SlideShare a Scribd company logo
1 of 3
Download to read offline
Page 1 of 3
Sequence of activities to operate - Monorail and Davit systems as Facade Access Equipment & limitations
SI System Sequence of activities to operate
1 Monorail tracks
• Identify & fix the access locations to rig & de-rig the suspension wires in a safe manner to the trolleys mounted on
monorail
• Aligned to this location provide the cradle location at ground or landing level to rig-de-rig the suspension wires
• Provide clear & safe transfer route from designated cradle parking location to rigging point and vice versa.
• Power supply sockets either at roof top or near ground level
• Any facade below a projection will require distant cleaning using extended tools as the cradle vertical movement is
in a line from suspension point. No touch cleaning so no maintenance while suspended in cradle.
• Projected features limits the cradle ascent unless the monorail is aligned to allow cradle descent on such features.
Depending on the projection, the touch cleaning will not be possible and so will be the maintenance.
• Any facade in the recess of more than 600mm could be cleaned with long squeegee. Maintenance purpose access will
need another approach and equipment.
• Ceiling mounting options & turn tables combinations to change directions & access the complete ceiling with clear
access points to rig & de-rig suspension wires and cradle at ground level
• Cleaning operations starts from top to down. In case of building height of more than 40 m, it must be restrained at
every 20 m descent from suspension point. In most of cases the cradle is stored on the ground. In this case, the
suspension wires are unrestrained while lowering after connecting to the trolleys mounted on the track, the first ascent
of the cradle, the last descent of the cradle and removal of the suspension wires. This leaves the risk unaddressed of
dangling wires and unrestrained cradle getting swayed for foreseeable possible mishap/ incident.
• This could be addressed by providing swing brackets to place & secure the cradle just below the monorail track or
extending the track inside the building to cradle designated parked position. Or use of suction cups during cradle
unrestrained first ascent & final descent as a primitive choice. The suspension wires during rig and de-rig could be
managed tied to nylon rope and held at the ground level by an operator.
• In case the dangling wires issue remains unaddressed, it will keep rubbing against the facade causing nuisance to
residents at that location and damage to the facade in addition to an eye sore.
Page 2 of 3
Safety & Performance Factors of Access Equipment
SI System Sequence of activities to operate
2 Davits
• Labour intensive system as davits and cradle are moved manually between every location of operations.
• For low profile davits – provide clear and obstruction free route for davits transfer on roof between fixations
points (sockets).
• Clear, Levelled & obstruction free route for cradle transfer on ground all along the facade line.
• To operate cradle at every location, operators have to follow the list of actions summarised in Table below.
• In case of building height more than 40m, it keeps the threat of unrestrained dangling wires at every location
and cradle vertical movement open to mishap and incident.
• The maintenance cost is high due to constant damage of cradle wheels, electric cable etc.
• More time is spent on shifting than cleaning the facade.
• Parapet mounted options is suitable for parapet height of up to 1.2 m otherwise a platform is required to access
and shift the davits at higher parapet height. Safety must be addressed.
• Horizontal jib reach limitations
• For High profile davits – clear & obstruction free path is required at roof level only as the cradle launch is
from the roof top.
• The cradle is always restrained due to launch from roof top.
• Safer solution compared to low profile davits for buildings higher than 40 m as it addresses the restraint system
needs.
• Sliding/ Traversing davits – Comparatively longer jib is possible compared to manual davit system.
• Any facade in the recess of more than 600mm could be cleaned with long squeegee. Maintenance purpose need
another approach and equipment.
• Projected features limits the cradle ascent in case of high profile davits unless the jib reach is aligned to allow
cradle descent on such features. Low profile davits application not a workable solution in such scenarios and any
canopy areas.
Page 3 of 3
Operation Method Statement
Low profile Davit Monorail
1. Connect suspension wires to the davit
2. Fix movable davits in the socket
3. Tie nylon rope to the loose end of suspension wires and lower to the ground level for another
operator to hold it
4. Lower the suspension wire in a controlled manner one by one with one person holding and
collecting the nylon rope until the loose end of suspension wires is fully lowered and detach
from nylon rope
5. Position cradle on location of operation
6. Connect supply cable to cradle control box
7. Connect power supply
8. Guide the suspension wires through the safety locks, to the hoists opening
9. Operate hoists to insert steel wires in hoist mechanism
10. Guide suspension wire to wire winders and secure the loose end to the wire winder point meant
for this purpose
11. Wind the additional length of wires on reelers operating the hoists
12. Board the cradle
13. Carry out the safety procedures & checks before starting operation
14. Lift the cradle to the top and fix the top limit plates
15. Operate downward carrying out cleaning operation to the landing level
16. Land the cradle and move out of the cradle
17. Take out the suspension wires out of wire winders, hoists and then safety locks
18. Disconnect the power supply
19. Remove supply cable plug from the supply socket
20. Push the cradle to new location
21. Remove the suspension wires from davits
22. Detach and fix one davit to next location in the direction of next location
23. And follow the sequence defined above
Note: Another quicker & safer way of cradle shifting and connecting to the low-profile davits at
next location is by disconnecting the wires, tying to nylon rope and lower to collect in the cradle.
Shift the cradle to next location and pull the wire up one by one tied to nylon wire, connect to the
davit at next location and fix the buffer plate before operation.
In case of high profile davit, it is comparatively simpler eliminating numerous activities as the
shitting of davits and cradle takes place at roof.
1. Rig the wires to monorail trolleys thro’ designated
access
2. Lower the suspension wires one at a time tied to
nylon rope managed at ground by another operator
for controlled lowering
3. Position the cradle at location at ground level or
relevant level
4. Connect the power cable to socket (either at roof or
just above GL)
5. Connect power supply cable to control box in cradle
6. Guide suspension wires thro’ safety locks to hoists
7. Operate hoists and wind the suspension wires on the
wire winders
8. Carry out the safety procedures and checks
9. Lift the cradle to top position
10. Descend carrying out cleaning operation
11. Ascend to the top suspension point and move
horizontally to next location of use
12. Lower the cradle carrying out the cleaning operation
13. Ascend again to the top suspension point and move
horizontally to next location
14. On work completion lower the cradle resting on
lowest designated landing point or inside the building
in case of monorail track leading to parking area
inside the building and secure
15. Remove the wires in case cradle parked position at
ground
16. Disconnect the power supply and store the cradle at
designated location
17. De-rig suspension wires from trolleys
18. Store with care

More Related Content

What's hot

Conveyor Safety
Conveyor SafetyConveyor Safety
Conveyor Safety
vtsiri
 
Crane Safety Training Presentation
Crane Safety Training PresentationCrane Safety Training Presentation
Crane Safety Training Presentation
FAIZ FAREED
 
Crane operator safety procedure
Crane operator safety procedureCrane operator safety procedure
Crane operator safety procedure
Abdul Shukur
 
American la france aerialoperationwylie, tx #0602973
American la france aerialoperationwylie, tx #0602973American la france aerialoperationwylie, tx #0602973
American la france aerialoperationwylie, tx #0602973
WylieFireRescue
 
Forklift Operator Safety Training by Platteville Public Schools
Forklift Operator Safety Training by Platteville Public SchoolsForklift Operator Safety Training by Platteville Public Schools
Forklift Operator Safety Training by Platteville Public Schools
Atlantic Training, LLC.
 

What's hot (20)

Crane Operations by EHS Compliance
Crane Operations by EHS ComplianceCrane Operations by EHS Compliance
Crane Operations by EHS Compliance
 
Conveyor Safety
Conveyor SafetyConveyor Safety
Conveyor Safety
 
Crane Safety Training Presentation
Crane Safety Training PresentationCrane Safety Training Presentation
Crane Safety Training Presentation
 
2015 CRW - Crucial Calls When Evaluating Wire Rope
2015 CRW - Crucial Calls When Evaluating Wire Rope2015 CRW - Crucial Calls When Evaluating Wire Rope
2015 CRW - Crucial Calls When Evaluating Wire Rope
 
Conveyor Belt Guarding as Metal and Nonmetal Mines
Conveyor Belt Guarding as Metal and Nonmetal MinesConveyor Belt Guarding as Metal and Nonmetal Mines
Conveyor Belt Guarding as Metal and Nonmetal Mines
 
Mobile crane safety rules
Mobile crane safety rulesMobile crane safety rules
Mobile crane safety rules
 
Overhead Crane Safety by FHM
Overhead Crane Safety by FHMOverhead Crane Safety by FHM
Overhead Crane Safety by FHM
 
Conveyor Safety
Conveyor SafetyConveyor Safety
Conveyor Safety
 
Crane Safety
Crane SafetyCrane Safety
Crane Safety
 
Crane operator safety procedure
Crane operator safety procedureCrane operator safety procedure
Crane operator safety procedure
 
American la france aerialoperationwylie, tx #0602973
American la france aerialoperationwylie, tx #0602973American la france aerialoperationwylie, tx #0602973
American la france aerialoperationwylie, tx #0602973
 
Catalog busbar ls 09. busduct installation&maintenance rev2
Catalog busbar ls 09. busduct installation&maintenance rev2Catalog busbar ls 09. busduct installation&maintenance rev2
Catalog busbar ls 09. busduct installation&maintenance rev2
 
Crane Hoist Operations
Crane Hoist OperationsCrane Hoist Operations
Crane Hoist Operations
 
Safe Rigging Practices
Safe Rigging PracticesSafe Rigging Practices
Safe Rigging Practices
 
2017 CRW: Wire Rope Challenges for Crawler Cranes (Mario Hartl)
2017 CRW:  Wire Rope Challenges for Crawler Cranes (Mario Hartl)2017 CRW:  Wire Rope Challenges for Crawler Cranes (Mario Hartl)
2017 CRW: Wire Rope Challenges for Crawler Cranes (Mario Hartl)
 
Rigging & slinging
Rigging & slingingRigging & slinging
Rigging & slinging
 
User manual for mobile scaffold
User manual for mobile scaffoldUser manual for mobile scaffold
User manual for mobile scaffold
 
Construction Technology II (Seminar) - Scaffolding
Construction Technology II (Seminar) - ScaffoldingConstruction Technology II (Seminar) - Scaffolding
Construction Technology II (Seminar) - Scaffolding
 
Eta Scaffold Training
Eta Scaffold TrainingEta Scaffold Training
Eta Scaffold Training
 
Forklift Operator Safety Training by Platteville Public Schools
Forklift Operator Safety Training by Platteville Public SchoolsForklift Operator Safety Training by Platteville Public Schools
Forklift Operator Safety Training by Platteville Public Schools
 

Similar to Sequence of activities to operate monorail and davits systems as fae & limitations

Do not let the electric cable rub the ground or be pressed by vehicles or oth...
Do not let the electric cable rub the ground or be pressed by vehicles or oth...Do not let the electric cable rub the ground or be pressed by vehicles or oth...
Do not let the electric cable rub the ground or be pressed by vehicles or oth...
thanh phuoc bui
 

Similar to Sequence of activities to operate monorail and davits systems as fae & limitations (20)

Lifting tools
Lifting toolsLifting tools
Lifting tools
 
Working at Heights
Working at Heights Working at Heights
Working at Heights
 
Failure analysis mtn526
Failure analysis mtn526Failure analysis mtn526
Failure analysis mtn526
 
Fall protection 502 feb 2016
Fall protection 502 feb 2016Fall protection 502 feb 2016
Fall protection 502 feb 2016
 
safe lift EMERSON EDUARDO RODRIGUES
safe lift EMERSON EDUARDO RODRIGUESsafe lift EMERSON EDUARDO RODRIGUES
safe lift EMERSON EDUARDO RODRIGUES
 
2014 CRW - Operating Cranes around Power Lines
2014 CRW - Operating Cranes around Power Lines2014 CRW - Operating Cranes around Power Lines
2014 CRW - Operating Cranes around Power Lines
 
Scissor Lifts Powerpoint
Scissor Lifts PowerpointScissor Lifts Powerpoint
Scissor Lifts Powerpoint
 
SG4:10 presentation
SG4:10 presentationSG4:10 presentation
SG4:10 presentation
 
SG4:10 presentation
SG4:10 presentationSG4:10 presentation
SG4:10 presentation
 
safety while prestressed concrete
safety while prestressed concretesafety while prestressed concrete
safety while prestressed concrete
 
Trulift presentation
Trulift presentationTrulift presentation
Trulift presentation
 
Safety at construction site
Safety at construction siteSafety at construction site
Safety at construction site
 
Overhead-Power-Cables classroom presentation
Overhead-Power-Cables classroom presentationOverhead-Power-Cables classroom presentation
Overhead-Power-Cables classroom presentation
 
Safety.pptx
Safety.pptxSafety.pptx
Safety.pptx
 
Overhead Crane Operator Safety 2021.pptx
Overhead Crane Operator Safety 2021.pptxOverhead Crane Operator Safety 2021.pptx
Overhead Crane Operator Safety 2021.pptx
 
1910.179 osha class
1910.179 osha class1910.179 osha class
1910.179 osha class
 
overhead_crane_operator_safety_manual.ppt
overhead_crane_operator_safety_manual.pptoverhead_crane_operator_safety_manual.ppt
overhead_crane_operator_safety_manual.ppt
 
overhead_crane_operator_safety_manual.ppt
overhead_crane_operator_safety_manual.pptoverhead_crane_operator_safety_manual.ppt
overhead_crane_operator_safety_manual.ppt
 
Safety at construction site
Safety at construction siteSafety at construction site
Safety at construction site
 
Do not let the electric cable rub the ground or be pressed by vehicles or oth...
Do not let the electric cable rub the ground or be pressed by vehicles or oth...Do not let the electric cable rub the ground or be pressed by vehicles or oth...
Do not let the electric cable rub the ground or be pressed by vehicles or oth...
 

Recently uploaded

Tales from a Passkey Provider Progress from Awareness to Implementation.pptx
Tales from a Passkey Provider  Progress from Awareness to Implementation.pptxTales from a Passkey Provider  Progress from Awareness to Implementation.pptx
Tales from a Passkey Provider Progress from Awareness to Implementation.pptx
FIDO Alliance
 
Hyatt driving innovation and exceptional customer experiences with FIDO passw...
Hyatt driving innovation and exceptional customer experiences with FIDO passw...Hyatt driving innovation and exceptional customer experiences with FIDO passw...
Hyatt driving innovation and exceptional customer experiences with FIDO passw...
FIDO Alliance
 
Harnessing Passkeys in the Battle Against AI-Powered Cyber Threats.pptx
Harnessing Passkeys in the Battle Against AI-Powered Cyber Threats.pptxHarnessing Passkeys in the Battle Against AI-Powered Cyber Threats.pptx
Harnessing Passkeys in the Battle Against AI-Powered Cyber Threats.pptx
FIDO Alliance
 

Recently uploaded (20)

The Zero-ETL Approach: Enhancing Data Agility and Insight
The Zero-ETL Approach: Enhancing Data Agility and InsightThe Zero-ETL Approach: Enhancing Data Agility and Insight
The Zero-ETL Approach: Enhancing Data Agility and Insight
 
Tales from a Passkey Provider Progress from Awareness to Implementation.pptx
Tales from a Passkey Provider  Progress from Awareness to Implementation.pptxTales from a Passkey Provider  Progress from Awareness to Implementation.pptx
Tales from a Passkey Provider Progress from Awareness to Implementation.pptx
 
Microsoft CSP Briefing Pre-Engagement - Questionnaire
Microsoft CSP Briefing Pre-Engagement - QuestionnaireMicrosoft CSP Briefing Pre-Engagement - Questionnaire
Microsoft CSP Briefing Pre-Engagement - Questionnaire
 
How we scaled to 80K users by doing nothing!.pdf
How we scaled to 80K users by doing nothing!.pdfHow we scaled to 80K users by doing nothing!.pdf
How we scaled to 80K users by doing nothing!.pdf
 
2024 May Patch Tuesday
2024 May Patch Tuesday2024 May Patch Tuesday
2024 May Patch Tuesday
 
How to Check GPS Location with a Live Tracker in Pakistan
How to Check GPS Location with a Live Tracker in PakistanHow to Check GPS Location with a Live Tracker in Pakistan
How to Check GPS Location with a Live Tracker in Pakistan
 
JavaScript Usage Statistics 2024 - The Ultimate Guide
JavaScript Usage Statistics 2024 - The Ultimate GuideJavaScript Usage Statistics 2024 - The Ultimate Guide
JavaScript Usage Statistics 2024 - The Ultimate Guide
 
Event-Driven Architecture Masterclass: Integrating Distributed Data Stores Ac...
Event-Driven Architecture Masterclass: Integrating Distributed Data Stores Ac...Event-Driven Architecture Masterclass: Integrating Distributed Data Stores Ac...
Event-Driven Architecture Masterclass: Integrating Distributed Data Stores Ac...
 
Hyatt driving innovation and exceptional customer experiences with FIDO passw...
Hyatt driving innovation and exceptional customer experiences with FIDO passw...Hyatt driving innovation and exceptional customer experiences with FIDO passw...
Hyatt driving innovation and exceptional customer experiences with FIDO passw...
 
Working together SRE & Platform Engineering
Working together SRE & Platform EngineeringWorking together SRE & Platform Engineering
Working together SRE & Platform Engineering
 
الأمن السيبراني - ما لا يسع للمستخدم جهله
الأمن السيبراني - ما لا يسع للمستخدم جهلهالأمن السيبراني - ما لا يسع للمستخدم جهله
الأمن السيبراني - ما لا يسع للمستخدم جهله
 
Harnessing Passkeys in the Battle Against AI-Powered Cyber Threats.pptx
Harnessing Passkeys in the Battle Against AI-Powered Cyber Threats.pptxHarnessing Passkeys in the Battle Against AI-Powered Cyber Threats.pptx
Harnessing Passkeys in the Battle Against AI-Powered Cyber Threats.pptx
 
Frisco Automating Purchase Orders with MuleSoft IDP- May 10th, 2024.pptx.pdf
Frisco Automating Purchase Orders with MuleSoft IDP- May 10th, 2024.pptx.pdfFrisco Automating Purchase Orders with MuleSoft IDP- May 10th, 2024.pptx.pdf
Frisco Automating Purchase Orders with MuleSoft IDP- May 10th, 2024.pptx.pdf
 
ERP Contender Series: Acumatica vs. Sage Intacct
ERP Contender Series: Acumatica vs. Sage IntacctERP Contender Series: Acumatica vs. Sage Intacct
ERP Contender Series: Acumatica vs. Sage Intacct
 
TEST BANK For, Information Technology Project Management 9th Edition Kathy Sc...
TEST BANK For, Information Technology Project Management 9th Edition Kathy Sc...TEST BANK For, Information Technology Project Management 9th Edition Kathy Sc...
TEST BANK For, Information Technology Project Management 9th Edition Kathy Sc...
 
Top 10 CodeIgniter Development Companies
Top 10 CodeIgniter Development CompaniesTop 10 CodeIgniter Development Companies
Top 10 CodeIgniter Development Companies
 
UiPath manufacturing technology benefits and AI overview
UiPath manufacturing technology benefits and AI overviewUiPath manufacturing technology benefits and AI overview
UiPath manufacturing technology benefits and AI overview
 
Intro to Passkeys and the State of Passwordless.pptx
Intro to Passkeys and the State of Passwordless.pptxIntro to Passkeys and the State of Passwordless.pptx
Intro to Passkeys and the State of Passwordless.pptx
 
Oauth 2.0 Introduction and Flows with MuleSoft
Oauth 2.0 Introduction and Flows with MuleSoftOauth 2.0 Introduction and Flows with MuleSoft
Oauth 2.0 Introduction and Flows with MuleSoft
 
AI+A11Y 11MAY2024 HYDERBAD GAAD 2024 - HelloA11Y (11 May 2024)
AI+A11Y 11MAY2024 HYDERBAD GAAD 2024 - HelloA11Y (11 May 2024)AI+A11Y 11MAY2024 HYDERBAD GAAD 2024 - HelloA11Y (11 May 2024)
AI+A11Y 11MAY2024 HYDERBAD GAAD 2024 - HelloA11Y (11 May 2024)
 

Sequence of activities to operate monorail and davits systems as fae & limitations

  • 1. Page 1 of 3 Sequence of activities to operate - Monorail and Davit systems as Facade Access Equipment & limitations SI System Sequence of activities to operate 1 Monorail tracks • Identify & fix the access locations to rig & de-rig the suspension wires in a safe manner to the trolleys mounted on monorail • Aligned to this location provide the cradle location at ground or landing level to rig-de-rig the suspension wires • Provide clear & safe transfer route from designated cradle parking location to rigging point and vice versa. • Power supply sockets either at roof top or near ground level • Any facade below a projection will require distant cleaning using extended tools as the cradle vertical movement is in a line from suspension point. No touch cleaning so no maintenance while suspended in cradle. • Projected features limits the cradle ascent unless the monorail is aligned to allow cradle descent on such features. Depending on the projection, the touch cleaning will not be possible and so will be the maintenance. • Any facade in the recess of more than 600mm could be cleaned with long squeegee. Maintenance purpose access will need another approach and equipment. • Ceiling mounting options & turn tables combinations to change directions & access the complete ceiling with clear access points to rig & de-rig suspension wires and cradle at ground level • Cleaning operations starts from top to down. In case of building height of more than 40 m, it must be restrained at every 20 m descent from suspension point. In most of cases the cradle is stored on the ground. In this case, the suspension wires are unrestrained while lowering after connecting to the trolleys mounted on the track, the first ascent of the cradle, the last descent of the cradle and removal of the suspension wires. This leaves the risk unaddressed of dangling wires and unrestrained cradle getting swayed for foreseeable possible mishap/ incident. • This could be addressed by providing swing brackets to place & secure the cradle just below the monorail track or extending the track inside the building to cradle designated parked position. Or use of suction cups during cradle unrestrained first ascent & final descent as a primitive choice. The suspension wires during rig and de-rig could be managed tied to nylon rope and held at the ground level by an operator. • In case the dangling wires issue remains unaddressed, it will keep rubbing against the facade causing nuisance to residents at that location and damage to the facade in addition to an eye sore.
  • 2. Page 2 of 3 Safety & Performance Factors of Access Equipment SI System Sequence of activities to operate 2 Davits • Labour intensive system as davits and cradle are moved manually between every location of operations. • For low profile davits – provide clear and obstruction free route for davits transfer on roof between fixations points (sockets). • Clear, Levelled & obstruction free route for cradle transfer on ground all along the facade line. • To operate cradle at every location, operators have to follow the list of actions summarised in Table below. • In case of building height more than 40m, it keeps the threat of unrestrained dangling wires at every location and cradle vertical movement open to mishap and incident. • The maintenance cost is high due to constant damage of cradle wheels, electric cable etc. • More time is spent on shifting than cleaning the facade. • Parapet mounted options is suitable for parapet height of up to 1.2 m otherwise a platform is required to access and shift the davits at higher parapet height. Safety must be addressed. • Horizontal jib reach limitations • For High profile davits – clear & obstruction free path is required at roof level only as the cradle launch is from the roof top. • The cradle is always restrained due to launch from roof top. • Safer solution compared to low profile davits for buildings higher than 40 m as it addresses the restraint system needs. • Sliding/ Traversing davits – Comparatively longer jib is possible compared to manual davit system. • Any facade in the recess of more than 600mm could be cleaned with long squeegee. Maintenance purpose need another approach and equipment. • Projected features limits the cradle ascent in case of high profile davits unless the jib reach is aligned to allow cradle descent on such features. Low profile davits application not a workable solution in such scenarios and any canopy areas.
  • 3. Page 3 of 3 Operation Method Statement Low profile Davit Monorail 1. Connect suspension wires to the davit 2. Fix movable davits in the socket 3. Tie nylon rope to the loose end of suspension wires and lower to the ground level for another operator to hold it 4. Lower the suspension wire in a controlled manner one by one with one person holding and collecting the nylon rope until the loose end of suspension wires is fully lowered and detach from nylon rope 5. Position cradle on location of operation 6. Connect supply cable to cradle control box 7. Connect power supply 8. Guide the suspension wires through the safety locks, to the hoists opening 9. Operate hoists to insert steel wires in hoist mechanism 10. Guide suspension wire to wire winders and secure the loose end to the wire winder point meant for this purpose 11. Wind the additional length of wires on reelers operating the hoists 12. Board the cradle 13. Carry out the safety procedures & checks before starting operation 14. Lift the cradle to the top and fix the top limit plates 15. Operate downward carrying out cleaning operation to the landing level 16. Land the cradle and move out of the cradle 17. Take out the suspension wires out of wire winders, hoists and then safety locks 18. Disconnect the power supply 19. Remove supply cable plug from the supply socket 20. Push the cradle to new location 21. Remove the suspension wires from davits 22. Detach and fix one davit to next location in the direction of next location 23. And follow the sequence defined above Note: Another quicker & safer way of cradle shifting and connecting to the low-profile davits at next location is by disconnecting the wires, tying to nylon rope and lower to collect in the cradle. Shift the cradle to next location and pull the wire up one by one tied to nylon wire, connect to the davit at next location and fix the buffer plate before operation. In case of high profile davit, it is comparatively simpler eliminating numerous activities as the shitting of davits and cradle takes place at roof. 1. Rig the wires to monorail trolleys thro’ designated access 2. Lower the suspension wires one at a time tied to nylon rope managed at ground by another operator for controlled lowering 3. Position the cradle at location at ground level or relevant level 4. Connect the power cable to socket (either at roof or just above GL) 5. Connect power supply cable to control box in cradle 6. Guide suspension wires thro’ safety locks to hoists 7. Operate hoists and wind the suspension wires on the wire winders 8. Carry out the safety procedures and checks 9. Lift the cradle to top position 10. Descend carrying out cleaning operation 11. Ascend to the top suspension point and move horizontally to next location of use 12. Lower the cradle carrying out the cleaning operation 13. Ascend again to the top suspension point and move horizontally to next location 14. On work completion lower the cradle resting on lowest designated landing point or inside the building in case of monorail track leading to parking area inside the building and secure 15. Remove the wires in case cradle parked position at ground 16. Disconnect the power supply and store the cradle at designated location 17. De-rig suspension wires from trolleys 18. Store with care