SlideShare a Scribd company logo
1 of 2
Download to read offline
Article ONE     “BEYOND CONTRACT” SERIES OF MUSINGS -- LESSONS LEARNED FROM 27 YEARS OF
                CONTRACT AND COMMERCIAL MANAGEMENT



Beyond Contract : Reliance on Instituted Procedure Maturity and
Compliance in the Prevention of Unfounded Contractual Claims Under
International EPC and Turnkey Contracts.

Andrew Ng, B Sc (Hons) Construction Management,

Change is an inevitable part of any project but some risks can be clearly identified and separated from
those which can’t or haven’t been considered as best managed by the Contractor. Against these risk
must be allocated appropriate rewards, incentives and reimbursements of resources which Contractor
have agreed to carry throughout the project duration. Unless there exceptional circumstances which
made those allocation grossly inadequate, like misrepresentation by the Employers etc., there can’t be
too many circumstances they need to be separately reimbursed, extra over the Contract sum.
However, what to do next is where the difference begins between the approach of practitioners of the
science of project control and the approach of those who are not.

As Contract and Project Contract consultant to many clients, I have never been ceased to be amazed by
the prevalence of a naive belief amongst many that reliance on some well-crafted Contract clauses
alone would somehow discourage the Contractors from engineering some dubious ground for recovery
of prelims and other costs. They have this puzzling abhorrence of what they consider redundant
procedures and processes beyond those what the professional would consider as whimsical and
impotent “motherhood statement like” write-ups. On my part I have always been requiring the
Contractors to comply procedures which require the Contractors’ provision of quantities of reasonably
verifiable records of man-hours of labour, management and plant/equipment used throughout the
project.

It may have something to do with the many failed projects(where the Clients paid millions of dollars)
and the lessons I learned there that the Contractor's honesty is not to be expected as a given or
foregone conclusion. It is rather the results of tough policing made possible through properly detailed
procedures which enable the Employers to speaking softly but always wielding a big stick to demand the
Contractor’s respect.

To enable the Employer’s Rep achieving a decent degree of policing, I have always advocated
supplementing the Contract Document and the Employer’s Requirements with the following:-
       a) complete suite of procedures (or process, usually forming part of the Employer's
            Requirement) stipulating the Contractor's obligation and commitment on strict compliance
            with a set of prior-agreed project deliverables, their timely submission of records of
            meetings, plant and labour records and returns at pre-set intervals. And if external parties
            are relied upon for supervision, the contract would further prescribes obligation on the part
            of the PMC;s team members and the Employers staff (where assigned) to attend to such
            deliverables and records and certifying them as true reflection of their field observation of
            the resources expended by the Contractor. For good measures too, the project managers
            are often required to rotate these assigned resources every quarter to avoid familiarity with
            any particular ground of contractors workforce or subcontractors;
       b) clearly defined baselines of these performance and resources requirement, with quantities
            and major categories of staff, labour, vehicles fuels and etc., which are tabulated in a
            histogram spreading over the whole Contract Period including those time identified as free
            floats in the Construction/Baseline programme.



2nd Aug 2011                              Andrew Ng, Consultant at RDP Consultants Pty Ltd Australia
Article ONE     “BEYOND CONTRACT” SERIES OF MUSINGS -- LESSONS LEARNED FROM 27 YEARS OF
                CONTRACT AND COMMERCIAL MANAGEMENT

In nearly all tender clarification meetings before award, I would revisit each of the above and negotiate
and rationalise these deliverables, procedures, processes, quantities and rates of each and require the
Contractor to confirm their acceptance of these parameters as the baselines beyond which their claims
begin to have any chance to be considered.

In most remote mining sites or in those more compact urban site, I also advocated the use of access
control for those plant and human resources entering site, site offices as well as mess/camps as means
of registering the hours and days of work . For those sites other than above, monitoring may be done
through some RFID, which should be relatively cheap now. But I must confess that I have not as yet
worked on a project which requires the latter todate.

Even in FIDIC Silver Book type of EPC Contract I would not be fooled into a complacent belief or reliance
on high level Pricing Schedule (<200 cost breakdowns/quantities) as the means of benchmarking the
Contractor's claim entitlement. This is even if the Contractors can prove to me that it has done for
example, the same configuration of CCPP twenty or more times before.

To pinnacles of the Employer's sins would be to accept Pricing Schedule without any kind of Prelims
breakdown, especially the details of those recurring ones separated from those for mobilisation and
demobilisation.

Even in FIDIC Silver Book type of EPC Contract I would not be fooled into a complacent belief or reliance
on high level Pricing Schedule ( those with <200 cost breakdowns/quantities) as the means of
benchmarking the Contractor's claim entitlement. This is even if the Contractors can prove to me that it
has done for example, the same configuration of CCPP twenty or more times before.

But I can tell from most of the projects in the skill-constrained resource industries in Australia Asia and
Africa, the Contractors are struggling to even assemble a team with half the years of experience or half
of the complete skillsets normally required in executing such a project. One needs to either have some
superior connection with the all mighty above or an indomitable conviction of one’s infallibility, to rely
on such poorly equipped parties to execute its project.

But nothing could surpass the pinnacles of the Employer's sins than to accept Pricing Schedule without
any kind of Prelims breakdown, especially the details of those recurring ones separated from those for
mobilisation and demobilisation.

It is nothing short of inviting future claims and headaches if Employers’ beliefs and relances like those
cited above stand uncorrected. In fact most savvy contractors consider the mere absence of project
control procedures requirements and properly configured breakdown of prelims from the Contract
document as the strongest sign of inviting open season on such misguided if not foolish paymaster. For
them, these clients are not worthy of any sympathies especially if they are long on ignorance but short
on acumen.




2nd Aug 2011                               Andrew Ng, Consultant at RDP Consultants Pty Ltd Australia

More Related Content

What's hot

Certificates and payments
Certificates and paymentsCertificates and payments
Certificates and paymentsHafizul Mukhlis
 
Ipwea inspire-issue-12- nov-2019- managing contractors (1)
Ipwea inspire-issue-12- nov-2019- managing contractors (1)Ipwea inspire-issue-12- nov-2019- managing contractors (1)
Ipwea inspire-issue-12- nov-2019- managing contractors (1)James Baker
 
Procurement Problems In The Credit Crunch
Procurement Problems In The Credit CrunchProcurement Problems In The Credit Crunch
Procurement Problems In The Credit Crunchjohnmunton
 
Day-01_1025 Engineer's Roles and Risks - Adrias Tan
Day-01_1025 Engineer's Roles and Risks - Adrias TanDay-01_1025 Engineer's Roles and Risks - Adrias Tan
Day-01_1025 Engineer's Roles and Risks - Adrias TanAdrias TAN
 
Building Economics:Individual Assessment
Building Economics:Individual AssessmentBuilding Economics:Individual Assessment
Building Economics:Individual Assessment마 이환
 
Letters of Intent, Bonds & Guarantees, Defects Liability Periods
Letters of Intent, Bonds & Guarantees, Defects Liability PeriodsLetters of Intent, Bonds & Guarantees, Defects Liability Periods
Letters of Intent, Bonds & Guarantees, Defects Liability PeriodsCerasela Angelescu
 
Project Management
Project ManagementProject Management
Project ManagementDr K M SONI
 
Determination of building_contracts
Determination of building_contractsDetermination of building_contracts
Determination of building_contractsHafizul Mukhlis
 
FIDIC 2016 Day02-1010 Variations Under FIDIC Forms, Adrias Tan
FIDIC 2016 Day02-1010 Variations Under FIDIC Forms, Adrias TanFIDIC 2016 Day02-1010 Variations Under FIDIC Forms, Adrias Tan
FIDIC 2016 Day02-1010 Variations Under FIDIC Forms, Adrias TanAdrias TAN
 
Advance Payments in Works
Advance Payments in WorksAdvance Payments in Works
Advance Payments in WorksDr K M SONI
 
Strategic Planning : the best way to manage EPC Contract Risks
Strategic Planning : the best way to manage EPC Contract RisksStrategic Planning : the best way to manage EPC Contract Risks
Strategic Planning : the best way to manage EPC Contract RisksPankaj K Sinha
 
Guide for Construction Contract Administrators
Guide for Construction Contract AdministratorsGuide for Construction Contract Administrators
Guide for Construction Contract AdministratorsSarah Fox
 

What's hot (20)

Certificates and payments
Certificates and paymentsCertificates and payments
Certificates and payments
 
Ipwea inspire-issue-12- nov-2019- managing contractors (1)
Ipwea inspire-issue-12- nov-2019- managing contractors (1)Ipwea inspire-issue-12- nov-2019- managing contractors (1)
Ipwea inspire-issue-12- nov-2019- managing contractors (1)
 
Procurement Problems In The Credit Crunch
Procurement Problems In The Credit CrunchProcurement Problems In The Credit Crunch
Procurement Problems In The Credit Crunch
 
Day-01_1025 Engineer's Roles and Risks - Adrias Tan
Day-01_1025 Engineer's Roles and Risks - Adrias TanDay-01_1025 Engineer's Roles and Risks - Adrias Tan
Day-01_1025 Engineer's Roles and Risks - Adrias Tan
 
Credicon Introduction
Credicon  IntroductionCredicon  Introduction
Credicon Introduction
 
Contract mgt stc
Contract mgt stcContract mgt stc
Contract mgt stc
 
Contract closing ppt
Contract closing pptContract closing ppt
Contract closing ppt
 
Earnest Money
Earnest MoneyEarnest Money
Earnest Money
 
Defects liability
Defects liabilityDefects liability
Defects liability
 
Building Economics:Individual Assessment
Building Economics:Individual AssessmentBuilding Economics:Individual Assessment
Building Economics:Individual Assessment
 
Letters of Intent, Bonds & Guarantees, Defects Liability Periods
Letters of Intent, Bonds & Guarantees, Defects Liability PeriodsLetters of Intent, Bonds & Guarantees, Defects Liability Periods
Letters of Intent, Bonds & Guarantees, Defects Liability Periods
 
Project Management
Project ManagementProject Management
Project Management
 
07-12-2014m
07-12-2014m07-12-2014m
07-12-2014m
 
Determination of building_contracts
Determination of building_contractsDetermination of building_contracts
Determination of building_contracts
 
Epc Vs Epcm
Epc Vs EpcmEpc Vs Epcm
Epc Vs Epcm
 
FIDIC 2016 Day02-1010 Variations Under FIDIC Forms, Adrias Tan
FIDIC 2016 Day02-1010 Variations Under FIDIC Forms, Adrias TanFIDIC 2016 Day02-1010 Variations Under FIDIC Forms, Adrias Tan
FIDIC 2016 Day02-1010 Variations Under FIDIC Forms, Adrias Tan
 
Advance Payments in Works
Advance Payments in WorksAdvance Payments in Works
Advance Payments in Works
 
Strategic Planning : the best way to manage EPC Contract Risks
Strategic Planning : the best way to manage EPC Contract RisksStrategic Planning : the best way to manage EPC Contract Risks
Strategic Planning : the best way to manage EPC Contract Risks
 
FIDIC variation, claim & dispute - CYLFEx workshop
FIDIC variation, claim & dispute - CYLFEx workshopFIDIC variation, claim & dispute - CYLFEx workshop
FIDIC variation, claim & dispute - CYLFEx workshop
 
Guide for Construction Contract Administrators
Guide for Construction Contract AdministratorsGuide for Construction Contract Administrators
Guide for Construction Contract Administrators
 

Similar to Beyond Contract Series Article One

10 Essentials For An Effective Construction Contract
10 Essentials For An Effective Construction Contract10 Essentials For An Effective Construction Contract
10 Essentials For An Effective Construction ContractSarah Fox
 
Seminar Presentation Slides (Chapter 2)
Seminar Presentation Slides (Chapter 2)Seminar Presentation Slides (Chapter 2)
Seminar Presentation Slides (Chapter 2)Melvin Lim
 
Construction management 2
Construction management 2Construction management 2
Construction management 2smumbahelp
 
Contracts & Claims Management Workshop (Session-1)
Contracts & Claims Management Workshop (Session-1)Contracts & Claims Management Workshop (Session-1)
Contracts & Claims Management Workshop (Session-1)Tahir B Mirza
 
Episode 28 : Project Management Contract
Episode 28 : Project Management ContractEpisode 28 : Project Management Contract
Episode 28 : Project Management ContractSAJJAD KHUDHUR ABBAS
 
Selecting E R P For Oil And Gas Industry Contractors And Vendors
Selecting  E R P For Oil And Gas Industry Contractors And VendorsSelecting  E R P For Oil And Gas Industry Contractors And Vendors
Selecting E R P For Oil And Gas Industry Contractors And VendorsIFS
 
Running head ACQUISITION STRATEGY PIEZOELECTRIC EMBEDDED TRA.docx
Running head  ACQUISITION STRATEGY  PIEZOELECTRIC EMBEDDED TRA.docxRunning head  ACQUISITION STRATEGY  PIEZOELECTRIC EMBEDDED TRA.docx
Running head ACQUISITION STRATEGY PIEZOELECTRIC EMBEDDED TRA.docxSUBHI7
 
Kreischer Miller Architecture & Engineering Industry Seminar
Kreischer Miller Architecture & Engineering Industry SeminarKreischer Miller Architecture & Engineering Industry Seminar
Kreischer Miller Architecture & Engineering Industry SeminarKreischer Miller
 
Yam yih hwan pp1 assignment aug 14
Yam yih hwan   pp1 assignment aug 14Yam yih hwan   pp1 assignment aug 14
Yam yih hwan pp1 assignment aug 14마 이환
 
Core_Services_White Papers Oracle Service PUR.pdf
Core_Services_White Papers Oracle Service PUR.pdfCore_Services_White Papers Oracle Service PUR.pdf
Core_Services_White Papers Oracle Service PUR.pdfTarigTaha3
 
Construction claims, disputes and project closure
Construction claims, disputes and project closureConstruction claims, disputes and project closure
Construction claims, disputes and project closuresrinivas2036
 
Construction Contract Issues for Owners of Residences
Construction Contract Issues for Owners of ResidencesConstruction Contract Issues for Owners of Residences
Construction Contract Issues for Owners of ResidencesConstruction Cicerone
 
Selecting ERP for Oil and Gas industry contractors and vendors
Selecting ERP for Oil and Gas industry contractors and vendorsSelecting ERP for Oil and Gas industry contractors and vendors
Selecting ERP for Oil and Gas industry contractors and vendorscthomassen
 
ConstructionFlow
ConstructionFlowConstructionFlow
ConstructionFlowJeff Dixon
 
RESUME FOR PROCUREMENT & CONTRACTS ENGINEER
RESUME FOR PROCUREMENT & CONTRACTS ENGINEERRESUME FOR PROCUREMENT & CONTRACTS ENGINEER
RESUME FOR PROCUREMENT & CONTRACTS ENGINEERShafeek Nazar
 
EMLI Training-An introduction to epc contract-clause by clause-Prepared by: D...
EMLI Training-An introduction to epc contract-clause by clause-Prepared by: D...EMLI Training-An introduction to epc contract-clause by clause-Prepared by: D...
EMLI Training-An introduction to epc contract-clause by clause-Prepared by: D...EMLI Indonesia
 
White papers selecting erp for oil and gas industry contractors and vendors
White papers selecting erp for oil and gas industry contractors and vendorsWhite papers selecting erp for oil and gas industry contractors and vendors
White papers selecting erp for oil and gas industry contractors and vendorsKaizenlogcom
 

Similar to Beyond Contract Series Article One (20)

10 Essentials For An Effective Construction Contract
10 Essentials For An Effective Construction Contract10 Essentials For An Effective Construction Contract
10 Essentials For An Effective Construction Contract
 
Claims and Counterclaims Preparation, Analysis, Assessment and Successful Set...
Claims and Counterclaims Preparation, Analysis, Assessment and Successful Set...Claims and Counterclaims Preparation, Analysis, Assessment and Successful Set...
Claims and Counterclaims Preparation, Analysis, Assessment and Successful Set...
 
Seminar Presentation Slides (Chapter 2)
Seminar Presentation Slides (Chapter 2)Seminar Presentation Slides (Chapter 2)
Seminar Presentation Slides (Chapter 2)
 
Construction management 2
Construction management 2Construction management 2
Construction management 2
 
Contracts & Claims Management Workshop (Session-1)
Contracts & Claims Management Workshop (Session-1)Contracts & Claims Management Workshop (Session-1)
Contracts & Claims Management Workshop (Session-1)
 
Bkozlowski wpa
Bkozlowski wpaBkozlowski wpa
Bkozlowski wpa
 
Episode 28 : Project Management Contract
Episode 28 : Project Management ContractEpisode 28 : Project Management Contract
Episode 28 : Project Management Contract
 
Selecting E R P For Oil And Gas Industry Contractors And Vendors
Selecting  E R P For Oil And Gas Industry Contractors And VendorsSelecting  E R P For Oil And Gas Industry Contractors And Vendors
Selecting E R P For Oil And Gas Industry Contractors And Vendors
 
Running head ACQUISITION STRATEGY PIEZOELECTRIC EMBEDDED TRA.docx
Running head  ACQUISITION STRATEGY  PIEZOELECTRIC EMBEDDED TRA.docxRunning head  ACQUISITION STRATEGY  PIEZOELECTRIC EMBEDDED TRA.docx
Running head ACQUISITION STRATEGY PIEZOELECTRIC EMBEDDED TRA.docx
 
Kreischer Miller Architecture & Engineering Industry Seminar
Kreischer Miller Architecture & Engineering Industry SeminarKreischer Miller Architecture & Engineering Industry Seminar
Kreischer Miller Architecture & Engineering Industry Seminar
 
Yam yih hwan pp1 assignment aug 14
Yam yih hwan   pp1 assignment aug 14Yam yih hwan   pp1 assignment aug 14
Yam yih hwan pp1 assignment aug 14
 
Core_Services_White Papers Oracle Service PUR.pdf
Core_Services_White Papers Oracle Service PUR.pdfCore_Services_White Papers Oracle Service PUR.pdf
Core_Services_White Papers Oracle Service PUR.pdf
 
Construction claims, disputes and project closure
Construction claims, disputes and project closureConstruction claims, disputes and project closure
Construction claims, disputes and project closure
 
Construction Contract Issues for Owners of Residences
Construction Contract Issues for Owners of ResidencesConstruction Contract Issues for Owners of Residences
Construction Contract Issues for Owners of Residences
 
Selecting ERP for Oil and Gas industry contractors and vendors
Selecting ERP for Oil and Gas industry contractors and vendorsSelecting ERP for Oil and Gas industry contractors and vendors
Selecting ERP for Oil and Gas industry contractors and vendors
 
ConstructionFlow
ConstructionFlowConstructionFlow
ConstructionFlow
 
RESUME FOR PROCUREMENT & CONTRACTS ENGINEER
RESUME FOR PROCUREMENT & CONTRACTS ENGINEERRESUME FOR PROCUREMENT & CONTRACTS ENGINEER
RESUME FOR PROCUREMENT & CONTRACTS ENGINEER
 
EMLI Training-An introduction to epc contract-clause by clause-Prepared by: D...
EMLI Training-An introduction to epc contract-clause by clause-Prepared by: D...EMLI Training-An introduction to epc contract-clause by clause-Prepared by: D...
EMLI Training-An introduction to epc contract-clause by clause-Prepared by: D...
 
Pre Bid Risk Assessment
Pre Bid Risk AssessmentPre Bid Risk Assessment
Pre Bid Risk Assessment
 
White papers selecting erp for oil and gas industry contractors and vendors
White papers selecting erp for oil and gas industry contractors and vendorsWhite papers selecting erp for oil and gas industry contractors and vendors
White papers selecting erp for oil and gas industry contractors and vendors
 

More from My own

eBook_ Digitizing and Automating Work Packaging (3).pdf
eBook_ Digitizing and Automating Work Packaging (3).pdfeBook_ Digitizing and Automating Work Packaging (3).pdf
eBook_ Digitizing and Automating Work Packaging (3).pdfMy own
 
Procurement and Contract Management Strategy-1.docx
Procurement and Contract Management Strategy-1.docxProcurement and Contract Management Strategy-1.docx
Procurement and Contract Management Strategy-1.docxMy own
 
AWP-Education-Primer.pdf
AWP-Education-Primer.pdfAWP-Education-Primer.pdf
AWP-Education-Primer.pdfMy own
 
The importance of 3 Core NEC Time Clauses when submitting a programme.docx
The importance of 3 Core NEC Time Clauses when submitting a programme.docxThe importance of 3 Core NEC Time Clauses when submitting a programme.docx
The importance of 3 Core NEC Time Clauses when submitting a programme.docxMy own
 
ENR Sep 2018 - Best Global Project Award - Sidra Citation -w Picture.pdf
ENR Sep 2018 - Best Global Project Award  - Sidra Citation -w Picture.pdfENR Sep 2018 - Best Global Project Award  - Sidra Citation -w Picture.pdf
ENR Sep 2018 - Best Global Project Award - Sidra Citation -w Picture.pdfMy own
 
Andrew 2008 Ipma Assessor Certificate
Andrew 2008 Ipma Assessor CertificateAndrew 2008 Ipma Assessor Certificate
Andrew 2008 Ipma Assessor CertificateMy own
 
2008 Ipma Pe Training Beijing
2008 Ipma Pe Training Beijing2008 Ipma Pe Training Beijing
2008 Ipma Pe Training BeijingMy own
 
2007 Advanced Primavera Project Management Module 6.0 Training
2007 Advanced Primavera Project Management Module 6.0 Training2007 Advanced Primavera Project Management Module 6.0 Training
2007 Advanced Primavera Project Management Module 6.0 TrainingMy own
 
Cipa 2009 Contract Master Class
Cipa 2009 Contract Master ClassCipa 2009 Contract Master Class
Cipa 2009 Contract Master ClassMy own
 
2010 Ipma Pe Training Beijing
2010 Ipma  Pe Training Beijing2010 Ipma  Pe Training Beijing
2010 Ipma Pe Training BeijingMy own
 
120606 Contract Management Skill Checklist &amp; Experience Grid Andrew Ng
120606  Contract Management Skill Checklist &amp; Experience Grid   Andrew Ng120606  Contract Management Skill Checklist &amp; Experience Grid   Andrew Ng
120606 Contract Management Skill Checklist &amp; Experience Grid Andrew NgMy own
 
Countries at the Forefronts of Project Management Excellence
Countries at the Forefronts of Project Management ExcellenceCountries at the Forefronts of Project Management Excellence
Countries at the Forefronts of Project Management ExcellenceMy own
 
Aw Award Marketing Presentation 2012
Aw Award Marketing Presentation 2012Aw Award Marketing Presentation 2012
Aw Award Marketing Presentation 2012My own
 
110801Proposed Fidic Contract Framework For Complex Epc Projects
110801Proposed Fidic Contract Framework For Complex Epc Projects110801Proposed Fidic Contract Framework For Complex Epc Projects
110801Proposed Fidic Contract Framework For Complex Epc ProjectsMy own
 
Skills &amp; Experience Compared with Planning Fraternity
Skills &amp; Experience Compared with Planning FraternitySkills &amp; Experience Compared with Planning Fraternity
Skills &amp; Experience Compared with Planning FraternityMy own
 
Ipma Proj Excel Mtg09
Ipma Proj Excel Mtg09Ipma Proj Excel Mtg09
Ipma Proj Excel Mtg09My own
 
Ipma Pe Draf Tnewassessmenttables Tm 20090515
Ipma Pe Draf Tnewassessmenttables Tm 20090515Ipma Pe Draf Tnewassessmenttables Tm 20090515
Ipma Pe Draf Tnewassessmenttables Tm 20090515My own
 

More from My own (17)

eBook_ Digitizing and Automating Work Packaging (3).pdf
eBook_ Digitizing and Automating Work Packaging (3).pdfeBook_ Digitizing and Automating Work Packaging (3).pdf
eBook_ Digitizing and Automating Work Packaging (3).pdf
 
Procurement and Contract Management Strategy-1.docx
Procurement and Contract Management Strategy-1.docxProcurement and Contract Management Strategy-1.docx
Procurement and Contract Management Strategy-1.docx
 
AWP-Education-Primer.pdf
AWP-Education-Primer.pdfAWP-Education-Primer.pdf
AWP-Education-Primer.pdf
 
The importance of 3 Core NEC Time Clauses when submitting a programme.docx
The importance of 3 Core NEC Time Clauses when submitting a programme.docxThe importance of 3 Core NEC Time Clauses when submitting a programme.docx
The importance of 3 Core NEC Time Clauses when submitting a programme.docx
 
ENR Sep 2018 - Best Global Project Award - Sidra Citation -w Picture.pdf
ENR Sep 2018 - Best Global Project Award  - Sidra Citation -w Picture.pdfENR Sep 2018 - Best Global Project Award  - Sidra Citation -w Picture.pdf
ENR Sep 2018 - Best Global Project Award - Sidra Citation -w Picture.pdf
 
Andrew 2008 Ipma Assessor Certificate
Andrew 2008 Ipma Assessor CertificateAndrew 2008 Ipma Assessor Certificate
Andrew 2008 Ipma Assessor Certificate
 
2008 Ipma Pe Training Beijing
2008 Ipma Pe Training Beijing2008 Ipma Pe Training Beijing
2008 Ipma Pe Training Beijing
 
2007 Advanced Primavera Project Management Module 6.0 Training
2007 Advanced Primavera Project Management Module 6.0 Training2007 Advanced Primavera Project Management Module 6.0 Training
2007 Advanced Primavera Project Management Module 6.0 Training
 
Cipa 2009 Contract Master Class
Cipa 2009 Contract Master ClassCipa 2009 Contract Master Class
Cipa 2009 Contract Master Class
 
2010 Ipma Pe Training Beijing
2010 Ipma  Pe Training Beijing2010 Ipma  Pe Training Beijing
2010 Ipma Pe Training Beijing
 
120606 Contract Management Skill Checklist &amp; Experience Grid Andrew Ng
120606  Contract Management Skill Checklist &amp; Experience Grid   Andrew Ng120606  Contract Management Skill Checklist &amp; Experience Grid   Andrew Ng
120606 Contract Management Skill Checklist &amp; Experience Grid Andrew Ng
 
Countries at the Forefronts of Project Management Excellence
Countries at the Forefronts of Project Management ExcellenceCountries at the Forefronts of Project Management Excellence
Countries at the Forefronts of Project Management Excellence
 
Aw Award Marketing Presentation 2012
Aw Award Marketing Presentation 2012Aw Award Marketing Presentation 2012
Aw Award Marketing Presentation 2012
 
110801Proposed Fidic Contract Framework For Complex Epc Projects
110801Proposed Fidic Contract Framework For Complex Epc Projects110801Proposed Fidic Contract Framework For Complex Epc Projects
110801Proposed Fidic Contract Framework For Complex Epc Projects
 
Skills &amp; Experience Compared with Planning Fraternity
Skills &amp; Experience Compared with Planning FraternitySkills &amp; Experience Compared with Planning Fraternity
Skills &amp; Experience Compared with Planning Fraternity
 
Ipma Proj Excel Mtg09
Ipma Proj Excel Mtg09Ipma Proj Excel Mtg09
Ipma Proj Excel Mtg09
 
Ipma Pe Draf Tnewassessmenttables Tm 20090515
Ipma Pe Draf Tnewassessmenttables Tm 20090515Ipma Pe Draf Tnewassessmenttables Tm 20090515
Ipma Pe Draf Tnewassessmenttables Tm 20090515
 

Recently uploaded

Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...lizamodels9
 
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deckPitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deckHajeJanKamps
 
Organizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessOrganizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessSeta Wicaksana
 
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptxContemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptxMarkAnthonyAurellano
 
Marketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent ChirchirMarketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent Chirchirictsugar
 
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfIntro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfpollardmorgan
 
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu MenzaYouth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu Menzaictsugar
 
MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?Olivia Kresic
 
Market Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMarket Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMintel Group
 
Case study on tata clothing brand zudio in detail
Case study on tata clothing brand zudio in detailCase study on tata clothing brand zudio in detail
Case study on tata clothing brand zudio in detailAriel592675
 
2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis Usage2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis UsageNeil Kimberley
 
Kenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby AfricaKenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby Africaictsugar
 
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCRashishs7044
 
Call Girls Miyapur 7001305949 all area service COD available Any Time
Call Girls Miyapur 7001305949 all area service COD available Any TimeCall Girls Miyapur 7001305949 all area service COD available Any Time
Call Girls Miyapur 7001305949 all area service COD available Any Timedelhimodelshub1
 
Buy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail AccountsBuy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail AccountsBuy Verified Accounts
 
Annual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesAnnual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesKeppelCorporation
 
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
Keppel Ltd. 1Q 2024 Business Update  Presentation SlidesKeppel Ltd. 1Q 2024 Business Update  Presentation Slides
Keppel Ltd. 1Q 2024 Business Update Presentation SlidesKeppelCorporation
 
Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737Riya Pathan
 
Islamabad Escorts | Call 03070433345 | Escort Service in Islamabad
Islamabad Escorts | Call 03070433345 | Escort Service in IslamabadIslamabad Escorts | Call 03070433345 | Escort Service in Islamabad
Islamabad Escorts | Call 03070433345 | Escort Service in IslamabadAyesha Khan
 

Recently uploaded (20)

Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
 
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deckPitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
 
Organizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessOrganizational Structure Running A Successful Business
Organizational Structure Running A Successful Business
 
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptxContemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
 
Marketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent ChirchirMarketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent Chirchir
 
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfIntro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
 
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu MenzaYouth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
 
MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?
 
Market Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMarket Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 Edition
 
Case study on tata clothing brand zudio in detail
Case study on tata clothing brand zudio in detailCase study on tata clothing brand zudio in detail
Case study on tata clothing brand zudio in detail
 
Corporate Profile 47Billion Information Technology
Corporate Profile 47Billion Information TechnologyCorporate Profile 47Billion Information Technology
Corporate Profile 47Billion Information Technology
 
2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis Usage2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis Usage
 
Kenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby AfricaKenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby Africa
 
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
 
Call Girls Miyapur 7001305949 all area service COD available Any Time
Call Girls Miyapur 7001305949 all area service COD available Any TimeCall Girls Miyapur 7001305949 all area service COD available Any Time
Call Girls Miyapur 7001305949 all area service COD available Any Time
 
Buy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail AccountsBuy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail Accounts
 
Annual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesAnnual General Meeting Presentation Slides
Annual General Meeting Presentation Slides
 
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
Keppel Ltd. 1Q 2024 Business Update  Presentation SlidesKeppel Ltd. 1Q 2024 Business Update  Presentation Slides
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
 
Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737
 
Islamabad Escorts | Call 03070433345 | Escort Service in Islamabad
Islamabad Escorts | Call 03070433345 | Escort Service in IslamabadIslamabad Escorts | Call 03070433345 | Escort Service in Islamabad
Islamabad Escorts | Call 03070433345 | Escort Service in Islamabad
 

Beyond Contract Series Article One

  • 1. Article ONE “BEYOND CONTRACT” SERIES OF MUSINGS -- LESSONS LEARNED FROM 27 YEARS OF CONTRACT AND COMMERCIAL MANAGEMENT Beyond Contract : Reliance on Instituted Procedure Maturity and Compliance in the Prevention of Unfounded Contractual Claims Under International EPC and Turnkey Contracts. Andrew Ng, B Sc (Hons) Construction Management, Change is an inevitable part of any project but some risks can be clearly identified and separated from those which can’t or haven’t been considered as best managed by the Contractor. Against these risk must be allocated appropriate rewards, incentives and reimbursements of resources which Contractor have agreed to carry throughout the project duration. Unless there exceptional circumstances which made those allocation grossly inadequate, like misrepresentation by the Employers etc., there can’t be too many circumstances they need to be separately reimbursed, extra over the Contract sum. However, what to do next is where the difference begins between the approach of practitioners of the science of project control and the approach of those who are not. As Contract and Project Contract consultant to many clients, I have never been ceased to be amazed by the prevalence of a naive belief amongst many that reliance on some well-crafted Contract clauses alone would somehow discourage the Contractors from engineering some dubious ground for recovery of prelims and other costs. They have this puzzling abhorrence of what they consider redundant procedures and processes beyond those what the professional would consider as whimsical and impotent “motherhood statement like” write-ups. On my part I have always been requiring the Contractors to comply procedures which require the Contractors’ provision of quantities of reasonably verifiable records of man-hours of labour, management and plant/equipment used throughout the project. It may have something to do with the many failed projects(where the Clients paid millions of dollars) and the lessons I learned there that the Contractor's honesty is not to be expected as a given or foregone conclusion. It is rather the results of tough policing made possible through properly detailed procedures which enable the Employers to speaking softly but always wielding a big stick to demand the Contractor’s respect. To enable the Employer’s Rep achieving a decent degree of policing, I have always advocated supplementing the Contract Document and the Employer’s Requirements with the following:- a) complete suite of procedures (or process, usually forming part of the Employer's Requirement) stipulating the Contractor's obligation and commitment on strict compliance with a set of prior-agreed project deliverables, their timely submission of records of meetings, plant and labour records and returns at pre-set intervals. And if external parties are relied upon for supervision, the contract would further prescribes obligation on the part of the PMC;s team members and the Employers staff (where assigned) to attend to such deliverables and records and certifying them as true reflection of their field observation of the resources expended by the Contractor. For good measures too, the project managers are often required to rotate these assigned resources every quarter to avoid familiarity with any particular ground of contractors workforce or subcontractors; b) clearly defined baselines of these performance and resources requirement, with quantities and major categories of staff, labour, vehicles fuels and etc., which are tabulated in a histogram spreading over the whole Contract Period including those time identified as free floats in the Construction/Baseline programme. 2nd Aug 2011 Andrew Ng, Consultant at RDP Consultants Pty Ltd Australia
  • 2. Article ONE “BEYOND CONTRACT” SERIES OF MUSINGS -- LESSONS LEARNED FROM 27 YEARS OF CONTRACT AND COMMERCIAL MANAGEMENT In nearly all tender clarification meetings before award, I would revisit each of the above and negotiate and rationalise these deliverables, procedures, processes, quantities and rates of each and require the Contractor to confirm their acceptance of these parameters as the baselines beyond which their claims begin to have any chance to be considered. In most remote mining sites or in those more compact urban site, I also advocated the use of access control for those plant and human resources entering site, site offices as well as mess/camps as means of registering the hours and days of work . For those sites other than above, monitoring may be done through some RFID, which should be relatively cheap now. But I must confess that I have not as yet worked on a project which requires the latter todate. Even in FIDIC Silver Book type of EPC Contract I would not be fooled into a complacent belief or reliance on high level Pricing Schedule (<200 cost breakdowns/quantities) as the means of benchmarking the Contractor's claim entitlement. This is even if the Contractors can prove to me that it has done for example, the same configuration of CCPP twenty or more times before. To pinnacles of the Employer's sins would be to accept Pricing Schedule without any kind of Prelims breakdown, especially the details of those recurring ones separated from those for mobilisation and demobilisation. Even in FIDIC Silver Book type of EPC Contract I would not be fooled into a complacent belief or reliance on high level Pricing Schedule ( those with <200 cost breakdowns/quantities) as the means of benchmarking the Contractor's claim entitlement. This is even if the Contractors can prove to me that it has done for example, the same configuration of CCPP twenty or more times before. But I can tell from most of the projects in the skill-constrained resource industries in Australia Asia and Africa, the Contractors are struggling to even assemble a team with half the years of experience or half of the complete skillsets normally required in executing such a project. One needs to either have some superior connection with the all mighty above or an indomitable conviction of one’s infallibility, to rely on such poorly equipped parties to execute its project. But nothing could surpass the pinnacles of the Employer's sins than to accept Pricing Schedule without any kind of Prelims breakdown, especially the details of those recurring ones separated from those for mobilisation and demobilisation. It is nothing short of inviting future claims and headaches if Employers’ beliefs and relances like those cited above stand uncorrected. In fact most savvy contractors consider the mere absence of project control procedures requirements and properly configured breakdown of prelims from the Contract document as the strongest sign of inviting open season on such misguided if not foolish paymaster. For them, these clients are not worthy of any sympathies especially if they are long on ignorance but short on acumen. 2nd Aug 2011 Andrew Ng, Consultant at RDP Consultants Pty Ltd Australia