SlideShare a Scribd company logo
1 of 10
1
A
Report on Industrial Training
At
A Solution Pharmaceuticals Pvt. Ltd.
SUBMITTED BY
Tushar N. Sonawane
DEPARTMENT OF BIOTECHNOLOGY
Shram Sadhana Bombay Trust's
COLLEGE OF ENGINEERING AND TECHNOLOGY, BAMBHORI
JALGAON-425001.(M.S.)
(2015)
2
ACKNOWLEDGEMENT
I would like to thank A Solution Pharmaceutical Pvt Ltd. for giving me opportunity to
work with your company. I want to express my deep sense of gratitude to Mr. Sandeep
Kurkure. I am thankful to CEO Mr. Nandkumar Chodankar for his valuable guidance and
helping me in each and every aspect of my Industrial Training. I would also like to thank all the
staff members for their support and help.
Yours sincerely,
Tushar N. Sonawane
3
INDEX:
1. Introduction …04
2. Location …04
3. General Process Flowchart …05
4. Raw Material …06
5. Warehouse …06
6. Research And Development …06
7. Quality Control …06
8. Production …06
9. Departments …07
9.1. Research And Development …07
9.2. Quality Control …08
9.3. Production …09
10. Conclusion …10
4
1. INTRODUCTION:
M/s ASolution Pharmaceuticals Private Limited proposes to manufacture Active Pharmaceutical
Ingredients, Intermediates and Specialty chemicals, herbal and natural products, specialty
chemicals, organic chemicals & Formulation of total capacity 3,590 MT/Annum. It is a proposed
manufacturing unit with MPCB consent for Research and Development facility
2. LOCATION:
The manufacturing plant of M/s ASolution Pharmaceuticals Pvt Ltd, is located at plot no: K-3/8
owned by the company in Additional Ambernath, MIDC, Ambernath (E), Dist: Thane,
Maharashtra. The site is 5 km from Ambernath town.
5
3. GENERAL PROCESS FLOWCHART:
Raw Material
Warehouse
Sampling
Quality Control
Production Batch
Intermediate Testing By QC
Product Dispatch
Research& Development
6
4. RAW MATERIAL:
 Raw material is nothing but the starting material for the production.
 It can be water, solvents or reagents.
5. WAREHOUSE:
 It is the storage space available for raw material as well as product.
 A specific number is given to each material.
6. RESEARCHAND DEVELOPMENT:
 A raw material is tested for the various developments.
 The yield can be improved by carrying out the reaction at different parameters.
 The parameters can be temperature, pH.
7. QUALITY CONTROL:
 The quality of the raw materials is checked here.
 The specifications of raw materials are checked at this department.
 The properties of the material are checked.
 If the properties do not match with the specification, then the material is rejected.
 The intermediate testing of product is also done by QC department.
8. PRODUCTION:
 The material from warehouse is sent to production department after testing in quality
control.
 The material is utilized batch wise for the production.
 There are equipments like reactor, centrifuge, multi-mill, dryer, sifter, etc.
7
9. DEPARTMENTS:
9.1 ResearchAnd Development:
 Material is sent to R & D from warehouse.
 A particular batch number is given to each sample.
 Various tests are carried out on the material.
 Highest yielding reaction is selected for the production.
 Chemicals are ordered, analyzed and stored in R & D.
Equipments:
9.1.1 Rota-Vapour:
 It is used for distillation of desired product.
 It works under the vaccum.
 Out of mixture, only desired product remains in the rota flask and remaining compounds
are evaporated under vaccum.
9.1.2 Melting Point Apparatus:
 It is used for determining compounds on the basis of their molecular weight .
 The compound is introduced into the capillary.
 Then the capillary is placed in the silicon oil.
9.1.3 UV Cabinet:
 The equipment is used to check whether the reaction is completed or not.
 A silicon coated strip is used for the purpose.
 Different spots of sample are seen on the strip.
9.1.4 Ultrasonication:
 It is used to dissolve the compound in the solution.
 High frequency ultrasonic waves are generated for the purpose.
8
9.2 Quality Control:
 The samples are tested for various parameters.
 The tests are carried out for moisture content, loss on drying, etc.
 It is the most important department.
 Sample is also sent to QC for intermediate testing.
Equipments:
9.2.1 HPLC:
 High-performance liquid chromatography.
 It is used to separate the components in a mixture.
 Also to identify each component, and to quantify each component.
9.2.2 GC:
 Gas centrifuge.
 It is used in analytical chemistry.
 GC is used for separating and analyzing the compounds that can be vaporized without
decomposition.
 In some situations, GC may used to identify the compound.
9.2.3 Karl FischerTitrator:
 This is used for the moisture determination.
 Small quantities of samples are required.
 The analysis takes very less time.
9
9.3 Production:
 The tested sample is sent to the production department.
 Production is done in batches.
Equipments:
9.3.1 Reactor:
 It is the place where the actual reaction takes place.
 It is made up of different materials.
 Mild Steel Reactor: Alkaline material.
 Stainless Steel Reactor: Alkaline material.
 Glass Line Reactor: Acidic as well as alkaline material.
 Rubber Line Reactor: Acidic materials.
 Hastalloy Reactor: Acidic as well as alkaline material.
9.3.2 Centrifuge:
 It is used for the separation of the product from rest material.
 There are two types of centrifuge.
 Stainless Steel Centrifuge: Alkaline material.
 Hallar Coated Centrifuge: Acidic as well as alkaline material.
9.3.3 Dryer:
 The dryer is used to dry the product.
 Drying is done on the fluidized bed.
 Air is introduced in the dryer from suction pump.
 It is heated and with the help of that heated air, the product is dried.
9.3.4 Multi-Mill:
 It is used to grind the product in desired particle sizes.
 It is very powerful equipment.
 Different particle sizes can be obtained with the help of the multi mill.
10
10. Conclusion:
In such a way I have seen the general manufacturing process of Pharmaceutical
Compounds in A Solution Pvt. Ltd. Ambernath, Mumbai.

More Related Content

What's hot

Aseptic processing
Aseptic processingAseptic processing
Aseptic processing
Shivaram
 
quality control tests for parenterals
quality control tests for parenteralsquality control tests for parenterals
quality control tests for parenterals
Ahmad Ali
 

What's hot (20)

Autoclave Steam Sterilizer - Pharmaceutical
Autoclave Steam Sterilizer - PharmaceuticalAutoclave Steam Sterilizer - Pharmaceutical
Autoclave Steam Sterilizer - Pharmaceutical
 
SMALL VOLUME PARENTRALS , MANUFACTURING AND QUALITY CONTROL
SMALL VOLUME PARENTRALS , MANUFACTURING AND QUALITY CONTROLSMALL VOLUME PARENTRALS , MANUFACTURING AND QUALITY CONTROL
SMALL VOLUME PARENTRALS , MANUFACTURING AND QUALITY CONTROL
 
Instrument of micro lab
Instrument of micro labInstrument of micro lab
Instrument of micro lab
 
Parentrals , preparation and evaluation
Parentrals , preparation and evaluationParentrals , preparation and evaluation
Parentrals , preparation and evaluation
 
Pilot plant scale up for parenteral dosage form
Pilot plant scale up for parenteral dosage formPilot plant scale up for parenteral dosage form
Pilot plant scale up for parenteral dosage form
 
Validation of sterilization methods
Validation of sterilization methodsValidation of sterilization methods
Validation of sterilization methods
 
validation of Sterilization process
validation of Sterilization  processvalidation of Sterilization  process
validation of Sterilization process
 
Quality control tests for parenterals ppt
Quality  control  tests  for  parenterals pptQuality  control  tests  for  parenterals ppt
Quality control tests for parenterals ppt
 
Aseptic processing
Aseptic processingAseptic processing
Aseptic processing
 
D7 Laundry Sanitizer and Disinfectant Test
D7 Laundry Sanitizer and Disinfectant Test D7 Laundry Sanitizer and Disinfectant Test
D7 Laundry Sanitizer and Disinfectant Test
 
Quality control of parentrals
Quality control of parentralsQuality control of parentrals
Quality control of parentrals
 
Steam sterilization monitoring
Steam sterilization monitoringSteam sterilization monitoring
Steam sterilization monitoring
 
quality control tests for parenterals
quality control tests for parenteralsquality control tests for parenterals
quality control tests for parenterals
 
Aseptic process tech & advanced sterile product mfg rashmi nasare
Aseptic process tech & advanced sterile product mfg  rashmi nasareAseptic process tech & advanced sterile product mfg  rashmi nasare
Aseptic process tech & advanced sterile product mfg rashmi nasare
 
Ipqc test for injectables
Ipqc test for injectablesIpqc test for injectables
Ipqc test for injectables
 
Manufacturing of Sterile Products Session 1 of 3-OA-13 May 2015
Manufacturing of Sterile Products Session 1 of 3-OA-13 May 2015Manufacturing of Sterile Products Session 1 of 3-OA-13 May 2015
Manufacturing of Sterile Products Session 1 of 3-OA-13 May 2015
 
QUALITY CONTROL OF PARENTERALS,STERILE PRODUCT
QUALITY CONTROL OF PARENTERALS,STERILE PRODUCTQUALITY CONTROL OF PARENTERALS,STERILE PRODUCT
QUALITY CONTROL OF PARENTERALS,STERILE PRODUCT
 
Rands Instruments Company, Chennai, Deep Freezer
Rands Instruments Company, Chennai, Deep FreezerRands Instruments Company, Chennai, Deep Freezer
Rands Instruments Company, Chennai, Deep Freezer
 
IPQC tests for Parenterals
IPQC tests for ParenteralsIPQC tests for Parenterals
IPQC tests for Parenterals
 
Validation of sterilization
Validation of sterilizationValidation of sterilization
Validation of sterilization
 

Viewers also liked (11)

Centrifugation
CentrifugationCentrifugation
Centrifugation
 
Process flow diagram pg
Process flow diagram pgProcess flow diagram pg
Process flow diagram pg
 
Chap3 flow charts
Chap3 flow chartsChap3 flow charts
Chap3 flow charts
 
centrifuge
centrifugecentrifuge
centrifuge
 
Centrifugation
CentrifugationCentrifugation
Centrifugation
 
centrifugation
centrifugationcentrifugation
centrifugation
 
Centrifugation
Centrifugation Centrifugation
Centrifugation
 
Introduction to flowchart
Introduction to flowchartIntroduction to flowchart
Introduction to flowchart
 
Algorithms and Flowcharts
Algorithms and FlowchartsAlgorithms and Flowcharts
Algorithms and Flowcharts
 
Principles and applications of centrifugation ppt
Principles and applications of centrifugation pptPrinciples and applications of centrifugation ppt
Principles and applications of centrifugation ppt
 
Types of centrifuges
Types of centrifugesTypes of centrifuges
Types of centrifuges
 

Similar to Training New

Quality DocumentationDocumentation OverviewThe Q.docx
Quality DocumentationDocumentation OverviewThe Q.docxQuality DocumentationDocumentation OverviewThe Q.docx
Quality DocumentationDocumentation OverviewThe Q.docx
makdul
 
Qualification of membrane filtration apparatus
Qualification of membrane filtration apparatusQualification of membrane filtration apparatus
Qualification of membrane filtration apparatus
PRAVADA
 
EDI Project Report-CC
EDI Project Report-CCEDI Project Report-CC
EDI Project Report-CC
Can Cui
 
A Report on Industrial visit at Chemi drug industry pvt.ltd
A Report on Industrial visit at Chemi drug industry pvt.ltdA Report on Industrial visit at Chemi drug industry pvt.ltd
A Report on Industrial visit at Chemi drug industry pvt.ltd
Nabin Bist
 
process validation of tablets madhu k s
process validation of tablets madhu k sprocess validation of tablets madhu k s
process validation of tablets madhu k s
Madhu Honey
 
Download-manuals-surface water-manual-sw-volume6fieldmanualwqsampling
 Download-manuals-surface water-manual-sw-volume6fieldmanualwqsampling Download-manuals-surface water-manual-sw-volume6fieldmanualwqsampling
Download-manuals-surface water-manual-sw-volume6fieldmanualwqsampling
hydrologywebsite1
 
Download-manuals-surface water-manual-sw-volume6fieldmanualwqsampling
 Download-manuals-surface water-manual-sw-volume6fieldmanualwqsampling Download-manuals-surface water-manual-sw-volume6fieldmanualwqsampling
Download-manuals-surface water-manual-sw-volume6fieldmanualwqsampling
hydrologyproject001
 
Download-manuals-surface water-manual-sw-volume6fieldmanualwqsampling
 Download-manuals-surface water-manual-sw-volume6fieldmanualwqsampling Download-manuals-surface water-manual-sw-volume6fieldmanualwqsampling
Download-manuals-surface water-manual-sw-volume6fieldmanualwqsampling
hydrologyproject001
 
Copy of jimma university institute of engineering and technology
Copy of jimma university institute of engineering and technologyCopy of jimma university institute of engineering and technology
Copy of jimma university institute of engineering and technology
Deginet Yossef
 
Ukesh Simulation Project
Ukesh Simulation ProjectUkesh Simulation Project
Ukesh Simulation Project
Chawal Ukesh
 

Similar to Training New (20)

Quality DocumentationDocumentation OverviewThe Q.docx
Quality DocumentationDocumentation OverviewThe Q.docxQuality DocumentationDocumentation OverviewThe Q.docx
Quality DocumentationDocumentation OverviewThe Q.docx
 
Qualification of membrane filtration apparatus
Qualification of membrane filtration apparatusQualification of membrane filtration apparatus
Qualification of membrane filtration apparatus
 
EDI Project Report-CC
EDI Project Report-CCEDI Project Report-CC
EDI Project Report-CC
 
Sample of a Standard Operating Procedure (SOP) for Cleaning and Sanitizing Ca...
Sample of a Standard Operating Procedure (SOP) for Cleaning and Sanitizing Ca...Sample of a Standard Operating Procedure (SOP) for Cleaning and Sanitizing Ca...
Sample of a Standard Operating Procedure (SOP) for Cleaning and Sanitizing Ca...
 
A Report on Industrial visit at Chemi drug industry pvt.ltd
A Report on Industrial visit at Chemi drug industry pvt.ltdA Report on Industrial visit at Chemi drug industry pvt.ltd
A Report on Industrial visit at Chemi drug industry pvt.ltd
 
BASF FINAL REPORT
BASF FINAL REPORTBASF FINAL REPORT
BASF FINAL REPORT
 
process validation of tablets madhu k s
process validation of tablets madhu k sprocess validation of tablets madhu k s
process validation of tablets madhu k s
 
Contoh protokol validasi metode analisis mikrobiologi #2
Contoh protokol validasi metode analisis mikrobiologi #2Contoh protokol validasi metode analisis mikrobiologi #2
Contoh protokol validasi metode analisis mikrobiologi #2
 
Autoclave validation maliba
Autoclave validation malibaAutoclave validation maliba
Autoclave validation maliba
 
Item 9. Equipment installation, use a maintenance – good practices
Item 9. Equipment installation, use a maintenance – good practicesItem 9. Equipment installation, use a maintenance – good practices
Item 9. Equipment installation, use a maintenance – good practices
 
Pilot plant scale up techniques - industrial pharmacy II
Pilot plant scale up techniques - industrial pharmacy II Pilot plant scale up techniques - industrial pharmacy II
Pilot plant scale up techniques - industrial pharmacy II
 
Validation of dissolution apparatus
Validation of dissolution apparatusValidation of dissolution apparatus
Validation of dissolution apparatus
 
Download-manuals-surface water-manual-sw-volume6fieldmanualwqsampling
 Download-manuals-surface water-manual-sw-volume6fieldmanualwqsampling Download-manuals-surface water-manual-sw-volume6fieldmanualwqsampling
Download-manuals-surface water-manual-sw-volume6fieldmanualwqsampling
 
Download-manuals-surface water-manual-sw-volume6fieldmanualwqsampling
 Download-manuals-surface water-manual-sw-volume6fieldmanualwqsampling Download-manuals-surface water-manual-sw-volume6fieldmanualwqsampling
Download-manuals-surface water-manual-sw-volume6fieldmanualwqsampling
 
Download-manuals-surface water-manual-sw-volume6fieldmanualwqsampling
 Download-manuals-surface water-manual-sw-volume6fieldmanualwqsampling Download-manuals-surface water-manual-sw-volume6fieldmanualwqsampling
Download-manuals-surface water-manual-sw-volume6fieldmanualwqsampling
 
BenchMark Special Stains Product Guide
BenchMark Special Stains Product GuideBenchMark Special Stains Product Guide
BenchMark Special Stains Product Guide
 
Quality control of packaging Material and filling Equipment
Quality control of packaging Material and filling EquipmentQuality control of packaging Material and filling Equipment
Quality control of packaging Material and filling Equipment
 
Copy of jimma university institute of engineering and technology
Copy of jimma university institute of engineering and technologyCopy of jimma university institute of engineering and technology
Copy of jimma university institute of engineering and technology
 
Micro nutrients quality control tests
Micro nutrients quality control testsMicro nutrients quality control tests
Micro nutrients quality control tests
 
Ukesh Simulation Project
Ukesh Simulation ProjectUkesh Simulation Project
Ukesh Simulation Project
 

Training New

  • 1. 1 A Report on Industrial Training At A Solution Pharmaceuticals Pvt. Ltd. SUBMITTED BY Tushar N. Sonawane DEPARTMENT OF BIOTECHNOLOGY Shram Sadhana Bombay Trust's COLLEGE OF ENGINEERING AND TECHNOLOGY, BAMBHORI JALGAON-425001.(M.S.) (2015)
  • 2. 2 ACKNOWLEDGEMENT I would like to thank A Solution Pharmaceutical Pvt Ltd. for giving me opportunity to work with your company. I want to express my deep sense of gratitude to Mr. Sandeep Kurkure. I am thankful to CEO Mr. Nandkumar Chodankar for his valuable guidance and helping me in each and every aspect of my Industrial Training. I would also like to thank all the staff members for their support and help. Yours sincerely, Tushar N. Sonawane
  • 3. 3 INDEX: 1. Introduction …04 2. Location …04 3. General Process Flowchart …05 4. Raw Material …06 5. Warehouse …06 6. Research And Development …06 7. Quality Control …06 8. Production …06 9. Departments …07 9.1. Research And Development …07 9.2. Quality Control …08 9.3. Production …09 10. Conclusion …10
  • 4. 4 1. INTRODUCTION: M/s ASolution Pharmaceuticals Private Limited proposes to manufacture Active Pharmaceutical Ingredients, Intermediates and Specialty chemicals, herbal and natural products, specialty chemicals, organic chemicals & Formulation of total capacity 3,590 MT/Annum. It is a proposed manufacturing unit with MPCB consent for Research and Development facility 2. LOCATION: The manufacturing plant of M/s ASolution Pharmaceuticals Pvt Ltd, is located at plot no: K-3/8 owned by the company in Additional Ambernath, MIDC, Ambernath (E), Dist: Thane, Maharashtra. The site is 5 km from Ambernath town.
  • 5. 5 3. GENERAL PROCESS FLOWCHART: Raw Material Warehouse Sampling Quality Control Production Batch Intermediate Testing By QC Product Dispatch Research& Development
  • 6. 6 4. RAW MATERIAL:  Raw material is nothing but the starting material for the production.  It can be water, solvents or reagents. 5. WAREHOUSE:  It is the storage space available for raw material as well as product.  A specific number is given to each material. 6. RESEARCHAND DEVELOPMENT:  A raw material is tested for the various developments.  The yield can be improved by carrying out the reaction at different parameters.  The parameters can be temperature, pH. 7. QUALITY CONTROL:  The quality of the raw materials is checked here.  The specifications of raw materials are checked at this department.  The properties of the material are checked.  If the properties do not match with the specification, then the material is rejected.  The intermediate testing of product is also done by QC department. 8. PRODUCTION:  The material from warehouse is sent to production department after testing in quality control.  The material is utilized batch wise for the production.  There are equipments like reactor, centrifuge, multi-mill, dryer, sifter, etc.
  • 7. 7 9. DEPARTMENTS: 9.1 ResearchAnd Development:  Material is sent to R & D from warehouse.  A particular batch number is given to each sample.  Various tests are carried out on the material.  Highest yielding reaction is selected for the production.  Chemicals are ordered, analyzed and stored in R & D. Equipments: 9.1.1 Rota-Vapour:  It is used for distillation of desired product.  It works under the vaccum.  Out of mixture, only desired product remains in the rota flask and remaining compounds are evaporated under vaccum. 9.1.2 Melting Point Apparatus:  It is used for determining compounds on the basis of their molecular weight .  The compound is introduced into the capillary.  Then the capillary is placed in the silicon oil. 9.1.3 UV Cabinet:  The equipment is used to check whether the reaction is completed or not.  A silicon coated strip is used for the purpose.  Different spots of sample are seen on the strip. 9.1.4 Ultrasonication:  It is used to dissolve the compound in the solution.  High frequency ultrasonic waves are generated for the purpose.
  • 8. 8 9.2 Quality Control:  The samples are tested for various parameters.  The tests are carried out for moisture content, loss on drying, etc.  It is the most important department.  Sample is also sent to QC for intermediate testing. Equipments: 9.2.1 HPLC:  High-performance liquid chromatography.  It is used to separate the components in a mixture.  Also to identify each component, and to quantify each component. 9.2.2 GC:  Gas centrifuge.  It is used in analytical chemistry.  GC is used for separating and analyzing the compounds that can be vaporized without decomposition.  In some situations, GC may used to identify the compound. 9.2.3 Karl FischerTitrator:  This is used for the moisture determination.  Small quantities of samples are required.  The analysis takes very less time.
  • 9. 9 9.3 Production:  The tested sample is sent to the production department.  Production is done in batches. Equipments: 9.3.1 Reactor:  It is the place where the actual reaction takes place.  It is made up of different materials.  Mild Steel Reactor: Alkaline material.  Stainless Steel Reactor: Alkaline material.  Glass Line Reactor: Acidic as well as alkaline material.  Rubber Line Reactor: Acidic materials.  Hastalloy Reactor: Acidic as well as alkaline material. 9.3.2 Centrifuge:  It is used for the separation of the product from rest material.  There are two types of centrifuge.  Stainless Steel Centrifuge: Alkaline material.  Hallar Coated Centrifuge: Acidic as well as alkaline material. 9.3.3 Dryer:  The dryer is used to dry the product.  Drying is done on the fluidized bed.  Air is introduced in the dryer from suction pump.  It is heated and with the help of that heated air, the product is dried. 9.3.4 Multi-Mill:  It is used to grind the product in desired particle sizes.  It is very powerful equipment.  Different particle sizes can be obtained with the help of the multi mill.
  • 10. 10 10. Conclusion: In such a way I have seen the general manufacturing process of Pharmaceutical Compounds in A Solution Pvt. Ltd. Ambernath, Mumbai.