Sogeti Ireland
   Effective Test Process Improvement
   Fran O’Hara
   fran.ohara@sogeti.com




   22nd July 2009

© Sogeti Group 2009                     Page 1




                      Contents



• Introduction
• TPI
• TMMi
• Process improvement challenges and
  sample solutions
• Summary
• Q&A




© Sogeti Group 2009                     Page 2
SOGETI Overview: A Worldwide Leader in IT Services


• Sogeti Group                                             Part of
   20,000 professionals                                    •   Leader in consulting, IT &
   200 locations in 14 countries                               outsourcing
• Providing worldwide standards                            •   88,000 staff
                                                           •   Revenue €8.7 billion
   Copyright        TMap®
                    and        TPI®
                           brands
                                                           •   Sogeti:
   Dedicated R&D on new developments
                                                                     • £1.6 billion revenues
   Test thought leadership
                                                                     • Testing revenues
USA                                                                    £150M (2007), £190M
                                                                       (2008)
                                                 Sweden
                                                           Test Centre of Excellence
                                                              provides for
                               UK               Denmark
                 Ireland                                   •   Reduced cost (>25% over 2 yrs)
        NL
                                               Germany
                                                           •   Improved quality
        Belux
                                             Switzerland   •   Improved flexibility
        France
                                                           •   Reduced time-to-test/market
                                                           •   Reduced risk
        Spain
                                                           •   Increased capacity
                                               India
                                                                                        3
 © Sogeti Group 2009                                                                     Page 3




                             Test Process Improvement - learning to work smarter,
                             to test software better, cheaper, faster




Process focus improves                   World Class
predictability of
performance (reduces
variation), as well as
performance itself
                                      Products/services
(difference between
desired and actual)



                                       Capability




                           People        Process               Technology

 © Sogeti Group 2009                                                                     Page 4
Triggers



•    Efficiency/cost?
•    Effectiveness?
•    Growing Complexity?
•    Different levels of Test Maturity?
•    Time Pressure?
•    Are we doing the right thing(s)?
                                Development                  Business

                            Automation                      Time-to-market

                           COTS             CBD             Standard. Reuse

                                                                    ty   Growin
                                                                ali
                             I’s Agile
                                                                                g
                                                              Qu         Complex
                           GU
                                                                                  ity
                                                               Cheap
                                     ic   esXML                          Error
                                serv
                                                                               free
                         We b                                     User-friendliness
                                 Integration
                                                   Tester         Maintainability




© Sogeti Group 2009                                                                                Page 5




                        The TPI® Model




                                               Key areas



                                                  Levels                                Test
                                                                                        Maturity
                                                                                        Matrix


                  Checkpoints                           Improvement suggestions




© Sogeti Group 2009                                                                                Page 6
20 Key Areas


•   Test strategy                                  • Commitment and motivation
•   Life-cycle model                               • Testing functions and
•   Moment of involvement                            training
•   Estimating and planning                        • Scope of methodology
•   Test specification                             • Communication
    techniques                                     • Reporting
•   Static test techniques                         • Defect management
•   Metrics                                        • Testware management
•   Test automation                                • Test process management
•   Test environment                               • Evaluation
•   Office environment                             • Low-level testing




© Sogeti Group 2009                                                                                Page 7




                                   Current Situation (example)


             Key area / Scale              0   1   2   3   4   5   6   7   8   9   10 11 12 13
        1    Test strategy                     A                   B               C       D
        2    Life - cycle model                A           B
        3    Moment of involvement                 A               B               C       D
        4    Estimating and planning                   A                           B
        5    Test specification                A       B
             techniques                                            Dependencies!
        6    Static test techniques                        A       B
        7    Metrics                                           A           B           C       D
        8    Test automation                           A               B           C
        9    Test environment                          A               B                       C
        10   Office environment                        A
        11   Commitment and                    A               B                       C
             motivation
        12   Test functions and training               A           B           C
        13   Scope of methodology                          A                       B           C
        14   Communication                         A       B                           C
        15   Reporting                         A           B       C                   D
        16   Defect management                 A               B       C
        17   Testware management                   A           B               C               D
        18   Test process management           A       B                               C
        19   Evaluation                                            A           B
        20   Low - level testing                           A       B       C



© Sogeti Group 2009                                                                                Page 8
Process Improvement ….


             Key area / Scale                 0   1   2   3   4   5   6   7   8   9   10 11 12 13
        1    Test strategy                        A                   B               C       D
        2    Life - cycle model                   A           B
        3    Moment of involvement                    A               B               C       D
        4    Estimating and planning                      A                           B
        5    Test specification                   A       B
             techniques
        6    Static test techniques                           A       B
        7    Metrics                                              A           B           C       D
        8    Test automation                              A               B           C
        9    Test environment                             A               B                       C
        10   Office environment                           A                                 Opti
                                                  ControlledB             Efficient
        11   Commitment and
             motivation
                                                  A                                       Cmizing
        12   Test functions and training                  A           B           C
        13   Scope of methodology                             A                       B           C
        14   Communication                            A       B                           C
        15   Reporting                            A           B       C                   D
        16   Defect management                    A               B       C
        17   Testware management                      A           B               C               D
        18   Test process management              A       B                               C
        19   Evaluation                                               A           B
        20   Low - level testing                              A       B       C



© Sogeti Group 2009                                                                                    Page 9




                                      Testing Maturity Model Integration (TMMi®)




     • Currently under development by the TMMi Foundation
                See www.tmmifoundation.org
                Levels 2 & 3 published
     • The TMMi® Foundation will provide:
                A standard TMMi® Model that can be used in isolation or
                in support of other process improvement models and is
                either staged or continuous.
                An independently managed data repository to support
                TMMi® assessment method accreditation, assessor and
                assessment certification/validation and validated
                assessment data and certificates.
                Assessment Method Accreditation/Audit Framework for
                TMMi® in accordance with ISO15504 and the process to
                certify commercial assessment methods against the
                standard model.
                Certification and training/examination process, procedures
                and standards for formal, public accreditation of
                Assessors and Lead Assessors and the on-going
                management.

© Sogeti Group 2009                                                                                   Page 10
TMMi® Model


       Level                                   Process Areas
       5 Optimisation                          Defect Prevention
                                               Test Process Optimisation
                                               Quality Control
       4 Management & Measurement              Test Measurement
                                               Software Quality Evaluation
                                               Advanced Peer Reviews

       3 Integration                           Test Organisation
                                               Test Training Program
                                               Test Life Cycle and Integration
                                               Non-Functional Testing
                                               Peer Reviews
       2 Managed                               Test   Policy and Strategy
                                               Test   Planning
                                               Test   Monitoring and Control
                                               Test   Design and Execution
                                               Test   Environment

       1 Initial


© Sogeti Group 2009                                                                       Page 11




                                Problems with Process Improvement

   Typical Issues with Process        Results from Sogeti ‘Worldwide survey on TPI’ :
      Improvement:
                                         Lack of management commitment **
       Lack of management
       commitment
                                         Unrealistic expectations *
       Lack of prioritised goals to      Unclear scope and target (i.e. goals) *
       focus/prioritise                  Unclear communication
                                         Only 17% had measurable results

       Excessive emphasis on
       documenting and assessing
       process                           Results unknown for too long a time

       Difficulty in defining and        Lack of change process
       deploying the process             Change team without influence

       Inadequate buy-in from staff      Involvement of people within the test process*
                                         Top down approach (‘Thou shalt..’)
       Lack of process architecture
                                         44% combined with other improvement projects




© Sogeti Group 2009                                                                       Page 12
Improvement Strategy - 1

                                          Lack of management commitment
            Problems
                                            - Lack of management commitment**

                                          Lack of prioritised goals to
                                          focus/prioritise
                                             - Unrealistic expectations*
                                             - Unclear scope and target (i.e. goals)*
                                             - Unclear communication
                                             - Only 17% had measurable results - NB

            Solutions
                                          Achieve sign-off on documented requirements
                                          and constraints and associated improvement
                                          (project) plan

                                          Align and prioritise improvement efforts with
                                          business goals through a goal-problem tree

                                          Focus on early and measurable results



© Sogeti Group 2009                                                                             Page 13




                                 Problem Scenario - 1

                                                                               Customer
                                                                               satisfaction
                          Reported Production Defects                          rating dropped
                                                                               20% in June
       80
                                                                               survey
       70
       60                                                                      compared to 6
       50                                                                      months
       40
                                                                               previously.
       30                                           # Severity 1 & 2 defects
       20
       10                                                                      Cost reduction
        0
             1   2    3     4    5    6
                                                                               of 10% is also
                      Months
                                                                               a department
                                                                               target


© Sogeti Group 2009                                                                             Page 14
Problem Scenario -2


               Origin of Production Defects                   Data also
                                                              shows that
                                                              rework of
                                                              production
                                        User requirements
                                        System requirements
                                                              defects is
                                        Architecture
                                                              costing 40% of
                                        Detailed design       development
                                        Code & Build          budget
                                        Integration




© Sogeti Group 2009                                                            Page 15




                             Examples of test-related improvement actions


       • Perform formal peer reviews of System requirements
                 Involve system testers
       • Use a risk-based approach to system test involving business
         users in risk workshops
       • Use a test driven development approach to unit test (unit
         test cases developed and automated before code written)
       • Design system tests as soon as system requirements
         become available
       • Resource system test with some dedicated test
         professionals
       • Perform formal planning of system test
       • Measure DDP for peer reviews, unit test and system test

       • Some ways to identify improvement actions:
                 Brainstorm process problems and vote
                 Brainstorm improvement ideas/actions
                 Model gap analysis – assessment results

© Sogeti Group 2009                                                            Page 16
Goal Tree & Cost/Benefit


Business Goal          Dev/Test              Test Process       Est. Cost   Est.
                       Department Goal       Goals              of          Benefit
                                                                required
                                                                actions
Reduce IT              Reduce rework         Improve            200k        1m
Appn.                  costs of production   effectiveness of               (10% of IT
Development            defects by 50%        Peer reviews,                  budget)
costs by 10%                                 Unit test, and
                                             System Test by
                                             75% (Currently
                                             running at 50%
                                             DDP)


Improve                Reduce number of      As above           0           Satisfied
Customer               production defects                                   customers
satisfaction           per month by 50%
ratings by 20%         (based on
                       equivalent appn.
                       throughput)

© Sogeti Group 2009                                                                   Page 17




                            Goal Metric Scenario – Sample Results




                      Defect Detection Percentage per Release

           100

            80

            60
     DDP




            40

            20

             0
                       1         2           3          4           5       6
                            Release number (or subsequent projects)



© Sogeti Group 2009                                                                   Page 18
Improvement Strategy - 2

                          Excessive emphasis on documenting and
            Problems      assessing process
                              - Results unknown for too long a time



                          Use a more agile approach to PI - Iterate in
            Solutions     short improvement cycles (2-3 months) – how
                          do you eat an elephant?

                          Focus on lightweight, rapid process modelling
                          for early deployment (80/20 rule for any gap
                          analysis)

                          Perform formal assessments to confirm
                          process maturity results




© Sogeti Group 2009                                                              Page 19




                        Improvement Strategy - 3

                           Difficulty in defining and deploying the
            Problems       process
                           Lack of change process
                           Change team without influence


                           Inadequate buy-in from staff
                           Involvement of people within the test process*
                           Top down approach (‘Thou shalt..’)


                           Use a facilitated workshop approach to process
            Solutions      modelling/improvement

                           Process owners involved in workshops, ‘change team’
                           become facilitators

                           Goal–problem driven focus

                           Use a continuously improving well-defined change
                           process




© Sogeti Group 2009                                                              Page 20
Example Modeling Session




 •Picture of process-level modeling (Image2)
            •session inserted here.


© Sogeti Group 2009                              Page 21




                      Example “Mapped” Element




© Sogeti Group 2009                              Page 22
When a standard framework is required –
                                      sample process level template
Level of Abstraction of tasks is                   Activity Controls or ‘Work Aids’ provide options
key to a common framework                          for supporting templates, tools, procedures, etc.


                         Activity Name                  Activity Purpose                     Activity Controls
                                   Action                                                             Artifact
                                                                                                             Artifact



                       Inputs           Entry                      Tasks                          Exit           Outputs
                       Artifact        Condition           ActionAction                         Condition         Artifact

                                                                                                                  Artifact
                       Artifact        Condition           Action                               Condition
                                                                 Action
                                                                                                                  Artifact

                             Issues                                Roles                              Measurements
                             Planning,                         Name Name                              Costs, Efforts,
                             Tailoring, …                                                             Time, Quality
Tailoring can also be used to highlight
key differences of approach required
  © Sogeti Group 2009                                                                                                                  Page 23




                                       Sample Test Process Element
                                       Define the Test Strategy

           Entry Criteria                            Controls / Work Aids                                       Exit Criteria
     1.    Inputs are under            1.   Project Lifecycles with defined Test Stages                  1.   Test-ware is placed under
           Configuration Management    2.   Test Methodology (identifying Test Methods & Test                 Configuration Management
           control                          Techniques.)                                                      control.
                                       3.   Review Meeting Minutes Template
                                       4.   Risk List Template
                                       5.   Test Strategy Template



                Inputs                                           Tasks                                             Outputs
     1.    Project Requirements        1.   Determine level of Requirements definition for the           1.   (Risk Based) Test Strategy.
           Document(s) [User,               project                                                      2.   Prioritised Risk List.
           System,                     2.   Divide the System under Test into its components, if
           Functional/Technical]            relevant. Prioritise component parts
     2.    Statement of Work           3.   Identify and analyse Product Risks, taking Project
     3.    Test Project Scope               Requirements, Statement of Work, Prioritized Quality
                                            Characteristics and System Components into
                                            consideration
                                       4.   Identify and Define Test Levels.
                                       5.   Identify and Define Test Level Attributes - Methods and
                                            Test Techniques, exit criteria, coverage, automation
                                            approach, etc.
                                       6.   Document the Testing Strategy.
                                       7.   Review and sign-off the Testing Strategy.

              Tailorings                                         Roles                                              Metrics
                                       1.   Test Manager (T.1-T.7)                                       1.   Planned versus actual effort
                                       2.   Test Designer (T.5)
                                       3.   Business Analyst (T.3, T.7)
                                       4.   System Expert (T.3-T.7)
                                       5.   End User (T.3, T.7)




  © Sogeti Group 2009                                                                                                                  Page 24
Process of change



                               Obtain
                              awareness

                         Determine target,
                       area of consideration
                           and approach

                                              Define
                                Execute    improvement
                              assessment     actions

                  Perform                           Formulate
                 evaluation                            plan
                                    Implement
                                  improvement
                                     actions
© Sogeti Group 2009                                                     Page 25




                         Suggestion: Use a performance-based ‘agile’
                         process improvement approach

Phase 2:                                                 Phase 1: Selected
Documented                                               goals and problems
baselines of                                             for process
current practice                                         improvement
and performance




Phase 3: Process                                         Phase 4: Revised
documents to be                                          process and
deployed                                                 performance
                                                         baselines




© Sogeti Group 2009                                                     Page 26
Do’s – from TPI® survey



•    Clear scope and target                 16%
•    Clear communication                     9%
•    Results periodically visible            8%
•    Champions in change team                8%
•    Use of a change process                 7%
• Other ...                                     5%


     Biggest DO’s:
     • Management commitment       24%
     • Involvement of “own” people 23%


© Sogeti Group 2009                                  Page 27




                      Summary – key suggestions



• Use an agile approach to test process
  improvement – incremental with
  80/20 prioritisation
           Driven by and linked to measurable
           business goals
           Addressing key staff process problems
• Involvement and ownership by test
  staff
• Lightweight, usable process
  definition (80/20 again!)
© Sogeti Group 2009                                  Page 28
Sogeti Support



• Capability building
           test process and how to improve it
           seminars, workshops and training
• Process assessments
           Model based (e.g. TPI®) and/or benchmarking
• Consulting/mentoring during process
  improvement

• fran.ohara@sogeti.com
• www.sogeti.ie

© Sogeti Group 2009                                      Page 29

More Related Content

What's hot (20)

Heizer chapter 01
Heizer chapter 01 Heizer chapter 01
Heizer chapter 01
 
Heizer 07
Heizer 07Heizer 07
Heizer 07
 
Heizer 13
Heizer 13Heizer 13
Heizer 13
 
Opti Products Overview
Opti Products OverviewOpti Products Overview
Opti Products Overview
 
Heizer supp 06
Heizer supp 06Heizer supp 06
Heizer supp 06
 
Heizer mod a
Heizer mod aHeizer mod a
Heizer mod a
 
Heizer mod d
Heizer mod dHeizer mod d
Heizer mod d
 
How to choose and implement wms
How to choose and implement wmsHow to choose and implement wms
How to choose and implement wms
 
The New Distribution Strategy And How IT Enables It
The New Distribution Strategy And How IT Enables ItThe New Distribution Strategy And How IT Enables It
The New Distribution Strategy And How IT Enables It
 
Heizer 09
Heizer 09Heizer 09
Heizer 09
 
Heizer 14
Heizer 14Heizer 14
Heizer 14
 
Heizer 11
Heizer 11Heizer 11
Heizer 11
 
Opti Sustainability
Opti SustainabilityOpti Sustainability
Opti Sustainability
 
Heizer supp 11
Heizer supp 11Heizer supp 11
Heizer supp 11
 
Heizer om10 ch11_r
Heizer om10 ch11_rHeizer om10 ch11_r
Heizer om10 ch11_r
 
Heizer Chapter ch02
Heizer Chapter  ch02Heizer Chapter  ch02
Heizer Chapter ch02
 
Heizer supp 07
Heizer supp 07Heizer supp 07
Heizer supp 07
 
Heizer 12
Heizer 12Heizer 12
Heizer 12
 
Heizer 04
Heizer 04Heizer 04
Heizer 04
 
Ch07
Ch07Ch07
Ch07
 

Similar to Sogeti Webinar Effective Test Process Improvement 220709

Business Value Articulation In Software Projects
Business Value Articulation In Software ProjectsBusiness Value Articulation In Software Projects
Business Value Articulation In Software ProjectsHARMAN Services
 
Bug deBug Chennai 2012 Talk - Business value articulation in software project...
Bug deBug Chennai 2012 Talk - Business value articulation in software project...Bug deBug Chennai 2012 Talk - Business value articulation in software project...
Bug deBug Chennai 2012 Talk - Business value articulation in software project...RIA RUI Society
 
Industrialization Of Testing Softec2012 Ramesh
Industrialization Of Testing   Softec2012   RameshIndustrialization Of Testing   Softec2012   Ramesh
Industrialization Of Testing Softec2012 Ramesharalikatte
 
Wcm tofas-2012-eng
Wcm tofas-2012-engWcm tofas-2012-eng
Wcm tofas-2012-engpxhsh
 
Automation as a project - lessons learnt
Automation as a project - lessons learntAutomation as a project - lessons learnt
Automation as a project - lessons learntZbyszek Mockun
 
Stephen K. Allott - People Challenges for Test Teams - SoftTest Ireland
Stephen K. Allott - People Challenges for Test Teams - SoftTest IrelandStephen K. Allott - People Challenges for Test Teams - SoftTest Ireland
Stephen K. Allott - People Challenges for Test Teams - SoftTest IrelandDavid O'Dowd
 
Combining Performance Testing And Modelling For Easy Jet.Com V 1.0
Combining Performance Testing And Modelling For Easy Jet.Com V 1.0Combining Performance Testing And Modelling For Easy Jet.Com V 1.0
Combining Performance Testing And Modelling For Easy Jet.Com V 1.0dannyq
 
Looking for my fittest process' model
Looking for my fittest process' modelLooking for my fittest process' model
Looking for my fittest process' modelEnrique Morey
 
Model-Based Testing to Help You Enhance Your Agile Testing Process
Model-Based Testing to Help You Enhance Your Agile Testing ProcessModel-Based Testing to Help You Enhance Your Agile Testing Process
Model-Based Testing to Help You Enhance Your Agile Testing ProcessFrederic Oehl
 
Made in Germany 2011
Made in Germany 2011Made in Germany 2011
Made in Germany 2011Carlito54
 
The Role of the Business Analyst in Benefits
The Role of the Business Analyst in BenefitsThe Role of the Business Analyst in Benefits
The Role of the Business Analyst in BenefitsIIBA UK Chapter
 
IDC & Gomez Webinar --Best Practices: Protect Your Online Revenue Through Web...
IDC & Gomez Webinar --Best Practices: Protect Your Online Revenue Through Web...IDC & Gomez Webinar --Best Practices: Protect Your Online Revenue Through Web...
IDC & Gomez Webinar --Best Practices: Protect Your Online Revenue Through Web...Compuware APM
 
Softtek Break Through Savings No Need Offshore 2011 Asug Final
Softtek Break Through Savings No Need Offshore 2011 Asug FinalSofttek Break Through Savings No Need Offshore 2011 Asug Final
Softtek Break Through Savings No Need Offshore 2011 Asug FinalMauro Okamoto
 
BA and CMMI by Ivaylo Gueorguiev
BA and CMMI by Ivaylo GueorguievBA and CMMI by Ivaylo Gueorguiev
BA and CMMI by Ivaylo GueorguievIIBA_Bulgaria
 
Testing as-a-service capability portfolio corbus 02-07-13
Testing as-a-service capability portfolio corbus 02-07-13Testing as-a-service capability portfolio corbus 02-07-13
Testing as-a-service capability portfolio corbus 02-07-13ebreger
 
Kaizen color
Kaizen colorKaizen color
Kaizen colorradit12
 
ServiceNow Event 15.11.2012 / Beispiele aus Kundenprojekten von Aspediens
ServiceNow Event 15.11.2012 / Beispiele aus Kundenprojekten von AspediensServiceNow Event 15.11.2012 / Beispiele aus Kundenprojekten von Aspediens
ServiceNow Event 15.11.2012 / Beispiele aus Kundenprojekten von AspediensRené Haeberlin
 

Similar to Sogeti Webinar Effective Test Process Improvement 220709 (20)

Business Value Articulation In Software Projects
Business Value Articulation In Software ProjectsBusiness Value Articulation In Software Projects
Business Value Articulation In Software Projects
 
Bug deBug Chennai 2012 Talk - Business value articulation in software project...
Bug deBug Chennai 2012 Talk - Business value articulation in software project...Bug deBug Chennai 2012 Talk - Business value articulation in software project...
Bug deBug Chennai 2012 Talk - Business value articulation in software project...
 
Industrialization Of Testing Softec2012 Ramesh
Industrialization Of Testing   Softec2012   RameshIndustrialization Of Testing   Softec2012   Ramesh
Industrialization Of Testing Softec2012 Ramesh
 
Wcm tofas-2012-eng
Wcm tofas-2012-engWcm tofas-2012-eng
Wcm tofas-2012-eng
 
Automation as a project - lessons learnt
Automation as a project - lessons learntAutomation as a project - lessons learnt
Automation as a project - lessons learnt
 
170 sspcc1 d_davis
170 sspcc1 d_davis170 sspcc1 d_davis
170 sspcc1 d_davis
 
Accelerate Time to Business Outcomes through BPM
Accelerate Time to Business Outcomes through BPMAccelerate Time to Business Outcomes through BPM
Accelerate Time to Business Outcomes through BPM
 
Stephen K. Allott - People Challenges for Test Teams - SoftTest Ireland
Stephen K. Allott - People Challenges for Test Teams - SoftTest IrelandStephen K. Allott - People Challenges for Test Teams - SoftTest Ireland
Stephen K. Allott - People Challenges for Test Teams - SoftTest Ireland
 
Combining Performance Testing And Modelling For Easy Jet.Com V 1.0
Combining Performance Testing And Modelling For Easy Jet.Com V 1.0Combining Performance Testing And Modelling For Easy Jet.Com V 1.0
Combining Performance Testing And Modelling For Easy Jet.Com V 1.0
 
Looking for my fittest process' model
Looking for my fittest process' modelLooking for my fittest process' model
Looking for my fittest process' model
 
Model-Based Testing to Help You Enhance Your Agile Testing Process
Model-Based Testing to Help You Enhance Your Agile Testing ProcessModel-Based Testing to Help You Enhance Your Agile Testing Process
Model-Based Testing to Help You Enhance Your Agile Testing Process
 
Six Sigma
Six SigmaSix Sigma
Six Sigma
 
Made in Germany 2011
Made in Germany 2011Made in Germany 2011
Made in Germany 2011
 
The Role of the Business Analyst in Benefits
The Role of the Business Analyst in BenefitsThe Role of the Business Analyst in Benefits
The Role of the Business Analyst in Benefits
 
IDC & Gomez Webinar --Best Practices: Protect Your Online Revenue Through Web...
IDC & Gomez Webinar --Best Practices: Protect Your Online Revenue Through Web...IDC & Gomez Webinar --Best Practices: Protect Your Online Revenue Through Web...
IDC & Gomez Webinar --Best Practices: Protect Your Online Revenue Through Web...
 
Softtek Break Through Savings No Need Offshore 2011 Asug Final
Softtek Break Through Savings No Need Offshore 2011 Asug FinalSofttek Break Through Savings No Need Offshore 2011 Asug Final
Softtek Break Through Savings No Need Offshore 2011 Asug Final
 
BA and CMMI by Ivaylo Gueorguiev
BA and CMMI by Ivaylo GueorguievBA and CMMI by Ivaylo Gueorguiev
BA and CMMI by Ivaylo Gueorguiev
 
Testing as-a-service capability portfolio corbus 02-07-13
Testing as-a-service capability portfolio corbus 02-07-13Testing as-a-service capability portfolio corbus 02-07-13
Testing as-a-service capability portfolio corbus 02-07-13
 
Kaizen color
Kaizen colorKaizen color
Kaizen color
 
ServiceNow Event 15.11.2012 / Beispiele aus Kundenprojekten von Aspediens
ServiceNow Event 15.11.2012 / Beispiele aus Kundenprojekten von AspediensServiceNow Event 15.11.2012 / Beispiele aus Kundenprojekten von Aspediens
ServiceNow Event 15.11.2012 / Beispiele aus Kundenprojekten von Aspediens
 

Recently uploaded

Gen AI in Business - Global Trends Report 2024.pdf
Gen AI in Business - Global Trends Report 2024.pdfGen AI in Business - Global Trends Report 2024.pdf
Gen AI in Business - Global Trends Report 2024.pdfAddepto
 
Dev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio WebDev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio WebUiPathCommunity
 
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024BookNet Canada
 
Beyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
Beyond Boundaries: Leveraging No-Code Solutions for Industry InnovationBeyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
Beyond Boundaries: Leveraging No-Code Solutions for Industry InnovationSafe Software
 
costume and set research powerpoint presentation
costume and set research powerpoint presentationcostume and set research powerpoint presentation
costume and set research powerpoint presentationphoebematthew05
 
Advanced Test Driven-Development @ php[tek] 2024
Advanced Test Driven-Development @ php[tek] 2024Advanced Test Driven-Development @ php[tek] 2024
Advanced Test Driven-Development @ php[tek] 2024Scott Keck-Warren
 
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks..."LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...Fwdays
 
Integration and Automation in Practice: CI/CD in Mule Integration and Automat...
Integration and Automation in Practice: CI/CD in Mule Integration and Automat...Integration and Automation in Practice: CI/CD in Mule Integration and Automat...
Integration and Automation in Practice: CI/CD in Mule Integration and Automat...Patryk Bandurski
 
Bun (KitWorks Team Study 노별마루 발표 2024.4.22)
Bun (KitWorks Team Study 노별마루 발표 2024.4.22)Bun (KitWorks Team Study 노별마루 발표 2024.4.22)
Bun (KitWorks Team Study 노별마루 발표 2024.4.22)Wonjun Hwang
 
Install Stable Diffusion in windows machine
Install Stable Diffusion in windows machineInstall Stable Diffusion in windows machine
Install Stable Diffusion in windows machinePadma Pradeep
 
SQL Database Design For Developers at php[tek] 2024
SQL Database Design For Developers at php[tek] 2024SQL Database Design For Developers at php[tek] 2024
SQL Database Design For Developers at php[tek] 2024Scott Keck-Warren
 
Developer Data Modeling Mistakes: From Postgres to NoSQL
Developer Data Modeling Mistakes: From Postgres to NoSQLDeveloper Data Modeling Mistakes: From Postgres to NoSQL
Developer Data Modeling Mistakes: From Postgres to NoSQLScyllaDB
 
Pigging Solutions in Pet Food Manufacturing
Pigging Solutions in Pet Food ManufacturingPigging Solutions in Pet Food Manufacturing
Pigging Solutions in Pet Food ManufacturingPigging Solutions
 
Scanning the Internet for External Cloud Exposures via SSL Certs
Scanning the Internet for External Cloud Exposures via SSL CertsScanning the Internet for External Cloud Exposures via SSL Certs
Scanning the Internet for External Cloud Exposures via SSL CertsRizwan Syed
 
SIP trunking in Janus @ Kamailio World 2024
SIP trunking in Janus @ Kamailio World 2024SIP trunking in Janus @ Kamailio World 2024
SIP trunking in Janus @ Kamailio World 2024Lorenzo Miniero
 
Are Multi-Cloud and Serverless Good or Bad?
Are Multi-Cloud and Serverless Good or Bad?Are Multi-Cloud and Serverless Good or Bad?
Are Multi-Cloud and Serverless Good or Bad?Mattias Andersson
 
Designing IA for AI - Information Architecture Conference 2024
Designing IA for AI - Information Architecture Conference 2024Designing IA for AI - Information Architecture Conference 2024
Designing IA for AI - Information Architecture Conference 2024Enterprise Knowledge
 
"ML in Production",Oleksandr Bagan
"ML in Production",Oleksandr Bagan"ML in Production",Oleksandr Bagan
"ML in Production",Oleksandr BaganFwdays
 

Recently uploaded (20)

Gen AI in Business - Global Trends Report 2024.pdf
Gen AI in Business - Global Trends Report 2024.pdfGen AI in Business - Global Trends Report 2024.pdf
Gen AI in Business - Global Trends Report 2024.pdf
 
Dev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio WebDev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio Web
 
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
 
Beyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
Beyond Boundaries: Leveraging No-Code Solutions for Industry InnovationBeyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
Beyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
 
DMCC Future of Trade Web3 - Special Edition
DMCC Future of Trade Web3 - Special EditionDMCC Future of Trade Web3 - Special Edition
DMCC Future of Trade Web3 - Special Edition
 
costume and set research powerpoint presentation
costume and set research powerpoint presentationcostume and set research powerpoint presentation
costume and set research powerpoint presentation
 
Advanced Test Driven-Development @ php[tek] 2024
Advanced Test Driven-Development @ php[tek] 2024Advanced Test Driven-Development @ php[tek] 2024
Advanced Test Driven-Development @ php[tek] 2024
 
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks..."LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...
 
Integration and Automation in Practice: CI/CD in Mule Integration and Automat...
Integration and Automation in Practice: CI/CD in Mule Integration and Automat...Integration and Automation in Practice: CI/CD in Mule Integration and Automat...
Integration and Automation in Practice: CI/CD in Mule Integration and Automat...
 
Bun (KitWorks Team Study 노별마루 발표 2024.4.22)
Bun (KitWorks Team Study 노별마루 발표 2024.4.22)Bun (KitWorks Team Study 노별마루 발표 2024.4.22)
Bun (KitWorks Team Study 노별마루 발표 2024.4.22)
 
Install Stable Diffusion in windows machine
Install Stable Diffusion in windows machineInstall Stable Diffusion in windows machine
Install Stable Diffusion in windows machine
 
SQL Database Design For Developers at php[tek] 2024
SQL Database Design For Developers at php[tek] 2024SQL Database Design For Developers at php[tek] 2024
SQL Database Design For Developers at php[tek] 2024
 
Developer Data Modeling Mistakes: From Postgres to NoSQL
Developer Data Modeling Mistakes: From Postgres to NoSQLDeveloper Data Modeling Mistakes: From Postgres to NoSQL
Developer Data Modeling Mistakes: From Postgres to NoSQL
 
Pigging Solutions in Pet Food Manufacturing
Pigging Solutions in Pet Food ManufacturingPigging Solutions in Pet Food Manufacturing
Pigging Solutions in Pet Food Manufacturing
 
Scanning the Internet for External Cloud Exposures via SSL Certs
Scanning the Internet for External Cloud Exposures via SSL CertsScanning the Internet for External Cloud Exposures via SSL Certs
Scanning the Internet for External Cloud Exposures via SSL Certs
 
SIP trunking in Janus @ Kamailio World 2024
SIP trunking in Janus @ Kamailio World 2024SIP trunking in Janus @ Kamailio World 2024
SIP trunking in Janus @ Kamailio World 2024
 
Are Multi-Cloud and Serverless Good or Bad?
Are Multi-Cloud and Serverless Good or Bad?Are Multi-Cloud and Serverless Good or Bad?
Are Multi-Cloud and Serverless Good or Bad?
 
Designing IA for AI - Information Architecture Conference 2024
Designing IA for AI - Information Architecture Conference 2024Designing IA for AI - Information Architecture Conference 2024
Designing IA for AI - Information Architecture Conference 2024
 
Hot Sexy call girls in Panjabi Bagh 🔝 9953056974 🔝 Delhi escort Service
Hot Sexy call girls in Panjabi Bagh 🔝 9953056974 🔝 Delhi escort ServiceHot Sexy call girls in Panjabi Bagh 🔝 9953056974 🔝 Delhi escort Service
Hot Sexy call girls in Panjabi Bagh 🔝 9953056974 🔝 Delhi escort Service
 
"ML in Production",Oleksandr Bagan
"ML in Production",Oleksandr Bagan"ML in Production",Oleksandr Bagan
"ML in Production",Oleksandr Bagan
 

Sogeti Webinar Effective Test Process Improvement 220709

  • 1. Sogeti Ireland Effective Test Process Improvement Fran O’Hara fran.ohara@sogeti.com 22nd July 2009 © Sogeti Group 2009 Page 1 Contents • Introduction • TPI • TMMi • Process improvement challenges and sample solutions • Summary • Q&A © Sogeti Group 2009 Page 2
  • 2. SOGETI Overview: A Worldwide Leader in IT Services • Sogeti Group Part of 20,000 professionals • Leader in consulting, IT & 200 locations in 14 countries outsourcing • Providing worldwide standards • 88,000 staff • Revenue €8.7 billion Copyright TMap® and TPI® brands • Sogeti: Dedicated R&D on new developments • £1.6 billion revenues Test thought leadership • Testing revenues USA £150M (2007), £190M (2008) Sweden Test Centre of Excellence provides for UK Denmark Ireland • Reduced cost (>25% over 2 yrs) NL Germany • Improved quality Belux Switzerland • Improved flexibility France • Reduced time-to-test/market • Reduced risk Spain • Increased capacity India 3 © Sogeti Group 2009 Page 3 Test Process Improvement - learning to work smarter, to test software better, cheaper, faster Process focus improves World Class predictability of performance (reduces variation), as well as performance itself Products/services (difference between desired and actual) Capability People Process Technology © Sogeti Group 2009 Page 4
  • 3. Triggers • Efficiency/cost? • Effectiveness? • Growing Complexity? • Different levels of Test Maturity? • Time Pressure? • Are we doing the right thing(s)? Development Business Automation Time-to-market COTS CBD Standard. Reuse ty Growin ali I’s Agile g Qu Complex GU ity Cheap ic esXML Error serv free We b User-friendliness Integration Tester Maintainability © Sogeti Group 2009 Page 5 The TPI® Model Key areas Levels Test Maturity Matrix Checkpoints Improvement suggestions © Sogeti Group 2009 Page 6
  • 4. 20 Key Areas • Test strategy • Commitment and motivation • Life-cycle model • Testing functions and • Moment of involvement training • Estimating and planning • Scope of methodology • Test specification • Communication techniques • Reporting • Static test techniques • Defect management • Metrics • Testware management • Test automation • Test process management • Test environment • Evaluation • Office environment • Low-level testing © Sogeti Group 2009 Page 7 Current Situation (example) Key area / Scale 0 1 2 3 4 5 6 7 8 9 10 11 12 13 1 Test strategy A B C D 2 Life - cycle model A B 3 Moment of involvement A B C D 4 Estimating and planning A B 5 Test specification A B techniques Dependencies! 6 Static test techniques A B 7 Metrics A B C D 8 Test automation A B C 9 Test environment A B C 10 Office environment A 11 Commitment and A B C motivation 12 Test functions and training A B C 13 Scope of methodology A B C 14 Communication A B C 15 Reporting A B C D 16 Defect management A B C 17 Testware management A B C D 18 Test process management A B C 19 Evaluation A B 20 Low - level testing A B C © Sogeti Group 2009 Page 8
  • 5. Process Improvement …. Key area / Scale 0 1 2 3 4 5 6 7 8 9 10 11 12 13 1 Test strategy A B C D 2 Life - cycle model A B 3 Moment of involvement A B C D 4 Estimating and planning A B 5 Test specification A B techniques 6 Static test techniques A B 7 Metrics A B C D 8 Test automation A B C 9 Test environment A B C 10 Office environment A Opti ControlledB Efficient 11 Commitment and motivation A Cmizing 12 Test functions and training A B C 13 Scope of methodology A B C 14 Communication A B C 15 Reporting A B C D 16 Defect management A B C 17 Testware management A B C D 18 Test process management A B C 19 Evaluation A B 20 Low - level testing A B C © Sogeti Group 2009 Page 9 Testing Maturity Model Integration (TMMi®) • Currently under development by the TMMi Foundation See www.tmmifoundation.org Levels 2 & 3 published • The TMMi® Foundation will provide: A standard TMMi® Model that can be used in isolation or in support of other process improvement models and is either staged or continuous. An independently managed data repository to support TMMi® assessment method accreditation, assessor and assessment certification/validation and validated assessment data and certificates. Assessment Method Accreditation/Audit Framework for TMMi® in accordance with ISO15504 and the process to certify commercial assessment methods against the standard model. Certification and training/examination process, procedures and standards for formal, public accreditation of Assessors and Lead Assessors and the on-going management. © Sogeti Group 2009 Page 10
  • 6. TMMi® Model Level Process Areas 5 Optimisation Defect Prevention Test Process Optimisation Quality Control 4 Management & Measurement Test Measurement Software Quality Evaluation Advanced Peer Reviews 3 Integration Test Organisation Test Training Program Test Life Cycle and Integration Non-Functional Testing Peer Reviews 2 Managed Test Policy and Strategy Test Planning Test Monitoring and Control Test Design and Execution Test Environment 1 Initial © Sogeti Group 2009 Page 11 Problems with Process Improvement Typical Issues with Process Results from Sogeti ‘Worldwide survey on TPI’ : Improvement: Lack of management commitment ** Lack of management commitment Unrealistic expectations * Lack of prioritised goals to Unclear scope and target (i.e. goals) * focus/prioritise Unclear communication Only 17% had measurable results Excessive emphasis on documenting and assessing process Results unknown for too long a time Difficulty in defining and Lack of change process deploying the process Change team without influence Inadequate buy-in from staff Involvement of people within the test process* Top down approach (‘Thou shalt..’) Lack of process architecture 44% combined with other improvement projects © Sogeti Group 2009 Page 12
  • 7. Improvement Strategy - 1 Lack of management commitment Problems - Lack of management commitment** Lack of prioritised goals to focus/prioritise - Unrealistic expectations* - Unclear scope and target (i.e. goals)* - Unclear communication - Only 17% had measurable results - NB Solutions Achieve sign-off on documented requirements and constraints and associated improvement (project) plan Align and prioritise improvement efforts with business goals through a goal-problem tree Focus on early and measurable results © Sogeti Group 2009 Page 13 Problem Scenario - 1 Customer satisfaction Reported Production Defects rating dropped 20% in June 80 survey 70 60 compared to 6 50 months 40 previously. 30 # Severity 1 & 2 defects 20 10 Cost reduction 0 1 2 3 4 5 6 of 10% is also Months a department target © Sogeti Group 2009 Page 14
  • 8. Problem Scenario -2 Origin of Production Defects Data also shows that rework of production User requirements System requirements defects is Architecture costing 40% of Detailed design development Code & Build budget Integration © Sogeti Group 2009 Page 15 Examples of test-related improvement actions • Perform formal peer reviews of System requirements Involve system testers • Use a risk-based approach to system test involving business users in risk workshops • Use a test driven development approach to unit test (unit test cases developed and automated before code written) • Design system tests as soon as system requirements become available • Resource system test with some dedicated test professionals • Perform formal planning of system test • Measure DDP for peer reviews, unit test and system test • Some ways to identify improvement actions: Brainstorm process problems and vote Brainstorm improvement ideas/actions Model gap analysis – assessment results © Sogeti Group 2009 Page 16
  • 9. Goal Tree & Cost/Benefit Business Goal Dev/Test Test Process Est. Cost Est. Department Goal Goals of Benefit required actions Reduce IT Reduce rework Improve 200k 1m Appn. costs of production effectiveness of (10% of IT Development defects by 50% Peer reviews, budget) costs by 10% Unit test, and System Test by 75% (Currently running at 50% DDP) Improve Reduce number of As above 0 Satisfied Customer production defects customers satisfaction per month by 50% ratings by 20% (based on equivalent appn. throughput) © Sogeti Group 2009 Page 17 Goal Metric Scenario – Sample Results Defect Detection Percentage per Release 100 80 60 DDP 40 20 0 1 2 3 4 5 6 Release number (or subsequent projects) © Sogeti Group 2009 Page 18
  • 10. Improvement Strategy - 2 Excessive emphasis on documenting and Problems assessing process - Results unknown for too long a time Use a more agile approach to PI - Iterate in Solutions short improvement cycles (2-3 months) – how do you eat an elephant? Focus on lightweight, rapid process modelling for early deployment (80/20 rule for any gap analysis) Perform formal assessments to confirm process maturity results © Sogeti Group 2009 Page 19 Improvement Strategy - 3 Difficulty in defining and deploying the Problems process Lack of change process Change team without influence Inadequate buy-in from staff Involvement of people within the test process* Top down approach (‘Thou shalt..’) Use a facilitated workshop approach to process Solutions modelling/improvement Process owners involved in workshops, ‘change team’ become facilitators Goal–problem driven focus Use a continuously improving well-defined change process © Sogeti Group 2009 Page 20
  • 11. Example Modeling Session •Picture of process-level modeling (Image2) •session inserted here. © Sogeti Group 2009 Page 21 Example “Mapped” Element © Sogeti Group 2009 Page 22
  • 12. When a standard framework is required – sample process level template Level of Abstraction of tasks is Activity Controls or ‘Work Aids’ provide options key to a common framework for supporting templates, tools, procedures, etc. Activity Name Activity Purpose Activity Controls Action Artifact Artifact Inputs Entry Tasks Exit Outputs Artifact Condition ActionAction Condition Artifact Artifact Artifact Condition Action Condition Action Artifact Issues Roles Measurements Planning, Name Name Costs, Efforts, Tailoring, … Time, Quality Tailoring can also be used to highlight key differences of approach required © Sogeti Group 2009 Page 23 Sample Test Process Element Define the Test Strategy Entry Criteria Controls / Work Aids Exit Criteria 1. Inputs are under 1. Project Lifecycles with defined Test Stages 1. Test-ware is placed under Configuration Management 2. Test Methodology (identifying Test Methods & Test Configuration Management control Techniques.) control. 3. Review Meeting Minutes Template 4. Risk List Template 5. Test Strategy Template Inputs Tasks Outputs 1. Project Requirements 1. Determine level of Requirements definition for the 1. (Risk Based) Test Strategy. Document(s) [User, project 2. Prioritised Risk List. System, 2. Divide the System under Test into its components, if Functional/Technical] relevant. Prioritise component parts 2. Statement of Work 3. Identify and analyse Product Risks, taking Project 3. Test Project Scope Requirements, Statement of Work, Prioritized Quality Characteristics and System Components into consideration 4. Identify and Define Test Levels. 5. Identify and Define Test Level Attributes - Methods and Test Techniques, exit criteria, coverage, automation approach, etc. 6. Document the Testing Strategy. 7. Review and sign-off the Testing Strategy. Tailorings Roles Metrics 1. Test Manager (T.1-T.7) 1. Planned versus actual effort 2. Test Designer (T.5) 3. Business Analyst (T.3, T.7) 4. System Expert (T.3-T.7) 5. End User (T.3, T.7) © Sogeti Group 2009 Page 24
  • 13. Process of change Obtain awareness Determine target, area of consideration and approach Define Execute improvement assessment actions Perform Formulate evaluation plan Implement improvement actions © Sogeti Group 2009 Page 25 Suggestion: Use a performance-based ‘agile’ process improvement approach Phase 2: Phase 1: Selected Documented goals and problems baselines of for process current practice improvement and performance Phase 3: Process Phase 4: Revised documents to be process and deployed performance baselines © Sogeti Group 2009 Page 26
  • 14. Do’s – from TPI® survey • Clear scope and target 16% • Clear communication 9% • Results periodically visible 8% • Champions in change team 8% • Use of a change process 7% • Other ... 5% Biggest DO’s: • Management commitment 24% • Involvement of “own” people 23% © Sogeti Group 2009 Page 27 Summary – key suggestions • Use an agile approach to test process improvement – incremental with 80/20 prioritisation Driven by and linked to measurable business goals Addressing key staff process problems • Involvement and ownership by test staff • Lightweight, usable process definition (80/20 again!) © Sogeti Group 2009 Page 28
  • 15. Sogeti Support • Capability building test process and how to improve it seminars, workshops and training • Process assessments Model based (e.g. TPI®) and/or benchmarking • Consulting/mentoring during process improvement • fran.ohara@sogeti.com • www.sogeti.ie © Sogeti Group 2009 Page 29