Team #1Javier GuerreroJeremy HalbardierOlakunle SosanyaGerardo Trevino DC DISTRUBUTION CONTROLLERSTATUS REPORT #603/31/2010
Project OverviewDesigning a system that takes energy from an array of Solar PV Array’s batteries, and be used in a DC circuit including controlling and safely using the DC power, with special plugs and outlets.
Completed TasksCCET Competition (1/30/2010)Construct DC Controller Prototype (2/20/10)Order Additional Parts Needed (2/25/10)Plan Sr. Design Demo (2/28/10)Plan Sr. Design Demo (3/29/10)
Milestone
Recent tasks1.   Testing DC-DC ConverterOrder Additional Parts Needed
Ongoing/Pending TasksMicrocontroller Algorithm Development  Testing prototype parts.Testing DC to DC ConverterFabricate Sr. Design DemoTesting Battery Charge item with prototype Rough Draft
Project Timeline
Video
Questions

Status report #6