Team #1 submitted their status report #4 on their project to design a DC distribution controller system. They have ordered remaining parts to be delivered by February 6th and will test and verify parts by February 12th. They will construct a prototype by February 20th and order any additional parts needed by February 27th. They will finalize the microcontroller programming for the system by March 10th.