SlideShare a Scribd company logo
1 of 16
Download to read offline
A WHITE PAPER 
Witness Testing of the UniEnergy Technologies 
Uni.System™ 
Utility Scale Energy Storage System 
COMMISSIONED BY 
UniEnergy Technologies 
Mukilteo, Washington 
PREPARED BY 
Garth P. Corey, Consultant 
Energy Storage Systems Engineer 
Albuquerque, NM 
July 31, 2014 
1 Copyright © UniEnergy Technologies, LLC 2014
A WHITE PAPER 
Introduction 
UniEnergy has commissioned me, a third party energy storage systems engineer, to produce a 
white paper reporting the results of witness testing for the Uni.System™ Vanadium Redox Flow 
Battery (VFB) onsite at the UET facilities in Mukilteo, Washington during the week of 21‐25 July, 
2014. Specifications of the Uni.System VFB as tested are as follows: 
SPECIFICATIONS OF UNI.SYSTEM™ 
Component Specification 
Number of modules per battery (20 ft. containers) 4 
Stacks per module 3 
Voltage window 450~986 VDC 
Current ‐1000~1000 ADC 
Electrolyte volume 23 m3 per battery module 
Operating temperature range ‐10~55 °C 
PCS power ‐600~600 kW (see following charge profile) 
The following photograph shows the 500 kW, 2 MWh Uni.System as installed at the UniEnergy 
Technologies facility in Mukilteo, Washington. The system consists of four each 20 ft. modules 
and one each 20 ft. electronics container. The system ran continuously throughout the testing 
activities with no down‐time. Human intervention was needed only for the purpose of activating 
the various tests reported here. 
2 Copyright © UniEnergy Technologies, LLC 2014
A WHITE PAPER 
Because of power limitations of the current Power Conditioning System (PCS), the maximum 
power available for charging is 400 kW; the maximum power available for discharging is 600 kW. 
The following graphic shows the limits in voltage at various states of charge. This limitation did 
not impact the results of the witness test and is scheduled to be addressed in the production 
version of the Uni.System system so that the maximum power available for discharging and 
charging will be 600 kW for both functions. 
PCS CHARGE PROFILE 
Third Party Witness Test Plan 
Witness testing was planned for the following five utility scale application areas: 
1. Regulation 
Signal “Aggressive” was employed for this testing. The signal is consistent with the PNNL testing 
protocol. The starting SOC was controlled around 50%. The duration of regulation testing is 
scheduled for 2h. 
3 Copyright © UniEnergy Technologies, LLC 2014
A WHITE PAPER 
Regulation Signal 
2. Capacity Testing 
The capacity testing included two discharge powers: 600kW and 400kW. The charge power was 
set to ‐400kW due to the de‐rating of the PCS. Because the regulation test (test #1) was centered 
around a 50% state‐of‐charge (SOC) point, the first charge cycle was started at that SOC. 
Roundtrip efficiency will be calculated based on the equation below: 
ߟோ௢௨௡ௗ௧௥௜௣ ൌ 
ܣܥ ݌ݎ݋݀ݑܿ݁݀ ݁݊݁ݎ݃ݕ െ ܣݑݔ ܿ݋݊ݏݑ݉݌ݐ݅݋݊ ݅݊ ݀݅ݏ݄ܿܽݎ݃݁ 
ܣܥ ܿ݋݊ݏݑ݉݁݀ ݁݊݁ݎ݃ݕ ൅ ܣݑݔ ܿ݋݊ݏݑ݉݌ݐ݅݋݊ ݅݊ ݄ܿܽݎ݃݁ ൅ ܣݑݔ ܿ݋݊ݏݑ݉݌ݐ݅݋݊ ݅݊ ݈݅݀݁ 
Aux consumption includes everything except PCS, such as pump loss, electronic loss, cooling loss, 
et al. 
Testing was scheduled as follows: (Capacity testing was scheduled to run for 36~48 continuous 
hours) 
 Two cycles of 400 kW charging and 600 kW max power discharging 
 Two cycles of 400 kW charging and 400 kW discharges, the second includes CV discharge 
to get max energy 
 Power Quality Test (to be performed during the peak power points and low power points 
in the peak shaving test) 
 Power quality was tested at 4 points for the duration of ~ 15 minutes: 
 Peak power discharge (600 kW) 
 End of peak power discharge interval 
 Peak power charge (‐400 kW) 
 End of peak power charge interval 
4 Copyright © UniEnergy Technologies, LLC 2014
A WHITE PAPER 
3. Ramping (sine wave) 
The California CPUC has mandated 1.325GW of storage by 2020 to overcome projected problems 
with generation and ramping. The duck curve shown below illustrates California’s looming 12GW 
ramping, over‐generation and peaking problem. The most serious aspects of these problems is 
the projected over capacity during mid‐day followed by an extreme ramp up of load of 13 GW in 
3 hours and then followed by a peaking load. A battery could absorb the mid‐day over‐generation 
caused by the high penetration of renewables saving the energy for later use as needed. A 
battery could also supply the ramping power to assist in the regulation activity and then supply 
some of the shortfall during peaking. 
4 
Net Load Curve 
Reduced Ramp 
Battery Output 
3GW/9GWh 
Storage 
6GW Flexible Capacity 
Equivalent performance 
to 12GW of fossil peakers 
3GW/3h storage in 2020: 
 Halve ramping to 
2013 levels 
 Absorb over‐generation 
 Reduce system peak by 
3GW 
and also yield system wide 
 frequency regulation 
 voltage control 
 resiliency 
 black start 
13GW ramp 
in 3 hours 
2GW peak 
in under 3h 
Big changes have 
already started! 
Over-Generation 
The sine wave signal was applied to test the system’s ability to follow a ramping application such 
as the California duck curve. The source of the load command signal was a signal generator which 
generated the signal as shown in the next graphic. The peak of discharge ramping is ‐400kW AC 
(due to PCS de‐rating) for charge and the peak for discharge was 600kW AC. Total energy in 
charging and discharging is equal to the area under the curve, in both charge and discharge, 
which equates to 1.6 MWh and 1.2 MWh respectively in each function. This test was scheduled 
to take about 13 hours. 
5 Copyright © UniEnergy Technologies, LLC 2014
A WHITE PAPER 
Power Ramping Signal 
4. Combined Ramping and Regulation 
The combined ramping and regulation function was tested with no interruption. The charge 
hours were 7 hours (‐400kW charge with regulation), followed by a 4 hours idle period (with 
regulation). Then continue with a discharge for 4 hours (400kW discharge with regulation) and 
another idle interval for 4 hours (with regulation). The total test time is 19 hours. The 
commanded signal is as follows: 
Combined Ramping and Regulation Signal 
6 Copyright © UniEnergy Technologies, LLC 2014
A WHITE PAPER 
5. Power Quality Test 
The power quality test will be carried out during the cycling and tracking. The meter will be set 
up to monitor the power quality. 
Testing as scheduled for the 5‐days of witness testing: 
21‐Jul 22‐Jul 23‐Jul 24‐Jul 25‐Jul 
Monday Tuesday Wednesday Thursday Friday 
0:00 
Capacity 
testing‐ 
400kWCharg 
e/600kW 
Discharge 
for two 
cycles 
(around 24 
hours) 
Capacity 
testing‐ 
400kWCharg 
e/400kW 
Discharge 
for two 
cycles 
Peak shaving 
testing‐Sine 
wave cycling 
for one cycle 
Combined 
function 
1:00 
2:00 
3:00 
4:00 
5:00 
6:00 
7:00 
8:00 
9:00 
10:00 
11:00 
12:00 
13:00 
Combined 
function 
14:00 
Regulation 
15:00 
16:00 
Capacity 
testing‐ 
400kWCharg 
e/600kW 
Discharge 
for two 
cycles 
17:00 
Capacity 
testing‐ 
400kWCharg 
e/400kW 
Discharge 
for two 
cycles 
18:00 
19:00 
20:00 
21:00 
22:00 
23:00 
7 Copyright © UniEnergy Technologies, LLC 2014
A WHITE PAPER 
Witness Testing Results 
All planned testing activities scheduled for witness testing of the Uni.System was completed 
without interruption during the week. Results reported in this section are correlated with the 
numbered test in the preceding test plan. 
1. Regulation 
The regulation control signal from the test plan was directed to the system controller of the 
Uni.System system. The following trace is the resulting response of the system. 
Of particular interest is the accuracy with which the system is tracking the AC command with one 
exception: because the 400 kW limit for the charge mode is present as indicated earlier in this 
report, the system was unable to track the signal for higher power charge commands that 
exceeded the 400 kW limit. This error will be corrected in the upgraded PCS scheduled for 
delivery with the production Uni.System system scheduled for delivery in late summer. 
Another item of interest is the Open Circuit Voltage (OCV), a voltage measurement on the 
electrolyte that very accurately indicates the state‐of‐charge of the battery in real time. In this 
“regulation only” application, the system initially begins operations slightly below the 50 % State 
of Charge (SOC) point, a point that is specifically selected to optimize the energy delivery for 
power dispatch for the energy storage system. The OCV varies slightly around the 45% SOC point 
indicating a changing SOC; however, as expected, there is a “net zero” consumption of energy 
during this 2‐hour regulation demonstration. Test 5, combined ramping and regulation is 
intended to show how the system can be used for regulation while dispatching in multiple modes 
simultaneously taking advantage of the energy available while in a regulation mode. 
8 Copyright © UniEnergy Technologies, LLC 2014
A WHITE PAPER 
The following table summarizes the key data points for the regulation test. 
Regulation Data 
Data Units 
Test Duration 2.0 hr 
Aux Power Consumption 16.3 kWh 
Charged AC Energy 230 kWh 
Discharged AC Energy 185 kWh 
Net Energy Consumed 246.3 kWh 
Net Energy Produced 185 kWh 
AC Efficiency 80.4 % 
Roundtrip Efficiency incl aux loads 75.1 % 
2. Capacity Testing 
Capacity testing consisted of four round trip capacity tests for two different power discharges, 
two at 400 kW charge, 600 kW discharge and two at 400 kW charge and 400 kW discharge. 
Results shown here are for one test of each of the power settings. For each of the two power 
output settings, the two sets of data are very comparable. The system is unable to charge at 600 
kW at this time because of a limit in the charge circuit of the inverter. This charging anomaly is 
scheduled to be corrected prior to deployment to a field demonstration scheduled for early fall, 
2014. All testing proceeded as planned with no unusual or unexpected events. 
During the first cycling stage of the first capacity testing sequence, the system tripped off at very 
near top‐of‐charge. It was noted that the voltage signal had fluctuated noticeably and an 
investigation was initiated to determine the cause of the trip. UET engineers reported the 
following finding and introduced a correction to mitigate any further tripping for all remaining 
tests: 
During the cycling testing we experienced an unexpected shut down of the PCS close to the end 
of the charge cycle near 100% SOC. This seems to have been due to an instability in the DC voltage 
imposed by the constant voltage control mode. The instability was avoided by operating the PCS 
in constant power control mode and relying instead on the integrated voltage limiting function of 
the PCS to maintain stability during high Voltage charging at 100% SOC. 
After this fix was implemented no further trips were experienced. 
9 Copyright © UniEnergy Technologies, LLC 2014
A WHITE PAPER 
The following table summarizes the capacity testing results for a 400 kW charge, 600 kW 
discharge capacity test: 
State 
Time 
h 
Aux 
consumption 
kWh 
Charged 
AC energy 
kWh 
Discharged 
AC energy 
kWh 
Net 
energy 
consumed 
kWh 
Net 
energy 
produced 
kWh 
AC 
efficiency 
% 
Roundtrip 
efficiency 
% 
Idle 0.25 2.1 
Charge 5.82 50.4 
Idle 0.25 1.8 
Discharge 1.95 22.2 
1798 1163 1852 1141 64.7 61.6 
The following graphic shows a full 400 kW charge and 600 kW discharge cycle. Details of power 
levels and efficiencies are shown in the preceding table. There were no remarkable events 
throughout the test cycle. The system operated as predicted. 
The following table summarizes the capacity testing results for a 400 kW charge, 400 kW 
discharge capacity test: 
State 
Time 
h 
Aux 
consumption 
kWh 
Charged 
AC energy 
kWh 
Discharged 
AC energy 
kWh 
Net 
energy 
consumed 
kWh 
Net 
energy 
produced 
kWh 
AC 
efficiency 
% 
Roundtrip 
efficiency 
% 
Idle 0.25 2.1 
Charge 8.25 68.0 
Idle 0.25 1.8 
Discharge 4.73 49.0 
2763 1893 2835 1844 68.5 65.0 
10 Copyright © UniEnergy Technologies, LLC 2014
A WHITE PAPER 
The following graphic shows a full 400 kW charge and 400 kW discharge cycle. Details of power 
levels and efficiencies are shown in the preceding table. There were no remarkable events 
throughout the test cycle. The system operated as predicted. 
This test included a CV voltage discharge to get the max energy, which showed 2.1 MWh for max 
energy (graph below). 
Throughout the four cycles of capacity testing, the system operated continuously interrupted 
only by the trips at near top of charge which are explained earlier in this report. Capacity 
delivered meets all claims and specifications. 
11 Copyright © UniEnergy Technologies, LLC 2014
A WHITE PAPER 
Ramping (Sine wave) 
The following graphic shows the ramping tracking accuracy of the system as it would be applied 
for mitigation following the California duck curve discussed earlier. 
3. Combined Ramping and Regulation 
The following graphic shows the signals generated during combined ramping and regulation 
testing. Regulation was performed during charging, idle and discharging stages. The system 
performed as claimed and as specified showing that multiple applications can be performed 
simultaneously with the Uni.System system. Note the tracking of the SOC throughout the test 
indicating the actual SOC at any given point in time. 
The following table summarizes the performance for the combined ramping and regulation test. 
12 Copyright © UniEnergy Technologies, LLC 2014
A WHITE PAPER 
Combined Ramping and Regulation Data 
Parameter Data Units 
Test Duration 19.8 hr 
Aux Power Consumption 184 kWh 
Charged AC Energy 2824 kWh 
Discharged AC Energy 1961 kWh 
Net Energy Consumed 3008 kWh 
Net Energy Produced 1961 kWh 
AC Efficiency 69.4 % 
Roundtrip Efficiency incl aux loads 65.2 % 
All results meet all system claims and specifications. 
4. Power Quality Test 
Total harmonic distortion (THD) was measured for short periods of time at near top of charge, 
near the start of a discharge, near the end of a discharge and at near the start of charge during 
the peak shaving (sine wave) test sequence. The following table shows THD for an entire cycle 
showing the gradual increase in un‐normalized THD as the system moves through lower powers 
in both charge and discharge. Normalized THD is shown in the last column. 
THD / % 
AC power Phase 1 Phase 2 Phase 3 Average of 3 phases Normalized 
‐417.37 5.69 6.97 6.33 6.33 4.40 
‐401.14 6.09 7.42 6.73 6.75 4.51 
‐350.93 6.96 8.52 7.55 7.68 4.49 
‐301.21 8.25 9.94 8.75 8.98 4.51 
‐250.16 9.72 11.93 10.14 10.60 4.42 
‐200.84 11.12 13.70 11.51 12.11 4.05 
‐151.11 14.13 17.40 14.61 15.38 3.87 
‐101.37 20.15 24.69 20.82 21.89 3.70 
‐51.63 36.85 45.60 36.97 39.81 3.43 
52.19 49.64 52.69 45.39 49.24 4.28 
104.52 23.95 25.38 22.30 23.88 4.16 
149.38 16.37 17.28 15.27 16.31 4.06 
201.71 11.89 12.31 10.87 11.69 3.93 
252.34 9.98 10.39 9.18 9.85 4.14 
298.32 8.39 8.67 7.65 8.24 4.10 
350.88 7.33 7.59 6.65 7.19 4.20 
402.21 6.51 6.68 5.81 6.33 4.25 
451.93 5.78 5.91 5.11 5.60 4.22 
499.15 4.92 5.06 4.36 4.78 3.98 
549.64 4.41 4.56 3.94 4.30 3.94 
587.99 4.67 4.82 4.41 4.63 4.54 
13 Copyright © UniEnergy Technologies, LLC 2014
A WHITE PAPER 
The graphics shown here are derived from the table on the preceding page. Harmonics 
generated are well within tolerance as shown. Note that harmonics are more prevalent at power 
levels approaching lowest levels as shown in these graphics. 
This photo shows the 
voltage waveforms for 
the 3 phases at near mid‐charge 
taken from the 
isolation transformer 
secondary during a 
capacity test cycle. 
Although there is some 
apparent distortion, it is 
insignificant and has little 
impact on the output 
voltage power quality. 
THD during this period 
was approximately 4.35 
to 4.55. 
14 Copyright © UniEnergy Technologies, LLC 2014
A WHITE PAPER 
Strengths and Weaknesses of Uni.System 
In Witness Testing 
Weaknesses: The only weakness I have seen in Uni.System is that it has not been field 
demonstrated in a utility application. That will be the final test for this emerging technology 
Strengths: There are many strong points in the tested Uni.System system. Some of the more 
important points are enumerated here: 
1. Since commissioning, the Uni.System has delivered nearly 100 MWh total power, without 
testing interruption to correct deficiencies noted during initial testing of the full scale 
Uni.System system. 
2. With the exception of a system trip at near top of charge early in the capacity testing, all 
components and subsystems operated flawlessly throughout the witness test program 
which ran continuously from noon on Monday through noon on Friday with operator 
intervention only to change testing sequences. 
3. The system exhibited high performance both in full and partial power settings and proved 
to be stable over the complete operational profiles tested. 
4. The system was proven to be able to operate in multiple applications, delivering both 
energy and power at the same time, with no compromise in performance. 
5. The strong UniEnergy design team consists of electrochemists and engineers with the 
necessary skills and attitude to bring the Uni.System development project to a successful 
completion. In my opinion, their efforts will result in the near term deployment of a fully 
qualified commercial product for the utility scale energy storage market. 
Conclusions 
Throughout the 5‐day witness testing program, the Uni.System operated continuously under the 
several witness test protocols scheduled with no interruptions in test operations. However; one 
event occurred that was not in the test plan providing an opportunity to confirm the functionality 
of the spill monitoring system in each of the eight electrolyte tanks. An unexpected overnight 
rainstorm occurred with the top covers of the container open allowing rain to collect in the top 
of the electrolyte service area which is continuously monitored for any liquid which might be 
present. Every spill monitor sensed the rain that gathered in the service area which resulted in 
the shutdown of all system pumps showing that the spill sensor subsystem operated as specified. 
Throughout the 5‐day testing program, no operational issues occurred which compromised the 
uninterrupted witness testing plan. All tests were successfully completed and all data correlated 
to expected results. In my opinion, with the updated PCS which will eliminate the 400 kW 
charging limit issues, the Uni.System system should be fully capable of meeting all application 
specifications and ready for a complete field demonstration program. 
15 Copyright © UniEnergy Technologies, LLC 2014
A WHITE PAPER 
Author Biography 
Garth P. Corey, retired from Sandia National Laboratories in Nov, 2006 as a Principal Member of 
the Technical Staff. During his tenure at Sandia, he had project management responsibilities with 
the Energy Infrastructure and Distributed Energy Resources Department. Most of his Sandia 
career was dedicated to communicating his system engineering and battery system management 
knowledge to engineers involved in the integration of various energy storage technologies with 
the balance of plant needed for the development of a successful operational energy storage 
system. 
During his more than 15 years at Sandia, Garth was involved in high technology energy storage 
R&D projects and energy storage systems development. He managed projects that spanned the 
utility scale energy storage arena including flywheels and ultracapacitor systems; sodium sulfur, 
nickel cadmium, lead acid, (including advanced lead‐acid technologies), and lithium ion batteries; 
and several flow battery technologies. Much of his time was dedicated to assisting Sandia 
Renewable Power engineers in the proper integration of batteries in both off‐grid and grid‐tied 
Photovoltaic systems. Since leaving Sandia, Garth has continued to stay current on new energy 
storage systems development. 
Garth is an internationally recognized subject matter expert in utility scale energy storage 
applications and systems and is frequently sought out to provide expert advice on emerging 
energy storage systems and energy storage device development and deployment. He is also very 
active in conducting technology due diligence investigations to determine the status of emerging 
energy storage technologies. He is a member of the IEEE Power and Energy Society and is active 
in balloting energy storage related standards. 
16 Copyright © UniEnergy Technologies, LLC 2014

More Related Content

What's hot

SungPilOe_PhD_Thesis_Presentation
SungPilOe_PhD_Thesis_PresentationSungPilOe_PhD_Thesis_Presentation
SungPilOe_PhD_Thesis_PresentationSung Pil Oe
 
Modeling & Analysis of 31 Bus Power System using Software simulation in PSAT ...
Modeling & Analysis of 31 Bus Power System using Software simulation in PSAT ...Modeling & Analysis of 31 Bus Power System using Software simulation in PSAT ...
Modeling & Analysis of 31 Bus Power System using Software simulation in PSAT ...nikhilkulk21
 
Study of the impact on the protection plan of a pv production integrated to t...
Study of the impact on the protection plan of a pv production integrated to t...Study of the impact on the protection plan of a pv production integrated to t...
Study of the impact on the protection plan of a pv production integrated to t...IAEME Publication
 
IRJET- Design Simulation and Control of Utility Grid Connected Solar Photovol...
IRJET- Design Simulation and Control of Utility Grid Connected Solar Photovol...IRJET- Design Simulation and Control of Utility Grid Connected Solar Photovol...
IRJET- Design Simulation and Control of Utility Grid Connected Solar Photovol...IRJET Journal
 
Load Flow Analysis of 66 kV substation using ETAP Software
Load Flow Analysis of 66 kV substation using ETAP SoftwareLoad Flow Analysis of 66 kV substation using ETAP Software
Load Flow Analysis of 66 kV substation using ETAP SoftwareIRJET Journal
 
Grid fault Control Scheme for Peak Current Reduction in Photovoltaic Inverte...
Grid fault Control Scheme for Peak Current Reduction in  Photovoltaic Inverte...Grid fault Control Scheme for Peak Current Reduction in  Photovoltaic Inverte...
Grid fault Control Scheme for Peak Current Reduction in Photovoltaic Inverte...IJMER
 
A Matlab/Simulink Model for the control scheme utilized to improve power qual...
A Matlab/Simulink Model for the control scheme utilized to improve power qual...A Matlab/Simulink Model for the control scheme utilized to improve power qual...
A Matlab/Simulink Model for the control scheme utilized to improve power qual...AM Publications
 
Transient stability analysis of the ieee 9 bus electric power system pgmslm
Transient stability analysis of the ieee 9 bus electric power system pgmslmTransient stability analysis of the ieee 9 bus electric power system pgmslm
Transient stability analysis of the ieee 9 bus electric power system pgmslmHarish PG
 
Analytics for utility-operated lithium-ion energy storage
Analytics for utility-operated lithium-ion energy storageAnalytics for utility-operated lithium-ion energy storage
Analytics for utility-operated lithium-ion energy storageDavid Ingram
 
Analysis of Low Voltage Ride through Capability of FSIG Based Wind Farm using...
Analysis of Low Voltage Ride through Capability of FSIG Based Wind Farm using...Analysis of Low Voltage Ride through Capability of FSIG Based Wind Farm using...
Analysis of Low Voltage Ride through Capability of FSIG Based Wind Farm using...IRJET Journal
 
Nonlinear control strategy of single-phase unified power flow controller
Nonlinear control strategy of single-phase unified power flow controller Nonlinear control strategy of single-phase unified power flow controller
Nonlinear control strategy of single-phase unified power flow controller IJECEIAES
 
Effects of the Droop Speed Governor and Automatic Generation Control AGC on G...
Effects of the Droop Speed Governor and Automatic Generation Control AGC on G...Effects of the Droop Speed Governor and Automatic Generation Control AGC on G...
Effects of the Droop Speed Governor and Automatic Generation Control AGC on G...IJAPEJOURNAL
 

What's hot (20)

19 schoeder grid stability support for ieee sandia labs symposium
19 schoeder grid stability support for ieee sandia labs symposium19 schoeder grid stability support for ieee sandia labs symposium
19 schoeder grid stability support for ieee sandia labs symposium
 
SungPilOe_PhD_Thesis_Presentation
SungPilOe_PhD_Thesis_PresentationSungPilOe_PhD_Thesis_Presentation
SungPilOe_PhD_Thesis_Presentation
 
Advanced WEC Controls Webinar June 2016
Advanced WEC Controls Webinar June 2016Advanced WEC Controls Webinar June 2016
Advanced WEC Controls Webinar June 2016
 
16 lave 2016_pv_grid_integration_workshop_lave3_sand
16 lave 2016_pv_grid_integration_workshop_lave3_sand16 lave 2016_pv_grid_integration_workshop_lave3_sand
16 lave 2016_pv_grid_integration_workshop_lave3_sand
 
Modeling & Analysis of 31 Bus Power System using Software simulation in PSAT ...
Modeling & Analysis of 31 Bus Power System using Software simulation in PSAT ...Modeling & Analysis of 31 Bus Power System using Software simulation in PSAT ...
Modeling & Analysis of 31 Bus Power System using Software simulation in PSAT ...
 
03 broderick qsts_sand2016-4697 c
03 broderick qsts_sand2016-4697 c03 broderick qsts_sand2016-4697 c
03 broderick qsts_sand2016-4697 c
 
Fg25969973
Fg25969973Fg25969973
Fg25969973
 
2014 PV Distribution System Modeling Workshop: IEEE Test Feeders for Advanced...
2014 PV Distribution System Modeling Workshop: IEEE Test Feeders for Advanced...2014 PV Distribution System Modeling Workshop: IEEE Test Feeders for Advanced...
2014 PV Distribution System Modeling Workshop: IEEE Test Feeders for Advanced...
 
Study of the impact on the protection plan of a pv production integrated to t...
Study of the impact on the protection plan of a pv production integrated to t...Study of the impact on the protection plan of a pv production integrated to t...
Study of the impact on the protection plan of a pv production integrated to t...
 
13 tansy ssa grid int @ epri_sandia 2016
13 tansy ssa grid int @ epri_sandia 201613 tansy ssa grid int @ epri_sandia 2016
13 tansy ssa grid int @ epri_sandia 2016
 
IRJET- Design Simulation and Control of Utility Grid Connected Solar Photovol...
IRJET- Design Simulation and Control of Utility Grid Connected Solar Photovol...IRJET- Design Simulation and Control of Utility Grid Connected Solar Photovol...
IRJET- Design Simulation and Control of Utility Grid Connected Solar Photovol...
 
Load Flow Analysis of 66 kV substation using ETAP Software
Load Flow Analysis of 66 kV substation using ETAP SoftwareLoad Flow Analysis of 66 kV substation using ETAP Software
Load Flow Analysis of 66 kV substation using ETAP Software
 
Grid fault Control Scheme for Peak Current Reduction in Photovoltaic Inverte...
Grid fault Control Scheme for Peak Current Reduction in  Photovoltaic Inverte...Grid fault Control Scheme for Peak Current Reduction in  Photovoltaic Inverte...
Grid fault Control Scheme for Peak Current Reduction in Photovoltaic Inverte...
 
A Matlab/Simulink Model for the control scheme utilized to improve power qual...
A Matlab/Simulink Model for the control scheme utilized to improve power qual...A Matlab/Simulink Model for the control scheme utilized to improve power qual...
A Matlab/Simulink Model for the control scheme utilized to improve power qual...
 
2014 PV Distribution System Modeling Workshop: Determining Recommended Settin...
2014 PV Distribution System Modeling Workshop: Determining Recommended Settin...2014 PV Distribution System Modeling Workshop: Determining Recommended Settin...
2014 PV Distribution System Modeling Workshop: Determining Recommended Settin...
 
Transient stability analysis of the ieee 9 bus electric power system pgmslm
Transient stability analysis of the ieee 9 bus electric power system pgmslmTransient stability analysis of the ieee 9 bus electric power system pgmslm
Transient stability analysis of the ieee 9 bus electric power system pgmslm
 
Analytics for utility-operated lithium-ion energy storage
Analytics for utility-operated lithium-ion energy storageAnalytics for utility-operated lithium-ion energy storage
Analytics for utility-operated lithium-ion energy storage
 
Analysis of Low Voltage Ride through Capability of FSIG Based Wind Farm using...
Analysis of Low Voltage Ride through Capability of FSIG Based Wind Farm using...Analysis of Low Voltage Ride through Capability of FSIG Based Wind Farm using...
Analysis of Low Voltage Ride through Capability of FSIG Based Wind Farm using...
 
Nonlinear control strategy of single-phase unified power flow controller
Nonlinear control strategy of single-phase unified power flow controller Nonlinear control strategy of single-phase unified power flow controller
Nonlinear control strategy of single-phase unified power flow controller
 
Effects of the Droop Speed Governor and Automatic Generation Control AGC on G...
Effects of the Droop Speed Governor and Automatic Generation Control AGC on G...Effects of the Droop Speed Governor and Automatic Generation Control AGC on G...
Effects of the Droop Speed Governor and Automatic Generation Control AGC on G...
 

Similar to UET Witness Test Report-Public Version

IRJET- STATCOM Enabled Modified iUPQC Controller
IRJET- STATCOM Enabled Modified iUPQC ControllerIRJET- STATCOM Enabled Modified iUPQC Controller
IRJET- STATCOM Enabled Modified iUPQC ControllerIRJET Journal
 
IRJET- Simple and Efficient Control Method for Battery Charging in High Penet...
IRJET- Simple and Efficient Control Method for Battery Charging in High Penet...IRJET- Simple and Efficient Control Method for Battery Charging in High Penet...
IRJET- Simple and Efficient Control Method for Battery Charging in High Penet...IRJET Journal
 
Data-driven Modelling of Prognostics of Lithium-ion Batteries Using LSTM
Data-driven Modelling of Prognostics of Lithium-ion Batteries Using LSTMData-driven Modelling of Prognostics of Lithium-ion Batteries Using LSTM
Data-driven Modelling of Prognostics of Lithium-ion Batteries Using LSTMIRJET Journal
 
Iirdem mitigation of voltage collapse at davanagere receiving station
Iirdem mitigation of voltage collapse at davanagere receiving stationIirdem mitigation of voltage collapse at davanagere receiving station
Iirdem mitigation of voltage collapse at davanagere receiving stationIaetsd Iaetsd
 
Yunasko methodology
Yunasko methodologyYunasko methodology
Yunasko methodologyYunasko
 
Ultracapacitor Charging Methods
Ultracapacitor Charging MethodsUltracapacitor Charging Methods
Ultracapacitor Charging MethodsIRJET Journal
 
Fp40 r catalogue-uk-rev.0-01-2013
Fp40 r catalogue-uk-rev.0-01-2013Fp40 r catalogue-uk-rev.0-01-2013
Fp40 r catalogue-uk-rev.0-01-2013Đặng Hảo
 
Development of Power Signal Distributor for Electronic Power Meters
Development of Power Signal Distributor for Electronic Power MetersDevelopment of Power Signal Distributor for Electronic Power Meters
Development of Power Signal Distributor for Electronic Power MetersIJAEMSJORNAL
 
DigSILENT PF - 01 pilot project palau
DigSILENT PF - 01 pilot project palauDigSILENT PF - 01 pilot project palau
DigSILENT PF - 01 pilot project palauHimmelstern
 
9i9 determination-of-bus-voltages-libre
9i9 determination-of-bus-voltages-libre9i9 determination-of-bus-voltages-libre
9i9 determination-of-bus-voltages-libreAbanihi
 
2017 Atlanta Regional User Seminar - Using OPAL-RT Real-Time Simulation and H...
2017 Atlanta Regional User Seminar - Using OPAL-RT Real-Time Simulation and H...2017 Atlanta Regional User Seminar - Using OPAL-RT Real-Time Simulation and H...
2017 Atlanta Regional User Seminar - Using OPAL-RT Real-Time Simulation and H...OPAL-RT TECHNOLOGIES
 
Development of a power factor model for power sysytem loads
Development of a power factor model for power sysytem loadsDevelopment of a power factor model for power sysytem loads
Development of a power factor model for power sysytem loadstheijes
 
Review on Different Time Domain Controlling Technique for UPQC
Review on Different Time Domain Controlling Technique for UPQCReview on Different Time Domain Controlling Technique for UPQC
Review on Different Time Domain Controlling Technique for UPQCIRJET Journal
 
Product: Power Factor & Harmonics: StacoVAR: Let's Discuss Power Factor Corre...
Product: Power Factor & Harmonics: StacoVAR: Let's Discuss Power Factor Corre...Product: Power Factor & Harmonics: StacoVAR: Let's Discuss Power Factor Corre...
Product: Power Factor & Harmonics: StacoVAR: Let's Discuss Power Factor Corre...Staco Energy
 
Power Quality Improvement Using FACT Devices
Power Quality Improvement Using FACT DevicesPower Quality Improvement Using FACT Devices
Power Quality Improvement Using FACT DevicesIJMER
 
VOLTAGE STABILITY IN NIGERIA 330KV INTEGRATED 52 BUS POWER NETWORK USING PATT...
VOLTAGE STABILITY IN NIGERIA 330KV INTEGRATED 52 BUS POWER NETWORK USING PATT...VOLTAGE STABILITY IN NIGERIA 330KV INTEGRATED 52 BUS POWER NETWORK USING PATT...
VOLTAGE STABILITY IN NIGERIA 330KV INTEGRATED 52 BUS POWER NETWORK USING PATT...Onyebuchi nosiri
 
Battery report - FirstGroup
Battery report - FirstGroupBattery report - FirstGroup
Battery report - FirstGroupJing Deng
 

Similar to UET Witness Test Report-Public Version (20)

IRJET- STATCOM Enabled Modified iUPQC Controller
IRJET- STATCOM Enabled Modified iUPQC ControllerIRJET- STATCOM Enabled Modified iUPQC Controller
IRJET- STATCOM Enabled Modified iUPQC Controller
 
IRJET- Simple and Efficient Control Method for Battery Charging in High Penet...
IRJET- Simple and Efficient Control Method for Battery Charging in High Penet...IRJET- Simple and Efficient Control Method for Battery Charging in High Penet...
IRJET- Simple and Efficient Control Method for Battery Charging in High Penet...
 
Data-driven Modelling of Prognostics of Lithium-ion Batteries Using LSTM
Data-driven Modelling of Prognostics of Lithium-ion Batteries Using LSTMData-driven Modelling of Prognostics of Lithium-ion Batteries Using LSTM
Data-driven Modelling of Prognostics of Lithium-ion Batteries Using LSTM
 
Eo34861869
Eo34861869Eo34861869
Eo34861869
 
Iirdem mitigation of voltage collapse at davanagere receiving station
Iirdem mitigation of voltage collapse at davanagere receiving stationIirdem mitigation of voltage collapse at davanagere receiving station
Iirdem mitigation of voltage collapse at davanagere receiving station
 
Yunasko methodology
Yunasko methodologyYunasko methodology
Yunasko methodology
 
Ultracapacitor Charging Methods
Ultracapacitor Charging MethodsUltracapacitor Charging Methods
Ultracapacitor Charging Methods
 
Fp40 r catalogue-uk-rev.0-01-2013
Fp40 r catalogue-uk-rev.0-01-2013Fp40 r catalogue-uk-rev.0-01-2013
Fp40 r catalogue-uk-rev.0-01-2013
 
Development of Power Signal Distributor for Electronic Power Meters
Development of Power Signal Distributor for Electronic Power MetersDevelopment of Power Signal Distributor for Electronic Power Meters
Development of Power Signal Distributor for Electronic Power Meters
 
DigSILENT PF - 01 pilot project palau
DigSILENT PF - 01 pilot project palauDigSILENT PF - 01 pilot project palau
DigSILENT PF - 01 pilot project palau
 
9i9 determination-of-bus-voltages-libre
9i9 determination-of-bus-voltages-libre9i9 determination-of-bus-voltages-libre
9i9 determination-of-bus-voltages-libre
 
2017 Atlanta Regional User Seminar - Using OPAL-RT Real-Time Simulation and H...
2017 Atlanta Regional User Seminar - Using OPAL-RT Real-Time Simulation and H...2017 Atlanta Regional User Seminar - Using OPAL-RT Real-Time Simulation and H...
2017 Atlanta Regional User Seminar - Using OPAL-RT Real-Time Simulation and H...
 
Development of a power factor model for power sysytem loads
Development of a power factor model for power sysytem loadsDevelopment of a power factor model for power sysytem loads
Development of a power factor model for power sysytem loads
 
Review on Different Time Domain Controlling Technique for UPQC
Review on Different Time Domain Controlling Technique for UPQCReview on Different Time Domain Controlling Technique for UPQC
Review on Different Time Domain Controlling Technique for UPQC
 
Product: Power Factor & Harmonics: StacoVAR: Let's Discuss Power Factor Corre...
Product: Power Factor & Harmonics: StacoVAR: Let's Discuss Power Factor Corre...Product: Power Factor & Harmonics: StacoVAR: Let's Discuss Power Factor Corre...
Product: Power Factor & Harmonics: StacoVAR: Let's Discuss Power Factor Corre...
 
Hioki solution car_industry_ denkei
Hioki solution car_industry_ denkeiHioki solution car_industry_ denkei
Hioki solution car_industry_ denkei
 
Power Quality Improvement Using FACT Devices
Power Quality Improvement Using FACT DevicesPower Quality Improvement Using FACT Devices
Power Quality Improvement Using FACT Devices
 
VOLTAGE STABILITY IN NIGERIA 330KV INTEGRATED 52 BUS POWER NETWORK USING PATT...
VOLTAGE STABILITY IN NIGERIA 330KV INTEGRATED 52 BUS POWER NETWORK USING PATT...VOLTAGE STABILITY IN NIGERIA 330KV INTEGRATED 52 BUS POWER NETWORK USING PATT...
VOLTAGE STABILITY IN NIGERIA 330KV INTEGRATED 52 BUS POWER NETWORK USING PATT...
 
Battery report - FirstGroup
Battery report - FirstGroupBattery report - FirstGroup
Battery report - FirstGroup
 
CSTEP BORRERO R poster
CSTEP BORRERO R posterCSTEP BORRERO R poster
CSTEP BORRERO R poster
 

UET Witness Test Report-Public Version

  • 1. A WHITE PAPER Witness Testing of the UniEnergy Technologies Uni.System™ Utility Scale Energy Storage System COMMISSIONED BY UniEnergy Technologies Mukilteo, Washington PREPARED BY Garth P. Corey, Consultant Energy Storage Systems Engineer Albuquerque, NM July 31, 2014 1 Copyright © UniEnergy Technologies, LLC 2014
  • 2. A WHITE PAPER Introduction UniEnergy has commissioned me, a third party energy storage systems engineer, to produce a white paper reporting the results of witness testing for the Uni.System™ Vanadium Redox Flow Battery (VFB) onsite at the UET facilities in Mukilteo, Washington during the week of 21‐25 July, 2014. Specifications of the Uni.System VFB as tested are as follows: SPECIFICATIONS OF UNI.SYSTEM™ Component Specification Number of modules per battery (20 ft. containers) 4 Stacks per module 3 Voltage window 450~986 VDC Current ‐1000~1000 ADC Electrolyte volume 23 m3 per battery module Operating temperature range ‐10~55 °C PCS power ‐600~600 kW (see following charge profile) The following photograph shows the 500 kW, 2 MWh Uni.System as installed at the UniEnergy Technologies facility in Mukilteo, Washington. The system consists of four each 20 ft. modules and one each 20 ft. electronics container. The system ran continuously throughout the testing activities with no down‐time. Human intervention was needed only for the purpose of activating the various tests reported here. 2 Copyright © UniEnergy Technologies, LLC 2014
  • 3. A WHITE PAPER Because of power limitations of the current Power Conditioning System (PCS), the maximum power available for charging is 400 kW; the maximum power available for discharging is 600 kW. The following graphic shows the limits in voltage at various states of charge. This limitation did not impact the results of the witness test and is scheduled to be addressed in the production version of the Uni.System system so that the maximum power available for discharging and charging will be 600 kW for both functions. PCS CHARGE PROFILE Third Party Witness Test Plan Witness testing was planned for the following five utility scale application areas: 1. Regulation Signal “Aggressive” was employed for this testing. The signal is consistent with the PNNL testing protocol. The starting SOC was controlled around 50%. The duration of regulation testing is scheduled for 2h. 3 Copyright © UniEnergy Technologies, LLC 2014
  • 4. A WHITE PAPER Regulation Signal 2. Capacity Testing The capacity testing included two discharge powers: 600kW and 400kW. The charge power was set to ‐400kW due to the de‐rating of the PCS. Because the regulation test (test #1) was centered around a 50% state‐of‐charge (SOC) point, the first charge cycle was started at that SOC. Roundtrip efficiency will be calculated based on the equation below: ߟோ௢௨௡ௗ௧௥௜௣ ൌ ܣܥ ݌ݎ݋݀ݑܿ݁݀ ݁݊݁ݎ݃ݕ െ ܣݑݔ ܿ݋݊ݏݑ݉݌ݐ݅݋݊ ݅݊ ݀݅ݏ݄ܿܽݎ݃݁ ܣܥ ܿ݋݊ݏݑ݉݁݀ ݁݊݁ݎ݃ݕ ൅ ܣݑݔ ܿ݋݊ݏݑ݉݌ݐ݅݋݊ ݅݊ ݄ܿܽݎ݃݁ ൅ ܣݑݔ ܿ݋݊ݏݑ݉݌ݐ݅݋݊ ݅݊ ݈݅݀݁ Aux consumption includes everything except PCS, such as pump loss, electronic loss, cooling loss, et al. Testing was scheduled as follows: (Capacity testing was scheduled to run for 36~48 continuous hours)  Two cycles of 400 kW charging and 600 kW max power discharging  Two cycles of 400 kW charging and 400 kW discharges, the second includes CV discharge to get max energy  Power Quality Test (to be performed during the peak power points and low power points in the peak shaving test)  Power quality was tested at 4 points for the duration of ~ 15 minutes:  Peak power discharge (600 kW)  End of peak power discharge interval  Peak power charge (‐400 kW)  End of peak power charge interval 4 Copyright © UniEnergy Technologies, LLC 2014
  • 5. A WHITE PAPER 3. Ramping (sine wave) The California CPUC has mandated 1.325GW of storage by 2020 to overcome projected problems with generation and ramping. The duck curve shown below illustrates California’s looming 12GW ramping, over‐generation and peaking problem. The most serious aspects of these problems is the projected over capacity during mid‐day followed by an extreme ramp up of load of 13 GW in 3 hours and then followed by a peaking load. A battery could absorb the mid‐day over‐generation caused by the high penetration of renewables saving the energy for later use as needed. A battery could also supply the ramping power to assist in the regulation activity and then supply some of the shortfall during peaking. 4 Net Load Curve Reduced Ramp Battery Output 3GW/9GWh Storage 6GW Flexible Capacity Equivalent performance to 12GW of fossil peakers 3GW/3h storage in 2020:  Halve ramping to 2013 levels  Absorb over‐generation  Reduce system peak by 3GW and also yield system wide  frequency regulation  voltage control  resiliency  black start 13GW ramp in 3 hours 2GW peak in under 3h Big changes have already started! Over-Generation The sine wave signal was applied to test the system’s ability to follow a ramping application such as the California duck curve. The source of the load command signal was a signal generator which generated the signal as shown in the next graphic. The peak of discharge ramping is ‐400kW AC (due to PCS de‐rating) for charge and the peak for discharge was 600kW AC. Total energy in charging and discharging is equal to the area under the curve, in both charge and discharge, which equates to 1.6 MWh and 1.2 MWh respectively in each function. This test was scheduled to take about 13 hours. 5 Copyright © UniEnergy Technologies, LLC 2014
  • 6. A WHITE PAPER Power Ramping Signal 4. Combined Ramping and Regulation The combined ramping and regulation function was tested with no interruption. The charge hours were 7 hours (‐400kW charge with regulation), followed by a 4 hours idle period (with regulation). Then continue with a discharge for 4 hours (400kW discharge with regulation) and another idle interval for 4 hours (with regulation). The total test time is 19 hours. The commanded signal is as follows: Combined Ramping and Regulation Signal 6 Copyright © UniEnergy Technologies, LLC 2014
  • 7. A WHITE PAPER 5. Power Quality Test The power quality test will be carried out during the cycling and tracking. The meter will be set up to monitor the power quality. Testing as scheduled for the 5‐days of witness testing: 21‐Jul 22‐Jul 23‐Jul 24‐Jul 25‐Jul Monday Tuesday Wednesday Thursday Friday 0:00 Capacity testing‐ 400kWCharg e/600kW Discharge for two cycles (around 24 hours) Capacity testing‐ 400kWCharg e/400kW Discharge for two cycles Peak shaving testing‐Sine wave cycling for one cycle Combined function 1:00 2:00 3:00 4:00 5:00 6:00 7:00 8:00 9:00 10:00 11:00 12:00 13:00 Combined function 14:00 Regulation 15:00 16:00 Capacity testing‐ 400kWCharg e/600kW Discharge for two cycles 17:00 Capacity testing‐ 400kWCharg e/400kW Discharge for two cycles 18:00 19:00 20:00 21:00 22:00 23:00 7 Copyright © UniEnergy Technologies, LLC 2014
  • 8. A WHITE PAPER Witness Testing Results All planned testing activities scheduled for witness testing of the Uni.System was completed without interruption during the week. Results reported in this section are correlated with the numbered test in the preceding test plan. 1. Regulation The regulation control signal from the test plan was directed to the system controller of the Uni.System system. The following trace is the resulting response of the system. Of particular interest is the accuracy with which the system is tracking the AC command with one exception: because the 400 kW limit for the charge mode is present as indicated earlier in this report, the system was unable to track the signal for higher power charge commands that exceeded the 400 kW limit. This error will be corrected in the upgraded PCS scheduled for delivery with the production Uni.System system scheduled for delivery in late summer. Another item of interest is the Open Circuit Voltage (OCV), a voltage measurement on the electrolyte that very accurately indicates the state‐of‐charge of the battery in real time. In this “regulation only” application, the system initially begins operations slightly below the 50 % State of Charge (SOC) point, a point that is specifically selected to optimize the energy delivery for power dispatch for the energy storage system. The OCV varies slightly around the 45% SOC point indicating a changing SOC; however, as expected, there is a “net zero” consumption of energy during this 2‐hour regulation demonstration. Test 5, combined ramping and regulation is intended to show how the system can be used for regulation while dispatching in multiple modes simultaneously taking advantage of the energy available while in a regulation mode. 8 Copyright © UniEnergy Technologies, LLC 2014
  • 9. A WHITE PAPER The following table summarizes the key data points for the regulation test. Regulation Data Data Units Test Duration 2.0 hr Aux Power Consumption 16.3 kWh Charged AC Energy 230 kWh Discharged AC Energy 185 kWh Net Energy Consumed 246.3 kWh Net Energy Produced 185 kWh AC Efficiency 80.4 % Roundtrip Efficiency incl aux loads 75.1 % 2. Capacity Testing Capacity testing consisted of four round trip capacity tests for two different power discharges, two at 400 kW charge, 600 kW discharge and two at 400 kW charge and 400 kW discharge. Results shown here are for one test of each of the power settings. For each of the two power output settings, the two sets of data are very comparable. The system is unable to charge at 600 kW at this time because of a limit in the charge circuit of the inverter. This charging anomaly is scheduled to be corrected prior to deployment to a field demonstration scheduled for early fall, 2014. All testing proceeded as planned with no unusual or unexpected events. During the first cycling stage of the first capacity testing sequence, the system tripped off at very near top‐of‐charge. It was noted that the voltage signal had fluctuated noticeably and an investigation was initiated to determine the cause of the trip. UET engineers reported the following finding and introduced a correction to mitigate any further tripping for all remaining tests: During the cycling testing we experienced an unexpected shut down of the PCS close to the end of the charge cycle near 100% SOC. This seems to have been due to an instability in the DC voltage imposed by the constant voltage control mode. The instability was avoided by operating the PCS in constant power control mode and relying instead on the integrated voltage limiting function of the PCS to maintain stability during high Voltage charging at 100% SOC. After this fix was implemented no further trips were experienced. 9 Copyright © UniEnergy Technologies, LLC 2014
  • 10. A WHITE PAPER The following table summarizes the capacity testing results for a 400 kW charge, 600 kW discharge capacity test: State Time h Aux consumption kWh Charged AC energy kWh Discharged AC energy kWh Net energy consumed kWh Net energy produced kWh AC efficiency % Roundtrip efficiency % Idle 0.25 2.1 Charge 5.82 50.4 Idle 0.25 1.8 Discharge 1.95 22.2 1798 1163 1852 1141 64.7 61.6 The following graphic shows a full 400 kW charge and 600 kW discharge cycle. Details of power levels and efficiencies are shown in the preceding table. There were no remarkable events throughout the test cycle. The system operated as predicted. The following table summarizes the capacity testing results for a 400 kW charge, 400 kW discharge capacity test: State Time h Aux consumption kWh Charged AC energy kWh Discharged AC energy kWh Net energy consumed kWh Net energy produced kWh AC efficiency % Roundtrip efficiency % Idle 0.25 2.1 Charge 8.25 68.0 Idle 0.25 1.8 Discharge 4.73 49.0 2763 1893 2835 1844 68.5 65.0 10 Copyright © UniEnergy Technologies, LLC 2014
  • 11. A WHITE PAPER The following graphic shows a full 400 kW charge and 400 kW discharge cycle. Details of power levels and efficiencies are shown in the preceding table. There were no remarkable events throughout the test cycle. The system operated as predicted. This test included a CV voltage discharge to get the max energy, which showed 2.1 MWh for max energy (graph below). Throughout the four cycles of capacity testing, the system operated continuously interrupted only by the trips at near top of charge which are explained earlier in this report. Capacity delivered meets all claims and specifications. 11 Copyright © UniEnergy Technologies, LLC 2014
  • 12. A WHITE PAPER Ramping (Sine wave) The following graphic shows the ramping tracking accuracy of the system as it would be applied for mitigation following the California duck curve discussed earlier. 3. Combined Ramping and Regulation The following graphic shows the signals generated during combined ramping and regulation testing. Regulation was performed during charging, idle and discharging stages. The system performed as claimed and as specified showing that multiple applications can be performed simultaneously with the Uni.System system. Note the tracking of the SOC throughout the test indicating the actual SOC at any given point in time. The following table summarizes the performance for the combined ramping and regulation test. 12 Copyright © UniEnergy Technologies, LLC 2014
  • 13. A WHITE PAPER Combined Ramping and Regulation Data Parameter Data Units Test Duration 19.8 hr Aux Power Consumption 184 kWh Charged AC Energy 2824 kWh Discharged AC Energy 1961 kWh Net Energy Consumed 3008 kWh Net Energy Produced 1961 kWh AC Efficiency 69.4 % Roundtrip Efficiency incl aux loads 65.2 % All results meet all system claims and specifications. 4. Power Quality Test Total harmonic distortion (THD) was measured for short periods of time at near top of charge, near the start of a discharge, near the end of a discharge and at near the start of charge during the peak shaving (sine wave) test sequence. The following table shows THD for an entire cycle showing the gradual increase in un‐normalized THD as the system moves through lower powers in both charge and discharge. Normalized THD is shown in the last column. THD / % AC power Phase 1 Phase 2 Phase 3 Average of 3 phases Normalized ‐417.37 5.69 6.97 6.33 6.33 4.40 ‐401.14 6.09 7.42 6.73 6.75 4.51 ‐350.93 6.96 8.52 7.55 7.68 4.49 ‐301.21 8.25 9.94 8.75 8.98 4.51 ‐250.16 9.72 11.93 10.14 10.60 4.42 ‐200.84 11.12 13.70 11.51 12.11 4.05 ‐151.11 14.13 17.40 14.61 15.38 3.87 ‐101.37 20.15 24.69 20.82 21.89 3.70 ‐51.63 36.85 45.60 36.97 39.81 3.43 52.19 49.64 52.69 45.39 49.24 4.28 104.52 23.95 25.38 22.30 23.88 4.16 149.38 16.37 17.28 15.27 16.31 4.06 201.71 11.89 12.31 10.87 11.69 3.93 252.34 9.98 10.39 9.18 9.85 4.14 298.32 8.39 8.67 7.65 8.24 4.10 350.88 7.33 7.59 6.65 7.19 4.20 402.21 6.51 6.68 5.81 6.33 4.25 451.93 5.78 5.91 5.11 5.60 4.22 499.15 4.92 5.06 4.36 4.78 3.98 549.64 4.41 4.56 3.94 4.30 3.94 587.99 4.67 4.82 4.41 4.63 4.54 13 Copyright © UniEnergy Technologies, LLC 2014
  • 14. A WHITE PAPER The graphics shown here are derived from the table on the preceding page. Harmonics generated are well within tolerance as shown. Note that harmonics are more prevalent at power levels approaching lowest levels as shown in these graphics. This photo shows the voltage waveforms for the 3 phases at near mid‐charge taken from the isolation transformer secondary during a capacity test cycle. Although there is some apparent distortion, it is insignificant and has little impact on the output voltage power quality. THD during this period was approximately 4.35 to 4.55. 14 Copyright © UniEnergy Technologies, LLC 2014
  • 15. A WHITE PAPER Strengths and Weaknesses of Uni.System In Witness Testing Weaknesses: The only weakness I have seen in Uni.System is that it has not been field demonstrated in a utility application. That will be the final test for this emerging technology Strengths: There are many strong points in the tested Uni.System system. Some of the more important points are enumerated here: 1. Since commissioning, the Uni.System has delivered nearly 100 MWh total power, without testing interruption to correct deficiencies noted during initial testing of the full scale Uni.System system. 2. With the exception of a system trip at near top of charge early in the capacity testing, all components and subsystems operated flawlessly throughout the witness test program which ran continuously from noon on Monday through noon on Friday with operator intervention only to change testing sequences. 3. The system exhibited high performance both in full and partial power settings and proved to be stable over the complete operational profiles tested. 4. The system was proven to be able to operate in multiple applications, delivering both energy and power at the same time, with no compromise in performance. 5. The strong UniEnergy design team consists of electrochemists and engineers with the necessary skills and attitude to bring the Uni.System development project to a successful completion. In my opinion, their efforts will result in the near term deployment of a fully qualified commercial product for the utility scale energy storage market. Conclusions Throughout the 5‐day witness testing program, the Uni.System operated continuously under the several witness test protocols scheduled with no interruptions in test operations. However; one event occurred that was not in the test plan providing an opportunity to confirm the functionality of the spill monitoring system in each of the eight electrolyte tanks. An unexpected overnight rainstorm occurred with the top covers of the container open allowing rain to collect in the top of the electrolyte service area which is continuously monitored for any liquid which might be present. Every spill monitor sensed the rain that gathered in the service area which resulted in the shutdown of all system pumps showing that the spill sensor subsystem operated as specified. Throughout the 5‐day testing program, no operational issues occurred which compromised the uninterrupted witness testing plan. All tests were successfully completed and all data correlated to expected results. In my opinion, with the updated PCS which will eliminate the 400 kW charging limit issues, the Uni.System system should be fully capable of meeting all application specifications and ready for a complete field demonstration program. 15 Copyright © UniEnergy Technologies, LLC 2014
  • 16. A WHITE PAPER Author Biography Garth P. Corey, retired from Sandia National Laboratories in Nov, 2006 as a Principal Member of the Technical Staff. During his tenure at Sandia, he had project management responsibilities with the Energy Infrastructure and Distributed Energy Resources Department. Most of his Sandia career was dedicated to communicating his system engineering and battery system management knowledge to engineers involved in the integration of various energy storage technologies with the balance of plant needed for the development of a successful operational energy storage system. During his more than 15 years at Sandia, Garth was involved in high technology energy storage R&D projects and energy storage systems development. He managed projects that spanned the utility scale energy storage arena including flywheels and ultracapacitor systems; sodium sulfur, nickel cadmium, lead acid, (including advanced lead‐acid technologies), and lithium ion batteries; and several flow battery technologies. Much of his time was dedicated to assisting Sandia Renewable Power engineers in the proper integration of batteries in both off‐grid and grid‐tied Photovoltaic systems. Since leaving Sandia, Garth has continued to stay current on new energy storage systems development. Garth is an internationally recognized subject matter expert in utility scale energy storage applications and systems and is frequently sought out to provide expert advice on emerging energy storage systems and energy storage device development and deployment. He is also very active in conducting technology due diligence investigations to determine the status of emerging energy storage technologies. He is a member of the IEEE Power and Energy Society and is active in balloting energy storage related standards. 16 Copyright © UniEnergy Technologies, LLC 2014