SlideShare a Scribd company logo
AMI Case Studies

Notes from the Field
Prepared by Tom Lawton,TESCO
for the Southeastern Electricity Metering Association (SEMA)
Abstract
•

As many utilities have elected to deploy advanced metering systems
and millions of new solid-state, microprocessor based end-points
with communications under glass, there has been a dramatic shift in
the approach to qualifying and certifying electricity meters.

•

This presentation will highlight the need for a rigorous approach to
meter certification as well as continued testing as both the meter
and the communication module and the firmware to run both are
upgraded and changed over the course of deployment.

•

Examples of issues which have arisen over the course of various
deployments along with varying approaches to and interpretations of
the same ANSI tests by manufacturers will be discussed.
AMI Deployment
Common Features and Common Sources of Concern
•
•
•
•
•
•

Compressed time frames for pre-deployment, pilots,
and deployment, pilots, and deployment
New features and functionality being added at a
tremendous rate
Bugs, fixes, improvements being implemented
constantly in the meter
Metering typically under represented or not
represented at all in AMI planning teams and
AMI deployment teams.
The need for testing throughout this process is
rarely understood or even appreciated by AMI
planning and deployment teams.
Issues around certification testing and acceptance
testing are initially seen simply as obstacles to
staying on schedule and not as valuable safeguards
against making potentially expensive mistakes
The Difference Between Meter Qualification, Meter
Certification & Meter Acceptance Testing
•

Meter Qualification – the easiest and least time consuming aspect
of putting a new AMI technology in the field.

•

Meter Certification – typically underestimated for the initial effort
and unanticipated over the course of deployment.

•

Meter Acceptance Testing – more than just accuracy testing.
Includes functional, firmware and communication testing of all
incoming shipments.
Managing Change – at the utility, at the vendor
and from the suppliers to our vendor
•

Every change is potentially important and should be treated this
way.

•

There is no “small change”.

•

There is rarely the same level of testing done for both the meter and
the communication device and never for the meter and the
communication module as an integrated device.

•

Are ANSI tests without the communication module integrated always
suitable from a business, commission and customer view point.
Who Should be Doing What?
And who is left standing that can do some
of these things at each step in the process?
•Meter Vendors
•Communication device vendors
•AMI Team
•Metering Group
•Third Party test Labs
- Where are the risks?
- How closely should each
participant be held accountable
and at which steps?
Effective Methodologies
•

Define the difference between each of the three types of testing and
certification

•

Define the testing protocols to be used – talk to other utilities,
vendors, third party labs. Define your own and be prepared for them
to evolve over the course of your project

•

Keep to the protocols.
Approvals, Failures
(do not term this “has
not passed yet”),
Deviations should all
be documented

FOLLOW

DEFINE

EVOLVE
Qualification Testing
Typical Protocols:
•
•

AMI Teams typically do a good job of defining what they expect the meters and
communications devices to do.
Meter Services can take this specifications document and check to see if the
devices proposed can handle these tasks.

Ways to stay out of trouble and to set yourself up for success in the subsequent
steps:
• Define the testing protocols to be used – talk to other utilities, vendors, third
party labs. Define your own and be prepared for them to evolve over the
course of your project.
• Keep to the protocols. Approvals, Failures (do not term this “has not passed
yet”), Deviations should all be documented.
• Check for yourself. If a feature is advertised then you should be able to verify
the feature is functional and whether this feature meets your needs. When
purchasing a “Smart” meter, know what you are getting.
Pre-deployment Certification Testing
•
•
•
•
•
•
•
•

ANSI Testing
Meter Functionality
Meter Data Acquisition Accuracy for Each Form
Dual Socket Meter Comparison – Data Collection & Accuracy
(Energy, Demand, Load Profile)
Large Test Platform Meter Comparison –
Data Collection & Accuracy
Disconnect/Reconnect Functionality
Outage Performance
Meter Communications Performance
Deployment and Post-Deployment
Certification Testing
•
•
•
•
•
•
•
•

ANSI Testing
Meter Functionality
Meter Data Acquisition Accuracy for Each Form
Dual Socket Meter Comparison – Data Collection & Accuracy
(Energy, Demand, Load Profile)
Large Test Platform Meter Comparison –
Data Collection & Accuracy
Disconnect/Reconnect Functionality
Outage Performance
Meter Communications Performance
Acceptance Testing
•

Accuracy testing

•

Meter Communications
Performance

•

Software and firmware
verification

•

Setting verification

•

Functional testing

•

Disconnect/reconnect
Functionality
and as left setting
Setting up Certification and
Acceptance Testing Plans
Questions that need to be asked:
• How does Acceptance Testing
differ from Certification Testing?
• When do we return to
Certification Testing?
• What should be built in to the
AMI Vendor Contracts?
• Who should be involved in
developing the Certification and
Acceptance Test Plans and
when should this be done?
Useful Tools & Potential Resources
• ISO 9001
• Quality System Documentation if not ISO 9001
• Quality systems and test reports from vendors
• ANSI Test results, and protocols used by various
manufacturers for these tests. Insist upon
additional testing where you feel necessary
• Third Party Labs for your own certification testing
ANSI & Other Standards
• Not all Standards are created equal. The same Standard is
often not interpreted the same way by all test facilities. The
devil is always in the details. Do not just ask if the meter
passed a particular test, but learn the details about how this
test was run. Also find out,
• What version of the meter?
• Was the communication module
integrated with the meter for any
of these tests?
Vendors, Consultants, Independent Labs,
Other Utilities, Networking
• You are not the first Utility to go through this process. At this point several others
utilities have completed or are nearing completion of a deployment with your
meter of choice or one of the meters you are considering choosing. There may
even be utilities who have deployed the same meter with the same
communication device. Ask your peers. Pick their brains. Talk to the metering
folks. We are pretty friendly individuals.
• Most of the vendors have gotten better about no
longer stone walling with “we have never seen
that issue before”. We are asking our meter
vendors to deploy new technology and new
features very rapidly. They generally want to
learn of any issues as quickly as possible and
address these issues as quickly as possible.
• You always have a first or a final resort to go to
an independent test facility – new feature never
used in the industry or a problem that crops
up after deployment has begun
Quality Audits
•

Schedule these for your meter manufacturer and your communication device
manufacturer.

•

Objective is to understand how they tested the product in the first place as well as
how any concerns that come up will be addressed. What is the mechanism, who are
the people, what capabilities do they have to investigate and determine root cause.
How and when are these responses fed back to you the customer and to the
manufacturing and supply chain.

•

In plant final inspection and testing

•

Plant first pass test results… if the number is less than 95% (which is typical),
validating and auditing the off-line repair process becomes equally as important as
auditing the main line quality checks

•

Vendor supply change management

•

Validation testing of firm ware changes
RMA’s and Self-Audits
•

In conjunction with auditing your vendor you should
audit your own procedures for identifying, reporting and
following up on issues.

•

For many this is simply a review of their RMA
procedures. These procedures need to be
strengthened and personnel assigned to them as the
number of issues will skyrocket over the course of a
deployment. Most will be of no or little consequence.
Some will be important and one or more may have
catastrophic results if not addressed quickly and
followed-up forcefully and with persistence.

•

Regardless of the extent of the self-audit, your quality
system will have to be strengthened and staffed to
handle the demands and the rigors of an AMI
deployment. Clear chains of command and reporting
protocols and decision matrixes will be as important as
any testing protocols.
Post-Deployment
Meter Farms as a Tool

•
•
•
•
•
•
•
•

Once deployment is complete the certification and acceptance testing does not
stop.
Everyone understands the importance of acceptance testing, but future
generations of a smart meter also require certification testing.
One new method for managing existing meter populations as well as future state
meters is through meter farms.
New software and firmware can be tested and compared against the performance
of older generations.
New hardware can be tested and compared to older generations.
Firmware upgrades can be checked
Long term issues can be identified or verified in the
meter farm
New head end systems or IT protocols can be
tested against the meter farm before going live
as well.
Real Life Examples of Change
Management in Action
•

Issues in the system not the components – what is the definition of a meter
and when did the meter change?
– Meter and communication device interface

•

Feature Creep – every manufacturer wants to differentiate themselves –
sometimes this works in unanticipated ways
– Recovery from power outages
– Short and long demand periods

•

But we only changed….lessons we should
have learned from Microsoft
– Over the air upgrades

•

Thank Goodness for testing plans and
contracts – right?
– Half closed disconnect devices
– Disconnect devices of unknown state
– Meters with incorrect firmware
Expected & Unexpected Trends Toward
the End of Deployment
Expected:
• The AMI deployment team will declare victory at some point and move on.
Clean-up will be left for the meter service department
• Change Management continues to be a tremendous challenge for every
vendor through every deployment
• Meter Acceptance testing including far more than accuracy testing for every
deployment
• Firmware upgrades must be checked and tested before mass deployment
Unexpected:
• Not all forms are available by the end of
deployment and must be installed as
part of normal operations by the meter
service department
• Meter Certification Testing never slowed
down over the course of any of the
deployments
Summary
• There are no bad manufacturers. Everyone is moving very
fast to meet the market demands. Without adequate checks
and balances there will be problems. Even with them, there
may still be problems – that is why we call this Risk Mitigation
and not Risk Elimination
• Each Utility must take a far more active role as part of this
system of checks and balances
Questions and Discussion
Tom Lawton
TESCO – The Eastern Specialty Company
Bristol, PA
215-688-0298 (cell) · 1-800-762-8211
Tom.Lawton@tescometermanager.com
This presentation can also be found under Meter
Conferences and Schools on the TESCO web site:
www.tesco-advent.com

More Related Content

What's hot

Regression testing
Regression testingRegression testing
Regression testing
gokilabrindha
 
Meter Operations In a Post AMI World
Meter Operations In a Post AMI WorldMeter Operations In a Post AMI World
Meter Operations In a Post AMI World
TESCO - The Eastern Specialty Company
 
Meter Operations in a Post AMI World
Meter Operations in a Post AMI WorldMeter Operations in a Post AMI World
Meter Operations in a Post AMI World
TESCO - The Eastern Specialty Company
 
Bjarne Mansson - Risk-based Testing,A Must For Medical Devices - EuroSTAR 2010
Bjarne Mansson - Risk-based Testing,A Must For Medical Devices - EuroSTAR 2010Bjarne Mansson - Risk-based Testing,A Must For Medical Devices - EuroSTAR 2010
Bjarne Mansson - Risk-based Testing,A Must For Medical Devices - EuroSTAR 2010
TEST Huddle
 
Michael Snyman - Software Test Automation Success
Michael Snyman - Software Test Automation Success Michael Snyman - Software Test Automation Success
Michael Snyman - Software Test Automation Success
TEST Huddle
 
Quality in software industry
Quality in software industryQuality in software industry
Quality in software industry
Richa Goel
 
Questions for successful test automation projects
Questions for successful test automation projectsQuestions for successful test automation projects
Questions for successful test automation projects
Daniel Ionita
 
Beyond Shingo: Prompt, Do, Check, Act (PDCA) & Universal Mistake Prevention a...
Beyond Shingo: Prompt, Do, Check, Act (PDCA) & Universal Mistake Prevention a...Beyond Shingo: Prompt, Do, Check, Act (PDCA) & Universal Mistake Prevention a...
Beyond Shingo: Prompt, Do, Check, Act (PDCA) & Universal Mistake Prevention a...
Tom Wiesen
 
Innovation day 2013 2.5 joris vanderschrick (verhaert) - embedded system de...
Innovation day 2013   2.5 joris vanderschrick (verhaert) - embedded system de...Innovation day 2013   2.5 joris vanderschrick (verhaert) - embedded system de...
Innovation day 2013 2.5 joris vanderschrick (verhaert) - embedded system de...Verhaert Masters in Innovation
 
Ian Smith - Mobile Software Testing - Facing Future Challenges
Ian Smith -  Mobile Software Testing - Facing Future ChallengesIan Smith -  Mobile Software Testing - Facing Future Challenges
Ian Smith - Mobile Software Testing - Facing Future Challenges
TEST Huddle
 
Verification and validation process in software testing
Verification and validation process in software testingVerification and validation process in software testing
Verification and validation process in software testing
pooja deshmukh
 
Software testing
Software testingSoftware testing
Software testing
sajedah abukhdeir
 
software testing metrics do's - don'ts-XBOSoft-QAI Webinar
software testing metrics do's - don'ts-XBOSoft-QAI Webinarsoftware testing metrics do's - don'ts-XBOSoft-QAI Webinar
software testing metrics do's - don'ts-XBOSoft-QAI WebinarXBOSoft
 
Learn software testing
Learn software testingLearn software testing
Learn software testing
sajedah abukhdeir
 
Se 381 - lec 28 -- 34 - 12 jun12 - testing 1 of 2
Se 381 -  lec 28 -- 34 - 12 jun12 - testing 1 of 2Se 381 -  lec 28 -- 34 - 12 jun12 - testing 1 of 2
Se 381 - lec 28 -- 34 - 12 jun12 - testing 1 of 2
babak danyal
 
Unit I Software Testing and Quality Assurance
Unit I Software Testing and Quality AssuranceUnit I Software Testing and Quality Assurance
Unit I Software Testing and Quality Assurance
VinothkumaR Ramu
 
Atos Origin - Testing - An Olympic Challenge
Atos Origin - Testing - An Olympic ChallengeAtos Origin - Testing - An Olympic Challenge
Atos Origin - Testing - An Olympic Challenge
TEST Huddle
 
ISTQB / ISEB Foundation Exam Practice - 2
ISTQB / ISEB Foundation Exam Practice - 2ISTQB / ISEB Foundation Exam Practice - 2
ISTQB / ISEB Foundation Exam Practice - 2Yogindernath Gupta
 
Software requirement verification & validation
Software requirement verification & validationSoftware requirement verification & validation
Software requirement verification & validationAbdul Basit
 

What's hot (20)

Regression testing
Regression testingRegression testing
Regression testing
 
Meter Operations In a Post AMI World
Meter Operations In a Post AMI WorldMeter Operations In a Post AMI World
Meter Operations In a Post AMI World
 
Meter Operations in a Post AMI World
Meter Operations in a Post AMI WorldMeter Operations in a Post AMI World
Meter Operations in a Post AMI World
 
Bjarne Mansson - Risk-based Testing,A Must For Medical Devices - EuroSTAR 2010
Bjarne Mansson - Risk-based Testing,A Must For Medical Devices - EuroSTAR 2010Bjarne Mansson - Risk-based Testing,A Must For Medical Devices - EuroSTAR 2010
Bjarne Mansson - Risk-based Testing,A Must For Medical Devices - EuroSTAR 2010
 
Michael Snyman - Software Test Automation Success
Michael Snyman - Software Test Automation Success Michael Snyman - Software Test Automation Success
Michael Snyman - Software Test Automation Success
 
Tqm
TqmTqm
Tqm
 
Quality in software industry
Quality in software industryQuality in software industry
Quality in software industry
 
Questions for successful test automation projects
Questions for successful test automation projectsQuestions for successful test automation projects
Questions for successful test automation projects
 
Beyond Shingo: Prompt, Do, Check, Act (PDCA) & Universal Mistake Prevention a...
Beyond Shingo: Prompt, Do, Check, Act (PDCA) & Universal Mistake Prevention a...Beyond Shingo: Prompt, Do, Check, Act (PDCA) & Universal Mistake Prevention a...
Beyond Shingo: Prompt, Do, Check, Act (PDCA) & Universal Mistake Prevention a...
 
Innovation day 2013 2.5 joris vanderschrick (verhaert) - embedded system de...
Innovation day 2013   2.5 joris vanderschrick (verhaert) - embedded system de...Innovation day 2013   2.5 joris vanderschrick (verhaert) - embedded system de...
Innovation day 2013 2.5 joris vanderschrick (verhaert) - embedded system de...
 
Ian Smith - Mobile Software Testing - Facing Future Challenges
Ian Smith -  Mobile Software Testing - Facing Future ChallengesIan Smith -  Mobile Software Testing - Facing Future Challenges
Ian Smith - Mobile Software Testing - Facing Future Challenges
 
Verification and validation process in software testing
Verification and validation process in software testingVerification and validation process in software testing
Verification and validation process in software testing
 
Software testing
Software testingSoftware testing
Software testing
 
software testing metrics do's - don'ts-XBOSoft-QAI Webinar
software testing metrics do's - don'ts-XBOSoft-QAI Webinarsoftware testing metrics do's - don'ts-XBOSoft-QAI Webinar
software testing metrics do's - don'ts-XBOSoft-QAI Webinar
 
Learn software testing
Learn software testingLearn software testing
Learn software testing
 
Se 381 - lec 28 -- 34 - 12 jun12 - testing 1 of 2
Se 381 -  lec 28 -- 34 - 12 jun12 - testing 1 of 2Se 381 -  lec 28 -- 34 - 12 jun12 - testing 1 of 2
Se 381 - lec 28 -- 34 - 12 jun12 - testing 1 of 2
 
Unit I Software Testing and Quality Assurance
Unit I Software Testing and Quality AssuranceUnit I Software Testing and Quality Assurance
Unit I Software Testing and Quality Assurance
 
Atos Origin - Testing - An Olympic Challenge
Atos Origin - Testing - An Olympic ChallengeAtos Origin - Testing - An Olympic Challenge
Atos Origin - Testing - An Olympic Challenge
 
ISTQB / ISEB Foundation Exam Practice - 2
ISTQB / ISEB Foundation Exam Practice - 2ISTQB / ISEB Foundation Exam Practice - 2
ISTQB / ISEB Foundation Exam Practice - 2
 
Software requirement verification & validation
Software requirement verification & validationSoftware requirement verification & validation
Software requirement verification & validation
 

Viewers also liked

Test Switch Operation, Specification & Accessories
Test Switch Operation, Specification & AccessoriesTest Switch Operation, Specification & Accessories
Test Switch Operation, Specification & Accessories
TESCO - The Eastern Specialty Company
 
TESCO Meter Manager - Tools to Help You More Efficiently Manage Your Meter De...
TESCO Meter Manager - Tools to Help You More Efficiently Manage Your Meter De...TESCO Meter Manager - Tools to Help You More Efficiently Manage Your Meter De...
TESCO Meter Manager - Tools to Help You More Efficiently Manage Your Meter De...
TESCO - The Eastern Specialty Company
 
ANSI 2014 Update
ANSI 2014 UpdateANSI 2014 Update
Site Verification - Protocols & Tools for Complex Metering Installations
Site Verification - Protocols & Tools for Complex Metering InstallationsSite Verification - Protocols & Tools for Complex Metering Installations
Site Verification - Protocols & Tools for Complex Metering Installations
TESCO - The Eastern Specialty Company
 
History of Electric Metering
History of Electric MeteringHistory of Electric Metering
History of Electric Metering
TESCO - The Eastern Specialty Company
 
TESCO New Product Updates
TESCO New Product UpdatesTESCO New Product Updates
TESCO New Product Updates
TESCO - The Eastern Specialty Company
 
Current Transformers: Ratio & Burden Testing
Current Transformers: Ratio & Burden TestingCurrent Transformers: Ratio & Burden Testing
Current Transformers: Ratio & Burden Testing
TESCO - The Eastern Specialty Company
 
Customer Request Field Meter Testing Programs
Customer Request Field Meter Testing ProgramsCustomer Request Field Meter Testing Programs
Customer Request Field Meter Testing Programs
TESCO - The Eastern Specialty Company
 
Meter Operations During and After AMI Deployment
Meter Operations During and After AMI DeploymentMeter Operations During and After AMI Deployment
Meter Operations During and After AMI Deployment
TESCO - The Eastern Specialty Company
 
Safety Topics - Hot Socket Issues, Causes & Best Practices
Safety Topics - Hot Socket Issues, Causes & Best PracticesSafety Topics - Hot Socket Issues, Causes & Best Practices
Safety Topics - Hot Socket Issues, Causes & Best Practices
TESCO - The Eastern Specialty Company
 
ANSI Testing
ANSI TestingANSI Testing
Customer Perceptions of New AMI Meters & What Meter Services Can do to Help...
Customer Perceptions of New AMI Meters & What Meter Services Can do to Help...Customer Perceptions of New AMI Meters & What Meter Services Can do to Help...
Customer Perceptions of New AMI Meters & What Meter Services Can do to Help...
TESCO - The Eastern Specialty Company
 
Meter Operations in a Post AMI World
Meter Operations in a Post AMI WorldMeter Operations in a Post AMI World
Meter Operations in a Post AMI World
TESCO - The Eastern Specialty Company
 
RF Meter Readings
RF Meter ReadingsRF Meter Readings
SEMA 2016 - Introduction to Transformer Rated Metering
SEMA 2016 -  Introduction to Transformer Rated MeteringSEMA 2016 -  Introduction to Transformer Rated Metering
SEMA 2016 - Introduction to Transformer Rated Metering
TESCO - The Eastern Specialty Company
 

Viewers also liked (15)

Test Switch Operation, Specification & Accessories
Test Switch Operation, Specification & AccessoriesTest Switch Operation, Specification & Accessories
Test Switch Operation, Specification & Accessories
 
TESCO Meter Manager - Tools to Help You More Efficiently Manage Your Meter De...
TESCO Meter Manager - Tools to Help You More Efficiently Manage Your Meter De...TESCO Meter Manager - Tools to Help You More Efficiently Manage Your Meter De...
TESCO Meter Manager - Tools to Help You More Efficiently Manage Your Meter De...
 
ANSI 2014 Update
ANSI 2014 UpdateANSI 2014 Update
ANSI 2014 Update
 
Site Verification - Protocols & Tools for Complex Metering Installations
Site Verification - Protocols & Tools for Complex Metering InstallationsSite Verification - Protocols & Tools for Complex Metering Installations
Site Verification - Protocols & Tools for Complex Metering Installations
 
History of Electric Metering
History of Electric MeteringHistory of Electric Metering
History of Electric Metering
 
TESCO New Product Updates
TESCO New Product UpdatesTESCO New Product Updates
TESCO New Product Updates
 
Current Transformers: Ratio & Burden Testing
Current Transformers: Ratio & Burden TestingCurrent Transformers: Ratio & Burden Testing
Current Transformers: Ratio & Burden Testing
 
Customer Request Field Meter Testing Programs
Customer Request Field Meter Testing ProgramsCustomer Request Field Meter Testing Programs
Customer Request Field Meter Testing Programs
 
Meter Operations During and After AMI Deployment
Meter Operations During and After AMI DeploymentMeter Operations During and After AMI Deployment
Meter Operations During and After AMI Deployment
 
Safety Topics - Hot Socket Issues, Causes & Best Practices
Safety Topics - Hot Socket Issues, Causes & Best PracticesSafety Topics - Hot Socket Issues, Causes & Best Practices
Safety Topics - Hot Socket Issues, Causes & Best Practices
 
ANSI Testing
ANSI TestingANSI Testing
ANSI Testing
 
Customer Perceptions of New AMI Meters & What Meter Services Can do to Help...
Customer Perceptions of New AMI Meters & What Meter Services Can do to Help...Customer Perceptions of New AMI Meters & What Meter Services Can do to Help...
Customer Perceptions of New AMI Meters & What Meter Services Can do to Help...
 
Meter Operations in a Post AMI World
Meter Operations in a Post AMI WorldMeter Operations in a Post AMI World
Meter Operations in a Post AMI World
 
RF Meter Readings
RF Meter ReadingsRF Meter Readings
RF Meter Readings
 
SEMA 2016 - Introduction to Transformer Rated Metering
SEMA 2016 -  Introduction to Transformer Rated MeteringSEMA 2016 -  Introduction to Transformer Rated Metering
SEMA 2016 - Introduction to Transformer Rated Metering
 

Similar to AMI Case Studies

Fundamentals of AMI Testing
Fundamentals of AMI TestingFundamentals of AMI Testing
Fundamentals of AMI Testing
TESCO - The Eastern Specialty Company
 
Meter Testing and AMI Deployment - Before, During and After
Meter Testing and AMI Deployment - Before, During and AfterMeter Testing and AMI Deployment - Before, During and After
Meter Testing and AMI Deployment - Before, During and After
TESCO - The Eastern Specialty Company
 
Fundamentals OF UAT
Fundamentals OF UATFundamentals OF UAT
Fundamentals OF UAT
ICHOFU VICTOR
 
ECNC 2016 - Managing Meter Shops of the Future
ECNC 2016 - Managing Meter Shops of the FutureECNC 2016 - Managing Meter Shops of the Future
ECNC 2016 - Managing Meter Shops of the Future
TESCO - The Eastern Specialty Company
 
Asset Management Gas Meter Farms
Asset Management Gas Meter FarmsAsset Management Gas Meter Farms
Asset Management Gas Meter Farms
TESCO - The Eastern Specialty Company
 
Meter Operations in a Post AMI World
Meter Operations in a Post AMI WorldMeter Operations in a Post AMI World
Meter Operations in a Post AMI World
TESCO - The Eastern Specialty Company
 
Meter Testing 101
Meter Testing 101Meter Testing 101
Software testing acceptance testing
Software testing  acceptance testingSoftware testing  acceptance testing
Software testing acceptance testing
GaneshKumarKanthiah
 
unit-2_20-july-2018 (1).pptx
unit-2_20-july-2018 (1).pptxunit-2_20-july-2018 (1).pptx
unit-2_20-july-2018 (1).pptx
PriyaFulpagare1
 
Meter Operations in a Post AMI World
Meter Operations in a Post AMI WorldMeter Operations in a Post AMI World
Meter Operations in a Post AMI World
TESCO - The Eastern Specialty Company
 
Tesco's AMI Specific Products and Services
Tesco's AMI Specific Products and ServicesTesco's AMI Specific Products and Services
Tesco's AMI Specific Products and Services
TESCO - The Eastern Specialty Company
 
Meter Operations in a Post AMI World
Meter Operations in a Post AMI WorldMeter Operations in a Post AMI World
Meter Operations in a Post AMI World
TESCO - The Eastern Specialty Company
 
Meter Testing 101.pptx
Meter Testing 101.pptxMeter Testing 101.pptx
Managing the Meter Shop of the Future Through Better Tools and Information
Managing the Meter Shop of the Future Through Better Tools and InformationManaging the Meter Shop of the Future Through Better Tools and Information
Managing the Meter Shop of the Future Through Better Tools and Information
TESCO - The Eastern Specialty Company
 
Introduction to Meter Testing
Introduction to Meter TestingIntroduction to Meter Testing
Introduction to Meter Testing
TESCO - The Eastern Specialty Company
 
Meter Testing 101
Meter Testing 101Meter Testing 101
Metering in a Post AMI World
Metering in a Post AMI WorldMetering in a Post AMI World
Metering in a Post AMI World
TESCO - The Eastern Specialty Company
 
Mini project.pptx
Mini project.pptxMini project.pptx
Mini project.pptx
VINAYAKCODM
 
ISTQB foundation level - day 2
ISTQB foundation level - day 2ISTQB foundation level - day 2
ISTQB foundation level - day 2
Shuchi Singla AKT,SPC4,PMI-ACP,ITIL(F),CP-AAT
 

Similar to AMI Case Studies (20)

Fundamentals of AMI Testing
Fundamentals of AMI TestingFundamentals of AMI Testing
Fundamentals of AMI Testing
 
Meter Testing and AMI Deployment - Before, During and After
Meter Testing and AMI Deployment - Before, During and AfterMeter Testing and AMI Deployment - Before, During and After
Meter Testing and AMI Deployment - Before, During and After
 
Fundamentals OF UAT
Fundamentals OF UATFundamentals OF UAT
Fundamentals OF UAT
 
ECNC 2016 - Managing Meter Shops of the Future
ECNC 2016 - Managing Meter Shops of the FutureECNC 2016 - Managing Meter Shops of the Future
ECNC 2016 - Managing Meter Shops of the Future
 
Asset Management Gas Meter Farms
Asset Management Gas Meter FarmsAsset Management Gas Meter Farms
Asset Management Gas Meter Farms
 
Telecom testing
Telecom testingTelecom testing
Telecom testing
 
Meter Operations in a Post AMI World
Meter Operations in a Post AMI WorldMeter Operations in a Post AMI World
Meter Operations in a Post AMI World
 
Meter Testing 101
Meter Testing 101Meter Testing 101
Meter Testing 101
 
Software testing acceptance testing
Software testing  acceptance testingSoftware testing  acceptance testing
Software testing acceptance testing
 
unit-2_20-july-2018 (1).pptx
unit-2_20-july-2018 (1).pptxunit-2_20-july-2018 (1).pptx
unit-2_20-july-2018 (1).pptx
 
Meter Operations in a Post AMI World
Meter Operations in a Post AMI WorldMeter Operations in a Post AMI World
Meter Operations in a Post AMI World
 
Tesco's AMI Specific Products and Services
Tesco's AMI Specific Products and ServicesTesco's AMI Specific Products and Services
Tesco's AMI Specific Products and Services
 
Meter Operations in a Post AMI World
Meter Operations in a Post AMI WorldMeter Operations in a Post AMI World
Meter Operations in a Post AMI World
 
Meter Testing 101.pptx
Meter Testing 101.pptxMeter Testing 101.pptx
Meter Testing 101.pptx
 
Managing the Meter Shop of the Future Through Better Tools and Information
Managing the Meter Shop of the Future Through Better Tools and InformationManaging the Meter Shop of the Future Through Better Tools and Information
Managing the Meter Shop of the Future Through Better Tools and Information
 
Introduction to Meter Testing
Introduction to Meter TestingIntroduction to Meter Testing
Introduction to Meter Testing
 
Meter Testing 101
Meter Testing 101Meter Testing 101
Meter Testing 101
 
Metering in a Post AMI World
Metering in a Post AMI WorldMetering in a Post AMI World
Metering in a Post AMI World
 
Mini project.pptx
Mini project.pptxMini project.pptx
Mini project.pptx
 
ISTQB foundation level - day 2
ISTQB foundation level - day 2ISTQB foundation level - day 2
ISTQB foundation level - day 2
 

Recently uploaded

Alt. GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using ...
Alt. GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using ...Alt. GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using ...
Alt. GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using ...
James Anderson
 
Pushing the limits of ePRTC: 100ns holdover for 100 days
Pushing the limits of ePRTC: 100ns holdover for 100 daysPushing the limits of ePRTC: 100ns holdover for 100 days
Pushing the limits of ePRTC: 100ns holdover for 100 days
Adtran
 
GraphSummit Singapore | Neo4j Product Vision & Roadmap - Q2 2024
GraphSummit Singapore | Neo4j Product Vision & Roadmap - Q2 2024GraphSummit Singapore | Neo4j Product Vision & Roadmap - Q2 2024
GraphSummit Singapore | Neo4j Product Vision & Roadmap - Q2 2024
Neo4j
 
Artificial Intelligence for XMLDevelopment
Artificial Intelligence for XMLDevelopmentArtificial Intelligence for XMLDevelopment
Artificial Intelligence for XMLDevelopment
Octavian Nadolu
 
Monitoring Java Application Security with JDK Tools and JFR Events
Monitoring Java Application Security with JDK Tools and JFR EventsMonitoring Java Application Security with JDK Tools and JFR Events
Monitoring Java Application Security with JDK Tools and JFR Events
Ana-Maria Mihalceanu
 
Mind map of terminologies used in context of Generative AI
Mind map of terminologies used in context of Generative AIMind map of terminologies used in context of Generative AI
Mind map of terminologies used in context of Generative AI
Kumud Singh
 
Removing Uninteresting Bytes in Software Fuzzing
Removing Uninteresting Bytes in Software FuzzingRemoving Uninteresting Bytes in Software Fuzzing
Removing Uninteresting Bytes in Software Fuzzing
Aftab Hussain
 
GraphRAG is All You need? LLM & Knowledge Graph
GraphRAG is All You need? LLM & Knowledge GraphGraphRAG is All You need? LLM & Knowledge Graph
GraphRAG is All You need? LLM & Knowledge Graph
Guy Korland
 
FIDO Alliance Osaka Seminar: The WebAuthn API and Discoverable Credentials.pdf
FIDO Alliance Osaka Seminar: The WebAuthn API and Discoverable Credentials.pdfFIDO Alliance Osaka Seminar: The WebAuthn API and Discoverable Credentials.pdf
FIDO Alliance Osaka Seminar: The WebAuthn API and Discoverable Credentials.pdf
FIDO Alliance
 
How to Get CNIC Information System with Paksim Ga.pptx
How to Get CNIC Information System with Paksim Ga.pptxHow to Get CNIC Information System with Paksim Ga.pptx
How to Get CNIC Information System with Paksim Ga.pptx
danishmna97
 
National Security Agency - NSA mobile device best practices
National Security Agency - NSA mobile device best practicesNational Security Agency - NSA mobile device best practices
National Security Agency - NSA mobile device best practices
Quotidiano Piemontese
 
Free Complete Python - A step towards Data Science
Free Complete Python - A step towards Data ScienceFree Complete Python - A step towards Data Science
Free Complete Python - A step towards Data Science
RinaMondal9
 
Encryption in Microsoft 365 - ExpertsLive Netherlands 2024
Encryption in Microsoft 365 - ExpertsLive Netherlands 2024Encryption in Microsoft 365 - ExpertsLive Netherlands 2024
Encryption in Microsoft 365 - ExpertsLive Netherlands 2024
Albert Hoitingh
 
DevOps and Testing slides at DASA Connect
DevOps and Testing slides at DASA ConnectDevOps and Testing slides at DASA Connect
DevOps and Testing slides at DASA Connect
Kari Kakkonen
 
GraphSummit Singapore | The Future of Agility: Supercharging Digital Transfor...
GraphSummit Singapore | The Future of Agility: Supercharging Digital Transfor...GraphSummit Singapore | The Future of Agility: Supercharging Digital Transfor...
GraphSummit Singapore | The Future of Agility: Supercharging Digital Transfor...
Neo4j
 
Communications Mining Series - Zero to Hero - Session 1
Communications Mining Series - Zero to Hero - Session 1Communications Mining Series - Zero to Hero - Session 1
Communications Mining Series - Zero to Hero - Session 1
DianaGray10
 
Generative AI Deep Dive: Advancing from Proof of Concept to Production
Generative AI Deep Dive: Advancing from Proof of Concept to ProductionGenerative AI Deep Dive: Advancing from Proof of Concept to Production
Generative AI Deep Dive: Advancing from Proof of Concept to Production
Aggregage
 
Video Streaming: Then, Now, and in the Future
Video Streaming: Then, Now, and in the FutureVideo Streaming: Then, Now, and in the Future
Video Streaming: Then, Now, and in the Future
Alpen-Adria-Universität
 
Secstrike : Reverse Engineering & Pwnable tools for CTF.pptx
Secstrike : Reverse Engineering & Pwnable tools for CTF.pptxSecstrike : Reverse Engineering & Pwnable tools for CTF.pptx
Secstrike : Reverse Engineering & Pwnable tools for CTF.pptx
nkrafacyberclub
 
GraphSummit Singapore | The Art of the Possible with Graph - Q2 2024
GraphSummit Singapore | The Art of the  Possible with Graph - Q2 2024GraphSummit Singapore | The Art of the  Possible with Graph - Q2 2024
GraphSummit Singapore | The Art of the Possible with Graph - Q2 2024
Neo4j
 

Recently uploaded (20)

Alt. GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using ...
Alt. GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using ...Alt. GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using ...
Alt. GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using ...
 
Pushing the limits of ePRTC: 100ns holdover for 100 days
Pushing the limits of ePRTC: 100ns holdover for 100 daysPushing the limits of ePRTC: 100ns holdover for 100 days
Pushing the limits of ePRTC: 100ns holdover for 100 days
 
GraphSummit Singapore | Neo4j Product Vision & Roadmap - Q2 2024
GraphSummit Singapore | Neo4j Product Vision & Roadmap - Q2 2024GraphSummit Singapore | Neo4j Product Vision & Roadmap - Q2 2024
GraphSummit Singapore | Neo4j Product Vision & Roadmap - Q2 2024
 
Artificial Intelligence for XMLDevelopment
Artificial Intelligence for XMLDevelopmentArtificial Intelligence for XMLDevelopment
Artificial Intelligence for XMLDevelopment
 
Monitoring Java Application Security with JDK Tools and JFR Events
Monitoring Java Application Security with JDK Tools and JFR EventsMonitoring Java Application Security with JDK Tools and JFR Events
Monitoring Java Application Security with JDK Tools and JFR Events
 
Mind map of terminologies used in context of Generative AI
Mind map of terminologies used in context of Generative AIMind map of terminologies used in context of Generative AI
Mind map of terminologies used in context of Generative AI
 
Removing Uninteresting Bytes in Software Fuzzing
Removing Uninteresting Bytes in Software FuzzingRemoving Uninteresting Bytes in Software Fuzzing
Removing Uninteresting Bytes in Software Fuzzing
 
GraphRAG is All You need? LLM & Knowledge Graph
GraphRAG is All You need? LLM & Knowledge GraphGraphRAG is All You need? LLM & Knowledge Graph
GraphRAG is All You need? LLM & Knowledge Graph
 
FIDO Alliance Osaka Seminar: The WebAuthn API and Discoverable Credentials.pdf
FIDO Alliance Osaka Seminar: The WebAuthn API and Discoverable Credentials.pdfFIDO Alliance Osaka Seminar: The WebAuthn API and Discoverable Credentials.pdf
FIDO Alliance Osaka Seminar: The WebAuthn API and Discoverable Credentials.pdf
 
How to Get CNIC Information System with Paksim Ga.pptx
How to Get CNIC Information System with Paksim Ga.pptxHow to Get CNIC Information System with Paksim Ga.pptx
How to Get CNIC Information System with Paksim Ga.pptx
 
National Security Agency - NSA mobile device best practices
National Security Agency - NSA mobile device best practicesNational Security Agency - NSA mobile device best practices
National Security Agency - NSA mobile device best practices
 
Free Complete Python - A step towards Data Science
Free Complete Python - A step towards Data ScienceFree Complete Python - A step towards Data Science
Free Complete Python - A step towards Data Science
 
Encryption in Microsoft 365 - ExpertsLive Netherlands 2024
Encryption in Microsoft 365 - ExpertsLive Netherlands 2024Encryption in Microsoft 365 - ExpertsLive Netherlands 2024
Encryption in Microsoft 365 - ExpertsLive Netherlands 2024
 
DevOps and Testing slides at DASA Connect
DevOps and Testing slides at DASA ConnectDevOps and Testing slides at DASA Connect
DevOps and Testing slides at DASA Connect
 
GraphSummit Singapore | The Future of Agility: Supercharging Digital Transfor...
GraphSummit Singapore | The Future of Agility: Supercharging Digital Transfor...GraphSummit Singapore | The Future of Agility: Supercharging Digital Transfor...
GraphSummit Singapore | The Future of Agility: Supercharging Digital Transfor...
 
Communications Mining Series - Zero to Hero - Session 1
Communications Mining Series - Zero to Hero - Session 1Communications Mining Series - Zero to Hero - Session 1
Communications Mining Series - Zero to Hero - Session 1
 
Generative AI Deep Dive: Advancing from Proof of Concept to Production
Generative AI Deep Dive: Advancing from Proof of Concept to ProductionGenerative AI Deep Dive: Advancing from Proof of Concept to Production
Generative AI Deep Dive: Advancing from Proof of Concept to Production
 
Video Streaming: Then, Now, and in the Future
Video Streaming: Then, Now, and in the FutureVideo Streaming: Then, Now, and in the Future
Video Streaming: Then, Now, and in the Future
 
Secstrike : Reverse Engineering & Pwnable tools for CTF.pptx
Secstrike : Reverse Engineering & Pwnable tools for CTF.pptxSecstrike : Reverse Engineering & Pwnable tools for CTF.pptx
Secstrike : Reverse Engineering & Pwnable tools for CTF.pptx
 
GraphSummit Singapore | The Art of the Possible with Graph - Q2 2024
GraphSummit Singapore | The Art of the  Possible with Graph - Q2 2024GraphSummit Singapore | The Art of the  Possible with Graph - Q2 2024
GraphSummit Singapore | The Art of the Possible with Graph - Q2 2024
 

AMI Case Studies

  • 1. AMI Case Studies Notes from the Field Prepared by Tom Lawton,TESCO for the Southeastern Electricity Metering Association (SEMA)
  • 2. Abstract • As many utilities have elected to deploy advanced metering systems and millions of new solid-state, microprocessor based end-points with communications under glass, there has been a dramatic shift in the approach to qualifying and certifying electricity meters. • This presentation will highlight the need for a rigorous approach to meter certification as well as continued testing as both the meter and the communication module and the firmware to run both are upgraded and changed over the course of deployment. • Examples of issues which have arisen over the course of various deployments along with varying approaches to and interpretations of the same ANSI tests by manufacturers will be discussed.
  • 3. AMI Deployment Common Features and Common Sources of Concern • • • • • • Compressed time frames for pre-deployment, pilots, and deployment, pilots, and deployment New features and functionality being added at a tremendous rate Bugs, fixes, improvements being implemented constantly in the meter Metering typically under represented or not represented at all in AMI planning teams and AMI deployment teams. The need for testing throughout this process is rarely understood or even appreciated by AMI planning and deployment teams. Issues around certification testing and acceptance testing are initially seen simply as obstacles to staying on schedule and not as valuable safeguards against making potentially expensive mistakes
  • 4. The Difference Between Meter Qualification, Meter Certification & Meter Acceptance Testing • Meter Qualification – the easiest and least time consuming aspect of putting a new AMI technology in the field. • Meter Certification – typically underestimated for the initial effort and unanticipated over the course of deployment. • Meter Acceptance Testing – more than just accuracy testing. Includes functional, firmware and communication testing of all incoming shipments.
  • 5. Managing Change – at the utility, at the vendor and from the suppliers to our vendor • Every change is potentially important and should be treated this way. • There is no “small change”. • There is rarely the same level of testing done for both the meter and the communication device and never for the meter and the communication module as an integrated device. • Are ANSI tests without the communication module integrated always suitable from a business, commission and customer view point.
  • 6. Who Should be Doing What? And who is left standing that can do some of these things at each step in the process? •Meter Vendors •Communication device vendors •AMI Team •Metering Group •Third Party test Labs - Where are the risks? - How closely should each participant be held accountable and at which steps?
  • 7. Effective Methodologies • Define the difference between each of the three types of testing and certification • Define the testing protocols to be used – talk to other utilities, vendors, third party labs. Define your own and be prepared for them to evolve over the course of your project • Keep to the protocols. Approvals, Failures (do not term this “has not passed yet”), Deviations should all be documented FOLLOW DEFINE EVOLVE
  • 8. Qualification Testing Typical Protocols: • • AMI Teams typically do a good job of defining what they expect the meters and communications devices to do. Meter Services can take this specifications document and check to see if the devices proposed can handle these tasks. Ways to stay out of trouble and to set yourself up for success in the subsequent steps: • Define the testing protocols to be used – talk to other utilities, vendors, third party labs. Define your own and be prepared for them to evolve over the course of your project. • Keep to the protocols. Approvals, Failures (do not term this “has not passed yet”), Deviations should all be documented. • Check for yourself. If a feature is advertised then you should be able to verify the feature is functional and whether this feature meets your needs. When purchasing a “Smart” meter, know what you are getting.
  • 9. Pre-deployment Certification Testing • • • • • • • • ANSI Testing Meter Functionality Meter Data Acquisition Accuracy for Each Form Dual Socket Meter Comparison – Data Collection & Accuracy (Energy, Demand, Load Profile) Large Test Platform Meter Comparison – Data Collection & Accuracy Disconnect/Reconnect Functionality Outage Performance Meter Communications Performance
  • 10. Deployment and Post-Deployment Certification Testing • • • • • • • • ANSI Testing Meter Functionality Meter Data Acquisition Accuracy for Each Form Dual Socket Meter Comparison – Data Collection & Accuracy (Energy, Demand, Load Profile) Large Test Platform Meter Comparison – Data Collection & Accuracy Disconnect/Reconnect Functionality Outage Performance Meter Communications Performance
  • 11. Acceptance Testing • Accuracy testing • Meter Communications Performance • Software and firmware verification • Setting verification • Functional testing • Disconnect/reconnect Functionality and as left setting
  • 12. Setting up Certification and Acceptance Testing Plans Questions that need to be asked: • How does Acceptance Testing differ from Certification Testing? • When do we return to Certification Testing? • What should be built in to the AMI Vendor Contracts? • Who should be involved in developing the Certification and Acceptance Test Plans and when should this be done?
  • 13. Useful Tools & Potential Resources • ISO 9001 • Quality System Documentation if not ISO 9001 • Quality systems and test reports from vendors • ANSI Test results, and protocols used by various manufacturers for these tests. Insist upon additional testing where you feel necessary • Third Party Labs for your own certification testing
  • 14. ANSI & Other Standards • Not all Standards are created equal. The same Standard is often not interpreted the same way by all test facilities. The devil is always in the details. Do not just ask if the meter passed a particular test, but learn the details about how this test was run. Also find out, • What version of the meter? • Was the communication module integrated with the meter for any of these tests?
  • 15. Vendors, Consultants, Independent Labs, Other Utilities, Networking • You are not the first Utility to go through this process. At this point several others utilities have completed or are nearing completion of a deployment with your meter of choice or one of the meters you are considering choosing. There may even be utilities who have deployed the same meter with the same communication device. Ask your peers. Pick their brains. Talk to the metering folks. We are pretty friendly individuals. • Most of the vendors have gotten better about no longer stone walling with “we have never seen that issue before”. We are asking our meter vendors to deploy new technology and new features very rapidly. They generally want to learn of any issues as quickly as possible and address these issues as quickly as possible. • You always have a first or a final resort to go to an independent test facility – new feature never used in the industry or a problem that crops up after deployment has begun
  • 16. Quality Audits • Schedule these for your meter manufacturer and your communication device manufacturer. • Objective is to understand how they tested the product in the first place as well as how any concerns that come up will be addressed. What is the mechanism, who are the people, what capabilities do they have to investigate and determine root cause. How and when are these responses fed back to you the customer and to the manufacturing and supply chain. • In plant final inspection and testing • Plant first pass test results… if the number is less than 95% (which is typical), validating and auditing the off-line repair process becomes equally as important as auditing the main line quality checks • Vendor supply change management • Validation testing of firm ware changes
  • 17. RMA’s and Self-Audits • In conjunction with auditing your vendor you should audit your own procedures for identifying, reporting and following up on issues. • For many this is simply a review of their RMA procedures. These procedures need to be strengthened and personnel assigned to them as the number of issues will skyrocket over the course of a deployment. Most will be of no or little consequence. Some will be important and one or more may have catastrophic results if not addressed quickly and followed-up forcefully and with persistence. • Regardless of the extent of the self-audit, your quality system will have to be strengthened and staffed to handle the demands and the rigors of an AMI deployment. Clear chains of command and reporting protocols and decision matrixes will be as important as any testing protocols.
  • 18. Post-Deployment Meter Farms as a Tool • • • • • • • • Once deployment is complete the certification and acceptance testing does not stop. Everyone understands the importance of acceptance testing, but future generations of a smart meter also require certification testing. One new method for managing existing meter populations as well as future state meters is through meter farms. New software and firmware can be tested and compared against the performance of older generations. New hardware can be tested and compared to older generations. Firmware upgrades can be checked Long term issues can be identified or verified in the meter farm New head end systems or IT protocols can be tested against the meter farm before going live as well.
  • 19. Real Life Examples of Change Management in Action • Issues in the system not the components – what is the definition of a meter and when did the meter change? – Meter and communication device interface • Feature Creep – every manufacturer wants to differentiate themselves – sometimes this works in unanticipated ways – Recovery from power outages – Short and long demand periods • But we only changed….lessons we should have learned from Microsoft – Over the air upgrades • Thank Goodness for testing plans and contracts – right? – Half closed disconnect devices – Disconnect devices of unknown state – Meters with incorrect firmware
  • 20. Expected & Unexpected Trends Toward the End of Deployment Expected: • The AMI deployment team will declare victory at some point and move on. Clean-up will be left for the meter service department • Change Management continues to be a tremendous challenge for every vendor through every deployment • Meter Acceptance testing including far more than accuracy testing for every deployment • Firmware upgrades must be checked and tested before mass deployment Unexpected: • Not all forms are available by the end of deployment and must be installed as part of normal operations by the meter service department • Meter Certification Testing never slowed down over the course of any of the deployments
  • 21. Summary • There are no bad manufacturers. Everyone is moving very fast to meet the market demands. Without adequate checks and balances there will be problems. Even with them, there may still be problems – that is why we call this Risk Mitigation and not Risk Elimination • Each Utility must take a far more active role as part of this system of checks and balances
  • 22. Questions and Discussion Tom Lawton TESCO – The Eastern Specialty Company Bristol, PA 215-688-0298 (cell) · 1-800-762-8211 Tom.Lawton@tescometermanager.com This presentation can also be found under Meter Conferences and Schools on the TESCO web site: www.tesco-advent.com