Saint Columban College
COLLEGE OF COMPUTER STUDIES
Software Project Management Plan
for
SCC Newscast System
Mach5
Almonte, Jelly Mae P.
Baltazar, Jessaneth B.
Ching Carl Angelo L.
Ihara Jr, Noel B.
Salazar, Ragde Ama T.
Signature
The following signature indicates approval of the enclosed Software Project Management Plan Document.
Noel B. Ihara
Project manager
Jelly Mae. P. Almonte Carl Angelo L. Ching
System Analyst Programmer
Ragde Ama T. Salazar Jessaneth B. Baltazar
Quality Assurance Documenter
Mr. Neil Owen B. Jandugan
Adviser/Editor
Submitted and accepted by:
Mr. Philipcris C. Encarnacion, MCS
CCS Dean
Change History
Table 1
Revisions Date Reason For Changes Person who
suggested the
changes
Group Name June 16, 2014 Team Celeron change its name to
Mach5 because the meaning of
Celeron itself does not suit the group’s
characteristics.
Jessaneth B. Baltazar
(Documenter)
Title Name September 8,2014 The title of the study was changed
from E-Bulletin to SCC Newscast
System to make it more suitable with
the proposed system.
Ragde Ama T. Salazar
(QA Tester)
List of tables October 24, 2014 The numbering of the tables was
changed and was properly ordered.
Mrs. Janus A. Naparan
(Client)
Purpose, scope
and objectives
October 24, 2014 The sentence construction of the
purpose, scope and objectives was
improved.
Mrs. Janus A. Naparan
(Client)
Schedule and
budget summary
October 24, 2014 The exact breakdown of the schedule
and budget summary were specified.
Mrs. Janus A. Naparan
(Client)
Evolution of plan October 24, 2014 The evolution of plan was changed
and a Gantt chart was presented.
Mrs. Janus A. Naparan
(Client)
Definitions October 24, 2014 The definitions was changed and
stated in complete sentence.
Mrs. Janus A. Naparan
External
interface
October 24, 2014 The external interface was improved
and was changed into a diagram.
Mr. Neil Owen B.
Jandugan
(Adviser)
Internal structure October 24, 2014 The group changed the internal
structure to correct what is wrong on
the diagram.
Mr. Syril Glenn Flores
(Panel)
External October 24, 2014 The group changed the external Mr. Syril Glenn Flores
structure structure to correct what is wrong on
the diagram.
(Panel)
Budget Control
plan
October 24, 2014 The budget control plan was revised
into a paragraph form.
Mr. Francis Rebo
Alegre
(Panel)
Preface
The purpose of this document is to specify the project plan to develop the SCC Newscast system. This document
outlines a brief plan about how the project will be shape. It also includes the milestones and deliverables. The
Software Project Management Plan (SPMP) document will serve as a guide for the student, developing the
product as part of the project. Updates of this document will serve to record the progress of the project.
Table of Contents
Signature....................................................................................................................................................................................2
Change History..........................................................................................................................................................................3
Preface........................................................................................................................................................................................5
Table of Contents.......................................................................................................................................................................6
List of Figures............................................................................................................................................................................8
List of Tables..............................................................................................................................................................................9
1. Overview...............................................................................................................................................................................10
1.1. Project Summary............................................................................................................................................................................10
1.1.1. Purpose, scope and objectives...............................................................................................................................................10
1.1.2. Assumptions And Constraints...............................................................................................................................................10
1.1.3. Project deliverables...............................................................................................................................................................11
1.1.4. Schedule and Budget Summary.............................................................................................................................................11
1.2. Evolution of plan............................................................................................................................................................................12
2. References............................................................................................................................................................................19
3. Definitions ...........................................................................................................................................................................20
4. Project organization............................................................................................................................................................25
4.1. External interface ..........................................................................................................................................................................25
4.2. Internal Structure ...........................................................................................................................................................................25
4.3. Roles and Responsibilities..............................................................................................................................................................26
5. Managerial process plans...................................................................................................................................................27
5.1. Start-Up Plan ................................................................................................................................................................................27
5.1.1. Estimation plan ....................................................................................................................................................................27
5.1.2. Staffing plan .........................................................................................................................................................................27
5.1.3. Resource acquisition plan ....................................................................................................................................................27
5.1.4. Project staff training plan ....................................................................................................................................................27
5.2. Work Plan ......................................................................................................................................................................................28
5.2.1. Work Activities......................................................................................................................................................................28
5.2.2. Schedule Allocation...............................................................................................................................................................28
5.2.3. Resource Allocation..............................................................................................................................................................28
5.2.4. Budget allocation..................................................................................................................................................................29
5.3. Control Plan ...................................................................................................................................................................................29
1.3.1.Requirements Control Plan ...................................................................................................................................................29
1.3.2.Schedule Control Plan ..........................................................................................................................................................29
1.3.3.Budget control plan................................................................................................................................................................30
1.3.4.Quality control plan...............................................................................................................................................................30
1.3.5.Reporting plan ......................................................................................................................................................................30
1.3.6.Metrics collection plan ..........................................................................................................................................................30
1.3.7.Risk management plan...........................................................................................................................................................30
5.3.8 Project closeout plan..............................................................................................................................................................31
6. Technical process plans ....................................................................................................................................................32
6.1. Process Model................................................................................................................................................................................32
6.2. Methods, tools, and techniques.......................................................................................................................................................32
6.3. Infrastructure Plan..........................................................................................................................................................................32
6.3. Product Acceptance Plan................................................................................................................................................................32
7. Supporting process plans ...................................................................................................................................................33
7.1. Configuration management plan ....................................................................................................................................................33
7.2. Verification and validation plan .....................................................................................................................................................33
7.3. Documentation plan .......................................................................................................................................................................33
7.4. Quality assurance plan ...................................................................................................................................................................33
7.5. Reviews and audits.........................................................................................................................................................................33
8.0 Additional Plans..............................................................................................................................................................................33
9. Plan Annexes.......................................................................................................................................................................34
10. Index..................................................................................................................................................................................35
Software Project Management Plan
SCC Newscast System
Document Version: 3.0
Published Date: 27 October 2014
Page 7 of 35
Software Project Management Plan
SCC Newscast System
Document Version: 3.0
Published Date: 27 October 2014
List of Figures
Figure 1: Evolution of Plan…………………………………………………………………..............................12-17
Figure 2: External Interface……….…………………………………………………………………………….…….24
Figure 3: Internal Interface ………………………………………………………………………..………………….24
Page 8 of 35
Software Project Management Plan
SCC Newscast System
Document Version: 3.0
Published Date: 27 October 2014
List of Tables
Table 1: Change History…………………………………………………………………………………….……..3-4
Table 2: Schedule and Budget Summary………………………………………………………...……….……...11
Table 3: Definitions………………………….………………………………………………………………...…19-23
Table 4: Roles and Responsibilities……...………………………………….………………………………….…26
Table 5: Work activities……………………………………………………………………………………….…….28
Table 6: Budget Allocation…..……………………………………………………………………………..……….29
Page 9 of 35
Software Project Management Plan
SCC Newscast System
Document Version: 3.0
Published Date: 27 October 2014
1. Overview
1.1. Project Summary
1.1.1. Purpose, scope and objectives
The scope of this project includes assumptions on where the project is based; and constraints of the project such
as schedule, budget and resources, software to be released, and product interfaces.
Project deliverables also include the list of task that will be delivered to the clients, delivery dates and qualities
required to satisfy the terms of the project agreement.
Schedule and budget summary provides a summary of the schedule and budget for the software project. The level
of detail should be restricted to an itemization of the major work activities and supporting processes.
Project organization that will identify interfaces to organizational entities external to the project and internal and
defines the roles and responsibilities for the project.
The purpose of this document is to highlight the managerial plan for the SCC Newscast system with a goal of
improving the user’s productivity by automating his/her work.
The objective is to enhance the user’s productivity by scheduling the tasks needed to be done in a specific
duration. The task assignment is given respectively and should be followed according to the work plan.
1.1.2. Assumptions And Constraints
The prototyping and documentation of the project shall be finished on October 4, 2014, at the end of the first
semester, S.Y. 2014-2015, of Capstone 1 Project course. All codes shall be written in C# language. The system
shall be standalone application in PC environment on MS Windows XP, Windows 7. The system is easy to install.
When the team develops the system, the group will need a budget in supplying the requirements needed to
establish the system.
The project has the following constraints:
• TIME
- The duration for the project design is one school year.
- By the end of the 2nd
semester, the software product is installed at the Information Office. The set-up of
the computers and other hardware, and the orientation for the users may take several hours.
Page 10 of 35
Software Project Management Plan
SCC Newscast System
Document Version: 3.0
Published Date: 27 October 2014
• STAFF
The Information personnel will be required for the consultation for the system design and process of the
system. The Information Office personnel can also consult the team/developers, when necessary.
1.1.3. Project deliverables
This project deliverables listed below should be provided before the completion of the system. Documents are
used to be presented to the client. It represents the internal system such as the capabilities, scope and limitations,
and etc. It will also present the Approval sheets, Software Requirement Specifications (SRS), Software Project
Management Plan (SPMP), Software Design Description (SDD) and Software Testing Design (STD).
Project Deliverables:
-Documents
-Project Proposal
-Use Case
-SRS
-SPMP
-SDD
-STD
-The SCC Newscast System
1.1.4. Schedule and Budget Summary
Table 2
Month Expenses
June
Record Book ₱ 35.00
Clear Book ₱ 45.00
Transportation ₱ 100.00
July Printing expenses for SRS Document ₱ 100.00
August Transportation ₱ 200.00
Others ₱ 100.00
September Transportation ₱ 200.00
Page 11 of 35
Software Project Management Plan
SCC Newscast System
Document Version: 3.0
Published Date: 27 October 2014
October Printing expenses for SRS Document ₱ 90.00
Printing expenses for SPMP Document ₱ 204.00
Printing expenses for SDD Document ₱ 156.00
Electricity ₱ 500.00
Others ₱ 310.00
TOTAL ₱ 2,040.00
1.2. Evolution of plan
Figure 1
Page 12 of 35
Software Project Management Plan
SCC Newscast System
Document Version: 3.0
Published Date: 27 October 2014
Page 13 of 35
Software Project Management Plan
SCC Newscast System
Document Version: 3.0
Published Date: 27 October 2014
Page 14 of 35
Software Project Management Plan
SCC Newscast System
Document Version: 3.0
Published Date: 27 October 2014
Page 15 of 35
Software Project Management Plan
SCC Newscast System
Document Version: 3.0
Published Date: 27 October 2014
Page 16 of 35
Software Project Management Plan
SCC Newscast System
Document Version: 3.0
Published Date: 27 October 2014
Page 17 of 35
Software Project Management Plan
SCC Newscast System
Document Version: 3.0
Published Date: 27 October 2014
Page 18 of 35
Software Project Management Plan
SCC Newscast System
Document Version: 3.0
Published Date: 27 October 2014
2. References
IEEE Std 1058-1998 IEEE standard for software project management plans.
Page 19 of 35
Software Project Management Plan
SCC Newscast System
Document Version: 3.0
Published Date: 27 October 2014
3. Definitions
Table 3
Term Definition
Acquirer
The individual or organization that specifies requirements for and
accepts delivery of a new or modified software product and its
documentation.
Additional Plan
Contains additional plans required to satisfy product requirements
and contractual terms.
Baseline
A work product that has been formally reviewed and accepted by the
involved parties. A baseline should be changed only through formal
configuration management procedures.
Budget Allocation
Provides a detailed breakdown of necessary resource budgets for
each of the major work activities in the work breakdown structure.
Budget Control Plan
Specifies the control mechanisms to be used to measure the cost of
work completed, compare planned cost to budgeted cost, and
implement corrective action when actual cost does not conform to
budgeted cost.
Configuration Management
Plan
Contains the configuration management plan for the software
project, to include the methods that will be used to provide
configuration identification, control, status accounting, evaluation,
and release management.
Control Plan
Specifies the metrics, reporting mechanisms, and control
procedures necessary to measure, report, and control the product
requirements, the project schedule, budget, and resources, and the
quality of work processes and work products.
Database It is where the collections of all the information being stored.
Documentation Plan
Contains the documentation plan for the software project, to
include plans for generating non-deliverable and deliverable work
products.
Estimation Plan
Specifies the cost and schedule for conducting the project as well as
methods, tools, and techniques used to estimate project cost,
schedule, resource requirements, and associated confidence levels.
External Interface
Describes the organizational boundaries between the project and
external entities.
IEEE The Institute of Electrical and Electronics Engineers (IEEE) is
a membership organization that includes engineers, scientists and
Page 20 of 35
Software Project Management Plan
SCC Newscast System
Document Version: 3.0
Published Date: 27 October 2014
students in electronics and allied fields.
Infrastructure Plan
Specifies the plan for establishing and maintaining the development
environment (hardware, operating system, network, and software),
and the policies, procedures, standards, and facilities required to
conduct the software project.
Internal Structure
Describes the internal structure of the project organization to include
the interfaces among the units of the software development team.
Methods, tools, and techniques
Specifies the development methodologies, programming languages
and other notations, and the tools and techniques to be used to
specify, design, build, test, integrate, document, deliver, modify and
maintain the project deliverable and nondeliverable work products.
In addition, the technical standards, policies, and procedures
governing development and/or modification of the work products
shall be specified.
Metrics Collection Plan
Specifies the methods, tools, and techniques to be used in
collecting and retaining project metrics.
Milestone
Milestone is an event that receives special attention. It is often put at
the end of a stage to mark the completion of a work package or
phase.
Problem Resolution Plan
Specifies the resources, methods, tools, techniques, and
procedures to be used in reporting, analyzing, prioritizing, and
processing software problem reports generated during the project.
Process Improvement Plan
Includes plans for periodically assessing the project, determining
areas for improvement, and implementing improvement plans.
Process Model
Defines the relationships among major project work activities and
supporting processes by specifying the flow of information and work
products among activities and functions, the timing of work products
to be generated, reviews to be conducted, major milestones to be
achieved, baselines to be established, project deliverables to be
completed, and required approvals that span the duration of the
project.
Product Acceptance Plan
Specifies the plan for acquirer acceptance of the deliverable work
products generated by the software project.
Project Agreement
A document or set of documents baseline by the acquirer and the
supplier that specifies the conditions under which the project will be
conducted.
Page 21 of 35
Software Project Management Plan
SCC Newscast System
Document Version: 3.0
Published Date: 27 October 2014
Project Closeout Plan
Contains the plans necessary to ensure orderly closeout of the
software project. Items in the closeout plan should include a staff
reassignment plan, a plan for archiving project materials, a plan for
post- mortem debriefings of project personnel, and preparation of a
final report to include lessons learned and analysis of project
objectives achieved.
Project deliverable A work product to be delivered to the acquirer
Project Staff Training Plan
Specifies the training needed to ensure that necessary skill levels in
sufficient numbers are available to successfully conduct the
software project.
Quality Assurance Plan
Provides the plans for assuring that the software project fulfills its
commitments to the software process and the software product as
specified in the requirements specification, the SPMP, supporting
plans, and any standards, procedures, or guidelines to which the
process or the product must adhere.
Quality Control Plan
Specifies the mechanisms to be used to measure and control the
quality of the work processes and the resulting work products.
Reporting Plan
Specifies the reporting mechanisms, report formats, and information
flows to be used in communicating the status of requirements,
schedule, budget, quality, and other desired or required status
metrics within the project and to entities external to the project.
Requirements Control Plan
Specifies the control mechanisms for measuring, reporting, and
controlling changes to the product requirements
Resource Acquisition Plan
Specifies the plan for acquiring the resources in addition to
personnel needed to successfully complete the project.
Resource Allocation
Provides a detailed itemization of the resources allocated to each
major work activity in the project work breakdown structure.
Reviews and Audits
Specifies the schedule, resources, and methods and procedures to
be used in conducting project reviews and audits.
Risk Management Plan
Specifies the risk management plan for identifying, analyzing, and
prioritizing project risk factors.
Schedule Allocation
Provides scheduling relationships among work activities in a manner
that depicts the time-sequencing constraints and illustrates
opportunities for concurrent work activities.
Page 22 of 35
Software Project Management Plan
SCC Newscast System
Document Version: 3.0
Published Date: 27 October 2014
Schedule Control Plan
Specifies the control mechanisms to be used to measure the
progress of work completed at the major and minor project
milestones, to compare actual progress to planned progress, and to
implement corrective action when actual progress does not conform
to planned progress.
SPMP Software Project Management Plan is the art and science of
planning and leading software projects. It is a sub-discipline of
project management in which software projects are planned,
implemented, monitored and controlled.
Staffing Plan
Specifies the number of staff required by skill level, the project
phases in which the numbers of personnel and types of skills are
needed, and the duration of need.
Start-up Plan
Specifies the estimation plan, staffing plan, resource acquisition
plan, and training plan.
Subcontractor Management
Plan
Contains plans for selecting and managing any subcontractors that
may contribute work products to the software project.
Supplier
An organization that develops some or all of the project deliverables
for an acquirer.
Supporting Process Plan
Contains plans for the supporting processes that span the duration
of the software project.
Technical Process Plan
Specifies the development process model, the technical methods,
tools, and techniques to be used to develop the various work
products; plans for establishing and maintaining the project
infrastructure; and the product acceptance plan.
User A person who uses or interacts with the said system.
Verification and Validation Plan
Contains the verification and validation plan for the software project
to include scope, tools, techniques, and responsibilities for the
verification and validation work activities.
Work Activities
Specifies the various work activities to be performed in the software
project.
Work Activity
A collection of work tasks spanning a fixed duration within the
schedule of a software project.
Work Package
A specification of the work that must be accomplished to complete a
work task.
Work Plan
Specifies the work activities, schedule, resources, and budget
details for the software project.
Page 23 of 35
Software Project Management Plan
SCC Newscast System
Document Version: 3.0
Published Date: 27 October 2014
Work Product
Any tangible item produced during the process of developing or
modifying software.
Work Task The smallest unit of work subject to management accountability.
Page 24 of 35
Software Project Management Plan
SCC Newscast System
Document Version: 3.0
Published Date: 27 October 2014
4. Project organization
4.1. External interface
Figure 2
Ihara as a project manager meets with the client weekly to discuss possible revisions and modification.
4.2. Internal Structure
Figure 3
All the work on this project will be performed by Ihara, Baltazar, Salazar, Almonte and Ching. Ihara as a project
manager meets with the team weekly to discuss possible changes and modification.
Page 25 of 35
Software Project Management Plan
SCC Newscast System
Document Version: 3.0
Published Date: 27 October 2014
4.3. Roles and Responsibilities
Table 4
ROLE RESPONSIBILITIES
Project Manager He/She:
1.Plans, organizes, coordinates, control the activities of the group
2. Has the overall responsibilities for the success of the project.
3. Leads the team in producing, assessing, updating, and reporting
on the plan.
4. Review of testing results and defects to determine/assess impact
to overall project plan and implementation schedule.
5. Review and Approval of the testing strategy, approach, and
plans.
Programmer He/She:
1. Assist with design, analysis, maintenance, documentation, and
testing of software.
2.Code, debug, test, and document routine application programs
3. Design new systems or enhancements to existing systems.
4. Verify that system meets performance criteria.
5. Advise or train users regarding the technical aspects and use of
standard software packages.
6. Design/modify, code, debug, test, and document moderately
complex application systems.
Quality Assurance He/She:
1. Responsible for management of all Quality Assurance functions
include planning, strategy, testing execution and tools.
System Analyst He/She:
1. Collect information to analyze and evaluate existing or proposed
systems.
2. Prepare detailed flow charts and diagrams outlining systems
capabilities and processes.
3. Select among authorized procedures and seek assistance when
guidelines are inadequate, significant deviations are proposed,
or when unanticipated problems arise.
4. Write and maintain system documentation.
Documenter He/She:
1. The documenters kept detailed meeting minutes.
2. Make sure the documents are complete.
Page 26 of 35
Software Project Management Plan
SCC Newscast System
Document Version: 3.0
Published Date: 27 October 2014
5. Managerial process plans
5.1. Start-Up Plan
5.1.1. Estimation plan
As previously stated, the total development time is estimated to be one school year, one school year is divided into
two semesters.
Each semester will cover part of the Gantt chart that was created at the beginning of the project through Microsoft
Excel. Gantt chart excel-based will be used to produce and to track a schedule that includes milestones for the
project.
At the beginning of each work phase, The Mach5 team will have to check the Gantt chart to define the tasks and
schedules. The Mach5 team will assess its status once a week and update and distribute the schedule
accordingly. Every topic listed in Gantt chart will be reviewed by using formal review methods.
5.1.2. Staffing plan
In the first semester, the managerial committee which include Noel Ihara Jr. as the Project Manager, Jessaneth
Baltazar the Documenter and Jelly Mae Almonte the System Analyst will be the head in assigning and
documenting with the help of the Programmer Carl Ching and Quality Assurance Ragde Ama Salazar. For the
second semester the Project Manager, Programmer and Quality Assurance will be the head in finalizing the
system with the assistance of Documenter and System Analyst.
5.1.3. Resource acquisition plan
All necessary hardware, software case tools for the project are already available. The system will be installed on a
computer unit, one in the Information Office as a server and one in each department namely, the College of
Business Education, College of Computer Studies and College of Teachers Education Arts and Sciences as a
client which is ready to use.
5.1.4. Project staff training plan
No additional staff training is needed for this project.
Page 27 of 35
Software Project Management Plan
SCC Newscast System
Document Version: 3.0
Published Date: 27 October 2014
5.2. Work Plan
5.2.1. Work Activities
Table 5
Week 1 SRS Chapter 1 Introduction and Chapter 2 Overall Description documentation.
Week 2 SRS Chapter 3 Specification requirements
Week 3 SPMP Chapter 1 Overview, Chapter 2 References, Chapter 3 Definition, Chapter 4 Project
Organization
Week 4 SPMP Chapter 5 Managerial Process Plans and Finalizing SRS and SPMP.
Week 5 SPMP Chapter 6 Technical Process Plans and Supporting Process Plans.
Week 6 SDD Chapter 1 Introduction and Chapter 2 References.
Week 7 SDD Chapter 3 Decomposition Description and Chapter 4 Dependency Description.
Week 8 SDD Chapter 5 Interface Description.
Week 9 SDD Chapter 6 Detailed Design.
Week 10 SDD Chapter 7 Appendices and Chapter 8 Index.
5.2.2. Schedule Allocation
The project duration is constrained to one semester (prelim, midterm, semi-finals, and finals), with final
deliverables due in the mid of October 2014. We will control our schedule with main artifacts.
5.2.3. Resource Allocation
The whole team member will work separately on their assigned task. The Project manager Noel Ihara will acquire
the role of monitoring the daily progress of the members, oversee implementation and the Quality assurance
Ragde Ama Salazar is responsible for overall quality, and interact with the client. Team members will meet at the
end of each day and discuss problems and progress. Formal meeting with the client will be held at the end of each
week to report progress and determine if any changes needed to be made. The Project manager will ensure that
schedule and budget requirements are met. The Project manager will be also responsible for the risk
management.
Minimizing faults and maximizing user-friendliness will be the project manager’s top priorities. The documenter
Jessaneth Baltazar has the overall responsibility for all documentation and has to ensure that it is up to date.
Page 28 of 35
Software Project Management Plan
SCC Newscast System
Document Version: 3.0
Published Date: 27 October 2014
5.2.4. Budget allocation
Table 6
Budget Allocation Cost
Printing Expenses for SRS, SPMP, SDD
Documents
₱ 550.00
Transportation ₱ 500.00
Electricity ₱ 500.00
Record Book ₱ 35.00
Clear Book ₱ 45.00
Others ₱ 410.00
TOTAL ₱ 2, 040.00
5.3. Control Plan
Any major changes that affect the budget of the project have to be approved by the project manager and
documented by the documenter. No outside quality assurance personnel are involved. The benefits of having
someone other than the individual who carried out the development do the testing will be accomplished by each
person testing another person’s work products.
The project manager will be responsible for ensuring that the project is completed on time and within the
estimated budget. This will be accomplished through daily meetings with the team members. At each meeting,
the documenter and the system analyst will present the day’s progress and problems. The project manager
will determine whether they are progressing as expected and whether they are following the specification
document and the project management plan. Any major problems faced by the team members will immediately b
e reported to the project manager.
1.3.1. Requirements Control Plan
Requirement will be managed in use case description of SRS as requirements are changed. More detailed
Requirement Management Plan Ver. 1.1
1.3.2. Schedule Control Plan
Page 29 of 35
Software Project Management Plan
SCC Newscast System
Document Version: 3.0
Published Date: 27 October 2014
Our team’s planning manager will maintain the schedule in a project document. The planning manager will be
responsible for gathering the individual tasks for each team member and supervise us to ensure the development
of our system’s documentation and the like. If schedule is not on track, our team will follow a schedule control
meeting.
1.3.3. Budget control plan
The budget is handled through funding and is limited in which it has to be consume properly. It will be handled
personally by one of the team members and every fund will be recorded at the Microsoft excel document to ensure
its exact amount funded. Any expenses will be consulted to every member.
1.3.4. Quality control plan
The quality manager will generate a separate Quality Control Plan document. From this document, checklists and
other evaluation measures will be determined necessary or otherwise.
Weekly meetings and reviews at the end of each phase will be the main mechanisms that our team will use to
control the quality of the work process and the resulting work.
In addition, our adviser will monitor quality control throughout the project by the mentoring. Each member is
encouraged to consult our mentor who will meet with the team on a regular class schedule (Mondays and
Thursdays of the month) to review individual and group progress and to address any managerial or technical
issues or questions. The mentor is encouraged to review the team’s work products and to ask questions to
determine the health and progress of the project.
1.3.5. Reporting plan
General Reporting
The team will use a set of applications and methods available from the template given to us by our mentor to
communicate to the client, mentors, and advisors to the status of requirements, schedules, quality, and other
desired or required status metrics for the team project.
Internal Reporting
Team members will submit individual document to the planning manager every Monday and Thursday as regards
to their assigned tasks. The planning manager will consolidate all files and present it to the mentor for checking
and approval. Additionally, the team is required to see and consult the mentor to discuss the project’s current
progress, unresolved issues, and need for assistance.
1.3.6. Metrics collection plan
Each team member will submit individual progress and every Monday and Thursday, each member will report
productivity on the tasks assigned, tasks done or not done, problems, hours planned, actual hours, and future
plans ate every week status meeting. The planner manager will consolidate the data and will analyze the efforts
spent per programmer every week.
1.3.7. Risk management plan
The risk factors and the tracking mechanisms are as follows. There is no existing product with which the new prod
Page 30 of 35
Software Project Management Plan
SCC Newscast System
Document Version: 3.0
Published Date: 27 October 2014
uct can be compared. Accordingly, it will not be possible to run the product in parallel with an existing one. Theref
ore, the product should be subjected to extensive testing. The client is assumed to be inexperienced with compute
rs. Therefore, special attention should be paid to the analysis workflow and communication with the client. The
product has to be made as user‐friendly as possible. Because of the ever‐present possibility of a major design fau
lt, extensive testing will be performed during the design workflow. Also, each of the team members will initially test
his or her own code and then test the code of another member. The QA will be responsible for integration testing
and in charge of product testing. The information must meet the specified storage requirements and response time
.
This should not be a major problem because of the small size of the product, but it will be monitored by Noel
Ihara throughout development.
There is a slim chance of hardware failure, in which case another machine will be leased. If there is a fault in the
compiler, it will be replaced
5.3.8 Project closeout plan
Not Applicable here.
Page 31 of 35
Software Project Management Plan
SCC Newscast System
Document Version: 3.0
Published Date: 27 October 2014
6. Technical process plans
6.1. Process Model
The Unified Process will be used. (Show the process diagram)
6.2. Methods, tools, and techniques
The workflows will be performed in accordance with the Unified Process. The product will be implemented in C#.
6.3. Infrastructure Plan
The product will be developed using Visual Studio running under windows 8.1 on a Laptop.
6.3. Product Acceptance Plan
Acceptance of the product by our client will be achieved by following the steps of the Unified Process.
Page 32 of 35
Software Project Management Plan
SCC Newscast System
Document Version: 3.0
Published Date: 27 October 2014
7. Supporting process plans
7.1. Configuration management plan
The server workstation and the client workstation must be connected to a local area network and a unique IP
address to prevent further error such as IP conflict. The server workstation must also set the output screens or the
LCD TV connected into an extended display with the corresponding resolution of 1366x768 landscape as a screen
orientation.
7.2. Verification and validation plan
Verification and validation plan is procedures that are used together for checking that a product, service, or system
meets requirements and specifications and that it fulfills its intended purpose.
7.3. Documentation plan
Documentation is distributed manually inside a folder which contains detailed paper documentations.
7.4. Quality assurance plan
The quality assurance performs a benchmark when the system is finished to define glitches of the system and the
accuracy of each function. Formulate a possible situation that makes the system down and planning a solution to
each glitches and bugs.
7.5. Reviews and audits
The SPMP specifies the plan, schedule and methods will be used in conducting product reviews and audits. So
far, the only products that Mach5 has created are documents and the methods for their review. It is expected that
in the future the details about the review and audits will be maintained within the Mach5 plan.
8.0 Additional Plans
Additional components:
Security:
A username and a password will be needed to use the product to maximize the security purposes.
Training:
Training will be performed with regards to the software functions and the steps on how to use the system
function efficiently by Carl at time of delivery. Because the product is straight forward to use, 1 day should be
sufficient for training. Carl will answer questions at no cost for the first year of use.
Page 33 of 35
Software Project Management Plan
SCC Newscast System
Document Version: 3.0
Published Date: 27 October 2014
9. Plan Annexes
Plan Annexes is part of the system or an addition to a main structure or it can be an attachment to current plans
and used as append or attach especially to a larger or more significant thing.
Page 34 of 35
Software Project Management Plan
SCC Newscast System
Document Version: 3.0
Published Date: 27 October 2014
10. Index
Constraints 8, 9, 14
Control plan 14, 15, 22
Dissemination 8, 9
Documentation 13, 16, 18, 19, 21, 22, 25
Documentation Plan 16, 25
Product 9, 13, 14, 15, 16, 21, 22, 23, 24, 25
Project 8, 9, 12, 13, 14, 15, 16, 17, 18, 20, 21, 22, 23
Project deliverables 8, 9, 13, 15
Purpose 8, 25,
Reporting plan 15, 23
Risk management 15, 21, 23
Table of contents 5
Workflow 21, 23, 24
Page 35 of 35

More Related Content

What's hot

Leave Management System Documentation
Leave Management System DocumentationLeave Management System Documentation
Leave Management System Documentationmuzammil siddiq
 
Example for SDS document in Software engineering
Example for SDS document in Software engineeringExample for SDS document in Software engineering
Example for SDS document in Software engineeringRavi Yasas
 
Library Management System Waterfall Model
Library Management System Waterfall ModelLibrary Management System Waterfall Model
Library Management System Waterfall Modelmitwa1990
 
Judiciary information management system
Judiciary information management systemJudiciary information management system
Judiciary information management systemKIRTIDEV MOHAPATRA
 
Final Year Project Presentation
Final Year Project PresentationFinal Year Project Presentation
Final Year Project PresentationSyed Absar
 
Vision and Scope Document For Library Management System
Vision and Scope Document For Library Management SystemVision and Scope Document For Library Management System
Vision and Scope Document For Library Management SystemSoman Sarim
 
Leave management system chp 1 4
Leave management system chp 1 4Leave management system chp 1 4
Leave management system chp 1 4Einstein Balaara
 
EMPLOYEE PAYROLL MANAGEMENT SYSTEM.pdf
EMPLOYEE PAYROLL MANAGEMENT SYSTEM.pdfEMPLOYEE PAYROLL MANAGEMENT SYSTEM.pdf
EMPLOYEE PAYROLL MANAGEMENT SYSTEM.pdfShridharSurada
 
Employee management system
Employee management systemEmployee management system
Employee management systemDeepák Soni
 
Payroll Management System SRS
Payroll Management System SRSPayroll Management System SRS
Payroll Management System SRSShubham Modi
 
Software Design Description (SDD) sample
Software Design Description (SDD) sampleSoftware Design Description (SDD) sample
Software Design Description (SDD) samplePeny Gama
 
EDE_Report_Final_14-12-22[1] (AutoRecovered).docx
EDE_Report_Final_14-12-22[1] (AutoRecovered).docxEDE_Report_Final_14-12-22[1] (AutoRecovered).docx
EDE_Report_Final_14-12-22[1] (AutoRecovered).docxRenuDeshmukh5
 
SRS for Online Medicine Ordering System
SRS for Online Medicine Ordering SystemSRS for Online Medicine Ordering System
SRS for Online Medicine Ordering SystemUmmeKalsoom11
 
Final Project Report of College Management System
Final Project Report of College Management SystemFinal Project Report of College Management System
Final Project Report of College Management SystemMuhammadHusnainRaza
 
PROJECT REPORT_ONLINE VOTING SYSTEM
PROJECT REPORT_ONLINE VOTING SYSTEMPROJECT REPORT_ONLINE VOTING SYSTEM
PROJECT REPORT_ONLINE VOTING SYSTEMNandasaba Wilson
 

What's hot (20)

Leave Management System Documentation
Leave Management System DocumentationLeave Management System Documentation
Leave Management System Documentation
 
Example for SDS document in Software engineering
Example for SDS document in Software engineeringExample for SDS document in Software engineering
Example for SDS document in Software engineering
 
Library Management System Waterfall Model
Library Management System Waterfall ModelLibrary Management System Waterfall Model
Library Management System Waterfall Model
 
Judiciary information management system
Judiciary information management systemJudiciary information management system
Judiciary information management system
 
Final Year Project Presentation
Final Year Project PresentationFinal Year Project Presentation
Final Year Project Presentation
 
Vision and Scope Document For Library Management System
Vision and Scope Document For Library Management SystemVision and Scope Document For Library Management System
Vision and Scope Document For Library Management System
 
Leave management system chp 1 4
Leave management system chp 1 4Leave management system chp 1 4
Leave management system chp 1 4
 
Chapter 6
Chapter 6Chapter 6
Chapter 6
 
Online school mangment system
Online school mangment system Online school mangment system
Online school mangment system
 
EMPLOYEE PAYROLL MANAGEMENT SYSTEM.pdf
EMPLOYEE PAYROLL MANAGEMENT SYSTEM.pdfEMPLOYEE PAYROLL MANAGEMENT SYSTEM.pdf
EMPLOYEE PAYROLL MANAGEMENT SYSTEM.pdf
 
Employee management system
Employee management systemEmployee management system
Employee management system
 
Online Job Portal
Online Job PortalOnline Job Portal
Online Job Portal
 
Srs for project
Srs for projectSrs for project
Srs for project
 
Payroll Management System SRS
Payroll Management System SRSPayroll Management System SRS
Payroll Management System SRS
 
Software Design Description (SDD) sample
Software Design Description (SDD) sampleSoftware Design Description (SDD) sample
Software Design Description (SDD) sample
 
EDE_Report_Final_14-12-22[1] (AutoRecovered).docx
EDE_Report_Final_14-12-22[1] (AutoRecovered).docxEDE_Report_Final_14-12-22[1] (AutoRecovered).docx
EDE_Report_Final_14-12-22[1] (AutoRecovered).docx
 
SRS for Online Medicine Ordering System
SRS for Online Medicine Ordering SystemSRS for Online Medicine Ordering System
SRS for Online Medicine Ordering System
 
Final Project Report of College Management System
Final Project Report of College Management SystemFinal Project Report of College Management System
Final Project Report of College Management System
 
File tracking system
File tracking systemFile tracking system
File tracking system
 
PROJECT REPORT_ONLINE VOTING SYSTEM
PROJECT REPORT_ONLINE VOTING SYSTEMPROJECT REPORT_ONLINE VOTING SYSTEM
PROJECT REPORT_ONLINE VOTING SYSTEM
 

Viewers also liked

Software development plan siabm
Software development plan siabmSoftware development plan siabm
Software development plan siabmBayu Pamungkas
 
Project management-plan
Project management-planProject management-plan
Project management-planTran Tien
 
Object-oriented analysis and design
Object-oriented analysis and designObject-oriented analysis and design
Object-oriented analysis and designAhmed Elnaggar
 
Library and member management system (lamms) by vikas sharma
Library and member management system (lamms) by vikas sharmaLibrary and member management system (lamms) by vikas sharma
Library and member management system (lamms) by vikas sharmaVikas Sharma
 
Project Scope Management Plan New
Project Scope Management Plan NewProject Scope Management Plan New
Project Scope Management Plan NewMelanieRos
 
Project Managing An Implementation Of A Library Management System
Project Managing An Implementation Of A Library Management SystemProject Managing An Implementation Of A Library Management System
Project Managing An Implementation Of A Library Management Systemianbays
 
17337071 srs-library-management-system
17337071 srs-library-management-system17337071 srs-library-management-system
17337071 srs-library-management-systemANAS NAIN
 
Project Management Plan - Cafe Au Lait.PDF
Project Management Plan - Cafe Au Lait.PDFProject Management Plan - Cafe Au Lait.PDF
Project Management Plan - Cafe Au Lait.PDFGeoff Penhorwood
 
Project Management Plan Template
Project Management Plan TemplateProject Management Plan Template
Project Management Plan TemplateSimplilearn
 
Library management system
Library management systemLibrary management system
Library management systemRaaghav Bhatia
 
Library Management System PPT
Library Management System PPTLibrary Management System PPT
Library Management System PPTTamaghna Banerjee
 
Software requirements specification of Library Management System
Software requirements specification of Library Management SystemSoftware requirements specification of Library Management System
Software requirements specification of Library Management SystemSoumili Sen
 
Library management system
Library management systemLibrary management system
Library management systemABhay Panchal
 
Library management system presentation
Library management system presentation Library management system presentation
Library management system presentation Smit Patel
 

Viewers also liked (20)

Spmp
SpmpSpmp
Spmp
 
Saneth docs revision
Saneth docs revisionSaneth docs revision
Saneth docs revision
 
Srs updated checked
Srs updated checkedSrs updated checked
Srs updated checked
 
Sdd updated checked
Sdd updated checkedSdd updated checked
Sdd updated checked
 
Software development plan siabm
Software development plan siabmSoftware development plan siabm
Software development plan siabm
 
Project management-plan
Project management-planProject management-plan
Project management-plan
 
The Shining
The ShiningThe Shining
The Shining
 
Object-oriented analysis and design
Object-oriented analysis and designObject-oriented analysis and design
Object-oriented analysis and design
 
Library and member management system (lamms) by vikas sharma
Library and member management system (lamms) by vikas sharmaLibrary and member management system (lamms) by vikas sharma
Library and member management system (lamms) by vikas sharma
 
Project Scope Management Plan New
Project Scope Management Plan NewProject Scope Management Plan New
Project Scope Management Plan New
 
Project Managing An Implementation Of A Library Management System
Project Managing An Implementation Of A Library Management SystemProject Managing An Implementation Of A Library Management System
Project Managing An Implementation Of A Library Management System
 
17337071 srs-library-management-system
17337071 srs-library-management-system17337071 srs-library-management-system
17337071 srs-library-management-system
 
Project Management Plan - Cafe Au Lait.PDF
Project Management Plan - Cafe Au Lait.PDFProject Management Plan - Cafe Au Lait.PDF
Project Management Plan - Cafe Au Lait.PDF
 
Project Management Plan Template
Project Management Plan TemplateProject Management Plan Template
Project Management Plan Template
 
Library management system
Library management systemLibrary management system
Library management system
 
Library Management System PPT
Library Management System PPTLibrary Management System PPT
Library Management System PPT
 
Software requirements specification of Library Management System
Software requirements specification of Library Management SystemSoftware requirements specification of Library Management System
Software requirements specification of Library Management System
 
Library management system
Library management systemLibrary management system
Library management system
 
Library Management System
Library Management SystemLibrary Management System
Library Management System
 
Library management system presentation
Library management system presentation Library management system presentation
Library management system presentation
 

Similar to Spmp updated checked 29

Kismetian.SRA.Poster Presentation.2
Kismetian.SRA.Poster Presentation.2Kismetian.SRA.Poster Presentation.2
Kismetian.SRA.Poster Presentation.2Maral Kismetian, CRA
 
lessons-learned-report
lessons-learned-reportlessons-learned-report
lessons-learned-reportColleen Palmer
 
Paul Capello Cerner Health Conference
Paul Capello Cerner Health ConferencePaul Capello Cerner Health Conference
Paul Capello Cerner Health Conferencetigcap
 
Paul Capello CHC 2010 Final
Paul Capello CHC 2010 FinalPaul Capello CHC 2010 Final
Paul Capello CHC 2010 Finaltigcap
 
XeroxFaxtonStLukes_A Partnership in Clinical Documentation FINAL
XeroxFaxtonStLukes_A Partnership in Clinical Documentation FINALXeroxFaxtonStLukes_A Partnership in Clinical Documentation FINAL
XeroxFaxtonStLukes_A Partnership in Clinical Documentation FINALAnil Bapat, M.S. PMP
 
Guide to Helping With Paper· Description of the key program .docx
Guide to Helping With Paper· Description of the key program .docxGuide to Helping With Paper· Description of the key program .docx
Guide to Helping With Paper· Description of the key program .docxshericehewat
 
Ppqa process manual_version_2.3_430722_7
Ppqa process manual_version_2.3_430722_7Ppqa process manual_version_2.3_430722_7
Ppqa process manual_version_2.3_430722_7Sundar Scorp
 
Management-Oriented Evaluation Approaches
Management-Oriented Evaluation ApproachesManagement-Oriented Evaluation Approaches
Management-Oriented Evaluation ApproachesLarry Weas
 
Techical Data on Typologies of Interventions in Knowledge Exchange and Enterp...
Techical Data on Typologies of Interventions in Knowledge Exchange and Enterp...Techical Data on Typologies of Interventions in Knowledge Exchange and Enterp...
Techical Data on Typologies of Interventions in Knowledge Exchange and Enterp...University of Wolverhampton
 
THE EFFECTS OF TOP MANAGEMENT SUPPORT ON STRATEGIC .docx
THE EFFECTS OF TOP MANAGEMENT SUPPORT ON STRATEGIC .docxTHE EFFECTS OF TOP MANAGEMENT SUPPORT ON STRATEGIC .docx
THE EFFECTS OF TOP MANAGEMENT SUPPORT ON STRATEGIC .docxtodd701
 
Rev3RPMS-ReorientationNTOTPerformance-Feedback.pptx
Rev3RPMS-ReorientationNTOTPerformance-Feedback.pptxRev3RPMS-ReorientationNTOTPerformance-Feedback.pptx
Rev3RPMS-ReorientationNTOTPerformance-Feedback.pptxMarkLoveenAng
 
Project Designing a Database using MS AccessDescription Work.docx
Project Designing a Database using MS AccessDescription Work.docxProject Designing a Database using MS AccessDescription Work.docx
Project Designing a Database using MS AccessDescription Work.docxwoodruffeloisa
 
Capello Pw 2011
Capello Pw 2011Capello Pw 2011
Capello Pw 2011tigcap
 
Capello Pw 2011
Capello Pw 2011Capello Pw 2011
Capello Pw 2011tigcap
 

Similar to Spmp updated checked 29 (20)

LSS Project_BDE S3 Notes
LSS Project_BDE S3 NotesLSS Project_BDE S3 Notes
LSS Project_BDE S3 Notes
 
Kismetian.SRA.Poster Presentation.2
Kismetian.SRA.Poster Presentation.2Kismetian.SRA.Poster Presentation.2
Kismetian.SRA.Poster Presentation.2
 
RPMS Re-orientation Workshop
RPMS Re-orientation WorkshopRPMS Re-orientation Workshop
RPMS Re-orientation Workshop
 
lessons-learned-report
lessons-learned-reportlessons-learned-report
lessons-learned-report
 
Paul Capello Cerner Health Conference
Paul Capello Cerner Health ConferencePaul Capello Cerner Health Conference
Paul Capello Cerner Health Conference
 
Paul Capello CHC 2010 Final
Paul Capello CHC 2010 FinalPaul Capello CHC 2010 Final
Paul Capello CHC 2010 Final
 
tsp
tsptsp
tsp
 
XeroxFaxtonStLukes_A Partnership in Clinical Documentation FINAL
XeroxFaxtonStLukes_A Partnership in Clinical Documentation FINALXeroxFaxtonStLukes_A Partnership in Clinical Documentation FINAL
XeroxFaxtonStLukes_A Partnership in Clinical Documentation FINAL
 
Guide to Helping With Paper· Description of the key program .docx
Guide to Helping With Paper· Description of the key program .docxGuide to Helping With Paper· Description of the key program .docx
Guide to Helping With Paper· Description of the key program .docx
 
Ppqa process manual_version_2.3_430722_7
Ppqa process manual_version_2.3_430722_7Ppqa process manual_version_2.3_430722_7
Ppqa process manual_version_2.3_430722_7
 
Backcasting 101
Backcasting 101Backcasting 101
Backcasting 101
 
Management-Oriented Evaluation Approaches
Management-Oriented Evaluation ApproachesManagement-Oriented Evaluation Approaches
Management-Oriented Evaluation Approaches
 
Techical Data on Typologies of Interventions in Knowledge Exchange and Enterp...
Techical Data on Typologies of Interventions in Knowledge Exchange and Enterp...Techical Data on Typologies of Interventions in Knowledge Exchange and Enterp...
Techical Data on Typologies of Interventions in Knowledge Exchange and Enterp...
 
THE EFFECTS OF TOP MANAGEMENT SUPPORT ON STRATEGIC .docx
THE EFFECTS OF TOP MANAGEMENT SUPPORT ON STRATEGIC .docxTHE EFFECTS OF TOP MANAGEMENT SUPPORT ON STRATEGIC .docx
THE EFFECTS OF TOP MANAGEMENT SUPPORT ON STRATEGIC .docx
 
09 project human resources management pmbok 5th
09 project human resources management pmbok 5th09 project human resources management pmbok 5th
09 project human resources management pmbok 5th
 
Change Champions Presentation 3
Change Champions Presentation 3Change Champions Presentation 3
Change Champions Presentation 3
 
Rev3RPMS-ReorientationNTOTPerformance-Feedback.pptx
Rev3RPMS-ReorientationNTOTPerformance-Feedback.pptxRev3RPMS-ReorientationNTOTPerformance-Feedback.pptx
Rev3RPMS-ReorientationNTOTPerformance-Feedback.pptx
 
Project Designing a Database using MS AccessDescription Work.docx
Project Designing a Database using MS AccessDescription Work.docxProject Designing a Database using MS AccessDescription Work.docx
Project Designing a Database using MS AccessDescription Work.docx
 
Capello Pw 2011
Capello Pw 2011Capello Pw 2011
Capello Pw 2011
 
Capello Pw 2011
Capello Pw 2011Capello Pw 2011
Capello Pw 2011
 

Recently uploaded

"Federated learning: out of reach no matter how close",Oleksandr Lapshyn
"Federated learning: out of reach no matter how close",Oleksandr Lapshyn"Federated learning: out of reach no matter how close",Oleksandr Lapshyn
"Federated learning: out of reach no matter how close",Oleksandr LapshynFwdays
 
The Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptxThe Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptxMalak Abu Hammad
 
Are Multi-Cloud and Serverless Good or Bad?
Are Multi-Cloud and Serverless Good or Bad?Are Multi-Cloud and Serverless Good or Bad?
Are Multi-Cloud and Serverless Good or Bad?Mattias Andersson
 
Transcript: New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024Transcript: New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024BookNet Canada
 
New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024
New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024
New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024BookNet Canada
 
CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):comworks
 
FULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | Delhi
FULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | DelhiFULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | Delhi
FULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | Delhisoniya singh
 
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmaticsKotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmaticscarlostorres15106
 
Unleash Your Potential - Namagunga Girls Coding Club
Unleash Your Potential - Namagunga Girls Coding ClubUnleash Your Potential - Namagunga Girls Coding Club
Unleash Your Potential - Namagunga Girls Coding ClubKalema Edgar
 
Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)Allon Mureinik
 
Breaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path MountBreaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path MountPuma Security, LLC
 
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking MenDelhi Call girls
 
Install Stable Diffusion in windows machine
Install Stable Diffusion in windows machineInstall Stable Diffusion in windows machine
Install Stable Diffusion in windows machinePadma Pradeep
 
08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking MenDelhi Call girls
 
Streamlining Python Development: A Guide to a Modern Project Setup
Streamlining Python Development: A Guide to a Modern Project SetupStreamlining Python Development: A Guide to a Modern Project Setup
Streamlining Python Development: A Guide to a Modern Project SetupFlorian Wilhelm
 
Swan(sea) Song – personal research during my six years at Swansea ... and bey...
Swan(sea) Song – personal research during my six years at Swansea ... and bey...Swan(sea) Song – personal research during my six years at Swansea ... and bey...
Swan(sea) Song – personal research during my six years at Swansea ... and bey...Alan Dix
 
Unblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen FramesUnblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen FramesSinan KOZAK
 

Recently uploaded (20)

"Federated learning: out of reach no matter how close",Oleksandr Lapshyn
"Federated learning: out of reach no matter how close",Oleksandr Lapshyn"Federated learning: out of reach no matter how close",Oleksandr Lapshyn
"Federated learning: out of reach no matter how close",Oleksandr Lapshyn
 
The Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptxThe Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptx
 
The transition to renewables in India.pdf
The transition to renewables in India.pdfThe transition to renewables in India.pdf
The transition to renewables in India.pdf
 
E-Vehicle_Hacking_by_Parul Sharma_null_owasp.pptx
E-Vehicle_Hacking_by_Parul Sharma_null_owasp.pptxE-Vehicle_Hacking_by_Parul Sharma_null_owasp.pptx
E-Vehicle_Hacking_by_Parul Sharma_null_owasp.pptx
 
Are Multi-Cloud and Serverless Good or Bad?
Are Multi-Cloud and Serverless Good or Bad?Are Multi-Cloud and Serverless Good or Bad?
Are Multi-Cloud and Serverless Good or Bad?
 
Transcript: New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024Transcript: New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024
 
New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024
New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024
New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024
 
CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):
 
FULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | Delhi
FULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | DelhiFULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | Delhi
FULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | Delhi
 
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmaticsKotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
 
Unleash Your Potential - Namagunga Girls Coding Club
Unleash Your Potential - Namagunga Girls Coding ClubUnleash Your Potential - Namagunga Girls Coding Club
Unleash Your Potential - Namagunga Girls Coding Club
 
Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)
 
Vulnerability_Management_GRC_by Sohang Sengupta.pptx
Vulnerability_Management_GRC_by Sohang Sengupta.pptxVulnerability_Management_GRC_by Sohang Sengupta.pptx
Vulnerability_Management_GRC_by Sohang Sengupta.pptx
 
Breaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path MountBreaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path Mount
 
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
 
Install Stable Diffusion in windows machine
Install Stable Diffusion in windows machineInstall Stable Diffusion in windows machine
Install Stable Diffusion in windows machine
 
08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men
 
Streamlining Python Development: A Guide to a Modern Project Setup
Streamlining Python Development: A Guide to a Modern Project SetupStreamlining Python Development: A Guide to a Modern Project Setup
Streamlining Python Development: A Guide to a Modern Project Setup
 
Swan(sea) Song – personal research during my six years at Swansea ... and bey...
Swan(sea) Song – personal research during my six years at Swansea ... and bey...Swan(sea) Song – personal research during my six years at Swansea ... and bey...
Swan(sea) Song – personal research during my six years at Swansea ... and bey...
 
Unblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen FramesUnblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen Frames
 

Spmp updated checked 29

  • 1. Saint Columban College COLLEGE OF COMPUTER STUDIES Software Project Management Plan for SCC Newscast System Mach5 Almonte, Jelly Mae P. Baltazar, Jessaneth B. Ching Carl Angelo L. Ihara Jr, Noel B. Salazar, Ragde Ama T.
  • 2. Signature The following signature indicates approval of the enclosed Software Project Management Plan Document. Noel B. Ihara Project manager Jelly Mae. P. Almonte Carl Angelo L. Ching System Analyst Programmer Ragde Ama T. Salazar Jessaneth B. Baltazar Quality Assurance Documenter Mr. Neil Owen B. Jandugan Adviser/Editor Submitted and accepted by: Mr. Philipcris C. Encarnacion, MCS CCS Dean
  • 3. Change History Table 1 Revisions Date Reason For Changes Person who suggested the changes Group Name June 16, 2014 Team Celeron change its name to Mach5 because the meaning of Celeron itself does not suit the group’s characteristics. Jessaneth B. Baltazar (Documenter) Title Name September 8,2014 The title of the study was changed from E-Bulletin to SCC Newscast System to make it more suitable with the proposed system. Ragde Ama T. Salazar (QA Tester) List of tables October 24, 2014 The numbering of the tables was changed and was properly ordered. Mrs. Janus A. Naparan (Client) Purpose, scope and objectives October 24, 2014 The sentence construction of the purpose, scope and objectives was improved. Mrs. Janus A. Naparan (Client) Schedule and budget summary October 24, 2014 The exact breakdown of the schedule and budget summary were specified. Mrs. Janus A. Naparan (Client) Evolution of plan October 24, 2014 The evolution of plan was changed and a Gantt chart was presented. Mrs. Janus A. Naparan (Client) Definitions October 24, 2014 The definitions was changed and stated in complete sentence. Mrs. Janus A. Naparan External interface October 24, 2014 The external interface was improved and was changed into a diagram. Mr. Neil Owen B. Jandugan (Adviser) Internal structure October 24, 2014 The group changed the internal structure to correct what is wrong on the diagram. Mr. Syril Glenn Flores (Panel) External October 24, 2014 The group changed the external Mr. Syril Glenn Flores
  • 4. structure structure to correct what is wrong on the diagram. (Panel) Budget Control plan October 24, 2014 The budget control plan was revised into a paragraph form. Mr. Francis Rebo Alegre (Panel)
  • 5. Preface The purpose of this document is to specify the project plan to develop the SCC Newscast system. This document outlines a brief plan about how the project will be shape. It also includes the milestones and deliverables. The Software Project Management Plan (SPMP) document will serve as a guide for the student, developing the product as part of the project. Updates of this document will serve to record the progress of the project.
  • 6. Table of Contents Signature....................................................................................................................................................................................2 Change History..........................................................................................................................................................................3 Preface........................................................................................................................................................................................5 Table of Contents.......................................................................................................................................................................6 List of Figures............................................................................................................................................................................8 List of Tables..............................................................................................................................................................................9 1. Overview...............................................................................................................................................................................10 1.1. Project Summary............................................................................................................................................................................10 1.1.1. Purpose, scope and objectives...............................................................................................................................................10 1.1.2. Assumptions And Constraints...............................................................................................................................................10 1.1.3. Project deliverables...............................................................................................................................................................11 1.1.4. Schedule and Budget Summary.............................................................................................................................................11 1.2. Evolution of plan............................................................................................................................................................................12 2. References............................................................................................................................................................................19 3. Definitions ...........................................................................................................................................................................20 4. Project organization............................................................................................................................................................25 4.1. External interface ..........................................................................................................................................................................25 4.2. Internal Structure ...........................................................................................................................................................................25 4.3. Roles and Responsibilities..............................................................................................................................................................26 5. Managerial process plans...................................................................................................................................................27 5.1. Start-Up Plan ................................................................................................................................................................................27 5.1.1. Estimation plan ....................................................................................................................................................................27 5.1.2. Staffing plan .........................................................................................................................................................................27 5.1.3. Resource acquisition plan ....................................................................................................................................................27 5.1.4. Project staff training plan ....................................................................................................................................................27 5.2. Work Plan ......................................................................................................................................................................................28 5.2.1. Work Activities......................................................................................................................................................................28 5.2.2. Schedule Allocation...............................................................................................................................................................28 5.2.3. Resource Allocation..............................................................................................................................................................28 5.2.4. Budget allocation..................................................................................................................................................................29 5.3. Control Plan ...................................................................................................................................................................................29 1.3.1.Requirements Control Plan ...................................................................................................................................................29 1.3.2.Schedule Control Plan ..........................................................................................................................................................29 1.3.3.Budget control plan................................................................................................................................................................30 1.3.4.Quality control plan...............................................................................................................................................................30 1.3.5.Reporting plan ......................................................................................................................................................................30 1.3.6.Metrics collection plan ..........................................................................................................................................................30 1.3.7.Risk management plan...........................................................................................................................................................30 5.3.8 Project closeout plan..............................................................................................................................................................31 6. Technical process plans ....................................................................................................................................................32 6.1. Process Model................................................................................................................................................................................32 6.2. Methods, tools, and techniques.......................................................................................................................................................32 6.3. Infrastructure Plan..........................................................................................................................................................................32 6.3. Product Acceptance Plan................................................................................................................................................................32 7. Supporting process plans ...................................................................................................................................................33 7.1. Configuration management plan ....................................................................................................................................................33 7.2. Verification and validation plan .....................................................................................................................................................33 7.3. Documentation plan .......................................................................................................................................................................33 7.4. Quality assurance plan ...................................................................................................................................................................33 7.5. Reviews and audits.........................................................................................................................................................................33 8.0 Additional Plans..............................................................................................................................................................................33 9. Plan Annexes.......................................................................................................................................................................34 10. Index..................................................................................................................................................................................35
  • 7. Software Project Management Plan SCC Newscast System Document Version: 3.0 Published Date: 27 October 2014 Page 7 of 35
  • 8. Software Project Management Plan SCC Newscast System Document Version: 3.0 Published Date: 27 October 2014 List of Figures Figure 1: Evolution of Plan…………………………………………………………………..............................12-17 Figure 2: External Interface……….…………………………………………………………………………….…….24 Figure 3: Internal Interface ………………………………………………………………………..………………….24 Page 8 of 35
  • 9. Software Project Management Plan SCC Newscast System Document Version: 3.0 Published Date: 27 October 2014 List of Tables Table 1: Change History…………………………………………………………………………………….……..3-4 Table 2: Schedule and Budget Summary………………………………………………………...……….……...11 Table 3: Definitions………………………….………………………………………………………………...…19-23 Table 4: Roles and Responsibilities……...………………………………….………………………………….…26 Table 5: Work activities……………………………………………………………………………………….…….28 Table 6: Budget Allocation…..……………………………………………………………………………..……….29 Page 9 of 35
  • 10. Software Project Management Plan SCC Newscast System Document Version: 3.0 Published Date: 27 October 2014 1. Overview 1.1. Project Summary 1.1.1. Purpose, scope and objectives The scope of this project includes assumptions on where the project is based; and constraints of the project such as schedule, budget and resources, software to be released, and product interfaces. Project deliverables also include the list of task that will be delivered to the clients, delivery dates and qualities required to satisfy the terms of the project agreement. Schedule and budget summary provides a summary of the schedule and budget for the software project. The level of detail should be restricted to an itemization of the major work activities and supporting processes. Project organization that will identify interfaces to organizational entities external to the project and internal and defines the roles and responsibilities for the project. The purpose of this document is to highlight the managerial plan for the SCC Newscast system with a goal of improving the user’s productivity by automating his/her work. The objective is to enhance the user’s productivity by scheduling the tasks needed to be done in a specific duration. The task assignment is given respectively and should be followed according to the work plan. 1.1.2. Assumptions And Constraints The prototyping and documentation of the project shall be finished on October 4, 2014, at the end of the first semester, S.Y. 2014-2015, of Capstone 1 Project course. All codes shall be written in C# language. The system shall be standalone application in PC environment on MS Windows XP, Windows 7. The system is easy to install. When the team develops the system, the group will need a budget in supplying the requirements needed to establish the system. The project has the following constraints: • TIME - The duration for the project design is one school year. - By the end of the 2nd semester, the software product is installed at the Information Office. The set-up of the computers and other hardware, and the orientation for the users may take several hours. Page 10 of 35
  • 11. Software Project Management Plan SCC Newscast System Document Version: 3.0 Published Date: 27 October 2014 • STAFF The Information personnel will be required for the consultation for the system design and process of the system. The Information Office personnel can also consult the team/developers, when necessary. 1.1.3. Project deliverables This project deliverables listed below should be provided before the completion of the system. Documents are used to be presented to the client. It represents the internal system such as the capabilities, scope and limitations, and etc. It will also present the Approval sheets, Software Requirement Specifications (SRS), Software Project Management Plan (SPMP), Software Design Description (SDD) and Software Testing Design (STD). Project Deliverables: -Documents -Project Proposal -Use Case -SRS -SPMP -SDD -STD -The SCC Newscast System 1.1.4. Schedule and Budget Summary Table 2 Month Expenses June Record Book ₱ 35.00 Clear Book ₱ 45.00 Transportation ₱ 100.00 July Printing expenses for SRS Document ₱ 100.00 August Transportation ₱ 200.00 Others ₱ 100.00 September Transportation ₱ 200.00 Page 11 of 35
  • 12. Software Project Management Plan SCC Newscast System Document Version: 3.0 Published Date: 27 October 2014 October Printing expenses for SRS Document ₱ 90.00 Printing expenses for SPMP Document ₱ 204.00 Printing expenses for SDD Document ₱ 156.00 Electricity ₱ 500.00 Others ₱ 310.00 TOTAL ₱ 2,040.00 1.2. Evolution of plan Figure 1 Page 12 of 35
  • 13. Software Project Management Plan SCC Newscast System Document Version: 3.0 Published Date: 27 October 2014 Page 13 of 35
  • 14. Software Project Management Plan SCC Newscast System Document Version: 3.0 Published Date: 27 October 2014 Page 14 of 35
  • 15. Software Project Management Plan SCC Newscast System Document Version: 3.0 Published Date: 27 October 2014 Page 15 of 35
  • 16. Software Project Management Plan SCC Newscast System Document Version: 3.0 Published Date: 27 October 2014 Page 16 of 35
  • 17. Software Project Management Plan SCC Newscast System Document Version: 3.0 Published Date: 27 October 2014 Page 17 of 35
  • 18. Software Project Management Plan SCC Newscast System Document Version: 3.0 Published Date: 27 October 2014 Page 18 of 35
  • 19. Software Project Management Plan SCC Newscast System Document Version: 3.0 Published Date: 27 October 2014 2. References IEEE Std 1058-1998 IEEE standard for software project management plans. Page 19 of 35
  • 20. Software Project Management Plan SCC Newscast System Document Version: 3.0 Published Date: 27 October 2014 3. Definitions Table 3 Term Definition Acquirer The individual or organization that specifies requirements for and accepts delivery of a new or modified software product and its documentation. Additional Plan Contains additional plans required to satisfy product requirements and contractual terms. Baseline A work product that has been formally reviewed and accepted by the involved parties. A baseline should be changed only through formal configuration management procedures. Budget Allocation Provides a detailed breakdown of necessary resource budgets for each of the major work activities in the work breakdown structure. Budget Control Plan Specifies the control mechanisms to be used to measure the cost of work completed, compare planned cost to budgeted cost, and implement corrective action when actual cost does not conform to budgeted cost. Configuration Management Plan Contains the configuration management plan for the software project, to include the methods that will be used to provide configuration identification, control, status accounting, evaluation, and release management. Control Plan Specifies the metrics, reporting mechanisms, and control procedures necessary to measure, report, and control the product requirements, the project schedule, budget, and resources, and the quality of work processes and work products. Database It is where the collections of all the information being stored. Documentation Plan Contains the documentation plan for the software project, to include plans for generating non-deliverable and deliverable work products. Estimation Plan Specifies the cost and schedule for conducting the project as well as methods, tools, and techniques used to estimate project cost, schedule, resource requirements, and associated confidence levels. External Interface Describes the organizational boundaries between the project and external entities. IEEE The Institute of Electrical and Electronics Engineers (IEEE) is a membership organization that includes engineers, scientists and Page 20 of 35
  • 21. Software Project Management Plan SCC Newscast System Document Version: 3.0 Published Date: 27 October 2014 students in electronics and allied fields. Infrastructure Plan Specifies the plan for establishing and maintaining the development environment (hardware, operating system, network, and software), and the policies, procedures, standards, and facilities required to conduct the software project. Internal Structure Describes the internal structure of the project organization to include the interfaces among the units of the software development team. Methods, tools, and techniques Specifies the development methodologies, programming languages and other notations, and the tools and techniques to be used to specify, design, build, test, integrate, document, deliver, modify and maintain the project deliverable and nondeliverable work products. In addition, the technical standards, policies, and procedures governing development and/or modification of the work products shall be specified. Metrics Collection Plan Specifies the methods, tools, and techniques to be used in collecting and retaining project metrics. Milestone Milestone is an event that receives special attention. It is often put at the end of a stage to mark the completion of a work package or phase. Problem Resolution Plan Specifies the resources, methods, tools, techniques, and procedures to be used in reporting, analyzing, prioritizing, and processing software problem reports generated during the project. Process Improvement Plan Includes plans for periodically assessing the project, determining areas for improvement, and implementing improvement plans. Process Model Defines the relationships among major project work activities and supporting processes by specifying the flow of information and work products among activities and functions, the timing of work products to be generated, reviews to be conducted, major milestones to be achieved, baselines to be established, project deliverables to be completed, and required approvals that span the duration of the project. Product Acceptance Plan Specifies the plan for acquirer acceptance of the deliverable work products generated by the software project. Project Agreement A document or set of documents baseline by the acquirer and the supplier that specifies the conditions under which the project will be conducted. Page 21 of 35
  • 22. Software Project Management Plan SCC Newscast System Document Version: 3.0 Published Date: 27 October 2014 Project Closeout Plan Contains the plans necessary to ensure orderly closeout of the software project. Items in the closeout plan should include a staff reassignment plan, a plan for archiving project materials, a plan for post- mortem debriefings of project personnel, and preparation of a final report to include lessons learned and analysis of project objectives achieved. Project deliverable A work product to be delivered to the acquirer Project Staff Training Plan Specifies the training needed to ensure that necessary skill levels in sufficient numbers are available to successfully conduct the software project. Quality Assurance Plan Provides the plans for assuring that the software project fulfills its commitments to the software process and the software product as specified in the requirements specification, the SPMP, supporting plans, and any standards, procedures, or guidelines to which the process or the product must adhere. Quality Control Plan Specifies the mechanisms to be used to measure and control the quality of the work processes and the resulting work products. Reporting Plan Specifies the reporting mechanisms, report formats, and information flows to be used in communicating the status of requirements, schedule, budget, quality, and other desired or required status metrics within the project and to entities external to the project. Requirements Control Plan Specifies the control mechanisms for measuring, reporting, and controlling changes to the product requirements Resource Acquisition Plan Specifies the plan for acquiring the resources in addition to personnel needed to successfully complete the project. Resource Allocation Provides a detailed itemization of the resources allocated to each major work activity in the project work breakdown structure. Reviews and Audits Specifies the schedule, resources, and methods and procedures to be used in conducting project reviews and audits. Risk Management Plan Specifies the risk management plan for identifying, analyzing, and prioritizing project risk factors. Schedule Allocation Provides scheduling relationships among work activities in a manner that depicts the time-sequencing constraints and illustrates opportunities for concurrent work activities. Page 22 of 35
  • 23. Software Project Management Plan SCC Newscast System Document Version: 3.0 Published Date: 27 October 2014 Schedule Control Plan Specifies the control mechanisms to be used to measure the progress of work completed at the major and minor project milestones, to compare actual progress to planned progress, and to implement corrective action when actual progress does not conform to planned progress. SPMP Software Project Management Plan is the art and science of planning and leading software projects. It is a sub-discipline of project management in which software projects are planned, implemented, monitored and controlled. Staffing Plan Specifies the number of staff required by skill level, the project phases in which the numbers of personnel and types of skills are needed, and the duration of need. Start-up Plan Specifies the estimation plan, staffing plan, resource acquisition plan, and training plan. Subcontractor Management Plan Contains plans for selecting and managing any subcontractors that may contribute work products to the software project. Supplier An organization that develops some or all of the project deliverables for an acquirer. Supporting Process Plan Contains plans for the supporting processes that span the duration of the software project. Technical Process Plan Specifies the development process model, the technical methods, tools, and techniques to be used to develop the various work products; plans for establishing and maintaining the project infrastructure; and the product acceptance plan. User A person who uses or interacts with the said system. Verification and Validation Plan Contains the verification and validation plan for the software project to include scope, tools, techniques, and responsibilities for the verification and validation work activities. Work Activities Specifies the various work activities to be performed in the software project. Work Activity A collection of work tasks spanning a fixed duration within the schedule of a software project. Work Package A specification of the work that must be accomplished to complete a work task. Work Plan Specifies the work activities, schedule, resources, and budget details for the software project. Page 23 of 35
  • 24. Software Project Management Plan SCC Newscast System Document Version: 3.0 Published Date: 27 October 2014 Work Product Any tangible item produced during the process of developing or modifying software. Work Task The smallest unit of work subject to management accountability. Page 24 of 35
  • 25. Software Project Management Plan SCC Newscast System Document Version: 3.0 Published Date: 27 October 2014 4. Project organization 4.1. External interface Figure 2 Ihara as a project manager meets with the client weekly to discuss possible revisions and modification. 4.2. Internal Structure Figure 3 All the work on this project will be performed by Ihara, Baltazar, Salazar, Almonte and Ching. Ihara as a project manager meets with the team weekly to discuss possible changes and modification. Page 25 of 35
  • 26. Software Project Management Plan SCC Newscast System Document Version: 3.0 Published Date: 27 October 2014 4.3. Roles and Responsibilities Table 4 ROLE RESPONSIBILITIES Project Manager He/She: 1.Plans, organizes, coordinates, control the activities of the group 2. Has the overall responsibilities for the success of the project. 3. Leads the team in producing, assessing, updating, and reporting on the plan. 4. Review of testing results and defects to determine/assess impact to overall project plan and implementation schedule. 5. Review and Approval of the testing strategy, approach, and plans. Programmer He/She: 1. Assist with design, analysis, maintenance, documentation, and testing of software. 2.Code, debug, test, and document routine application programs 3. Design new systems or enhancements to existing systems. 4. Verify that system meets performance criteria. 5. Advise or train users regarding the technical aspects and use of standard software packages. 6. Design/modify, code, debug, test, and document moderately complex application systems. Quality Assurance He/She: 1. Responsible for management of all Quality Assurance functions include planning, strategy, testing execution and tools. System Analyst He/She: 1. Collect information to analyze and evaluate existing or proposed systems. 2. Prepare detailed flow charts and diagrams outlining systems capabilities and processes. 3. Select among authorized procedures and seek assistance when guidelines are inadequate, significant deviations are proposed, or when unanticipated problems arise. 4. Write and maintain system documentation. Documenter He/She: 1. The documenters kept detailed meeting minutes. 2. Make sure the documents are complete. Page 26 of 35
  • 27. Software Project Management Plan SCC Newscast System Document Version: 3.0 Published Date: 27 October 2014 5. Managerial process plans 5.1. Start-Up Plan 5.1.1. Estimation plan As previously stated, the total development time is estimated to be one school year, one school year is divided into two semesters. Each semester will cover part of the Gantt chart that was created at the beginning of the project through Microsoft Excel. Gantt chart excel-based will be used to produce and to track a schedule that includes milestones for the project. At the beginning of each work phase, The Mach5 team will have to check the Gantt chart to define the tasks and schedules. The Mach5 team will assess its status once a week and update and distribute the schedule accordingly. Every topic listed in Gantt chart will be reviewed by using formal review methods. 5.1.2. Staffing plan In the first semester, the managerial committee which include Noel Ihara Jr. as the Project Manager, Jessaneth Baltazar the Documenter and Jelly Mae Almonte the System Analyst will be the head in assigning and documenting with the help of the Programmer Carl Ching and Quality Assurance Ragde Ama Salazar. For the second semester the Project Manager, Programmer and Quality Assurance will be the head in finalizing the system with the assistance of Documenter and System Analyst. 5.1.3. Resource acquisition plan All necessary hardware, software case tools for the project are already available. The system will be installed on a computer unit, one in the Information Office as a server and one in each department namely, the College of Business Education, College of Computer Studies and College of Teachers Education Arts and Sciences as a client which is ready to use. 5.1.4. Project staff training plan No additional staff training is needed for this project. Page 27 of 35
  • 28. Software Project Management Plan SCC Newscast System Document Version: 3.0 Published Date: 27 October 2014 5.2. Work Plan 5.2.1. Work Activities Table 5 Week 1 SRS Chapter 1 Introduction and Chapter 2 Overall Description documentation. Week 2 SRS Chapter 3 Specification requirements Week 3 SPMP Chapter 1 Overview, Chapter 2 References, Chapter 3 Definition, Chapter 4 Project Organization Week 4 SPMP Chapter 5 Managerial Process Plans and Finalizing SRS and SPMP. Week 5 SPMP Chapter 6 Technical Process Plans and Supporting Process Plans. Week 6 SDD Chapter 1 Introduction and Chapter 2 References. Week 7 SDD Chapter 3 Decomposition Description and Chapter 4 Dependency Description. Week 8 SDD Chapter 5 Interface Description. Week 9 SDD Chapter 6 Detailed Design. Week 10 SDD Chapter 7 Appendices and Chapter 8 Index. 5.2.2. Schedule Allocation The project duration is constrained to one semester (prelim, midterm, semi-finals, and finals), with final deliverables due in the mid of October 2014. We will control our schedule with main artifacts. 5.2.3. Resource Allocation The whole team member will work separately on their assigned task. The Project manager Noel Ihara will acquire the role of monitoring the daily progress of the members, oversee implementation and the Quality assurance Ragde Ama Salazar is responsible for overall quality, and interact with the client. Team members will meet at the end of each day and discuss problems and progress. Formal meeting with the client will be held at the end of each week to report progress and determine if any changes needed to be made. The Project manager will ensure that schedule and budget requirements are met. The Project manager will be also responsible for the risk management. Minimizing faults and maximizing user-friendliness will be the project manager’s top priorities. The documenter Jessaneth Baltazar has the overall responsibility for all documentation and has to ensure that it is up to date. Page 28 of 35
  • 29. Software Project Management Plan SCC Newscast System Document Version: 3.0 Published Date: 27 October 2014 5.2.4. Budget allocation Table 6 Budget Allocation Cost Printing Expenses for SRS, SPMP, SDD Documents ₱ 550.00 Transportation ₱ 500.00 Electricity ₱ 500.00 Record Book ₱ 35.00 Clear Book ₱ 45.00 Others ₱ 410.00 TOTAL ₱ 2, 040.00 5.3. Control Plan Any major changes that affect the budget of the project have to be approved by the project manager and documented by the documenter. No outside quality assurance personnel are involved. The benefits of having someone other than the individual who carried out the development do the testing will be accomplished by each person testing another person’s work products. The project manager will be responsible for ensuring that the project is completed on time and within the estimated budget. This will be accomplished through daily meetings with the team members. At each meeting, the documenter and the system analyst will present the day’s progress and problems. The project manager will determine whether they are progressing as expected and whether they are following the specification document and the project management plan. Any major problems faced by the team members will immediately b e reported to the project manager. 1.3.1. Requirements Control Plan Requirement will be managed in use case description of SRS as requirements are changed. More detailed Requirement Management Plan Ver. 1.1 1.3.2. Schedule Control Plan Page 29 of 35
  • 30. Software Project Management Plan SCC Newscast System Document Version: 3.0 Published Date: 27 October 2014 Our team’s planning manager will maintain the schedule in a project document. The planning manager will be responsible for gathering the individual tasks for each team member and supervise us to ensure the development of our system’s documentation and the like. If schedule is not on track, our team will follow a schedule control meeting. 1.3.3. Budget control plan The budget is handled through funding and is limited in which it has to be consume properly. It will be handled personally by one of the team members and every fund will be recorded at the Microsoft excel document to ensure its exact amount funded. Any expenses will be consulted to every member. 1.3.4. Quality control plan The quality manager will generate a separate Quality Control Plan document. From this document, checklists and other evaluation measures will be determined necessary or otherwise. Weekly meetings and reviews at the end of each phase will be the main mechanisms that our team will use to control the quality of the work process and the resulting work. In addition, our adviser will monitor quality control throughout the project by the mentoring. Each member is encouraged to consult our mentor who will meet with the team on a regular class schedule (Mondays and Thursdays of the month) to review individual and group progress and to address any managerial or technical issues or questions. The mentor is encouraged to review the team’s work products and to ask questions to determine the health and progress of the project. 1.3.5. Reporting plan General Reporting The team will use a set of applications and methods available from the template given to us by our mentor to communicate to the client, mentors, and advisors to the status of requirements, schedules, quality, and other desired or required status metrics for the team project. Internal Reporting Team members will submit individual document to the planning manager every Monday and Thursday as regards to their assigned tasks. The planning manager will consolidate all files and present it to the mentor for checking and approval. Additionally, the team is required to see and consult the mentor to discuss the project’s current progress, unresolved issues, and need for assistance. 1.3.6. Metrics collection plan Each team member will submit individual progress and every Monday and Thursday, each member will report productivity on the tasks assigned, tasks done or not done, problems, hours planned, actual hours, and future plans ate every week status meeting. The planner manager will consolidate the data and will analyze the efforts spent per programmer every week. 1.3.7. Risk management plan The risk factors and the tracking mechanisms are as follows. There is no existing product with which the new prod Page 30 of 35
  • 31. Software Project Management Plan SCC Newscast System Document Version: 3.0 Published Date: 27 October 2014 uct can be compared. Accordingly, it will not be possible to run the product in parallel with an existing one. Theref ore, the product should be subjected to extensive testing. The client is assumed to be inexperienced with compute rs. Therefore, special attention should be paid to the analysis workflow and communication with the client. The product has to be made as user‐friendly as possible. Because of the ever‐present possibility of a major design fau lt, extensive testing will be performed during the design workflow. Also, each of the team members will initially test his or her own code and then test the code of another member. The QA will be responsible for integration testing and in charge of product testing. The information must meet the specified storage requirements and response time . This should not be a major problem because of the small size of the product, but it will be monitored by Noel Ihara throughout development. There is a slim chance of hardware failure, in which case another machine will be leased. If there is a fault in the compiler, it will be replaced 5.3.8 Project closeout plan Not Applicable here. Page 31 of 35
  • 32. Software Project Management Plan SCC Newscast System Document Version: 3.0 Published Date: 27 October 2014 6. Technical process plans 6.1. Process Model The Unified Process will be used. (Show the process diagram) 6.2. Methods, tools, and techniques The workflows will be performed in accordance with the Unified Process. The product will be implemented in C#. 6.3. Infrastructure Plan The product will be developed using Visual Studio running under windows 8.1 on a Laptop. 6.3. Product Acceptance Plan Acceptance of the product by our client will be achieved by following the steps of the Unified Process. Page 32 of 35
  • 33. Software Project Management Plan SCC Newscast System Document Version: 3.0 Published Date: 27 October 2014 7. Supporting process plans 7.1. Configuration management plan The server workstation and the client workstation must be connected to a local area network and a unique IP address to prevent further error such as IP conflict. The server workstation must also set the output screens or the LCD TV connected into an extended display with the corresponding resolution of 1366x768 landscape as a screen orientation. 7.2. Verification and validation plan Verification and validation plan is procedures that are used together for checking that a product, service, or system meets requirements and specifications and that it fulfills its intended purpose. 7.3. Documentation plan Documentation is distributed manually inside a folder which contains detailed paper documentations. 7.4. Quality assurance plan The quality assurance performs a benchmark when the system is finished to define glitches of the system and the accuracy of each function. Formulate a possible situation that makes the system down and planning a solution to each glitches and bugs. 7.5. Reviews and audits The SPMP specifies the plan, schedule and methods will be used in conducting product reviews and audits. So far, the only products that Mach5 has created are documents and the methods for their review. It is expected that in the future the details about the review and audits will be maintained within the Mach5 plan. 8.0 Additional Plans Additional components: Security: A username and a password will be needed to use the product to maximize the security purposes. Training: Training will be performed with regards to the software functions and the steps on how to use the system function efficiently by Carl at time of delivery. Because the product is straight forward to use, 1 day should be sufficient for training. Carl will answer questions at no cost for the first year of use. Page 33 of 35
  • 34. Software Project Management Plan SCC Newscast System Document Version: 3.0 Published Date: 27 October 2014 9. Plan Annexes Plan Annexes is part of the system or an addition to a main structure or it can be an attachment to current plans and used as append or attach especially to a larger or more significant thing. Page 34 of 35
  • 35. Software Project Management Plan SCC Newscast System Document Version: 3.0 Published Date: 27 October 2014 10. Index Constraints 8, 9, 14 Control plan 14, 15, 22 Dissemination 8, 9 Documentation 13, 16, 18, 19, 21, 22, 25 Documentation Plan 16, 25 Product 9, 13, 14, 15, 16, 21, 22, 23, 24, 25 Project 8, 9, 12, 13, 14, 15, 16, 17, 18, 20, 21, 22, 23 Project deliverables 8, 9, 13, 15 Purpose 8, 25, Reporting plan 15, 23 Risk management 15, 21, 23 Table of contents 5 Workflow 21, 23, 24 Page 35 of 35