Bardarash is located 70 km North of Erbil, the Capital of Iraqi Kurdistan
Region. The population consists mainly of Sunni Muslim Kurds as well as
some Christians and Yazidis.
BardaRash District
• The name of Bardarash city means “black stone”.
• Under the Ottoman Empire, Bardarash was recognized first as a district (Nahiya)
in 1879. In 2006 Bardarash became a district of Dohuk province within the
semi-autonomous Kurdistan Region of Iraq (KRI), governed by the Kurdistan
Regional Government (KRG). The KRG has it’s own parliament and security
forces, but uses the Iraqi dinar and is represented in the Iraqi Parliament.
• It was also known as ‘Ashair Al Sab’aa, which it means the "Seven Tribes" in
English, because there are seven major tribes of the Gorani people living in
Bardarash.
• Bardarash District is located between two rivers which they are Upper- Zab/ Zey
Badinan and Xazir. These rivers flow into the nearby Tigris river.
• The land is used largely for agriculture: grazing, wheat growing and other crops.
It is very hot (up to 50 C) and very dry in the summer and, lush and green in late
winter and early spring.
• Bardarash consists of 7 villages that are linked to Bardarash center and three
sub-districts, which are Daratu (29 villages), Roviya (49 villages), Kalak (29
villages) . The population of Bardarash District now is more than 135,000
people. Slide 3
Bardarash District
Slide 4
Mayor of Bardarash
Mr. Serdar Barzingi
Locals celebrating
Bardarash Festival
Slide 5
Community Affairs – Management system
Local
Bardarash
Authorities
Internal
(Afren)
MNR & KRG
Community
& NGOs
Engagement
Engagement - NGOs , Syrian refugee camp
Slide 6
Certificate of appreciation to Afren for donating 10 sea containers to the Syrian refugee camp
in Gawylan, this area falls under the district of Bardarash, The refugee camp director was
very grateful as the containers will allow for shelter & storages for the growing numbers of
refugees in the area.
Engagement - Woman Union , Education
Slide 7
Certificate of appreciation from
BR Education Director to Afren
for supporting Education system.
A gift from the Head of Women
Union to Afren CSR for supporting
their union in Bardarash
Engagement - Universities
Slide 8
Job Fair & Seminars
Afren supporting the Capacity Building in KRG Universities
Engagement - Community
Slide 9
Afren is known as the best oil company in community
relations in KRG
Engagement - Community
Slide 10
Afren CSR with a village chief
Afren CSR with Village Chiefs &
Community leaders
Engagement - Community
Slide 11
CSR officer with Landowners
David Kennedy with Texas
cowboy in BR
Engagement - Local Authorities
Slide 12
During Crop & Land compensation process Afren CSR
with Government committee & landowners.
Seismic crop damageLand Survey Crop payment process
Engagement - Local Authorities
Slide 13
Paying Crop & Land compensation to Land
owners by Afren CSR & Government committee
Engagement - Local Authorities
Slide 14
Afren CSR, HSE, Operation Manager
meeting with the Mayor of BR, Health
Dept. and BR Security
Commanders
Afren General Manager & Security
Manager with BR Fire Dept.
Engagement - MNR & KRG level
Slide 15
David Kennedy with Safeen
Dizayee the KRG President
Spokesman at the KRG job fair
CSR team with the MNR Chairman
Mr. Saad Sadollah
Engagement - Afren Staff
Slide 16
CSR on-going coordination with
other departments (C&P, Finance)
in all projects
Afren CSR, External Relation Manager
and Office Assist Manager meeting
with the former first lady of Iraq, Mrs.
Nasrin Barwari.
CSR Project – Soccer Pitch
Slide 17
Soccer pitch located in Bardarash at an excellent central
location of the city that brought a positive impact on the
youth of BR.
CSR Project – Soccer Pitch
Slide 18
Government head of committee
Engineer inspecting work progress
Project completed
CSR Project – Afren Education Hall
Slide 19
Before After
This hall is getting used for BR formal ceremonies,
Student exams & for community celebrations.
CSR Project – Afren Education Hall
Slide 20
Music Band Seminar
CSR Project - Doctors Accommodation
Slide 21
Before After
10 new doctors were transferred to work at Bardarash hospital
and allocated with subsidized housing in poor condition. Afren
refurbished and furnished the accommodations.
CSR Project - Doctors Accommodation
Slide 22
This project was low cost and completed in short time duration.
It made an instant impact in improving the quality of living
conditions for the doctors who serve the community.
Before & After
CSR Project – Bardarash Women Unions
Slide 23
There are two women union centers run by volunteers. These centers provide
the following services to the women of Bardarash: sewing classes, driving
lessons, computer, language classes and education seminars
CSR Project – Bardarash Woman's Union
Slide 24
Women Union opening
ceremony
Afren purchased IT Equipment,
sewing machines, furniture and
renovated the building.
CSR Project - Construction of medical and emergency unit
Slide 25
Background: there was no Emergency Hospital to treat patients in the
case of emergency, patients are normally getting transferred to hospitals
in Dohuk or Erbil, putting increased risks to patients health & life.
Before Ongoing
CSR Project - Construction of medical and emergency unit
Slide 26
Impact: This will have a life saving impact to the community as patients
in emergency cases can be treated and stabilised at Bardarash before
being transferred to other central hospitals in Dohuk or Erbil, hence
increasing the chances of survival.
CSR Project - Afren park
Slide 27
The oldest park in the district, dating back to the 1970’s, had been neglected over
the years. The park is at the centre of Bardarash with easy public access and it can
be used daily by the community. This was the high priority project requested by
the Bardarash Mayor, municipality office and the local community.
Before After
CSR Project - Afren park
Slide 28
Impact: the park is used by majority of local community from surrounding
villages and central Bardarash. By introducing children play area, picnic
tables, snack area and refurbishing washrooms, most families are enjoying
using the park.
CSR Project - Newroz (Kurdish new year)
Slide 29
Supplied and installed the Newroz flame. Newroz is celebrated in
Bardarash every year on a hilltop above the city where locals
gather to observe Kurdish new year. It gives the residents of
Bardarash a new year celebration to remember year after year.
CSR Project – Water Wells
Slide 30
Drilled three water wells: One well in central Bardarash located
near the local park, which provides park irrigation and
community water supply. Wells at Zimzmuk village and Kheleki
village addressed critical water shortages.
Bardarash city Zimzmuk VillageKheleki Village
CSR Project – Top Student recognition awards
Slide 31
This ceremony will be a repeated every year to award high
grade/achieving Bardarash students with gifts to recognize their
academic achievements & encourage future students. These awards
highlight the importance of education in the region.
CSR Project - Bardarash community Centre
Slide 32
Afren supplied the community center with furniture & indoor
sporting equipment such as ping pong table, pool table and musical
instruments. Now the recreational life of Bardarash people has
been improved with all the entertainment projects provided by
CSR Project - Bardarash community Centre
Slide 33
David Kennedy playing pool with the Mayor
Too bad the Mayor won the competition!
Local Leaders with Afren
Slide 34
Project Selection & Planning
Gap
Analysis
• Gather information from local
authorities – Mayor’s office
Internal
Review
(Afren)
• Share information & ideas
internally with management.
Seek approval
Review with
Government
• Share information & ideas
with MNR CSR department
Community Affairs – Management system
Start Project
Slide 35
Community Challenge 1 – Local contractors
Community Affairs – Management system
Problem: Local companies are finding it difficult to compete for
projects. i.e. small value projects such as water hauling, supplying fuel,
catering etc..
Solution: Set up tendering workshops to assist in pre-qualification &
expectations
Result: Local company is given a chance to compete and therefore
they do not feel that they have been left out
Slide 36
Community Challenge 2 – Local employment
Community Affairs – Management system
Problem: Local villagers getting frustrated because they are not being
offered employment. (Mostly unskilled work: cleaning, catering,
maintenance, etc..
Solution: Set up a database with the assistance of the Mayor’s office
and village elders, listing people with their contact details looking for
employment.
Result: Afren CSR has an up to date list of villagers looking for work,
which is distributed to our operations and contractors.
Slide 37
Challenges within Afren
Community Affairs – Management system
Challenge: Applying corporate processes and procedures to local
contractors. The biggest challenge CSR has is getting local companies
to follow and meet requirements such as complying with technical &
EHS standards.
Solution: Simplify the process. Give the local companies an
opportunity to perform on a trial period and give them adequate
training so they can perform the job.
Outcome: More local companies will be educated to follow procedures
and meet required Afren standards, therefore leading to better
community relations.
Slide 38
Community Affairs – Management system
Sustainability
Example: Bardarash Park Renovation Project
• Park is in constant use by local community in a central location
• Managed by Municipality Directorate of Bardarash
• Positive environmental impact - tree & flower plantings
• Creates jobs for locals
• Multiple usage, i.e. picnics, sports and children's play area
• Park is upgradable - Afren plan to expand on project for many
years to come
Slide 39
Community Affairs – Management system
Many government projects in Kurdistan are non-sustainable
• Authorities do not follow up on projects
• No long term planning , training or procedures in place
• Lack of project management mostly due to limited experience
Slide 40
Community Affairs – Management system
Project handover process
Completed
project by
Afren
Committee
inspection
& approval
Project
handover
to local
authorities
Afren CSR to
follow up on
future
requirements
Slide 41
Community Projects Summery 2013 Completion Date
Water wells: Zimzimuk, Kheleki and Central Bardarash Feb 2013
Purchase and installation of Nawroz torch March 2013
Furnish and equip Bardarash education hall March 2013
Furnish and decorate subsidized doctor’s housing April 2013
Renovation of existing soccer field, Bardarash April 2013
IT and Office equipment for BR Agriculture and land office April 2013
Top Student Recognition Ceremony (2nd year running) Aug 2013
Bardarash City Park Restoration Oct 2013
Construct a new M&E wing at Bardarash central hospital On-going
Community Affairs – Management system
Community Affairs – Management system
Slide 42
Hishyar Bamerni Reza Khaleghi
CSR Officer External Relation & CSR Manager

More Related Content

What's hot (10)

deepak gorad Final csr
deepak gorad Final csrdeepak gorad Final csr
deepak gorad Final csr
 
A REPORT
A    REPORTA    REPORT
A REPORT
 
report
reportreport
report
 
900 East Market Street Master Plan Design Jan 2007
900 East Market Street Master Plan Design Jan 2007900 East Market Street Master Plan Design Jan 2007
900 East Market Street Master Plan Design Jan 2007
 
Master Plan2
Master Plan2Master Plan2
Master Plan2
 
Sasaki Parks Master Plan Presentation
Sasaki Parks Master Plan PresentationSasaki Parks Master Plan Presentation
Sasaki Parks Master Plan Presentation
 
Sasaki Bridgeport Parks Master Plan Final Presentation
Sasaki Bridgeport Parks Master Plan Final PresentationSasaki Bridgeport Parks Master Plan Final Presentation
Sasaki Bridgeport Parks Master Plan Final Presentation
 
Case study on village devp.
Case study on village devp.Case study on village devp.
Case study on village devp.
 
Sibale, Romblon Master Development Plan
Sibale, Romblon Master Development PlanSibale, Romblon Master Development Plan
Sibale, Romblon Master Development Plan
 
Hume_Pride_Spring_2012
Hume_Pride_Spring_2012Hume_Pride_Spring_2012
Hume_Pride_Spring_2012
 

Similar to Team Workshop - CA management system

NIPM ISTD Seminar 2012 -NMDC
NIPM ISTD Seminar 2012 -NMDCNIPM ISTD Seminar 2012 -NMDC
NIPM ISTD Seminar 2012 -NMDC
Smith Sam
 
Sinead carr setting the scene in south tipperary
Sinead carr setting the scene in south tipperarySinead carr setting the scene in south tipperary
Sinead carr setting the scene in south tipperary
southtippcoco
 
B22934 PPN Work Plan
B22934 PPN Work PlanB22934 PPN Work Plan
B22934 PPN Work Plan
Jamie Moore
 
IRSP Annual Review 2010
IRSP Annual Review 2010IRSP Annual Review 2010
IRSP Annual Review 2010
Shazia Sardar
 

Similar to Team Workshop - CA management system (20)

Lisdoonvarna Sustainable Community Plan 2017 Actions
Lisdoonvarna Sustainable Community Plan 2017 ActionsLisdoonvarna Sustainable Community Plan 2017 Actions
Lisdoonvarna Sustainable Community Plan 2017 Actions
 
Srijan
SrijanSrijan
Srijan
 
AQUA FARMING PROJECT.HARSAH.pdf
AQUA FARMING PROJECT.HARSAH.pdfAQUA FARMING PROJECT.HARSAH.pdf
AQUA FARMING PROJECT.HARSAH.pdf
 
Regional Australia Institute, Social Infrastructure Presentation
Regional Australia Institute, Social Infrastructure PresentationRegional Australia Institute, Social Infrastructure Presentation
Regional Australia Institute, Social Infrastructure Presentation
 
NIPM ISTD SEMINAR 2012- ITC ABD
NIPM ISTD SEMINAR 2012- ITC ABDNIPM ISTD SEMINAR 2012- ITC ABD
NIPM ISTD SEMINAR 2012- ITC ABD
 
NIPM ISTD Seminar 2012 -NMDC
NIPM ISTD Seminar 2012 -NMDCNIPM ISTD Seminar 2012 -NMDC
NIPM ISTD Seminar 2012 -NMDC
 
Quality of Life + Community Supportive Services Presentation
Quality of Life + Community Supportive Services PresentationQuality of Life + Community Supportive Services Presentation
Quality of Life + Community Supportive Services Presentation
 
Teeny Tiny Summit - Reslience - Opasatika Community Hub - October 28, 2020
Teeny Tiny Summit - Reslience - Opasatika Community Hub - October 28, 2020Teeny Tiny Summit - Reslience - Opasatika Community Hub - October 28, 2020
Teeny Tiny Summit - Reslience - Opasatika Community Hub - October 28, 2020
 
Sustainable model community development
Sustainable model community development Sustainable model community development
Sustainable model community development
 
Sustainable community development model
Sustainable community development modelSustainable community development model
Sustainable community development model
 
Sinead carr setting the scene in south tipperary
Sinead carr setting the scene in south tipperarySinead carr setting the scene in south tipperary
Sinead carr setting the scene in south tipperary
 
B22934 PPN Work Plan
B22934 PPN Work PlanB22934 PPN Work Plan
B22934 PPN Work Plan
 
Hillside-Quadra Community News Fall 2014
Hillside-Quadra Community News Fall 2014Hillside-Quadra Community News Fall 2014
Hillside-Quadra Community News Fall 2014
 
Tom Addistcott Co-production: how a community successfully acquired £1.2 mil...
Tom Addistcott  Co-production: how a community successfully acquired £1.2 mil...Tom Addistcott  Co-production: how a community successfully acquired £1.2 mil...
Tom Addistcott Co-production: how a community successfully acquired £1.2 mil...
 
CSR Report PPT.pptx
CSR Report PPT.pptxCSR Report PPT.pptx
CSR Report PPT.pptx
 
COR_SOE_1011
COR_SOE_1011COR_SOE_1011
COR_SOE_1011
 
Rainier Beach Environment Action Team Presentation 2010
Rainier Beach Environment Action Team Presentation 2010Rainier Beach Environment Action Team Presentation 2010
Rainier Beach Environment Action Team Presentation 2010
 
Maharashtra's performance in TSC_Nitin Mane_2012
Maharashtra's performance in TSC_Nitin Mane_2012Maharashtra's performance in TSC_Nitin Mane_2012
Maharashtra's performance in TSC_Nitin Mane_2012
 
IRSP Annual Review 2010
IRSP Annual Review 2010IRSP Annual Review 2010
IRSP Annual Review 2010
 
IRSP Annual Review 2010
IRSP Annual Review 2010IRSP Annual Review 2010
IRSP Annual Review 2010
 

Team Workshop - CA management system

  • 1. By: Reza Khaleghi May 2014 Community Affairs Management System
  • 2. Bardarash District Slide 2 Bardarash is located 70 km North of Erbil, the Capital of Iraqi Kurdistan Region. The population consists mainly of Sunni Muslim Kurds as well as some Christians and Yazidis.
  • 3. BardaRash District • The name of Bardarash city means “black stone”. • Under the Ottoman Empire, Bardarash was recognized first as a district (Nahiya) in 1879. In 2006 Bardarash became a district of Dohuk province within the semi-autonomous Kurdistan Region of Iraq (KRI), governed by the Kurdistan Regional Government (KRG). The KRG has it’s own parliament and security forces, but uses the Iraqi dinar and is represented in the Iraqi Parliament. • It was also known as ‘Ashair Al Sab’aa, which it means the "Seven Tribes" in English, because there are seven major tribes of the Gorani people living in Bardarash. • Bardarash District is located between two rivers which they are Upper- Zab/ Zey Badinan and Xazir. These rivers flow into the nearby Tigris river. • The land is used largely for agriculture: grazing, wheat growing and other crops. It is very hot (up to 50 C) and very dry in the summer and, lush and green in late winter and early spring. • Bardarash consists of 7 villages that are linked to Bardarash center and three sub-districts, which are Daratu (29 villages), Roviya (49 villages), Kalak (29 villages) . The population of Bardarash District now is more than 135,000 people. Slide 3
  • 4. Bardarash District Slide 4 Mayor of Bardarash Mr. Serdar Barzingi Locals celebrating Bardarash Festival
  • 5. Slide 5 Community Affairs – Management system Local Bardarash Authorities Internal (Afren) MNR & KRG Community & NGOs Engagement
  • 6. Engagement - NGOs , Syrian refugee camp Slide 6 Certificate of appreciation to Afren for donating 10 sea containers to the Syrian refugee camp in Gawylan, this area falls under the district of Bardarash, The refugee camp director was very grateful as the containers will allow for shelter & storages for the growing numbers of refugees in the area.
  • 7. Engagement - Woman Union , Education Slide 7 Certificate of appreciation from BR Education Director to Afren for supporting Education system. A gift from the Head of Women Union to Afren CSR for supporting their union in Bardarash
  • 8. Engagement - Universities Slide 8 Job Fair & Seminars Afren supporting the Capacity Building in KRG Universities
  • 9. Engagement - Community Slide 9 Afren is known as the best oil company in community relations in KRG
  • 10. Engagement - Community Slide 10 Afren CSR with a village chief Afren CSR with Village Chiefs & Community leaders
  • 11. Engagement - Community Slide 11 CSR officer with Landowners David Kennedy with Texas cowboy in BR
  • 12. Engagement - Local Authorities Slide 12 During Crop & Land compensation process Afren CSR with Government committee & landowners. Seismic crop damageLand Survey Crop payment process
  • 13. Engagement - Local Authorities Slide 13 Paying Crop & Land compensation to Land owners by Afren CSR & Government committee
  • 14. Engagement - Local Authorities Slide 14 Afren CSR, HSE, Operation Manager meeting with the Mayor of BR, Health Dept. and BR Security Commanders Afren General Manager & Security Manager with BR Fire Dept.
  • 15. Engagement - MNR & KRG level Slide 15 David Kennedy with Safeen Dizayee the KRG President Spokesman at the KRG job fair CSR team with the MNR Chairman Mr. Saad Sadollah
  • 16. Engagement - Afren Staff Slide 16 CSR on-going coordination with other departments (C&P, Finance) in all projects Afren CSR, External Relation Manager and Office Assist Manager meeting with the former first lady of Iraq, Mrs. Nasrin Barwari.
  • 17. CSR Project – Soccer Pitch Slide 17 Soccer pitch located in Bardarash at an excellent central location of the city that brought a positive impact on the youth of BR.
  • 18. CSR Project – Soccer Pitch Slide 18 Government head of committee Engineer inspecting work progress Project completed
  • 19. CSR Project – Afren Education Hall Slide 19 Before After This hall is getting used for BR formal ceremonies, Student exams & for community celebrations.
  • 20. CSR Project – Afren Education Hall Slide 20 Music Band Seminar
  • 21. CSR Project - Doctors Accommodation Slide 21 Before After 10 new doctors were transferred to work at Bardarash hospital and allocated with subsidized housing in poor condition. Afren refurbished and furnished the accommodations.
  • 22. CSR Project - Doctors Accommodation Slide 22 This project was low cost and completed in short time duration. It made an instant impact in improving the quality of living conditions for the doctors who serve the community. Before & After
  • 23. CSR Project – Bardarash Women Unions Slide 23 There are two women union centers run by volunteers. These centers provide the following services to the women of Bardarash: sewing classes, driving lessons, computer, language classes and education seminars
  • 24. CSR Project – Bardarash Woman's Union Slide 24 Women Union opening ceremony Afren purchased IT Equipment, sewing machines, furniture and renovated the building.
  • 25. CSR Project - Construction of medical and emergency unit Slide 25 Background: there was no Emergency Hospital to treat patients in the case of emergency, patients are normally getting transferred to hospitals in Dohuk or Erbil, putting increased risks to patients health & life. Before Ongoing
  • 26. CSR Project - Construction of medical and emergency unit Slide 26 Impact: This will have a life saving impact to the community as patients in emergency cases can be treated and stabilised at Bardarash before being transferred to other central hospitals in Dohuk or Erbil, hence increasing the chances of survival.
  • 27. CSR Project - Afren park Slide 27 The oldest park in the district, dating back to the 1970’s, had been neglected over the years. The park is at the centre of Bardarash with easy public access and it can be used daily by the community. This was the high priority project requested by the Bardarash Mayor, municipality office and the local community. Before After
  • 28. CSR Project - Afren park Slide 28 Impact: the park is used by majority of local community from surrounding villages and central Bardarash. By introducing children play area, picnic tables, snack area and refurbishing washrooms, most families are enjoying using the park.
  • 29. CSR Project - Newroz (Kurdish new year) Slide 29 Supplied and installed the Newroz flame. Newroz is celebrated in Bardarash every year on a hilltop above the city where locals gather to observe Kurdish new year. It gives the residents of Bardarash a new year celebration to remember year after year.
  • 30. CSR Project – Water Wells Slide 30 Drilled three water wells: One well in central Bardarash located near the local park, which provides park irrigation and community water supply. Wells at Zimzmuk village and Kheleki village addressed critical water shortages. Bardarash city Zimzmuk VillageKheleki Village
  • 31. CSR Project – Top Student recognition awards Slide 31 This ceremony will be a repeated every year to award high grade/achieving Bardarash students with gifts to recognize their academic achievements & encourage future students. These awards highlight the importance of education in the region.
  • 32. CSR Project - Bardarash community Centre Slide 32 Afren supplied the community center with furniture & indoor sporting equipment such as ping pong table, pool table and musical instruments. Now the recreational life of Bardarash people has been improved with all the entertainment projects provided by
  • 33. CSR Project - Bardarash community Centre Slide 33 David Kennedy playing pool with the Mayor Too bad the Mayor won the competition! Local Leaders with Afren
  • 34. Slide 34 Project Selection & Planning Gap Analysis • Gather information from local authorities – Mayor’s office Internal Review (Afren) • Share information & ideas internally with management. Seek approval Review with Government • Share information & ideas with MNR CSR department Community Affairs – Management system Start Project
  • 35. Slide 35 Community Challenge 1 – Local contractors Community Affairs – Management system Problem: Local companies are finding it difficult to compete for projects. i.e. small value projects such as water hauling, supplying fuel, catering etc.. Solution: Set up tendering workshops to assist in pre-qualification & expectations Result: Local company is given a chance to compete and therefore they do not feel that they have been left out
  • 36. Slide 36 Community Challenge 2 – Local employment Community Affairs – Management system Problem: Local villagers getting frustrated because they are not being offered employment. (Mostly unskilled work: cleaning, catering, maintenance, etc.. Solution: Set up a database with the assistance of the Mayor’s office and village elders, listing people with their contact details looking for employment. Result: Afren CSR has an up to date list of villagers looking for work, which is distributed to our operations and contractors.
  • 37. Slide 37 Challenges within Afren Community Affairs – Management system Challenge: Applying corporate processes and procedures to local contractors. The biggest challenge CSR has is getting local companies to follow and meet requirements such as complying with technical & EHS standards. Solution: Simplify the process. Give the local companies an opportunity to perform on a trial period and give them adequate training so they can perform the job. Outcome: More local companies will be educated to follow procedures and meet required Afren standards, therefore leading to better community relations.
  • 38. Slide 38 Community Affairs – Management system Sustainability Example: Bardarash Park Renovation Project • Park is in constant use by local community in a central location • Managed by Municipality Directorate of Bardarash • Positive environmental impact - tree & flower plantings • Creates jobs for locals • Multiple usage, i.e. picnics, sports and children's play area • Park is upgradable - Afren plan to expand on project for many years to come
  • 39. Slide 39 Community Affairs – Management system Many government projects in Kurdistan are non-sustainable • Authorities do not follow up on projects • No long term planning , training or procedures in place • Lack of project management mostly due to limited experience
  • 40. Slide 40 Community Affairs – Management system Project handover process Completed project by Afren Committee inspection & approval Project handover to local authorities Afren CSR to follow up on future requirements
  • 41. Slide 41 Community Projects Summery 2013 Completion Date Water wells: Zimzimuk, Kheleki and Central Bardarash Feb 2013 Purchase and installation of Nawroz torch March 2013 Furnish and equip Bardarash education hall March 2013 Furnish and decorate subsidized doctor’s housing April 2013 Renovation of existing soccer field, Bardarash April 2013 IT and Office equipment for BR Agriculture and land office April 2013 Top Student Recognition Ceremony (2nd year running) Aug 2013 Bardarash City Park Restoration Oct 2013 Construct a new M&E wing at Bardarash central hospital On-going Community Affairs – Management system
  • 42. Community Affairs – Management system Slide 42 Hishyar Bamerni Reza Khaleghi CSR Officer External Relation & CSR Manager