SlideShare a Scribd company logo
1 of 2
Download to read offline
INTERIM PROGRAMME MANAGER - MANUFACTURING PRODUCT TRANSFER CASE STUDY
Tim Dyer
THE CLIENT
MORGAN ADVANCED MATERIALS PLC IS AN ADVANCED MATERIALS TECHNOLOGY COMPANY THAT PROVIDES HIGHLY ENGINEERED SOLUTIONS TO
ITS CHOSEN MARKETS. MORGAN ADVANCED MATERIALS HAS A GLOBAL PRESENCE WITH OPERATIONS IN MORE THAN 50 COUNTRIES. FROM
MEDICAL INSTRUMENTS, AEROSPACE, POWER GENERATION AND SATELLITE COMMUNICATIONS, TO BODY ARMOUR, TRAINS AND FIRE
PROTECTION SYSTEMS, MORGAN ADVANCED MATERIALS PRODUCTS ARE FUNDAMENTAL COMPONENTS OR ENABLING TECHNOLOGIES FOR MANY
OF THE MODERN WORLD'S SOPHISTICATED PRODUCTS.
THE CHALLENGE
THE COMPANY HAD ANNOUNCED A PRODUCT RATIONALISATION AND STANDARDISATION STRATEGY IN ORDER TO IMPROVE THE FINANCIAL
PERFORMANCE OF THE GROUP. IT WAS THEREFORE REQUIRED TO DOWNSIZE THE SWANSEA SITE BY 100 HEADS AND TRANSFER PRODUCT LINES
TO OTHER MORGAN GROUP SITES BASED IN ITALY, HUNGARY AND THE USA.
OBJECTIVES
 ‘SENSE CHECK’ PROJECT GOALS & OBJECTIVES AND MAKE RECOMMENDATIONS AS APPROPRIATE
 FACILITATE PROJECT MEETINGS AND ASSIST IN SETTING AND REINFORCING MANAGEMENT OWNERSHIP, CONTROLS & EXPECTATIONS
 INTERFACE WITH RECEIVING SITE PROJECT TEAMS/MANAGEMENT AS NECESSARY TO ENSURE GOAL ALIGNMENT
 MAINTAIN OVERVIEW OF PROJECT AS EXECUTION PHASES PROCEED AND RECOMMEND ADJUSTMENTS AS NECESSARY
 RECOMMEND AND PREPARE APPROPRIATE PROJECT TOOLS, FORMATS, DOCUMENTS ETC IN ORDER TO MAINTAIN & DEMONSTRATE
ADEQUATE PROJECT TIMESCALE & COST CONTROLS
 RECOMMEND AND PROVIDE APPROPRIATE PROJECT METHODOLOGIES TO MORGAN TEAM MEMBERS
THE SOLUTION
 AGREE PROJECT OBJECTIVES AND TIMESCALES
 DEFINE A DETAILED OVERALL PROJECT PLAN HIGHLIGHTING THE REQUIRED STEPS FOR THE VARIOUS PROJECT STAGES: PRE-
ANNOUNCEMENT, CONSULTATION PERIOD, POST CONSULTATION PERIOD AND TRANSFER OF PRODUCT LINES
 SET UP PROJECT TEAMS IN EACH OF THE RECEIVING SITES AND ORGANISE REGULAR PROJECT REVIEWS FOR EACH OF THE TRANSFERRING
PRODUCTS
 SET UP PROJECT TRACKING TOOLS AND KPIs AND COMMUNICATE THEM ON A REGULAR BASIS
 ENSURE GOOD COMMUNICATION WITH THE SWANSEA SITE MANAGEMENT TEAM TO ENSURE THEIR BUY-IN TO PROJECT OBJECTIVES
AND TIMESCALES
 DEFINE RISK REGISTER OF POTENTIAL ISSUES WHICH COULD CAUSE PROJECT DELAY
 SET UP A PROJECT GOVERNANCE MODEL WITH MORGAN SENIOR MANAGEMENT
THE RESULTS
 PROJECT TIMESCALES AND OBJECTIVES WERE AGREED WITH MORGAN SENIOR MANAGEMENT
 A DETAILED PROJECT PLAN WAS DEFINED WITH THE KEY MILESTONES AND IT WAS USED TO KEEP THE VARIOUS PROJECT STAGES ON
TRACK
 EXCELLENT WORK FROM THE SWANSEA GENERAL MANAGER AND HR MANAGER ENSURED THAT THE RESTRUCTURING ANNOUNCEMENT
AND CONSULTATION PERIOD WENT SMOOTHLY
 GOOD INTERACTION WITH THE RECEIVING SITE PROJECT TEAMS ENSURED THAT PROJECT GOALS WERE AGREED AND THEN ACHIEVED ON
TIME
 REGULAR COMMUNICATION WITH THE SWANSEA SITE MANAGEMENT TEAM ENSURED THAT THE PROJECT GOALS AND TIMESCALES
WERE KNOWN AND REVIEWED
 THESE REGULAR REVIEWS ALLOWED FOR ANY POTENTIAL ISSUES TO BE HIGHLIGHTED AND OVERCOME
 MONTHLY GOVERNANCE REVIEWS KEPT SENIOR MORGAN MANAGEMENT INFORMED OF PROJECT PROGRESS
 THE PROJECT TRACKING TOOLS AND KPIs WERE USED TO MEASURE PROJECT STATUS
 AT THE END OF 2014 THE PROJECT WAS ON TIME AND ALSO AHEAD OF THE FINANCIAL BUDGET DUE TO RELEASING EMPLOYEES AHEAD
OF THE ORIGINAL TIMESCALES:
o 2014 year: £289K ahead of original budget
o 2015 year: £1.82m savings (£171K ahead of original budget)
o 2016 year: £3.5m savings (£578K ahead of original budget)
o Annualised savings on completion: £3.6m (£675K ahead of original budget)
 ALL MORGAN CUSTOMERS HAD BEEN RETAINED DESPITE THE POTENTIAL RISKS OF TRANSFER
 NO INDUSTRIAL RELATIONS ISSUES HAD BEEN ENCOUNTERED WITH THE EMPLOYEES OR THE TRADE UNIONS
CLIENT TESTIMONIAL – GARY SIMPSON
TIM DYER PROVIDED INTERIM SENIOR LEVEL PROJECT MANAGEMENT SUPPORT TO THIS MAJOR RESTRUCTURING PROJECT THROUGH INTERIM
PARTNERS FROM MARCH TO DECEMBER 2014.
DURING HIS ASSIGNMENT, TIM PROVED TO BE AN EXTREMELY CAPABLE RESOURCE PROVIDING PROJECT TOOLS, TECHNICAL PROJECT PROCESSES
AND GENERAL SUPPORT TO THE BUSINESS MANAGEMENT TEAM.
TIM REGULARLY ACTED AS A PRIMARY INTERFACE WITH EXECUTIVE/BOARD LEVEL, SENIOR LOCAL MANAGEMENT AND RECEIVING SITE PROJECT
STAKEHOLDERS DURING PLANNING AND EXECUTION PHASES OF THE COMPLEX GLOBAL STRATEGIC PROJECT WITH A BUDGET EXCEEDING £5M.
THE PROJECT WILL INCREMENTALLY RESULT IN MULTIPLE SUB BUSINESSES ENGAGED ON THE SITE TRANSFERRING TO OTHER DIVISIONS AROUND
THE WORLD OVER AN EXTENDED TIMESCALE (C.18 MONTHS), CONCLUDING IN A REDUCTION IN FORCE OF APPROXIMATELY 117 EMPLOYEES
(CIRCA 55%). THIS PROVIDED A POTENTIALLY DIFFICULT SITUATION TO PARTICIPATE IN AS AN EXTERNAL RESOURCE BUT TIM PROVED HIGHLY
CAPABLE WITH EXCELLENT ENGAGEMENT FROM THE OUTSET, WORKING ENTHUSIASTICALLY WITH ALL APPROPRIATE STAKEHOLDERS AND AT ALL
LEVELS OF THE ORGANISATION.
HIS DISCIPLINED, ETHICAL AND COMMON SENSE APPROACH TO BUSINESS WAS REFRESHING WITH THE ABILITY TO OFFER LOGICAL GUIDANCE
FROM A POSITION OF EXTENSIVE SENIOR LEVEL MANAGEMENT EXPERIENCE.
THE SUCCESS OF THE PROJECT TO-DATE HAS BEEN DUE TO EXCELLENT PLANNING, COORDINATION AND POSITIVE COMMUNICATIONS, TIM HAS
CONTRIBUTED TO THIS SUCCESS THROUGH EXCELLENT ENGAGEMENT, PERSONAL CREDIBILITY AND HIS ABILITY TO INTERFACE WELL AT ALL LEVELS
OF AN ORGANISATION THROUGH AN AUTHORITATIVE PRESENCE, AFFABLE NATURE AND EXCELLENT COMMUNICATION SKILLS.

More Related Content

What's hot (19)

Kim lynchresume july2016
Kim lynchresume july2016Kim lynchresume july2016
Kim lynchresume july2016
 
BF CV - 18th Nov16
BF CV - 18th Nov16BF CV - 18th Nov16
BF CV - 18th Nov16
 
Auxer - Resume - v12_4
Auxer - Resume - v12_4Auxer - Resume - v12_4
Auxer - Resume - v12_4
 
Resume
ResumeResume
Resume
 
Orville Whitlock Resume 2
Orville Whitlock Resume 2Orville Whitlock Resume 2
Orville Whitlock Resume 2
 
Dlw resume july 2016
Dlw  resume july 2016Dlw  resume july 2016
Dlw resume july 2016
 
Srae2014 - Construction Projects Risks from the Perspective of Project Manage...
Srae2014 - Construction Projects Risks from the Perspective of Project Manage...Srae2014 - Construction Projects Risks from the Perspective of Project Manage...
Srae2014 - Construction Projects Risks from the Perspective of Project Manage...
 
Colin Purnell CV
Colin Purnell CVColin Purnell CV
Colin Purnell CV
 
Dave Parta sipm resume 2017 11 15
Dave Parta sipm resume 2017 11 15Dave Parta sipm resume 2017 11 15
Dave Parta sipm resume 2017 11 15
 
Tri-Core Projects Statement of Qualifications
Tri-Core Projects Statement of QualificationsTri-Core Projects Statement of Qualifications
Tri-Core Projects Statement of Qualifications
 
GAFM Academy HOW TO START A PROJECT
GAFM Academy HOW TO START A PROJECTGAFM Academy HOW TO START A PROJECT
GAFM Academy HOW TO START A PROJECT
 
Uribe Res Program 12-01-15
Uribe Res Program 12-01-15Uribe Res Program 12-01-15
Uribe Res Program 12-01-15
 
Dlw resume march 2016 p
Dlw  resume march 2016 pDlw  resume march 2016 p
Dlw resume march 2016 p
 
R. Chapa. Resume May. 2015
R. Chapa. Resume May. 2015R. Chapa. Resume May. 2015
R. Chapa. Resume May. 2015
 
Certified Planning Engineer CPE
Certified Planning Engineer CPE Certified Planning Engineer CPE
Certified Planning Engineer CPE
 
Fme project-risk
Fme project-riskFme project-risk
Fme project-risk
 
Certified Project Consultant
Certified Project Consultant  Certified Project Consultant
Certified Project Consultant
 
RESUME
RESUMERESUME
RESUME
 
Craig Paradis Resume 9-19-15
Craig Paradis Resume 9-19-15Craig Paradis Resume 9-19-15
Craig Paradis Resume 9-19-15
 

Similar to Tim Dyer Morgan Case Study 300115

Lawrence dick 10 02-2016-pm
Lawrence dick 10 02-2016-pmLawrence dick 10 02-2016-pm
Lawrence dick 10 02-2016-pmLawrence Dick
 
Project Management Extensive
Project Management  ExtensiveProject Management  Extensive
Project Management Extensivelarryawc
 
20150206 Evette Currie PM CV
20150206  Evette Currie PM CV20150206  Evette Currie PM CV
20150206 Evette Currie PM CVEvette Currie
 
Lakshman_Kumar_Profile
Lakshman_Kumar_ProfileLakshman_Kumar_Profile
Lakshman_Kumar_ProfileLakshman Kumar
 
Tony van uden cv summary 2013 08
Tony van uden cv summary 2013 08Tony van uden cv summary 2013 08
Tony van uden cv summary 2013 08avanuden
 
Christopher Salerno Resume
Christopher Salerno ResumeChristopher Salerno Resume
Christopher Salerno ResumeChris Salerno
 
Christopher Salerno April16
Christopher Salerno April16Christopher Salerno April16
Christopher Salerno April16Chris Salerno
 
Sai Boonwaat Linked In
Sai Boonwaat Linked InSai Boonwaat Linked In
Sai Boonwaat Linked InSaiB123
 
R. Jay Gann - Resume - Project Management Leader
R. Jay Gann - Resume - Project Management LeaderR. Jay Gann - Resume - Project Management Leader
R. Jay Gann - Resume - Project Management LeaderJay Gann
 
Luke M.Marais_CV
Luke M.Marais_CVLuke M.Marais_CV
Luke M.Marais_CVLuke Walker
 
000 Brad E Magro PMP Resume September 2016
000 Brad E Magro PMP Resume September 2016000 Brad E Magro PMP Resume September 2016
000 Brad E Magro PMP Resume September 2016brad magro
 
Nirmal R Shah CV 2016
Nirmal R Shah CV 2016Nirmal R Shah CV 2016
Nirmal R Shah CV 2016Nirmal Shah
 
Thomas Lupica Rev D for dbC
Thomas Lupica Rev D for dbCThomas Lupica Rev D for dbC
Thomas Lupica Rev D for dbCThomas Lupica
 
Delivery Head with 16 yrs experience.docx
Delivery Head with 16 yrs experience.docxDelivery Head with 16 yrs experience.docx
Delivery Head with 16 yrs experience.docxKarthic Ramamurthy
 
Le IE exigencias de presentación como asesor financiero
Le IE exigencias de presentación como asesor financieroLe IE exigencias de presentación como asesor financiero
Le IE exigencias de presentación como asesor financieroDel Ergueza
 
Austin C Mattson_II_resume_May 2013
Austin C  Mattson_II_resume_May 2013Austin C  Mattson_II_resume_May 2013
Austin C Mattson_II_resume_May 2013Austin C. Mattson II
 

Similar to Tim Dyer Morgan Case Study 300115 (20)

Lawrence dick 10 02-2016-pm
Lawrence dick 10 02-2016-pmLawrence dick 10 02-2016-pm
Lawrence dick 10 02-2016-pm
 
Project Management Extensive
Project Management  ExtensiveProject Management  Extensive
Project Management Extensive
 
20150206 Evette Currie PM CV
20150206  Evette Currie PM CV20150206  Evette Currie PM CV
20150206 Evette Currie PM CV
 
Lakshman_Kumar_Profile
Lakshman_Kumar_ProfileLakshman_Kumar_Profile
Lakshman_Kumar_Profile
 
JohnsonBruce 2015
JohnsonBruce 2015JohnsonBruce 2015
JohnsonBruce 2015
 
Tony van uden cv summary 2013 08
Tony van uden cv summary 2013 08Tony van uden cv summary 2013 08
Tony van uden cv summary 2013 08
 
Christopher Salerno Resume
Christopher Salerno ResumeChristopher Salerno Resume
Christopher Salerno Resume
 
Christopher Salerno April16
Christopher Salerno April16Christopher Salerno April16
Christopher Salerno April16
 
Sai Boonwaat Linked In
Sai Boonwaat Linked InSai Boonwaat Linked In
Sai Boonwaat Linked In
 
R. Jay Gann - Resume - Project Management Leader
R. Jay Gann - Resume - Project Management LeaderR. Jay Gann - Resume - Project Management Leader
R. Jay Gann - Resume - Project Management Leader
 
Luke M.Marais_CV
Luke M.Marais_CVLuke M.Marais_CV
Luke M.Marais_CV
 
CURICULUM VITAE ( Sree ) latest
CURICULUM VITAE ( Sree ) latestCURICULUM VITAE ( Sree ) latest
CURICULUM VITAE ( Sree ) latest
 
000 Brad E Magro PMP Resume September 2016
000 Brad E Magro PMP Resume September 2016000 Brad E Magro PMP Resume September 2016
000 Brad E Magro PMP Resume September 2016
 
Nirmal R Shah CV 2016
Nirmal R Shah CV 2016Nirmal R Shah CV 2016
Nirmal R Shah CV 2016
 
Thomas Lupica Rev D for dbC
Thomas Lupica Rev D for dbCThomas Lupica Rev D for dbC
Thomas Lupica Rev D for dbC
 
Delivery Head with 16 yrs experience.docx
Delivery Head with 16 yrs experience.docxDelivery Head with 16 yrs experience.docx
Delivery Head with 16 yrs experience.docx
 
Le IE exigencias de presentación como asesor financiero
Le IE exigencias de presentación como asesor financieroLe IE exigencias de presentación como asesor financiero
Le IE exigencias de presentación como asesor financiero
 
Wiz CV - 2015
Wiz CV - 2015Wiz CV - 2015
Wiz CV - 2015
 
Austin C Mattson_II_resume_May 2013
Austin C  Mattson_II_resume_May 2013Austin C  Mattson_II_resume_May 2013
Austin C Mattson_II_resume_May 2013
 
Neelesh Thakare CV.
Neelesh Thakare CV.Neelesh Thakare CV.
Neelesh Thakare CV.
 

Tim Dyer Morgan Case Study 300115

  • 1. INTERIM PROGRAMME MANAGER - MANUFACTURING PRODUCT TRANSFER CASE STUDY Tim Dyer THE CLIENT MORGAN ADVANCED MATERIALS PLC IS AN ADVANCED MATERIALS TECHNOLOGY COMPANY THAT PROVIDES HIGHLY ENGINEERED SOLUTIONS TO ITS CHOSEN MARKETS. MORGAN ADVANCED MATERIALS HAS A GLOBAL PRESENCE WITH OPERATIONS IN MORE THAN 50 COUNTRIES. FROM MEDICAL INSTRUMENTS, AEROSPACE, POWER GENERATION AND SATELLITE COMMUNICATIONS, TO BODY ARMOUR, TRAINS AND FIRE PROTECTION SYSTEMS, MORGAN ADVANCED MATERIALS PRODUCTS ARE FUNDAMENTAL COMPONENTS OR ENABLING TECHNOLOGIES FOR MANY OF THE MODERN WORLD'S SOPHISTICATED PRODUCTS. THE CHALLENGE THE COMPANY HAD ANNOUNCED A PRODUCT RATIONALISATION AND STANDARDISATION STRATEGY IN ORDER TO IMPROVE THE FINANCIAL PERFORMANCE OF THE GROUP. IT WAS THEREFORE REQUIRED TO DOWNSIZE THE SWANSEA SITE BY 100 HEADS AND TRANSFER PRODUCT LINES TO OTHER MORGAN GROUP SITES BASED IN ITALY, HUNGARY AND THE USA. OBJECTIVES  ‘SENSE CHECK’ PROJECT GOALS & OBJECTIVES AND MAKE RECOMMENDATIONS AS APPROPRIATE  FACILITATE PROJECT MEETINGS AND ASSIST IN SETTING AND REINFORCING MANAGEMENT OWNERSHIP, CONTROLS & EXPECTATIONS  INTERFACE WITH RECEIVING SITE PROJECT TEAMS/MANAGEMENT AS NECESSARY TO ENSURE GOAL ALIGNMENT  MAINTAIN OVERVIEW OF PROJECT AS EXECUTION PHASES PROCEED AND RECOMMEND ADJUSTMENTS AS NECESSARY  RECOMMEND AND PREPARE APPROPRIATE PROJECT TOOLS, FORMATS, DOCUMENTS ETC IN ORDER TO MAINTAIN & DEMONSTRATE ADEQUATE PROJECT TIMESCALE & COST CONTROLS  RECOMMEND AND PROVIDE APPROPRIATE PROJECT METHODOLOGIES TO MORGAN TEAM MEMBERS THE SOLUTION  AGREE PROJECT OBJECTIVES AND TIMESCALES  DEFINE A DETAILED OVERALL PROJECT PLAN HIGHLIGHTING THE REQUIRED STEPS FOR THE VARIOUS PROJECT STAGES: PRE- ANNOUNCEMENT, CONSULTATION PERIOD, POST CONSULTATION PERIOD AND TRANSFER OF PRODUCT LINES  SET UP PROJECT TEAMS IN EACH OF THE RECEIVING SITES AND ORGANISE REGULAR PROJECT REVIEWS FOR EACH OF THE TRANSFERRING PRODUCTS  SET UP PROJECT TRACKING TOOLS AND KPIs AND COMMUNICATE THEM ON A REGULAR BASIS  ENSURE GOOD COMMUNICATION WITH THE SWANSEA SITE MANAGEMENT TEAM TO ENSURE THEIR BUY-IN TO PROJECT OBJECTIVES AND TIMESCALES  DEFINE RISK REGISTER OF POTENTIAL ISSUES WHICH COULD CAUSE PROJECT DELAY  SET UP A PROJECT GOVERNANCE MODEL WITH MORGAN SENIOR MANAGEMENT
  • 2. THE RESULTS  PROJECT TIMESCALES AND OBJECTIVES WERE AGREED WITH MORGAN SENIOR MANAGEMENT  A DETAILED PROJECT PLAN WAS DEFINED WITH THE KEY MILESTONES AND IT WAS USED TO KEEP THE VARIOUS PROJECT STAGES ON TRACK  EXCELLENT WORK FROM THE SWANSEA GENERAL MANAGER AND HR MANAGER ENSURED THAT THE RESTRUCTURING ANNOUNCEMENT AND CONSULTATION PERIOD WENT SMOOTHLY  GOOD INTERACTION WITH THE RECEIVING SITE PROJECT TEAMS ENSURED THAT PROJECT GOALS WERE AGREED AND THEN ACHIEVED ON TIME  REGULAR COMMUNICATION WITH THE SWANSEA SITE MANAGEMENT TEAM ENSURED THAT THE PROJECT GOALS AND TIMESCALES WERE KNOWN AND REVIEWED  THESE REGULAR REVIEWS ALLOWED FOR ANY POTENTIAL ISSUES TO BE HIGHLIGHTED AND OVERCOME  MONTHLY GOVERNANCE REVIEWS KEPT SENIOR MORGAN MANAGEMENT INFORMED OF PROJECT PROGRESS  THE PROJECT TRACKING TOOLS AND KPIs WERE USED TO MEASURE PROJECT STATUS  AT THE END OF 2014 THE PROJECT WAS ON TIME AND ALSO AHEAD OF THE FINANCIAL BUDGET DUE TO RELEASING EMPLOYEES AHEAD OF THE ORIGINAL TIMESCALES: o 2014 year: £289K ahead of original budget o 2015 year: £1.82m savings (£171K ahead of original budget) o 2016 year: £3.5m savings (£578K ahead of original budget) o Annualised savings on completion: £3.6m (£675K ahead of original budget)  ALL MORGAN CUSTOMERS HAD BEEN RETAINED DESPITE THE POTENTIAL RISKS OF TRANSFER  NO INDUSTRIAL RELATIONS ISSUES HAD BEEN ENCOUNTERED WITH THE EMPLOYEES OR THE TRADE UNIONS CLIENT TESTIMONIAL – GARY SIMPSON TIM DYER PROVIDED INTERIM SENIOR LEVEL PROJECT MANAGEMENT SUPPORT TO THIS MAJOR RESTRUCTURING PROJECT THROUGH INTERIM PARTNERS FROM MARCH TO DECEMBER 2014. DURING HIS ASSIGNMENT, TIM PROVED TO BE AN EXTREMELY CAPABLE RESOURCE PROVIDING PROJECT TOOLS, TECHNICAL PROJECT PROCESSES AND GENERAL SUPPORT TO THE BUSINESS MANAGEMENT TEAM. TIM REGULARLY ACTED AS A PRIMARY INTERFACE WITH EXECUTIVE/BOARD LEVEL, SENIOR LOCAL MANAGEMENT AND RECEIVING SITE PROJECT STAKEHOLDERS DURING PLANNING AND EXECUTION PHASES OF THE COMPLEX GLOBAL STRATEGIC PROJECT WITH A BUDGET EXCEEDING £5M. THE PROJECT WILL INCREMENTALLY RESULT IN MULTIPLE SUB BUSINESSES ENGAGED ON THE SITE TRANSFERRING TO OTHER DIVISIONS AROUND THE WORLD OVER AN EXTENDED TIMESCALE (C.18 MONTHS), CONCLUDING IN A REDUCTION IN FORCE OF APPROXIMATELY 117 EMPLOYEES (CIRCA 55%). THIS PROVIDED A POTENTIALLY DIFFICULT SITUATION TO PARTICIPATE IN AS AN EXTERNAL RESOURCE BUT TIM PROVED HIGHLY CAPABLE WITH EXCELLENT ENGAGEMENT FROM THE OUTSET, WORKING ENTHUSIASTICALLY WITH ALL APPROPRIATE STAKEHOLDERS AND AT ALL LEVELS OF THE ORGANISATION. HIS DISCIPLINED, ETHICAL AND COMMON SENSE APPROACH TO BUSINESS WAS REFRESHING WITH THE ABILITY TO OFFER LOGICAL GUIDANCE FROM A POSITION OF EXTENSIVE SENIOR LEVEL MANAGEMENT EXPERIENCE. THE SUCCESS OF THE PROJECT TO-DATE HAS BEEN DUE TO EXCELLENT PLANNING, COORDINATION AND POSITIVE COMMUNICATIONS, TIM HAS CONTRIBUTED TO THIS SUCCESS THROUGH EXCELLENT ENGAGEMENT, PERSONAL CREDIBILITY AND HIS ABILITY TO INTERFACE WELL AT ALL LEVELS OF AN ORGANISATION THROUGH AN AUTHORITATIVE PRESENCE, AFFABLE NATURE AND EXCELLENT COMMUNICATION SKILLS.