and shape b) Pt. II Estimation of deleterious materials ii organic impurities c) Pt. IIi Specific gravity, density, (km and bulking. d) Pt. IV Mechanical properties. IS 12269 Specification for ordinary Portland Cement ****End of check sheet****