CURRICULUM VITAE
Muhammad Tofique Material Control Supervisor
Educational Profile:
 EMBA (H R) ( NIMS FAISAL ABAD)2012
 B.A BZU Multan ( Punjab/Pakistan ) 1998
 F.A D.G khan ( Punjab/Pakistan ) 1996
 Metric D.G khan ( Punjab/Pakistan ) 1994
Technical Education Profile:
 Diploma In Computer Sciences (6 months)
 Diploma In Library Science (8 months)
 Certificate of Trine Textile Supervisor
Address for communication:
Life Books College Road
Layyah
E-Mail:-
tofiquesulahri@yahoo.com
lifesulahri@yahoo.com
Contact No Pakistan :-
+92-300-6768476
+92-300- 8619554
Iraq No.
00964-7509872418
.
OBJECTIVE:.
Seeking a result oriented company having a globally competitive environment that is
looking for an ambitious and career conscious person, where a blend of my acquired skills
and education will be utilized on challenging assignments in a creative atmosphere, using
innovative technologies that shell out a steady-paced professional growth to organization
& me.
.
EXTRA SKILLS:.
.
 Inter Net
 Microsoft Office / XP Professional
Responsibilities
 As per your requirements, I have practical experience of working in EPC companies
like AES LAL PIR THERMAL POWER 730 MW,PARCO, WAPDA,ICI,IFC,General Electric
and Skoda
 etc. and have handled jobs related to Petrochemicals, Refineries, Oil & Gas, POWER
PLANTS etc. Good knowledge of Computer Applications with practical experience.
 Presently I am working in IRAQ with PAKISTANEE Company. AEPL OASIS as a
MATERIAL CONTROL SUPERVIOR in its SHATUL BASRA 1250 MW OPEN CYCLE
POWER PROJECT responsible for Preservation of all the material including Equipments,
GAS TURBAIN 1009E GE ,Vessels, Pumps, Piping, Compressors and various other
Packages and Machines
 I have vast experience in Materials Control / Stores Management with very good
knowledge of Procurement, Purchasing and many other fields related to Oil & Gas,
Refineries and Petrochemical Projects and Power Plants with more than 16 years of
experience.
 Very good command on written and spoken English with very good computer skills MS
office, Auto-cad & and I can become familiar with any package within few days.
 Other skills include
Purchasing of Engineering Materials (Purchased Materials like Structural steel, Rebar,
Civil Engg. Materials, Electrical Items, Safety, Machinery, Tools etc, knowledge of
indent raising, Tendering or asking for quotations, Comparative statements, P.O.
Generation etc. 2. Stores Management
 Materials Requirement Planning ( Knowledge of ABC & FSN techniques with a
qualification in Materials management )
 Logistics / ware housing ( Can Economically & Efficiently distribute the required
materials to various locations by assessing most shortest & Feasible Transport Routes
)
 Vendor development ( Good experience of Vendor development – Keeping record of
Reliable vendors, Alternate vendors in case of Emergency, Maintaining good
communication & information )
 Experience of maintaining optimum inventory by ensuring that there is no delay in the
production due to shortage of material. And at the same time making it sure that too
much Material is not accumulated due to which more inventory carrying cost has to be
spent, and also avoid blocking of the company€™s money
 Sufficient knowledge regarding Design, Construction, Erection, and various ASME
codes related to Pipes, Fittings, Valves, Vessels, Equipments, Pumps,
Compressors, Boilers, Turbines and various types of Machines and Materials related to
Oil & Gas, Refineries, Petrochemicals and Power Plants etc.
 Good documentation skills. Can generate all types of progress reports / documentation
work independently
 Calculation of quantities e.g. pipes, fittings, structural steel etc. with the help of drawings.
Required for Petrochemical, Bop, Gas Turbine well as Steam turbines.
 ERECTION & FABRICATION:
Erection & fabrication of pipes, vessels, equipments, Gas turbines 1009E GE & Steam
Turbines ,Hrsg,Water Treatment ,Boilers ,Steel Structure .
Company Name : ALBARIO ENGINEERING (AEPLOASIS BASRA IRAQ)
Client/Project : SHATT AL BASRA POWER PLANT 1250 MW
Designation : Material Control (SUPERVISOR)
Duration : 15-09-2013 T0 TILL DATE
Company Name : ALBARIO ENGINEERING
Client/Project : GUDDU POWER PLANT CCPP KASHMOR 747 MW
Designation : Material Coordinator
Duration : 12-01-2013 T0 10-09-013
Company Name : USMAN CONSTRUCTION & SERVICES
Client/Project : LAL PIR THERMAL POWER 730 MW & PARCO
Designation : Material Coordinator
Duration : 05-04-2010 T0 05-01-2013
Company Name : ALBARIO ENGINEERING
Client/Project : Muridke power plant CCPP 234 MW
Designation : Material Coordinator
Duration : 20-09-2008 to 30-03-2010
Company Name : Descon Engineering
Client/Project : AES Lal Pir Thermal power station 730 MW
Designation : Lead Man
Duration : 10-05-2007 to 13-10-2008
Experience
Company Name : Descon Engineering
Client/Project : Parco OIL REFINERY
Designation : Mech. Fitter
Duration : 05-30-2007 to 12-04 -2007
Company Name : Descon Engineering
Client/Project : PTA plant Karachi
Designation : Mech. Fitter
Duration : Febuary 2007
Company Name : Descon Engineering
Client/Project : AES Lal Pir Thermal power station 730 MW
Designation : Mech. Fitter
Duration : 01-Nov-06 to 27-Dec-2006
Company Name : Descon Engineering
Client/Project : AES Lal Pir Thermal power station 730 MW
Designation : Mech. Fitter
Duration : 03-Sep-2006 to 30-Sep-2006.
Company Name : ATLANTS PURE WATER LAHORE
Client/Project : Atlantis Pure Water
Designation : Mech. Fitter
Duration : 27-July-2006 to 30-Aug-2006.
Company Name : ABRAHAM FIBERS LTD TEXTILE PLANT NO. 1
Client/Project : Abraham Fibers
Designation : Supervisor
Duration : 22-Feb-2006 to 20-July-2006
Company Name : Descon Engineering
Client/Project : AES Lal Pir Thermal power station 730 MW
Designation : Mech. Fitter
Duration : 01-Nov-2005 to 30-Nov-2005
Company Name : Descon Engineering
Client/Project : PTA plant Karachi
Designation : Mech. Fitter
Duration : 01-May-2005 to 31-May-2005.
Company Name : Layyah Sugar Mills Layyah
Client/Project : Layyah Sugar Mills
Designation : Mech. Fitter
Duration : 05-Dec-2004 to 20-April-2005.
Company Name : SSS Company
Client/Project : AES Lal Pir Thermal Power 730 MW
Designation : supervisor
Duration : 27-Oct-1997 to 11-Nov-2004
Personal Profile
Father’s Name Allah Rakha
Date of Birth 01-05-1978
Marital Status Married
Nationality Pakistani
Permanent Address:-
House No.27 Street No,02 Modal
Town Chowk Azam Road Layyah
.

tofique cv up dated

  • 1.
    CURRICULUM VITAE Muhammad TofiqueMaterial Control Supervisor Educational Profile:  EMBA (H R) ( NIMS FAISAL ABAD)2012  B.A BZU Multan ( Punjab/Pakistan ) 1998  F.A D.G khan ( Punjab/Pakistan ) 1996  Metric D.G khan ( Punjab/Pakistan ) 1994 Technical Education Profile:  Diploma In Computer Sciences (6 months)  Diploma In Library Science (8 months)  Certificate of Trine Textile Supervisor Address for communication: Life Books College Road Layyah E-Mail:- tofiquesulahri@yahoo.com lifesulahri@yahoo.com Contact No Pakistan :- +92-300-6768476 +92-300- 8619554 Iraq No. 00964-7509872418 . OBJECTIVE:. Seeking a result oriented company having a globally competitive environment that is looking for an ambitious and career conscious person, where a blend of my acquired skills and education will be utilized on challenging assignments in a creative atmosphere, using innovative technologies that shell out a steady-paced professional growth to organization & me. . EXTRA SKILLS:. .  Inter Net  Microsoft Office / XP Professional Responsibilities
  • 2.
     As peryour requirements, I have practical experience of working in EPC companies like AES LAL PIR THERMAL POWER 730 MW,PARCO, WAPDA,ICI,IFC,General Electric and Skoda  etc. and have handled jobs related to Petrochemicals, Refineries, Oil & Gas, POWER PLANTS etc. Good knowledge of Computer Applications with practical experience.  Presently I am working in IRAQ with PAKISTANEE Company. AEPL OASIS as a MATERIAL CONTROL SUPERVIOR in its SHATUL BASRA 1250 MW OPEN CYCLE POWER PROJECT responsible for Preservation of all the material including Equipments, GAS TURBAIN 1009E GE ,Vessels, Pumps, Piping, Compressors and various other Packages and Machines  I have vast experience in Materials Control / Stores Management with very good knowledge of Procurement, Purchasing and many other fields related to Oil & Gas, Refineries and Petrochemical Projects and Power Plants with more than 16 years of experience.  Very good command on written and spoken English with very good computer skills MS office, Auto-cad & and I can become familiar with any package within few days.  Other skills include Purchasing of Engineering Materials (Purchased Materials like Structural steel, Rebar, Civil Engg. Materials, Electrical Items, Safety, Machinery, Tools etc, knowledge of indent raising, Tendering or asking for quotations, Comparative statements, P.O. Generation etc. 2. Stores Management  Materials Requirement Planning ( Knowledge of ABC & FSN techniques with a qualification in Materials management )  Logistics / ware housing ( Can Economically & Efficiently distribute the required materials to various locations by assessing most shortest & Feasible Transport Routes )  Vendor development ( Good experience of Vendor development – Keeping record of Reliable vendors, Alternate vendors in case of Emergency, Maintaining good communication & information )  Experience of maintaining optimum inventory by ensuring that there is no delay in the production due to shortage of material. And at the same time making it sure that too much Material is not accumulated due to which more inventory carrying cost has to be spent, and also avoid blocking of the company€™s money  Sufficient knowledge regarding Design, Construction, Erection, and various ASME codes related to Pipes, Fittings, Valves, Vessels, Equipments, Pumps, Compressors, Boilers, Turbines and various types of Machines and Materials related to Oil & Gas, Refineries, Petrochemicals and Power Plants etc.  Good documentation skills. Can generate all types of progress reports / documentation work independently
  • 3.
     Calculation ofquantities e.g. pipes, fittings, structural steel etc. with the help of drawings. Required for Petrochemical, Bop, Gas Turbine well as Steam turbines.  ERECTION & FABRICATION: Erection & fabrication of pipes, vessels, equipments, Gas turbines 1009E GE & Steam Turbines ,Hrsg,Water Treatment ,Boilers ,Steel Structure . Company Name : ALBARIO ENGINEERING (AEPLOASIS BASRA IRAQ) Client/Project : SHATT AL BASRA POWER PLANT 1250 MW Designation : Material Control (SUPERVISOR) Duration : 15-09-2013 T0 TILL DATE Company Name : ALBARIO ENGINEERING Client/Project : GUDDU POWER PLANT CCPP KASHMOR 747 MW Designation : Material Coordinator Duration : 12-01-2013 T0 10-09-013 Company Name : USMAN CONSTRUCTION & SERVICES Client/Project : LAL PIR THERMAL POWER 730 MW & PARCO Designation : Material Coordinator Duration : 05-04-2010 T0 05-01-2013 Company Name : ALBARIO ENGINEERING Client/Project : Muridke power plant CCPP 234 MW Designation : Material Coordinator Duration : 20-09-2008 to 30-03-2010 Company Name : Descon Engineering Client/Project : AES Lal Pir Thermal power station 730 MW Designation : Lead Man Duration : 10-05-2007 to 13-10-2008 Experience
  • 4.
    Company Name :Descon Engineering Client/Project : Parco OIL REFINERY Designation : Mech. Fitter Duration : 05-30-2007 to 12-04 -2007 Company Name : Descon Engineering Client/Project : PTA plant Karachi Designation : Mech. Fitter Duration : Febuary 2007 Company Name : Descon Engineering Client/Project : AES Lal Pir Thermal power station 730 MW Designation : Mech. Fitter Duration : 01-Nov-06 to 27-Dec-2006 Company Name : Descon Engineering Client/Project : AES Lal Pir Thermal power station 730 MW Designation : Mech. Fitter Duration : 03-Sep-2006 to 30-Sep-2006. Company Name : ATLANTS PURE WATER LAHORE Client/Project : Atlantis Pure Water Designation : Mech. Fitter Duration : 27-July-2006 to 30-Aug-2006. Company Name : ABRAHAM FIBERS LTD TEXTILE PLANT NO. 1 Client/Project : Abraham Fibers Designation : Supervisor Duration : 22-Feb-2006 to 20-July-2006 Company Name : Descon Engineering Client/Project : AES Lal Pir Thermal power station 730 MW Designation : Mech. Fitter Duration : 01-Nov-2005 to 30-Nov-2005
  • 5.
    Company Name :Descon Engineering Client/Project : PTA plant Karachi Designation : Mech. Fitter Duration : 01-May-2005 to 31-May-2005. Company Name : Layyah Sugar Mills Layyah Client/Project : Layyah Sugar Mills Designation : Mech. Fitter Duration : 05-Dec-2004 to 20-April-2005. Company Name : SSS Company Client/Project : AES Lal Pir Thermal Power 730 MW Designation : supervisor Duration : 27-Oct-1997 to 11-Nov-2004 Personal Profile Father’s Name Allah Rakha Date of Birth 01-05-1978 Marital Status Married Nationality Pakistani Permanent Address:- House No.27 Street No,02 Modal Town Chowk Azam Road Layyah .