Timothy Warner
(812) 343-6843                                                                                  2934 Prairie Stream Way
Email: TimothyLWarner@yahoo.com          www.linkedin.com/in/TimothyLWarner                        Columbus, IN 47203



                                                   PROFILE

Experienced engineering professional with emphasis in both project and process engineering. Proven ability to
handle multi-faceted projects of both long-term and short-term nature. Complimentary experiences in safety and
tooling. Key skills and expertise include:

                   •   Project Engineering                        •    Safety
                   •   Project Management                         •    Tooling
                   •   Process Engineering                        •    Supervision

                                   SELECTED ACCOMPLISHMENTS
Project Engineering
    o Developed bid packages for vendors, construction, and rigging contractors for new machinery, equipment
        relocations, and machine upgrades.
    o Conducted detailed bid comparisons.
    o Drew CAD representations of plant layout (plan and elevation) including equipment locations, utilities,
        offices, etc.
    o Designed machine improvements, equipment integrations, fabrications, etc.
Project Management
    o Wrote appropriation requests.
    o Presented project summaries to upper management and city government officials.
    o Developed project punch lists and timelines, and established milestone events.
    o Coordinated the activities of vendors, contractors, plant personnel, and tooling shops.
    o Led planned and emergency equipment rebuilds.
Process Engineering
    o Tooling modification which resulted in a 43% increase in productivity.
    o Designed tooling sub-plates and press bed modifications for quick set-up and changeover.
    o Purchased and had installed new press controls, which facilitated quick change-over, tooling protection,
        and increased operator safety.
    o Launched new assembly and weld cells.
Safety
    o Safety Committee Leader.
    o Developed Machine Guarding PowerPoint for presentation to Division Safety & Health Council.
    o Worked with Safety Manager and Engineering Technicians to develop Lock-Out Tag-Out instruction
       sheets.
    o Worked with vendors, contractors, and maintenance in determining machine guarding strategies.
    o Incorporated safety concerns into new equipment purchases.
Tooling
   o Designed new transfer fingers for use with 3 axis servo transfer.
   o Worked with tool shops to effect repairs and improvements.
   o Analyzed tonnage requirements of tooling to determine press capability.
Supervision
   o Supervised teams of 5 – 18 production associates.
   o Project based oversight of maintenance skilled trades personnel.
Timothy Warner
(812) 343-6843
Email: TimothyLWarner@yahoo.com       www.linkedin.com/in/TimothyLWarner                          Page 2 of 2



                           SIGNIFICANT PROJECT ACCOMPLISHMENTS

    1100 Ton Automatic Transfer Press Line Installation.
    • Specified, purchased, and supervised installation of an 1100 ton automatic transfer press along
        with ancillary equipment including an electronic servo controlled parts transfer, coil feeding
        system, and die exchange system. Value of investment – $2,500,000.
    Inter & Intra-plant Press Line Relocations.
    • Coordinated several relocations of stamping press lines ranging in size from 200 ton to 600 ton.
    New Overhead 15 Ton Crane.
    Semi-Truck Interior Drive-Thru.
    • Worked with contractors to modify a section of the facility to allow semi-trucks to enter the plant
        from an adjacent city street, through a new overhead doorway and exit at the opposite side of the
        plant. Project included obtaining City Engineering approval, installing a new overhead doorway,
        modifying an existing overhead crane runway, and constructing a new floor slab with a drainage
        trench.



                                  PROFESSIONAL CAREER HISTORY

Columbus Components Group, LLC (formerly part of ArvinMeritor), Columbus, IN
Sr. Process Engineer                                                                             18 Years

Dorel Juvenile Group (formerly Cosco, Incorporated), Columbus, IN
Project Engineer                                                                                1 ½ Years

Sonoco Flexible Packaging (formerly Rexham Corporation), Edinburgh, IN
Project Engineer                                                                                   6 Years

                                              EDUCATION

                                 Indiana State University, Terre Haute, IN
                       B.S. in Mechanical Technology, Minor in Mechanical Drafting

                                  COMPUTER SKILLS & TRAINING

             Microsoft Word, Excel, PowerPoint, Project, AutoCAD, Pro Engineer, Six Sigma

Timothy Warner Resume

  • 1.
    Timothy Warner (812) 343-6843 2934 Prairie Stream Way Email: TimothyLWarner@yahoo.com www.linkedin.com/in/TimothyLWarner Columbus, IN 47203 PROFILE Experienced engineering professional with emphasis in both project and process engineering. Proven ability to handle multi-faceted projects of both long-term and short-term nature. Complimentary experiences in safety and tooling. Key skills and expertise include: • Project Engineering • Safety • Project Management • Tooling • Process Engineering • Supervision SELECTED ACCOMPLISHMENTS Project Engineering o Developed bid packages for vendors, construction, and rigging contractors for new machinery, equipment relocations, and machine upgrades. o Conducted detailed bid comparisons. o Drew CAD representations of plant layout (plan and elevation) including equipment locations, utilities, offices, etc. o Designed machine improvements, equipment integrations, fabrications, etc. Project Management o Wrote appropriation requests. o Presented project summaries to upper management and city government officials. o Developed project punch lists and timelines, and established milestone events. o Coordinated the activities of vendors, contractors, plant personnel, and tooling shops. o Led planned and emergency equipment rebuilds. Process Engineering o Tooling modification which resulted in a 43% increase in productivity. o Designed tooling sub-plates and press bed modifications for quick set-up and changeover. o Purchased and had installed new press controls, which facilitated quick change-over, tooling protection, and increased operator safety. o Launched new assembly and weld cells. Safety o Safety Committee Leader. o Developed Machine Guarding PowerPoint for presentation to Division Safety & Health Council. o Worked with Safety Manager and Engineering Technicians to develop Lock-Out Tag-Out instruction sheets. o Worked with vendors, contractors, and maintenance in determining machine guarding strategies. o Incorporated safety concerns into new equipment purchases. Tooling o Designed new transfer fingers for use with 3 axis servo transfer. o Worked with tool shops to effect repairs and improvements. o Analyzed tonnage requirements of tooling to determine press capability. Supervision o Supervised teams of 5 – 18 production associates. o Project based oversight of maintenance skilled trades personnel.
  • 2.
    Timothy Warner (812) 343-6843 Email:TimothyLWarner@yahoo.com www.linkedin.com/in/TimothyLWarner Page 2 of 2 SIGNIFICANT PROJECT ACCOMPLISHMENTS 1100 Ton Automatic Transfer Press Line Installation. • Specified, purchased, and supervised installation of an 1100 ton automatic transfer press along with ancillary equipment including an electronic servo controlled parts transfer, coil feeding system, and die exchange system. Value of investment – $2,500,000. Inter & Intra-plant Press Line Relocations. • Coordinated several relocations of stamping press lines ranging in size from 200 ton to 600 ton. New Overhead 15 Ton Crane. Semi-Truck Interior Drive-Thru. • Worked with contractors to modify a section of the facility to allow semi-trucks to enter the plant from an adjacent city street, through a new overhead doorway and exit at the opposite side of the plant. Project included obtaining City Engineering approval, installing a new overhead doorway, modifying an existing overhead crane runway, and constructing a new floor slab with a drainage trench. PROFESSIONAL CAREER HISTORY Columbus Components Group, LLC (formerly part of ArvinMeritor), Columbus, IN Sr. Process Engineer 18 Years Dorel Juvenile Group (formerly Cosco, Incorporated), Columbus, IN Project Engineer 1 ½ Years Sonoco Flexible Packaging (formerly Rexham Corporation), Edinburgh, IN Project Engineer 6 Years EDUCATION Indiana State University, Terre Haute, IN B.S. in Mechanical Technology, Minor in Mechanical Drafting COMPUTER SKILLS & TRAINING Microsoft Word, Excel, PowerPoint, Project, AutoCAD, Pro Engineer, Six Sigma