GENERAL FUND ENTERPRISE BUSINESS SYSTEM




                   SAP Transaction and Command Codes Job Aid




                                      Prepared by Accenture
                                         June 27, 2011




Department of the Army
United States of America
SAP Transaction and Command Codes Job Aid                                             GFEBS




        Transaction and Command Codes Job Aid Overview

Purpose:
   • The purpose of this job aid is to provide transaction codes and command codes that end users
     can use to easily navigate through the various screens of the SAP application. These
     transaction codes are listed by business process area and by role.
   • Transaction codes and command codes are slightly different:
         o A transaction code is a unique identifier attached to each transaction in SAP.
         o A command code is the text typed into the command field in order to access a
           transaction. It consists of the transaction code when the user is on the home screen
           (the SAP Easy Access Menu), or the transaction code and a prefix if the user is
           currently working within a transaction.
   • Command codes are entered into the command field as follows:
         o “<transaction code>” takes the user to the associated transaction if one is currently at
           the SAP Easy Access Menu.
         o “/N” ends the current transaction and returns the user to the main SAP Easy Access
           Menu.
            o “/N<transaction code>” ends the current transaction and starts the new specified
              transaction.
            o “/O” displays an overview of the open sessions.
            o “/O<transaction code>” starts a new session with the specified transaction while
              keeping the current session open.
            o    “/I” closes the active session.
            o “/Nend” ends the current transaction and prompts the user to log off of SAP.

Audience:
  • All GFEBS end users will utilize this job aid.




For Official Use Only                                                                    Page 2
SAP Transaction and Command Codes Job Aid                                            GFEBS




        Transaction Codes by Business Process Area

Click on the following Business Process Areas to be taken directly to that section:
    • Cost Management
    • Equipment & Assets
    • Financial Management
    • Funds Management
    • Plant Maintenance
    • Project System
    • Real Property Inventory
    • Reimbursables
    • Spending Chain


                                           Cost Management

     Role                                         Transaction Codes
Centralized             CM-EXT-2055- Add Custom Fields to Cost Center Master
Controlling             CP01 - Create Business Process
Master Data             CP02 - Change Business Process
Maintainer
                        CP04 - Delete Business Process
                        CP12 - Edit Business Processes
                        CP14 - Delete Business Processes
                        CPH1 - Create Business Process Group
                        CPH2 - Change Business Process Group
                        CPH4N - Change Standard Hierarchy
                        FMDERIVER - Object Assignment - Maintenance
                        IM01 - Create Investment Program Definition
                        IM02 - Change Investment Program Definition
                        IM11 - Create Investment Program Position
                        IM12 - Change Investment Program Position
                        IM13 - Display Investment Program Position
                        IM22 - Change Investment Program Structure
                        IM27 - Open New Approval Year
                        IM27_CLOSE- Close Old Approval Year
                        KA01 - Create Cost Element
                        KA02 - Change Cost Element
                        KA04 - Delete Cost Element
                        KA06 - Create Secondary Cost Element
                        KA24 - Delete Cost Elements
For Official Use Only                                                                  Page 3
SAP Transaction and Command Codes Job Aid                                      GFEBS

     Role                                       Transaction Codes
                        KAH1- Create Cost Element Group
                        KAH2 - Change Cost Element Group
                        KAK2 - Change Statistical Key Figures
                        KBH1 - Create Statistical Key Figure Group
                        KBH2 - Change Statistical Key Figure Group
                        KK01- Create Statistical Figure
                        KK02- Change Statistical Figure
                        KK03DEL - Delete Statistical Key Figures
                        KL01 - Create Activity Type
                        KL02 - Change Activity Type
                        KL04 - Delete Activity Type
                        KL14 - Delete Activity Types
                        KLH1 - Create Activity Type Group
                        KLH2 - Change Activity Type Group
                        KO01 - Create Internal Order
                        KO02 - Change Internal Order
                        KO04 - Order Manager
                        KOH1 - Create Order Group
                        KOH2 - Change Order Group
                        KOK6 - Collect. Printing of Internal Orders
                        KOSRLIST_OR - Internal Orders: Coll. Displ. SettRu
                        KP97 - Copy Planning for Cost Centers
                        KP98 - Copy Actual to Plan for Cost Center
                        KS01 - Create Cost Center
                        KS02- Change Cost Center
                        KS04 - Delete Cost Center
                        KS12 - Change Cost Centers
                        KS14- Delete Cost Centers
                        KSH1- Create Cost Center Group
                        KSH2- Change Cost Center Group
                        OKEON - Change Standard Hierarchy
                        S_ALR_87005263 - IMG Activity: SIMG_CFMENUORKAOK02
                        ZSCM_BIZ_PROC_LOAD - Business Process Upload
                        Extension
                        ZSCM_GPR_ACCT_DERIVE - GL Account Derivation Table
                        ZSCM_HOUR_CODE - Change View "Hour Code Indicators"
                        ZSCM_INTERN_ORD_LOAD - Internal Order Upload
                        Extension
                        ZSCM_TABLE_AREARESP – Check Table – Area of
                        Responsibility
                        ZSCM_TABLE_ATTRIB1 – Check Table - Attribute 1
                        ZSCM_TABLE_ATTRIB2 – Check Table - Attribute 2
                        ZSCM_TABLE_DMISID – Check Table - Defense Medical Sys
For Official Use Only                                                            Page 4
SAP Transaction and Command Codes Job Aid                                       GFEBS

     Role                                        Transaction Codes
                        ID
                        ZSCM_TABLE_FCACD – Check Table - Functnl Cost Acct
                        Code
                        ZSCM_TABLE_FDC – Table for Custom Field FDC
                        ZSCM_TABLE_INTIND – Check Table – Interface Indicator
                        ZSCM_TABLE_OUID – Check Table – Organizational Unit ID
                        ZSCM_TABLE_PRGAREA – Check Table – Program Area
                        ZSCM_TABLE_TDA – Check Table – TDA/TOE Paragraph
                        ZSCM_TABLE_UIC – Check Table – Unit ID Code
                        ZSCM_CC_MAINT – Upload Cost Center Master Data
Decentralized           IM01 - Create Investment Program Definition
Controlling             IM02- Change Investment Program Definition
Master Data             IM11 - Create Investment Program Position
Maintainer
                        IM12 - Change Investment Program Position
                        IM22 - Change Investment Program Structure
                        IM27 - Open New Approval Year
                        IM27_CLOSE- Close Old Approval Year
                        KO01 - Create Internal Order
                        KO02 - Change Internal Order
                        KO04 - Order Manager
                        KOH1 - Create Order Group
                        KOH2 - Change Order Group
                        KOK6 - Collect. Printing of Internal Orders
                        ZSCM_INTERN_ORD_LOAD - Internal Order Upload
                        Extension
Cost                    CPP1 - Create Actual Assess. for Processes
Allocation              CPP2 - Change Actual Assess. for Processes
Processor               CPP4 - Delete Actual Assess. for Processes
                        CPP6 - Actual Assess. Processes: Overview
                        CPP7 - Create Plan Assess. for Processes
                        CPP8 - Change Plan Assess. for Processes
                        CPPA - Delete Plan Assessment for Processes
                        CPT1 - Create Template
                        CPT2 - Change Template
                        CPT4 - Delete Template
                        CPV1 - Create Actual Process Distribution
                        CPV2 - Change Actual Distribution Process
                        CPV4 - Delete Actual Process Distribution
                        CPV6 - Actual Process Distribution Overview
                        CPV7 - Create Plan Process Distribution
                        CPV8 - Change Plan Process Distribution
                        CPVA - Delete Plan Process Distribution
                        KSC1 – Create Actual Indirect Acty Alloc.
For Official Use Only                                                             Page 5
SAP Transaction and Command Codes Job Aid                                   GFEBS

     Role                                      Transaction Codes
                        KSC2 – Change Actual Indirect Acty Alloc.
                        KSC4 – Delete Actual Indirect Acty Alloc.
                        KSC7 – Create Indirect Activity Alloc. Plan
                        KSC8 – Change Indirect Activity Alloc. Plan
                        KSCA – Delete Indirect Activity Alloc. Plan
                        KSU1 - Create Actual Assessment
                        KSU2 - Change Actual Assessment
                        KSU4 - Delete Actual Assessment
                        KSU7 – Create Plan Assessment
                        KSU8 - Change Plan Assessment
                        KSUA - Delete Plan Assessment
                        KSUC - Plan Assessment: Overview
                        KSV1 - Create Actual Distribution
                        KSV2 - Change Actual Distribution
                        KSV4 - Delete Actual Distribution
                        KSV6 - Actual Distribution: Overview
                        KSV7 - Create Plan Distribution
                        KSV8 - Change Plan Distribution
                        KSVA - Delete Plan Distribution
                        KSVC - Plan Distribution: Overview
                        KSW1 - Create Periodic Reposting
                        KSW2 - Change Periodic Reposting
                        KSW4 - Delete Periodic Reposting
                        KZA1 - Maintain Overhead Tables
                        KZB2 - Calculation Base: Cost Element/Origin
                        KZB4 - Calculation Base: Cost Center/Activity Type
                        KZE2 – Credit
                        KZM2 - Maintain Quantity Based Overhead
                        KZS2 - Costing Sheet
                        KZZ2 - Maintain Percentage Overhead
                        OKOZ - Maintain Overhead Tables
                        S_ALR_87005104 - IMG Activity: SIMG_CFMENUORKAKZS2
Cost Plan               CJZ7 - Planned Int.Calc: Indiv.CO Ord.Proc.
Maintainer              CJZ9 - Plan Int.Calc.: Coll.CO Order Prc.
                        CP06 - Activity Inputs
                        CP26 - Change Plan Data for Business Processes
                        CP46 - Statistical Key Figures
                        CPCB - Execute Plan Indirect Acty Alloc.
                        CPP7 - Create Plan Assess. for Processes
                        CPP8 - Change Plan Assess. for Processes
                        CPPA - Delete Plan Assessment for Processes
                        CPPB - Execute Plan Assess. for Processes
                        CPPS - Plan Template Allocation: Process
For Official Use Only                                                         Page 6
SAP Transaction and Command Codes Job Aid                                             GFEBS

     Role                                         Transaction Codes
                        CPUA - Plan Template Allocation: Order
                        CPUB - Plan Template Allocation: Orders
                        CPV7 - Create Plan Process Distribution
                        CPV8 - Change Plan Process Distribution
                        CPVA - Delete Plan Process Distribution
                        CPVB - Execute Plan Process Distribution
                        CPZP - Plan Overhead: Business Processes
                        KGP2 - Overhead Plan.: Int.Orders Ind.Pro.
                        KGP4 - Overhead Plan.: Int.Orders Col.Pro.
                        KO12 - Change Order Plan (Overall, Year)
                        KO9E - Plan Settlement: Internal Order
                        KO9G - Plan Settlement: Internal Orders
                        KP04 - Set Planner Profile
                        KP06 - Change CElem/Activity Input Planning
                        KP26 - Change Plan Data for Activity Types
                        KP46 - Change Stat. Key Figure Plan Data
                        KPD6 - Change Stat. Key Figure Plan Data
                        KPF6 - Change CElem/Activity Input Planning
                        KPPS - Allocation Templ. Plan: CCtr/ATyp
                        KSC7 - Create Indirect Activity Alloc. Plan
                        KSC8 - Change Indirect Activity Alloc. Plan
                        KSCA - Delete Indirect Activity Alloc. Plan
                        KSCB - Execute Plan Indirect Acty Alloc.
                        KSP4 - Plan Overhead: Cost Centers
                        KSPI – Iterative Plan Price Calculation
                        KSU7 – Create Plan Assessment
                        KSU8 - Change Plan Assessment
                        KSUA - Delete Plan Assessment
                        KSUB - Execute Plan Assessment
                        KSUC - Plan Assessment: Overview
                        KSV7 - Create Plan Distribution
                        KSV8 - Change Plan Distribution
                        KSVA - Delete Plan Distribution
                        KSVB - Execute Plan Distribution
                        KSVC - Plan Distribution: Overview
                        KSWB - Execute Plan Periodic Reposting
                        ZSCM_ATBP - Activity Type and Business Process Rates Extension from Load
                        Spreadsheet
Payroll                 BD87 - Status Monitor for ALE Messages
Interface               CM-INT-2014- DCPS Unfunded Leave
Processing              CM-INT-2015 - DCPS GPF
Monitor
                        SM35 - Batch Input Monitoring
                        WE02 - Display IDoc
                        ZOS_IST - IDoc Status Report

For Official Use Only                                                                    Page 7
SAP Transaction and Command Codes Job Aid                                             GFEBS

     Role                                         Transaction Codes
                        ZSCA_TT_ERR_MAINT - Maintain Error Tracking Table
                        ZSCM_ATAAPS_OP_AGNCY - Maintain Operations Agency Table
                        ZSCM_ATAAPS_OUTBOUND - View Outbound Cost Master Data
                        Tables
                        ZSCM_DISB_ALLOC – Disbursement Extension for Time Trac
                        ZSCM_GL_ACCRUAL- Accrual GL Account Derivation Table
                        ZSCM_GPR_ACCT_DERIVE - GL Account Derivation Table
                        ZSCM_GPR_RECONCILE – Gross Pay Reconcilliation (GPR)
                        ZSCM_PAYROLL_ACCRUAL - Payroll Accrual Process
DTS                     BD87 - Reprocess Failed IDocs
Interface               BD87 - Status Monitor for ALE Messages
Processing              WE02 - Display IDoc
Monitor
                        WE09 - Search for IDoc in Database
                        ZOS_IST - IDoc Status Report
Controlling             KB15N - Enter Manual Allocations
Close                   KGI2 - Actual Overhead Calcuation: Order
Processor               KGI4 - Actual Overhead: Int.Ord. Coll. Proc.
                        KO88 - Individual Processing
                        KO8G - Act. Settlment: Int.-/Maint. Orders
                        KOC4 - Cost Analysis
                        KOK2 - Collective Proc. Internal Orders
                        KOK3 – Collective Disp. Internal Orders
                        KOK4 - Aut. Collect. Proc. Internal Orders
                        KON1 - Actual Reval.: Int.Orders Ind.Pro.
                        KON2 - Actual Reval.: Int.Orders Col.Pro.
                        KOSRLIST_OR- Internal Orders: Coll. Displ. SettRu
                        KSII - Actual Price Determination: CCtrs
                        KSS2 - Actual Cost Splitting: Cost Centers
                        KSU5 – Assessment
                        KSV5 - Execute Actual Distribution
                        KSW5 - Execute Actual Periodic Reposting
                        RECOSEVAR – Collective Processing-Settlement of Line Items
                        ZSCM_ACTUP - Manual Activity and Business Process Allocation Upload from
                        Load Spreadsheet
Cost ECC                CP03 - Display Business Process
Display and             CP07 - Display Activity Inputs
Reporter                CP13 - Business Processes: Master Data Rep.
                        CP27 - Display Plan Data for Business Processes
                        CP47 - Display Statistical Key Figures
                        CPB1 - Business Processes: Actual Line Items
                        CPBT - Business Process Price Report
                        CPH3 - Display Business Process Group
                        CPH5N - Display Std Hierarchy/Business Proc.
                        CPP3 - Display Actual Assess. for Processes
For Official Use Only                                                                    Page 8
SAP Transaction and Command Codes Job Aid                                   GFEBS

     Role                                          Transaction Codes
                        CPP9 - Display Plan Assess. for Processes
                        CPT3 - Display Template
                        CPV3 - Display Actual Process Distribution
                        CPV9 - Display Plan Process Distribution
                        IM03 - Display Investment Program Definition
                        IM23 - Display Investment Program Structure
                        KA03 - Display Cost Element
                        KA05 - Cost Element: Display Changes
                        KA23 - Cost Elements: Master Data Report
                        KABL - Order: Planning Overview
                        KABP - Controlling Documents: Plan
                        KAH3 - Display Cost Element Group
                        KAK3- Display Statistical Key Figures
                        KB16N – View Manual Cost Allocations
                        KB23N - Display Direct Activity Allocation
                        KB33N - Display Statistical Key Figures
                        KB53N - Display Services
                        KBH3 - Display Statistical Key Figure Group
                        KK03 - Display Statistical Key Figures
                        KK04 - Stat.Key Figures: Master Data Report
                        KL03 - Display Activity Type
                        KL05 - Activity type: Display Changes
                        KL13 - Activity Types: Master Data Report
                        KL20 - Templ. Alloc. Struct. CCTR/Acty Type
                        KLH3 - Display Activity Type Group
                        KO03 - Display Internal Order
                        KO13 - Display Order Plan (Overall, Year)
                        KOB1 - Orders: Actual Line Items
                        KOB2 - Orders: Commitment Line Items
                        KOBP - Orders: Plan Line Items
                        KOC4 - Cost Analysis
                        KOH3 - Display Order Group
                        KOK3 - Collective Disp. Internal Orders
                        KOK5 - Master Data List Internal Orders
                        KOSRLIST_OR - Internal Orders: Coll. Displ. SettRu
                        KP07 - Display Planning CElem/Act. Input
                        KP27 - Display Plan Data for Activity Types
                        KP47 - Display Stat. Key Figure Plan Data
                        KPD7 - Display Stat. Key Figure Plan Data
                        KPF7 - Display CElem./Acty Input Planning
                        KS03 - Display Cost Center
                        KS05 - Cost Center: Display Changes
                        KS13 - Cost Centers: Master Data Report
                        KSB1 - Cost Centers: Actual Line Items
                        KSB2 - Cost Centers: Commitment Line Items

For Official Use Only                                                         Page 9
SAP Transaction and Command Codes Job Aid                                           GFEBS

     Role                                         Transaction Codes
                        KSB5 - Controlling Documents: Actual
                        KSBL - Cost Centers: Planning overview
                        KSBP - Cost Centers: Plan Line Items
                        KSBT - Cost centers: Activity Prices
                        KSC3 - Display Actual Indirect Acty Alloc.
                        KSC9 - Display Indirect Acty Alloc. Plan
                        KSH3 - Display Cost Center Group
                        KSU3 - Display Actual Assessment
                        KSU6 - Actual Assessment: Overview
                        KSU9 - Display Plan Assessment
                        KSV3 - Display Actual Distribution
                        KSV9 - Display Plan Distribution
                        KSW3 - Display Periodic Reposting
                        OKENN - Display Standard Hierarchy
                        RECOSEVAR - Collective Processing-Settlement of Line Items
                        REISCOCSTACT - Report for Costs/Revenue: Period
                        Overview – Actual (RE Cost Objects)
                        REISCOCSTACTPLN - Report for Costs/Revenue: Plan/Actual
                        Comparison (RE Cost Objects)
                        REISCOCSTACTPRE - Report for Costs/Revenue: Plan/Actual
                        Comparison Previous Year (RE Cost Objects)
                        REISCOLIBD - Information System: Actual Line Items Master
                        Data (RE Cost Objects)
                        S_ALR_87005104 - IMG Activity: SIMG_CFMENUORKAKZS2
                        S_ALR_87012105 - Down Payment Made to Vendor Report
                        S_ALR_87012805 - Structure and Value List for Investment
                        Program
                        S_ALR_87012806 - Structure and Value List for Investment
                        Program
                        S_ALR_87012808- Overall Plan/Annual Plan in Program Title
                        S_ALR_87012993 - Orders: Actual/Plan/Variance
                        S_ALR_87012994 - Orders: Current Period/Cumulative
                        S_ALR_87012995 - List: Orders
                        S_ALR_87012996 - List: Orders by Cost Element
                        S_ALR_87012997 - List: Cost Elements by Order
                        S_ALR_87012998 - Orders: Breakdown by Partner
                        S_ALR_87012999 - Orders: Actual/Plan/Commitments
                        S_ALR_87013000 - List: Actual/Plan/Commitments
                        S_ALR_87013001 - Orders: Yearly Comparison - Actual
                        S_ALR_87013002 - Orders: Quarterly Comparison - Act.
                        S_ALR_87013003 - Orders: Period Comparison - Actual
                        S_ALR_87013004 - Orders: Yearly Comparison - Plan
                        S_ALR_87013005 - Orders: Quarterly Comparison - Plan
                        S_ALR_87013006 - Orders: Period Comparison - Plan
For Official Use Only                                                                 Page 10
SAP Transaction and Command Codes Job Aid                                      GFEBS

     Role                                        Transaction Codes
                        S_ALR_87013010 - Orders: Breakdown by Period
                        S_ALR_87013011 - Orders: Actual/Plan/Price Variance
                        S_ALR_87013012 - Orders: Actual/Plan/Consumption
                        S_ALR_87013013 - Orders: Actual TCrcy/OCrcy/CAcrcy
                        S_ALR_87013014 - List: Cost Elements (True Postings)
                        S_ALR_87013015 - List: Actual Debit/Credit
                        S_ALR_87013016 - List: Plan Debit/Credit
                        S_ALR_87013017 - List: Actual/Plan/Var. Cumulative
                        S_ALR_87013018 - List: Total Plan/Actual/Commitments
                        S_ALR_87013019 - List: Budget/Actual/Commitments
                        S_ALR_87013611 - Cost Centers: Actual/Plan/Variance
                        S_ALR_87013612 - Area: Cost Centers
                        S_ALR_87013613 - Range: Cost Elements
                        S_ALR_87013614 - CCtrs: Current Period / Cumulative
                        S_ALR_87013615 - Cost Centers: Breakdown by Partner
                        S_ALR_87013616 - Cost Centers: Breakdown by BusTrans
                        S_ALR_87013617 - Range: Activity Types
                        S_ALR_87013618 - Range: Statistical Key Figures
                        S_ALR_87013619 - Areas: Assigned Orders/WBS Elements
                        S_ALR_87013620 - Cost Centers: Act./Plan/Commitments
                        S_ALR_87013621 - Range: Actual/Plan/Commitments
                        S_ALR_87013622 - Cost Centers: Projection
                        S_ALR_87013623 - Cost Centers: Quarterly Comparison
                        S_ALR_87013624 - Cost Ctrs: Fiscal Year Comparison
                        S_ALR_87013625 - Cost Centers: Actual/Target/Variance
                        S_ALR_87013626 - Range: Cost Elements
                        S_ALR_87013627 - Cost Centers: Variances
                        S_ALR_87013628 - Cost Centers: Splitting
                        S_ALR_87013629 - Activity Types: Reconciliation
                        S_ALR_87013630 - Activity Types: Plan receivers
                        S_ALR_87013631 - Cost Centers: Rolling Year
                        S_ALR_87013632 - Cost Centers: Average Costs
                        S_ALR_87013633 - Cost Centers: Act./Plan/Var./Prev.Yr
                        S_ALR_87013636 - Cost Centers: Object Comparison
                        S_ALR_87013637 - Area: Internal Business Volume
                        S_ALR_87013638 - Cost Centers: Curr./Cum./Total Year
                        S_ALR_87013639 - Cost Centers: Act/Target from Summ.
                        S_ALR_87013640 - CCtrs: Period Breakdown Actual/Plan
                        S_ALR_87013641 - CCtrs: Period Breakdown Act./Target
                        S_ALR_87013643 - Range: Orders
                        S_ALR_87013645 - Stat. Key Figs: Period Breakdown
For Official Use Only                                                            Page 11
SAP Transaction and Command Codes Job Aid                                                 GFEBS

     Role                                           Transaction Codes
                         S_ALR_87013646 - Activity Types: Period Breakdown
                         S_ALR_87013647 - Activity Types: Scheduled/Plan
                         S_ALR_87013648 - Range: Actual/Budget/Commitments
                         ZSPPE_ASSET_PFOLIO – Asset Management Portfolio
                         Report
Payroll                 FB50 – G/L Acct. Posting – Single Screen Trans. Document Type ZW
Corrections             ZSCM_TT_ERRORS - View Partner (ATAAPS, AWPS) System Errors
Processor               ZSCM_DCPS_ERROR – Process DCPS Errors

Cost Driver              KB21N - Enter Direct Activity Allocation
Controller               KB24N - Reverse Direct Activity Allocation
                         KB31N - Enter Statistical Key Figures
                         KB34N - Reverse Statistical Key Figures
                         KB51N - Enter Services
                         KB54N - Reverse Activities
                         ZSCM_ACTUP - Manual Activity and Business Process Allocation Upload from
                         Load Spreadsheet
                         ZSCM_STATKEY - Statistical Key Figure Value Upload from Load Spreadsheet
HR Master               S_AHR_61016369 - Employee List Report
Data Verifier
Manual Time-            SM37 – Overview of Job Selection
Tracking                SP01 – Output Controller
Extension               ZSCM_MAN_TIMETRACK             - Manual Time-Tracking Extension
Processor
Cost Driver              BD87 - Reprocess Failed IDocs
Interface                SM35 - Batch Input Monitoring
Processing               WE02 - Display IDoc
Monitor
                         WE09 - Search for IDoc in Database
                         ZOS_IST - IDoc Status Report
                         ZSCM_OSMIS_2005 - Display Error Log for OSMIS Interface
                         ZSCMT_DODIC_ACT – WARS DODIC Crosswalk
DMLSS                   SP01 - Output Controller
Interface               WE02 - Display IDoc
Processing              WE09 - Search for IDoc in Database
Monitor                 ZOS_IST - IDoc Status Report
CIMS                    SBWP        - Business Workplace
Interface               WE02 - Display IDoc
Processing              WE09- Search for IDoc in Database
Monitor                 ZOS_IST- IDoc Status Report
                        ZSCM_TT_ERRORS - View Partner (ATAAPS, AWPS) System Errors
Cost Rate               CP26 – Change Plan Data for Business Processes
Maintainer              KP26 – Change Plan Data for Activity Types
                        ZSCM_ATBP – Activity Type and Business Process Rates
For Official Use Only                                                                       Page 12
SAP Transaction and Command Codes Job Aid                                           GFEBS

     Role                                           Transaction Codes
                        Extension from Load Spreadsheet

Cost                    KB15N - Enter Manual Allocations
Recovery
Processor
EASI                    SBWP        - Business Workplace
Interface               SP01- Output Controller
Processing              ZOS_IST - IDoc Status Report
Monitor                 ZSCM_COST_EASI - Outbound Cost Data Interface to EASI
NMP                     BD87 – Status Monitor for ALE Messages
Interface               WE02 – Display IDoc
Processing              WE09 – Search for IDoc in Database
Monitor
German LN               CJ20N – Project Builder
Payroll                 FB03 – Display Document
Corrections             FB50 – G/L Account Pstg: Single Screen Transaction
Processor               FMZ1 – Create Funds Commitment
                        FMZ2 – Change Funds Commitment
                        FMZ3 – Display Funds Commitment
                        SBWP – SAP Business Workplace
                        VA01 – Create Sales Order
                        VA02 – Change Sales Order
                        VA03 – Display Sales Order
                        Z_FUND_STATUS – Fund Status Report in ECC
                        ZSCM_FFPO_ERROR – Process Error Corrections for German LN Payroll
                        ZSCM_FFPO_OBLG – Create Funds Commitment for German LN Payroll
                        ZSCM_FFPO_HIST – Display FFPO History Table
German LN               F-04 – Post with Clearing
Payroll                 FB02 – Change Document
Processor               FB03 – Display Document
                        FB08 – Reverse Document
                        FB50 – G/L Account Pstg: Single Screen Transaction
                        FB65 – Enter Incoming Credit Memos
                        FMDPREF – Enter Down Payment Request
                        SBWP – SAP Business Workplace
                        SM35 – Batch Input Monitoring
                        SP01 – Output Controller
                        WE02 – Display IDoc
                        Z_FUND_STATUS – Fund Status Report in ECC
                        ZSCM_FFPO_DPR – Enter Down Payment Request for German LN Payroll
                        ZSCM_FFPO_HIST – Display FFPO History Table
                        ZSCM_FFPO_INT – Reverse DPR and Post Actuals for German LN Payroll
                        ZSCM_LNPAY_1081 – Generate 1081 for LN Payroll
                        ZSSC_GET_FLUX_RATE – Maintain Budget Rate Table
Italian LN              FB01 – Post Document
Payroll                 FB02 – Change Document
For Official Use Only                                                                  Page 13
SAP Transaction and Command Codes Job Aid                                                GFEBS

     Role                                          Transaction Codes
Processor               FB03 – Display Document
                        FB08 – Reverse Document
                        FB50 – G/L Account Pstg: Single Screen Transaction
                        FB60 – Enter Incoming Invoices
                        SBWP – SAP Business Workplace
                        SP01 – Output Controller
                        Z_FUND_STATUS – Fund Status Report in ECC
                        ZSSC_GET_FLUX_RATE – Maintain Budget Rate Table
Italian LN              CJ20N – Project Builder
Payroll                 F.81 – Mass Reversal of Accruals
Obligation              FB02 – Change Document
and Accrual             FB03 – Display Document
Processor               FBS1 – Enter Accrual/Deferral Document
                        FMZ1 – Create Funds Commitment
                        FMZ2 – Change Funds Commitment
                        FMZ3 – Display Funds Commitment
                        SBWP – SAP Business Workplace
                        SP01 – Output Controller
                        VA01 – Create Sales Order
                        VA02 – Change Sales Order
                        VA03 – Display Sales Order
                        Z_FUND_STATUS – Fund Status Report in ECC
                        ZSCM_LNP_ACCRUAL – Initiate Accrual Postings for LN Payroll
                        ZSCM_OBLIG_UPLOAD – Initiate Obligation Postings for LN Payroll
Korean LN               F.81 – Mass Reversal of Accruals
Payroll                 FB01 – Post Document
Processor               FB02 – Change Document
                        FB03 – Display Document
                        FB08 – Reverse Document
                        FB50 – G/L Account Pstg: Single Screen Transaction
                        FB60 – Enter Incoming Invoices
                        SBWP – SAP Business Workplace
                        SP01 – Output Controller
                        Z_FUND_STATUS – Fund Status Report in ECC
                        ZSCM_KNPS_ORGFC – Display KNP Org to Fund Custom Table
                        ZSSC_GET_FLUX_RATE – Maintain Budget Rate Table
Korean LN               CJ20N – Project Builder
Payroll                 F.81 – Mass Reversal of Accruals
Obligation              FB02 – Change Document
and Accrual             FB03 – Display Document
Processor               FBS1 – Enter Accrual/Deferral Document
                        FMZ1 – Create Funds Commitment
                        FMZ2 – Change Funds Commitment
                        FMZ3 – Display Funds Commitment
                        SBWP – SAP Business Workplace
                        SP01 – Output Controller
For Official Use Only                                                                      Page 14
SAP Transaction and Command Codes Job Aid                                       GFEBS

     Role                                           Transaction Codes
                        VA01 – Create Sales Order
                        VA02 – Change Sales Order
                        VA03 – Display Sales Order
                        Z_FUND_STATUS – Fund Status Report in ECC
                        ZSCM_LNP_ACCRUAL – Initiate Accrual Postings for LN Payroll
                        ZSCM_OBLIG_UPLOAD – Initiate Obligation Postings for LN Payroll
Belgian                 FB02 – Change Document
Manual LN               FB03 – Display Document
Payroll                 FB08 – Reverse Document
Processor               FB50 – G/L Account Pstg: Single Screen Transaction
                        FB60 – Enter Incoming Invoices
                        FB65 – Enter Incoming Credit Memos
                        FBL1N – Vendor Line Item Display
                        SBWP – SAP Business Workplace
                        SP02 – Output Controller
                        Z_FUND_STATUS – Fund Status Report in ECC
                        ZSCM_LOCL_PAYROLL – Custom Tcode for CM_EXT-2046 to access Manual
                        Payroll Upload File screen
                        ZSSC_COSTRNFR_LOAD – Custom Tcode for CM-EXT-4319 to access Manual
                        Cost Transfers Upload from Load Sheet screen
                        ZSSC_GET_FLUX_RATE – Maintain Budget Rate Table
Belgian                 CJ20N – Project Builder
Manual LN               F.81 – Mass Reversal of Accruals
Payroll                 FB02 – Change Document
Obligation              FB03 – Display Document
and Accrual             FBS1 – Enter Accrual/Deferral Document
Processor               FMZ1 – Create Funds Commitment
                        FMZ2 – Change Funds Commitment
                        FMZ3 – Display Funds Commitment
                        SBWP – SAP Business Workplace
                        SP02 – Output Controller
                        VA01 – Create Sales Order
                        VA02 – Change Sales Order
                        VA03 – Display Sales Order
                        Z_FUND_STATUS – Fund Status Report in ECC
                        ZSCM_LNP_ACCRUAL – Initiate Accrual Postings for LN Payroll
                        ZSCM_OBLIG_UPLOAD – Initiate Obligation Postings for LN Payroll

Dutch                   FB02 – Change Document
Manual LN               FB03 – Display Document
Payroll                 FB08 – Reverse Document
Processor               FB50 – G/L Account Pstg: Single Screen Transaction
                        FB60 – Enter Incoming Invoices
                        FBL1N – Vendor Line Item Display
                        SBWP – SAP Business Workplace
                        SP02 – Output Controller
For Official Use Only                                                              Page 15
SAP Transaction and Command Codes Job Aid                                            GFEBS

     Role                                         Transaction Codes
                        Z_FUND_STATUS – Fund Status Report in ECC
                        ZSCM_LOCL_PAYROLL _ Custom Tcode for CM-EXT-2046 to access Manual
                        Payroll Upload File screen
                        ZSSC_COSTRNFR_LOAD – Custom Tcode for CM-EXT-4319 to access Manual
                        Cost Transfers Upload from Load Sheet screen
                        ZSSC_GET_FLUX_RATE – Maintain Budget Rate Table
Dutch                   FBS1 – Enter Accrual/Deferral Document
Manual LN               FB02 – Change Document
Payroll                 FB03 – Display Document
Accrual                 CJ20N – Project Builder
Processor               VA01 – Create Sales Order
                        VA02 – Change Sales Order
                        VA03 – Display Sales Order
                        SBWP – SAP Business Workplace
Dutch                   CJ20N – Project Builder
Manual LN               Custom Tcode for CM-EXT-4305 – Initiate Accrual Postings for LN Payroll
Payroll                 F.81 – Mass Reversal of Accruals
Obligation              FB02 – Change Document
and Accrual             FB03 – Display Document
Processor               FBS1 – Enter Accrual/Deferral Document
                        FMZ1 – Create Funds Commitment
                        FMZ2 – Change Funds Commitment
                        FMZ3 – Display Funds Commitment
                        SBWP – SAP Business Workplace
                        SP02 – Output Controller
                        VA01 – Create Sales Order
                        VA02 – Change Sales Order
                        VA03 – Display Sales Order
                        Z_FUND_STATUS – Fund Status Report in ECC
                        ZSCM_OBLIG_UPLOAD – Custom Tcode for CM-EXT-4306 for Manual Upload
                        Extension to Create/Change Obligation from Load Sheet screen


Click here to return to top.




For Official Use Only                                                                  Page 16
SAP Transaction and Command Codes Job Aid                                    GFEBS




                                          Equipment & Assets

    Role                                           Transaction Codes
Asset Master            AB08 - Reverse Line Items
Data                    ABAA - Write-Down/Unplanned Depreciation
Maintainer              ABAVN - Asset Retirement by Scrapping
                        ABSO - Miscellaneous Transactions
                        ABUMN - Transfer within Company Code
                        ABZU - Write-Up
                        AFABN - Post Depreciation
                        AR01 - Call Asset List
                        AR02- Call Up Asset History Sheet
                        AR03 - Call Up Depreciation List
                        AS01 - Create Asset Master Record
                        AS02- Change Asset Master Record
                        AS06 - Delete Asset Record/Mark for Delete
                        AS11 - Create Asset Subnumber
                        CJ20N - Project Builder
                        CJ88 - Settle Projects and Networks
                        CJ8G - Actual Settlement: Projects/Networks
                        OARP- Call Up AM Report Overview
                        RE80 – RE Navigator
                        S_ALR_87010173- Revaluation
                        S_ALR_87010175 - Depreciation Posted to Cost Center
                        S_ALR_87011963 - Asset Balances
                        S_ALR_87011966 - Asset Balances
                        S_ALR_87011967 - Asset Balances
                        S_ALR_87011969 - Asset Balances
                        S_ALR_87011990 - Asset History Sheet
                        S_ALR_87011992- Liabilities from Leasing Agreements
                        S_ALR_87011994 - Asset Balances
                        S_ALR_87012004 – Depreciation
                        S_ALR_87012006 – Depreciation
                        S_ALR_87012008 – Depreciation
                        S_ALR_87012011 - Write-Ups
                        S_ALR_87012013 - Depreciation Comparison
                        S_ALR_87012015 - Manual Depreciation
                        S_ALR_87012018 - Depreciation and Interest
                        S_ALR_87012048 - Asset Transactions
                        S_ALR_87012056 - Directory of Unposted Assets
For Official Use Only                                                          Page 17
SAP Transaction and Command Codes Job Aid                                              GFEBS

    Role                                           Transaction Codes
                        S_P99_41000192 - SAP Standard Variant
                        SM37 - Overview of Job Selection
                        ZSPPE_ASSET_PFOLIO – Asset Management Portfolio Report
                        ZSPPET_GEQUIP - Create/Update/Deactivate General Equipment Federal Supply
                        Class/Federal Supply Group to Asset Class Mapping
                        ZSPPET_MEQUIP - Create/Update/Deactivate Military Equipment Federal Supply
                        Class/Federal Supply Group to Asset Class Mapping
                        ZSPPET_NSN - Update the National Stock Number to Asset Class Mapping as well
                        as the Usage Based Depreciation Data
Asset                   AW01N – Asset Explorer
Interface               BD87- Status Monitor for ALE Messages
Processing              S_ALR_87011963 - Asset Balances
Monitor
                        SM37 - Overview of Job Selection
                        WE02 - Display IDoc
                        WE07- IDoc Statistics
                        ZOS_IST - IDoc Status Report
                        ZSPPE_ASSET_PFOLIO – Asset Management Portfolio Report
                        ZSPPE_DELE_IDOC_ERR - Work/Evaluate PBUSE IDoc Errors
Asset Close             AB03 - Display Asset Document
Processor               AFABN - Post Depreciation
                        AFAR - Usage Based Depreciation
                        AFBP – Create Depreciation Posting Log
                        AJAB – Year End Closing
                        AJRW - Fiscal Year Change
                        AS03 - Display Asset Master Record
                        AUVA - FI-AA Incomplete Assets
                        AW01N – Asset Explorer
                        GD23 – FI-SL: Local Actual Document Display
                        S_ALR_87011964 – Asset Balances
                        S_ALR_87012050 – Asset Acquisitions
                        S_ALR_87012052 – Asset Retirements
                        SM37 - Overview of Job Selection
                        ZSPPE_ASSET_PFOLIO – Asset Management Portfolio Report
AMIS                    ABAVN - Asset Retirement by Scrapping
Interface               ABSO - Miscellaneous Transactions
Processor               AS01 - Create Asset Master Record
                        AS02 - Change Asset Master Record
                        AS06 - Delete Asset Record/Mark for Delete
                        AS11 - Create Asset Subnumber
                        BD87 - Status Monitor for ALE Messages
                        S_ALR_87010173 – Revaluation
                        S_ALR_87010175 - Depreciation Posted to Cost Center

For Official Use Only                                                                    Page 18
SAP Transaction and Command Codes Job Aid                                       GFEBS

    Role                                         Transaction Codes
                        S_ALR_87011963 - Asset Balances
                        S_ALR_87011964 – Asset Balances
                        S_ALR_87011966 - Asset Balances
                        S_ALR_87011967 - Asset Balances
                        S_ALR_87011969 - Asset Balances
                        S_ALR_87011990 - Asset History Sheet
                        S_ALR_87011992 - Liabilities from Leasing Agreements
                        S_ALR_87011994 - Asset Balances
                        S_ALR_87012004 - Depreciation
                        S_ALR_87012006 - Depreciation
                        S_ALR_87012008 - Depreciation
                        S_ALR_87012011 - Write-Ups
                        S_ALR_87012013 - Depreciation Comparison
                        S_ALR_87012015 - Manual Depreciation
                        S_ALR_87012018 - Depreciation and Interest
                        S_ALR_87012048 - Asset Transactions
                        S_ALR_87012050 – Asset Acquisitions
                        S_ALR_87012052 – Asset Retirements
                        S_ALR_87012056 - Directory of Unposted Assets
                        S_P99_41000192 - SAP Standard Variant
                        SM37 - Overview of Job Selection
                        WE02 - Display IDoc
                        WE07 - IDoc Statistics
                        ZSPPE_ASSET_PFOLIO – Asset Management Portfolio Report

Click here to return to top.


                                              Financials

    Role                                        Transaction Codes
General            FS00 - G/L Acct. Master Record Maintenance
Ledger             S_ALR_87012326 - Chart of Accounts
Master Data
Approver
General            FS00 - G/L Acct. Master Record Maintenance
Ledger             FS01 - Edit G/L Account Centrally
Master Data        S_ALR_87012308 - Display Audit Trail
Maintainer         S_ALR_87012326 - Chart of Accounts
                   S_ALR_87012328 – G/L Account List



For Official Use Only                                                             Page 19
SAP Transaction and Command Codes Job Aid                                           GFEBS

    Role                                        Transaction Codes
General            FB03 - Display Document
Ledger             FS00 - G/L Acct. Master Record Maintenance
Master Data        GD23 - FI-SL: Local Actual Document Display
Reviewer           S_ALR_87012326 - Chart of Accounts
Journal            ZSFI_JV_UPLOAD - JV Upload Tool
Voucher
Master
Processor
Journal             FB02 - Change Document
Voucher             FB50 - G/L Acct. Posting - Single Screen Trans. Document Type
Processor           ZW
                    FBV2 - Change Parked Document
                    FBV3 - Display Parked Document
                    FV50 - Park G/L Account Items
                    FV53 - Display Parked G/L Account Document
                    S_ALR_87012293 – Display of Changed Documents
                    SHD0 - Transaction and Screen Variants
                    ZSCC_COSTRNFR_LOAD – Cost Transfer Upload Extension
                    from Load Template
Journal            FBV3 - Display Parked Document
Voucher            FV53 - Display Parked G/L Account Document
Reviewer

Journal             FBV0 - Post Parked Document
Voucher             FBV3- Display Parked Document
Approver            FV53 - Display Parked G/L Account Document
                    GRR3 - Status of Funds
                    S_ALR_87012293 – Display of Changed Documents
Journal             ZSFI_JV_EDIT_ORG - Edit JV Processor ID Table
Voucher             ZSFI_JV_EDIT_RA - Edit JV Reviewer/Approver ID and Dollar Threshold
Workflow            Table
Maintainer          ZSFI_JV_LOAD_ORG - Load via File JV Processor ID Table
                    ZSFI_JV_LOAD_RA - Load via File JV Reviewer/Approver
Period              FMAVCR01 - Display Annual Values of Control Objects
Close               FMAVCR02 - Display Overall Values of Control Objects
Schedule            SCMA- Schedule Manager
Processor
Period              FMAVCR01 - Display Annual Values of Control Objects
Close               FMAVCR02 - Display Overall Values of Control Objects
Schedule            S_ALR_87012277 - G/L Account Balance
Monitor
                    SCMA - Schedule Manager


For Official Use Only                                                                     Page 20
SAP Transaction and Command Codes Job Aid                                    GFEBS

    Role                                     Transaction Codes
Open_Close          FMIR - Detail Maintenance of Open Int Rules
Processor           FMMI - Mass Maintenance of Open Intervals
                    MMPV - Close Periods
                    MMRV - Allow Posting to Previous Period
                    OB52 - C FI Maintain Table T001B
                    OKP1 - Maintain Period Lock
Accounting          F.81 - Reverse Accrual/Deferral Document
Processor           FAGL_FC_TRANS - Currency Translation of Balance.
                    FAGL_FC_VAL- Foreign Currency Valuation
                    FB03 - Display Document
                    FBS1 - Enter Accrual/Deferral Document
                    GD23 - FI-SL: Local Actual Document Display
                    RFMFGRCN_RP1 - Reconciliation Analysis Report
                    RFMFGRCN_RP2 - Batch Reconciliation Check
                    ZSFI_ABNORMAL_BALRPT - Abnormal Balance Report
Year End            FMFG_RCV - Treasury Report on Receivable
Certifier           FS10N - Balance Display
                    S_ALR_87012277 - G/L Account Balance
                    S_KI4_38000323 - Trial Balance by SGL Level
                    S_KI4_38000323 – Trial Balance by Fund at SGL Level
                    S_KI4_38000325 - Trial Balance by Fund
                    SM37 - Overview of Job Selection
                    ZSFI_SFISREPORT- SFIS Report
Year End            AJAB – Year End Closing
Processor           AJRW - Fiscal Year Change
                    AUVA – FI-AA Incomplete Assets
                    CO99 - Set Status Closed
                    F.05 – Foreign Currency Valuation
                    F.07 – G/L: Balance Carryforward
                    F.16 – ABAP/4 Report: G/L Bal Carryforward
                    F.80 – Mass Reversal of Documents
                    FAGLGVTR - G/L: Balance Carried Forward
                    FMAVCR02 - Display Overall Values of Control Objects
                    FMAVCREINIT – Re-initialize AVC Ledger
                    FMBB - Budgeting Workbench
                    FMFG_CANCELED_AP – Canceled Fund for Account Payable - FI
                    FMFG_CANCELED_AP_MM – Canceled Fund for Account Payable - MM
                    FMFG_CANCELED_AR - Account Receivables
                    FMFG_E_TRANS_REG - Federal Transaction Register
                    FMFG_YEAR_END_CLOSE - Close Budget Accounts with Residual
                    Balance
                    FMIR - Detail Maintenance of Open Int Rules
For Official Use Only                                                          Page 21
SAP Transaction and Command Codes Job Aid                                       GFEBS

    Role                                     Transaction Codes
                    FMMC - Close Commitment Items
                    FMRP_RFFMEP1AX- All Postings
                    FMSU - Change Status
                    FMY2 – Change Funds Commitment
                    FMZ2 - Change Funds Commitment
                    GVTR - FI-SL: Balance Carryforward
                    ME23N- Display Purchase Order
                    ME52N- Change Purchase Requisition
                    ME53N- Display Purchase Requisition
                    MMPV - Close Periods
                    MMRV - Allow Posting to Previous Period
                    OB52 – C FI Maintain Table T001B
                    OKP1 - Maintain Period Lock
                    S_KI4_38000039 – Index of Funds
                    S_KI4_38000325 - Trial Balance by Fund
                    VA02 - Change Sales Order
                    Z_OPEN_COM – FM Open Commitments
                    Z_OPEN_OB – FM Open Obligations
                    Z_RM_FUND_STATUS – Reimbursable Fund Status Report
                    ZFSC1 – Cumulative Status by FC
                    ZFSC2 – Cumulative Status by FA
                    ZFSC3 – Cumulative Status by FP
                    ZFSC4 – Cumulative Status by FC - Summary
                    ZFSC5 – Cumulative Status by FC - Detail
                    ZFSC6 – Cumulative Status by FA Group - Summary
                    ZFSC7 – Cumulative Status by FA Group - Detail
                    ZFSC8 – Cumulative Status with Open Commitments - Summary
                    ZFSC9 – Cumulative Status with Open Commitments - Detail
                    ZFSNC1 – Non- Cumulative Status by FC
                    ZFSNC2 – Non- Cumulative Status by FA
                    ZFSNC3 – Non- Cumulative Status by FP
                    ZFSNC4 – Non- Cumulative Status by FC - Summary
                    ZFSNC5 – Non- Cumulative Status by FC - Detail
                    ZFSNC6 – Non- Cumulative Status by FC Pre-Posted
                    ZRFSC1 – Reimbursable Cumulative Status by FC
                    ZRFSC2 – Reimbursable Cumulative Status by FP
                    ZRFSNC1 – Reimbursable Non-Cumulative Status by FC
                    ZRFSNC2 – Reimbursable Non-Cumulative Status by FP
                    ZSFI_DDRS_TRL_BAL2 - DDRS Trial Balance Exact Program
                    ZSFI_SFISREPORT - SFIS Report
                    ZSFM_RPT_E_UNFILLED – Year End Closing Operations: Update Sales
                    Order




For Official Use Only                                                             Page 22
SAP Transaction and Command Codes Job Aid                                          GFEBS

    Role                                       Transaction Codes
Balance             FAGLGVTR - G/L: Balance Carried Forward
Forward             FB03 - Display Document
Processor           GD23 - FI-SL: Local Actual Document Display
                    GVTR - FI-SL: Balance Carryforward
Financial           FAGLL03 – G/L Account Line Items
Reviewer            FB03 - Display Document
                    FBL1N - Vendor Line Item Display
                    FBL3N - G/L Account Line Items
                    FBV3 - Display Parked Document
                    FMB_B01 – Budget View by Document Type
                    FMEDDW - Drilldown For Budget Entry Documents
                    FMFG_E_TRANS_REG - Federal Transaction Register
                    FMFG_E_ZFZALI00 - Display a Payment Settlement List
                    FMFG_RCV - Treasury Report on Receivable
                    FMRP_RFFMEP1AX – All Postings
                    FMRP_RFFMEP1FX – FI Posting. Individual Items According to Document
                    Number.
                    FMST - Evaluation of Penalty Interest
                    FMY3 - Display Funds Precommitment
                    FMZ3 - Display Funds Commitment
                    FS10N - Balance Display
                    GD23 - FI-SL: Local Actual Document Display
                    GRR3 - Status of Funds
                    ME23N - Display Purchase Order
                    ME2K - PO List Display by Account Assignment – General
                    ME2L - PO List Display by Vendor
                    ME2N - PO List Display by PO Number
                    ME53N - Display Purchase Requisition
                    ME5A - PR List Display - General
                    RFMFGRCN_RP1 - Reconciliation Analysis Report
                    RFMFGRCN_RP2 - Batch Reconciliation Check
                    S_ALR_87012077 - Vendor Information System
                    S_ALR_87012082 – Vendor Balance Display
                    S_ALR_87012083 - List of Vendor Open Item
                    S_ALR_87012086 – Vendor List
                    S_ALR_87012105 - Down Payment Made to Vendor Report
                    S_ALR_87012167 - Accounts Receivable Information System
                    S_ALR_87012174 – List of Customer Open Items
                    S_ALR_87012277 - G/L Account Balance
                    S_ALR_87012308 - Display Audit Trail
                    S_ALR_87012326 - Chart of Accounts
                    S_KI4_38000323 - Trial Balance by Fund at SGL level
For Official Use Only                                                                Page 23
SAP Transaction and Command Codes Job Aid                                      GFEBS

    Role                                      Transaction Codes
                    S_KI4_38000323 – Trial Balance by SGL Level
                    S_KI4_38000325 - Trial Balance by Fund
                    S_P99_41000099 – Payment List
                    S_P99_41000147 - Funds Commitment: Display InitScrn
                    SE16N - Edit Table
                    SM37 - Simple Overview of Job Selection
                    VF03 - Display Billing Document
                    WE09 - Search for IDoc in Database
                    Z_OPEN_COM – FM - Open Commitments
                    Z_OPEN_OB – FM - Open Obligations
                    ZFSC1 – Cumulative Status by FC
                    ZFSC2 – Cumulative Status by FA
                    ZFSC3 – Cumulative Status by FP
                    ZFSC4 – Cumulative Status by FC - Summary
                    ZFSC5 – Cumulative Status by FC - Detail
                    ZFSC6 – Cumulative Status by FA Group - Summary
                    ZFSC7 – Cumulative Status by FA Group - Detail
                    ZFSC8 – Cumulative Status with Open Commitments - Summary
                    ZFSC9 – Cumulative Status with Open Commitments - Detail
                    ZFSNC1 – Non- Cumulative Status by FC
                    ZFSNC2 – Non- Cumulative Status by FA
                    ZFSNC3 – Non- Cumulative Status by FP
                    ZFSNC4 – Non- Cumulative Status by FC - Summary
                    ZFSNC5 – Non- Cumulative Status by FC - Detail
                    ZFSNC6 – Non- Cumulative Status by FC Pre-Posted
                    ZRFSC1 – Reimbursable Cumulative Status by FC
                    ZRFSC2 – Reimbursable Cumulative Status by FP
                    ZRFSNC1 – Reimbursable Non-Cumulative Status by FC
                    ZRFSNC2 – Reimbursable Non-Cumulative Status by FP
                    ZOS_IFV - IDoc Field Values Report
                    ZSCM_DCPS_ERROR – Process DCPS Errors
                    ZSFI_ABNORMAL_BALRPT - Abnormal Balance Report
                    ZSFI_DCAS_ID – DCAS ID Table
                    ZSFI_REP_1081 – Query for 1081 Table
                    ZSFI_SFISREPORT - SFIS Report
External            FB03 - Display Document
Information         FMFG_RCV - Treasury Report on Receivable
Monitor             GD23 - FI-SL: Local Actual Document Display
                    S_KI4_38000323 - Trial Balance by SGL Level
                    S_KI4_38000325 - Trial Balance by Fund
                    SM37 - Overview of Job Selection
                    ZSFI_DDRS_TRL_BAL - DDRS layout file
                    ZSFI_DDRS_TRL_BAL2 – DDRS Trial Balance Exact Program
                    ZSFI_SFIS_TRLBAL_EXT - SFIS Trial Balance

For Official Use Only                                                            Page 24
SAP Transaction and Command Codes Job Aid                                   GFEBS

    Role                                       Transaction Codes
                    ZSFI_SFISREPORT - SFIS Report
                    ZSFI_TROR - TROR Report Interface
                    ZSFI_TROR_DDRS – DDRS Trial Balance Extract Program

Cash                FAGLL03 - G/L Account Line Items
Balancing           FB03 - Display Document
Approver            FBL1N - Vendor Line Item Display
                    FBL5N - Customer Line Item
                    FMRP_RFFMEP1AX – All Postings
                    FMY3 - Display Funds Precommitment
                    FMZ3 - Display Funds Commitment
                    GD23 - FI-SL: Local Actual Document Display
                    ME23N - Display Purchase Order
                    ME2K - PO List Display by Account Assignment – General
                    ME2L - PO List Display by Vendor
                    ME2N - PO List Display by PO Number
                    ME53N - Display Purchase Requisition
                    ME5A - PR List Display - General
                    S_ALR_87012083 - List of Vendor Open Item
                    S_ALR_87012105 - Down Payment Made to Vendor Report
                    S_P99_41000147 - Funds Commitment: Display InitScrn
                    SE16N - Edit Table
                    VF03 - Display Billing Document
                    ZOS_IFV - IDoc Field Values Report
                    ZOS_IST - IDoc Status Report
                    ZSFI_Auto_Sweep – Auto Sweep Program
                    ZSSC_DCAS1081_EXTRCT – 1081 Outbound Interface
Cash                F-03 – Clear G/L Account
Balancing           F-04 - Post with Clearing
Processor           F-28 – Collections
                    F-44 - Clear Vendor
                    FAGLL03 - G/L Account Line Items
                    FB01 - Post Document
                    FB02 – Change Document
                    FB03 - Display Document
                    FB08 - Reverse Document
                    FBL1N - Vendor Line Item Display
                    FBL3N - G/L Account Line Items
                    FBL5N - Customer Line Item
                    FMEDDW - Drilldown for Budget Entry Documents
                    FMFG_E_ZFZALI00 - Display a Payment Settlement List

For Official Use Only                                                         Page 25
SAP Transaction and Command Codes Job Aid                                     GFEBS

    Role                                        Transaction Codes
                    FMRP_RFFMEP1AX – All Postings
                    FMST - Evaluation of Penalty Interest
                    FMY3 - Display Funds Precommitment
                    FMZ3 - Display Funds Commitment
                    GD23 - FI-SL: Local Actual Document Display
                    ME23N - Display Purchase Order
                    ME2K - PO List Display by Account Assignment – General
                    ME2L - PO List Display by Vendor
                    ME2N - PO List Display by PO Number
                    ME53N - Display Purchase Requisition
                    ME5A - PR List Display - General
                    S_ALR_87012077 - Vendor Information System
                    S_ALR_87012083 - List of Vendor Open Item
                    S_ALR_87012105 - Down Payment Made to Vendor Report
                    S_ALR_87012167 - Accounts Receivable Information System.
                    S_ALR_87012174 - List of Customer Open Items
                    S_P99_41000147 - Funds Commitment: Display InitScrn
                    SE16N - Edit Table
                    VF03 - Display Billing Document
                    WE09 - Search for IDoc in Database
                    ZOS_IFV - IDoc Field Values Report
                    ZOS_IST - IDoc Status Report
                    ZSFI_1081 - Post 1081 Adjustment transaction
                    ZSFI_Auto_Sweep – Auto Sweep Program
                    ZSFI_DCAS_ID – DCAS ID Table
                    ZSFI_REP_1081 – Query for 1081 Table
LMP                FB03 - Display Document
Depreciation
Reviewer
Cross-Code         ZSFI_LOAXREFLOAD – Load Data File into LOA XREF Tables
Maintainer         ZSFI_LOA – Maintain Table ZSFIT_LOAXREF
Payment             BD87 - Status Monitor for ALE Messages
Interface           FB03 - Display Document
Processing          FBD3 - Display Recurring Document
Monitor             FBL1N - Vendor Line Item Display
                    FBZ0 - Payment Proposal
                    GD23 - FI-SL: Local Actual Document Display
                    IW33 - Display PM Order
                    MB03 - Display Material Document
                    MB51 – Material Document List
                    ME23N - Display Purchase Order

For Official Use Only                                                           Page 26
SAP Transaction and Command Codes Job Aid                                   GFEBS

    Role                                       Transaction Codes
                    ME2J - PO List Display by Project/WBS
                    ME2K - PO List Display by Account Assignment – General
                    ME2L - PO List Display by Vendor
                    ME2N - PO List Display by PO Number
                    ME53N - Display Purchase Requisition
                    ME5A - PR List Display - General
                    ME5J - PR List Display by Project/WBS
                    ME5K - PR List Display by Account Assignment – General
                    MIR4 - Display Invoice Document
                    MIR5 - Display List of Invoice Documents
                    S_ALR_87012082 - Vendor Balance Display
                    S_ALR_87012086 - Vendor List
                    S_P99_41000099 - Payment List
                    SBWP - Business Workplace
                    SM37 - Overview of Job Selection
                    SO01 - Business Workplace: Inbox
                    WE02 - IDoc List
                    XK03 - Display Vendor Master
                    ZOS_IST - IDoc Status Report

Click here to return to top.


                                        Funds Management

    Role                                        Transaction Codes
Funds               BD87 - Status Monitor for ALE Messages
Management          FB03 – Display Document
Interface           FM_Function – FM: Functional Area
Processing          FM_Sets_FIPEX3 – Display Commitment Item Group
Monitor             FM_Sets_Function3 – Display Functional Area Group
                    FM5S – FIFM: Display Fund
                    FM6S – FIFM: Display Application of Funds
                    FMBB – Budgeting Workbench
                    FMCIC – Display Commitment Item
                    FMEDD – Display Entry Document
                    FMMEASURED – Funded Program Display
                    FMSC – Display Funds Center in FM area
                    FMSE – Display Funds Center Hierarchy
                    WE02 - IDoc List
                     Z_OPEN_COM – FM - Open Commitments
                     Z_OPEN_OB – FM - Open Obligations
                     ZFSC1 – Cumulative Status by FC

For Official Use Only                                                         Page 27
SAP Transaction and Command Codes Job Aid                                          GFEBS

    Role                                          Transaction Codes
                        ZFSC2 – Cumulative Status by FA
                        ZFSC3 – Cumulative Status by FP
                        ZFSC4 – Cumulative Status by FC - Summary
                        ZFSC5 – Cumulative Status by FC - Detail
                        ZFSC6 – Cumulative Status by FA Group - Summary
                        ZFSC7 – Cumulative Status by FA Group - Detail
                        ZFSC8 – Cumulative Status with Open Commitments - Summary
                        ZFSC9 – Cumulative Status with Open Commitments - Detail
                        ZFSNC1 – Non- Cumulative Status by FC
                        ZFSNC2 – Non- Cumulative Status by FA
                        ZFSNC3 – Non- Cumulative Status by FP
                        ZFSNC4 – Non- Cumulative Status by FC - Summary
                        ZFSNC5 – Non- Cumulative Status by FC - Detail
                        ZFSNC6 – Non- Cumulative Status by FC Pre-Posted
                        ZOS_IST - IDoc Status Report
                        ZRFSC1 – Reimbursable Cumulative Status by FC
                        ZRFSC2 – Reimbursable Cumulative Status by FP
                        ZRFSNC1 – Reimbursable Non-Cumulative Status by FC
                        ZRFSNC2 – Reimbursable Non-Cumulative Status by FP
                        ZSBF_AFP_RETRACTION – AFP Retraction
                        ZSFM_ASN_MAINT – Update Period of Availability Z-Table
                        ZSFM_POA_MAINT – Update Allotment Serial Number Table
                        ZSFM_THRESHOLD – Update Threshold Table
ECC Budget              FB03 - Display Document
Reporter                FM_Function - FM: Functional Area
                        FM_Sets_FIPEX3 - Display Commitment Item Group
                        FM_Sets_Function3 - Display Functional Area Group
                        FM5S - FIFM: Display Fund
                        FM6S - FIFM: Display Application of Funds
                        FMAVCR02 - Display Overall Values of Control Objects
                        FMCIC - Display Commitment Item
                        FMMEASURED - Funded Program: Display
                        FMSC - Display Funds Center in FM Area
                        FMSE - Display Funds Center Hierarchy
                        ME23N - Display Purchase Order
                        ME53N - Display Purchase Requisition
                        ME5A - PR List Display - General
                        S_ALR_87012105 - Down Payment Made to Vendor Report
                        Z_FUND_STATUS – Status of Funds Report - Cumulative
                        Z_OPEN_COM – FM Open Commitments
                        Z_OPEN_OB – FM Open Obligations
                        ZFSC1 – Cumulative Status by FC
                        ZFSC2 – Cumulative Status by FA
                        ZFSC3 – Cumulative Status by FP
For Official Use Only                                                                Page 28
SAP Transaction and Command Codes Job Aid                                          GFEBS

    Role                                          Transaction Codes
                        ZFSC4 – Cumulative Status by FC - Summary
                        ZFSC5 – Cumulative Status by FC - Detail
                        ZFSC6 – Cumulative Status by FA Group - Summary
                        ZFSC7 – Cumulative Status by FA Group - Detail
                        ZFSC8 – Cumulative Status with Open Commitments - Summary
                        ZFSC9 – Cumulative Status with Open Commitments - Detail
                        ZFSNC1 – Non- Cumulative Status by FC
                        ZFSNC2 – Non- Cumulative Status by FA
                        ZFSNC3 – Non- Cumulative Status by FP
                        ZFSNC4 – Non- Cumulative Status by FC - Summary
                        ZFSNC5 – Non- Cumulative Status by FC - Detail
                        ZFSNC6 – Non- Cumulative Status by FC Pre-Posted
                        ZRFSC1 – Reimbursable Cumulative Status by FC
                        ZRFSC2 – Reimbursable Cumulative Status by FP
                        ZRFSNC1 – Reimbursable Non-Cumulative Status by FC
                        ZRFSNC2 – Reimbursable Non-Cumulative Status by FP
                        ZSFM_SFISLOAREPORT – SFIS LOA Report
Funds                   FMBB - Budgeting Workbench
Management              FMEDDW - Drilldown for Budget Entry Documents
Maintainer              FMMEASURE - Change Funded Program
                        VA03 - Display Sales Order
                        Z_FUND_STATUS - Status of Funds Report – Cumulative
                        Z_OPEN_COM – FM Open Commitments
                        Z_OPEN_OB – FM Open Obligations
                        ZFSC1 – Cumulative Status by FC
                        ZFSC2 – Cumulative Status by FA
                        ZFSC3 – Cumulative Status by FP
                        ZFSC4 – Cumulative Status by FC - Summary
                        ZFSC5 – Cumulative Status by FC - Detail
                        ZFSC6 – Cumulative Status by FA Group - Summary
                        ZFSC7 – Cumulative Status by FA Group - Detail
                        ZFSC8 – Cumulative Status with Open Commitments - Summary
                        ZFSC9 – Cumulative Status with Open Commitments - Detail
                        ZFSNC1 – Non- Cumulative Status by FC
                        ZFSNC2 – Non- Cumulative Status by FA
                        ZFSNC3 – Non- Cumulative Status by FP
                        ZFSNC4 – Non- Cumulative Status by FC - Summary
                        ZFSNC5 – Non- Cumulative Status by FC - Detail
                        ZFSNC6 – Non- Cumulative Status by FC Pre-Posted
                        ZRFSC1 – Reimbursable Cumulative Status by FC
                        ZRFSC2 – Reimbursable Cumulative Status by FP
                        ZRFSNC1 – Reimbursable Non-Cumulative Status by FC
                        ZRFSNC2 – Reimbursable Non-Cumulative Status by FP



For Official Use Only                                                                Page 29
SAP Transaction and Command Codes Job Aid                                                 GFEBS

    Role                                           Transaction Codes
Funds                   FMBB - Budgeting Workbench
Management              FMEDDW - Drilldown for Budget Entry Documents
Approver                FMMEASURE - Change Funded Program
                        VA03 - Display Sales Order
                        Z_FUND_STATUS - Status of Funds Report – Cumulative
                        Z_OPEN_COM – FM Open Commitments
                        Z_OPEN_OB – FM Open Obligations
                        ZFSC1 – Cumulative Status by FC
                        ZFSC2 – Cumulative Status by FA
                        ZFSC3 – Cumulative Status by FP
                        ZFSC4 – Cumulative Status by FC - Summary
                        ZFSC5 – Cumulative Status by FC - Detail
                        ZFSC6 – Cumulative Status by FA Group - Summary
                        ZFSC7 – Cumulative Status by FA Group - Detail
                        ZFSC8 – Cumulative Status with Open Commitments - Summary
                        ZFSC9 – Cumulative Status with Open Commitments - Detail
                        ZFSNC1 – Non- Cumulative Status by FC
                        ZFSNC2 – Non- Cumulative Status by FA
                        ZFSNC3 – Non- Cumulative Status by FP
                        ZFSNC4 – Non- Cumulative Status by FC - Summary
                        ZFSNC5 – Non- Cumulative Status by FC - Detail
                        ZFSNC6 – Non- Cumulative Status by FC Pre-Posted
                        ZRFSC1 – Reimbursable Cumulative Status by FC
                        ZRFSC2 – Reimbursable Cumulative Status by FP
                        ZRFSNC1 – Reimbursable Non-Cumulative Status by FC
                        ZRFSNC2 – Reimbursable Non-Cumulative Status by FP
Funds                   FB03 - Display Document
Execution               FB50 - G/L Acct. Posting - Single Screen Trans. Document Type ZW
Controller              FMBB - Budgeting Workbench
                        FMEDDW - Drilldown for Budget Entry Documents
                        FMZ3 - Display Funds Commitment
                        MB03 - Display Material Document
                        ME23N - Display Purchase Order
                        VA03 - Display Sales Order
                        Z_FUND_STATUS - Status of Funds Report - Cumulative
                        Z_OPEN_COM – FM Open Commitments
                        Z_OPEN_OB – FM Open Obligations
                        ZFSC1 – Cumulative Status by FC
                        ZFSC2 – Cumulative Status by FA
                        ZFSC3 – Cumulative Status by FP
                        ZFSC4 – Cumulative Status by FC - Summary
                        ZFSC5 – Cumulative Status by FC - Detail
                        ZFSC6 – Cumulative Status by FA Group - Summary
                        ZFSC7 – Cumulative Status by FA Group - Detail
                        ZFSC8 – Cumulative Status with Open Commitments - Summary
For Official Use Only                                                                       Page 30
SAP Transaction and Command Codes Job Aid                                             GFEBS

    Role                                          Transaction Codes
                        ZFSC9 – Cumulative Status with Open Commitments - Detail
                        ZFSNC1 – Non- Cumulative Status by FC
                        ZFSNC2 – Non- Cumulative Status by FA
                        ZFSNC3 – Non- Cumulative Status by FP
                        ZFSNC4 – Non- Cumulative Status by FC - Summary
                        ZFSNC5 – Non- Cumulative Status by FC - Detail
                        ZFSNC6 – Non- Cumulative Status by FC Pre-Posted
                        ZRFSC1 – Reimbursable Cumulative Status by FC
                        ZRFSC2 – Reimbursable Cumulative Status by FP
                        ZRFSNC1 – Reimbursable Non-Cumulative Status by FC
                        ZRFSNC2 – Reimbursable Non-Cumulative Status by FP
                        ZSFM_DISTBUDGET – Inbound Distribute Budget Interface
                        ZSFM_THRESHOLD – Update Threshold Table
                        ZSSC_FCM_FP - FCM Financial Position Report
Funds                   FM_Function - FM: Functional Area
Management              FM_Sets_FIPEX1 - Create Commitment Item Group
Master Data             FM_Sets_FIPEX2 - Change Commitment Item Group
Maintainer
                        FM_Sets_Function1 - Create Functional Area Group
                        FM_Sets_Function2 - Change Functional Area Group
                        FM4M – Directory of Functional Areas
                        FM5I - FIFM: Create Fund
                        FM5M – Index of Funds
                        FM5U - FIFM: Change Fund
                        FM6I - FIFM: Create Application of Funds
                        FM6M – Index of Application of Funds
                        FM6U - FIFM: Change Application of Funds
                        FM7M – Directory of Funded Programs
                        FMCIA - Edit Commitment Item
                        FMDERIVATIONANALYSIS – Analysis Report on FM Derivations
                        FMDERIVER - Object Assignment - Maintenance
                        FMMEASURE - Change Funded Program
                        FMMEASURED - Funded Program: Display
                        FMSA - Create Funds Center in FM Area
                        FMSB - Change Funds Center in FM Area
                        FMWHEREUSED – Where-Used FM Assignments
                        FRFNSUB1 - PPB BOS Transaction to Pull Data from Legacy System to
                        GFEBS
                        FRFNSUB2 - PPB BOS Transaction to Pull Data from Legacy System to
                        GFEBS
                        FRFNSUB3 - PPB BOS Transaction to Pull Data from Legacy System to
                        GFEBS
                        WE02 - IDoc List
                        Z_FUND_STATUS – Status of Funds Report - Cumulative
                        Z_OPEN_COM – FM Open Commitments
                        Z_OPEN_OB – FM Open Obligations
For Official Use Only                                                                       Page 31
SAP Transaction and Command Codes Job Aid                                          GFEBS

    Role                                           Transaction Codes
                        ZFSC1 – Cumulative Status by FC
                        ZFSC2 – Cumulative Status by FA
                        ZFSC3 – Cumulative Status by FP
                        ZFSC4 – Cumulative Status by FC - Summary
                        ZFSC5 – Cumulative Status by FC - Detail
                        ZFSC6 – Cumulative Status by FA Group - Summary
                        ZFSC7 – Cumulative Status by FA Group - Detail
                        ZFSC8 – Cumulative Status with Open Commitments - Summary
                        ZFSC9 – Cumulative Status with Open Commitments - Detail
                        ZFSNC1 – Non- Cumulative Status by FC
                        ZFSNC2 – Non- Cumulative Status by FA
                        ZFSNC3 – Non- Cumulative Status by FP
                        ZFSNC4 – Non- Cumulative Status by FC - Summary
                        ZFSNC5 – Non- Cumulative Status by FC - Detail
                        ZFSNC6 – Non- Cumulative Status by FC Pre-Posted
                        ZRFSC1 – Reimbursable Cumulative Status by FC
                        ZRFSC2 – Reimbursable Cumulative Status by FP
                        ZRFSNC1 – Reimbursable Non-Cumulative Status by FC
                        ZRFSNC2 – Reimbursable Non-Cumulative Status by FP
                        ZSFM_ASN – Table Maintenance for ZSFMT_PBAS_ASN
                        ZSFM_ASN_MAINT – Update Period of Availability Z-Table
                        ZSFM_POA – Upload Data for ZSFMT_PBAS_POA
                        ZSFM_POA_MAINT - Update Allotment Serial Number Table

Click here to return to top.




                                            Plant Maintenance

     Role                                           Transaction Codes
Work                    CA85 – Replace Work Center
Notification            IW21 - Create PM Notification - General
Processor               IW22 - Change PM Notification
                        IW28 - Change Notifications
                        IW30 - Notification List (Multi-Level)
                        IW32 – Change Order
                        IW34 - PM Order for PM Notification
                        IW36 - Create PM Sub-Order
                        IW37N – Change Orders and Operations
                        IW38 - Change PM Orders
                        IW3D - Print Order
                        IW41 - Enter PM Order Confirmation
For Official Use Only                                                                Page 32
SAP Transaction and Command Codes Job Aid                              GFEBS

     Role                                           Transaction Codes
                        IW42 - Overall Completion Confirmation
                        IW44 - PM Order Collective Confirmation


Order                   CN41 - Structure Overview Report
Maintainer              I_GRAPH_MONITOR - Monitor for Jobs
                        IE02 – Change Equipment
                        IE03 - Display Equipment
                        IE05 – Change Equipment: Equipment Selection
                        IH01 - Functional Location Structural Display
                        IK07 - Display Measuring Points
                        IK11 - Create Measurement Document
                        IK12 - Change Measurement Document
                        IK13 - Display Measurement Document
                        IK14 - Collective Entry of MeasDocuments
                        IK16 - Collective Entry of MeasDocuments
                        IK17 - Display Measurement Documents
                        IK18 - Change Measurement Documents
                        IK21 - Collective Entry of MeasDocuments
                        IK22 - Collective Entry of MeasDocuments
                        IK34 - Collective Entry of MeasDocuments
                        IL07 - Functional Location List (Multi-Level)
                        IPMD - Maintain/Display Permits
                        IR01 – Create Work Center
                        IR02 – Change Work Center
                        IW13 - Material Where-used List
                        IW22 - Change PM Notification
                        IW23 - Display PM Notification
                        IW28 - Change Notifications
                        IW29 - Display Notifications
                        IW30 - Notification List (Multi-Level)
                        IW32 - Change Order
                        IW33 - Display PM Order
                        IW37 - Change Operations
                        IW37N – Change Orders and Operations
                        IW38 - Change PM Orders
                        IW39 - Display PM orders
                        IW3D - Print Order
                        IW3K - Change Order Component List
                        IW3L - Display Order Component List
                        IW40 - Display Orders (Multi-Level)
                        IW41 - Enter PM Order Confirmation
For Official Use Only                                                    Page 33
SAP Transaction and Command Codes Job Aid                                                 GFEBS

     Role                                            Transaction Codes
                         IW42 - Overall Completion Confirmation
                         IW43 - Display PM Order Confirmation
                         IW44 - PM Order Collective Confirmation
                         IW48 – Confirmation Using Operation List
                         IW49 - Display Operations
                         IW70 - Orders Overall Network Scheduling
                         KGI2 - Actual Overhead Calculation: Order
                         KGI4 - Actual Overhead Calculation: Internal/Maintenance Orders
                         KO8G - Act. Settlment: Int.-/Maint. Orders
                         MIGO - Goods Movement
                         S_ALR_87013421 - Display Measurement Reading Entry List
                         ZSSC_PRINT_PR – Print PR/Quote
Order                   CJ2B - Project Scheduling Board
Approver                CM01 - Cap. Planning; Work Center Load
                        CM02 - Capac. Planning; Work Center Orders
                        CM03 - Capac. Planning; Work Center Pool
                        CM04 - Capac. Planning; Work Center Backlog
                        CM05 - Capacity Plan; Work Center Overload
                        CM07 - Cap. Planning: Variable Access
                        CM24 - Capacity Leveling: PM Indiv. Tab.
                        CM25 - Capacity Leveling: Variable
                        CM30 - Cap. Leveling: PM Indiv. Cap. Graph.
                        CM33 - Cap. Leveling: PM Work Cntr. Graphic
                        CM34 - Cap. Leveling: PM Work Cntr. Tab.
                        CM50 – Capacity Level: SFC Work Cntr List
                        CM51 – Cap. Level: SFC Individual Cap. List
                        CM52 – Cap. Leveling: SFC Orders List
                        CN41 - Structure Overview Report
                        CO99 - Set Status "Closed"
                        COGI - Processing Goods Movemnts w. Errors
                        IA01 - Create Equipment Task List
                        IA02 - Change Equipment Task List
                        IA03 - Display Equipment Task List
                        IA05 - Create General Task List
                        IA06 - Change Material Maintenance Task List
                        IA11 - Create Functional Location Task List
                        IA12 - Change Functional Location Task List
                        IE02 – Change Equipment
                        IE03 - Display Equipment
                        IE05 – Change Equipment: Equipment Selection
For Official Use Only                                                                       Page 34
SAP Transaction and Command Codes Job Aid                                GFEBS

     Role                                             Transaction Codes
                        IH01 - Functional Location Structural Display
                        IK07 - Display Measuring Points
                        IK11 - Create Measurement Document
                        IK12 - Change Measurement Document
                        IK13 - Display Measurement Document
                        IK16 - Collective Entry of MeasDocuments
                        IK17 - Display Measurement Documents
                        IK18 - Change Measurement Documents
                        IK21 - Collective Entry of MeasDocuments
                        IK22 - Collective Entry of MeasDocuments
                        IK34 - Collective Entry of MeasDocuments
                        IK41 - Display MeasDocs From Archive
                        IL07 - Functional Location List (Multi-Level)
                        IP19 - Maintenance Scheduling Overview
                        IP24 - Scheduling Overview List Form
                        IP30 - MaintSchedule Date Monitoring
                        IP31 - Maintenance Plan Cost Display
                        IPMD - Maintain/Display Permits
                        IQS8 - Worklist: Notifications (General)
                        IQS9 - Worklist: Tasks (General)
                        IW12 - Document Flow List
                        IW13 - Material Where-used List
                        IW21 - Create PM Notification - General
                        IW22 - Change PM Notification
                        IW23 - Display PM Notification
                        IW28 - Change Notifications
                        IW29 - Display Notifications
                        IW30 - Notification List (Multi-Level)
                        IW31 -Create Order
                        IW32 - Change Order
                        IW33 - Display PM Order
                        IW34 - PM Order for PM Notification
                        IW36 - Create PM Sub-Order
                        IW37 - Change Operations
                        IW37N - Change Orders and Operations
                        IW38 - Change PM Orders
                        IW39 - Display PM Orders
                        IW3D - Print Order
                        IW3K - Change Order Component List
For Official Use Only                                                      Page 35
SAP Transaction and Command Codes Job Aid                                        GFEBS

     Role                                          Transaction Codes
                        IW3L - Display Order Component List
                        IW3M - Lists of Good Movements for Order
                        IW40 - Display Orders (Multi-Level)
                        IW41 - Enter PM Order Confirmation
                        IW42 - Overall Completion Confirmation
                        IW43 - Display PM Order Confirmation
                        IW44 - PM Order Collective Confirmation
                        IW45 - Cancel PM Order Confirmation
                        IW47 - Confirmation List
                        IW48 - Confirmation Using Operation List
                        IW49 - Display Operations
                        IW70 - Orders Overall Network Scheduling
                        MCI1 - Object Class
                        MCI2 - Manufacturer
                        MCI4 - Planner Group
                        MCI5 - Damage Analysis
                        MCI6 - Object Statistics
                        MCI8 - Cost Analysis
                        MD04 - Display Stock/Requirements Situation
                        S_ALR_87013421 - Display Measurement Reading Entry List
Permit                   CN41 - Structure Overview Report
Approver                 IH01 - Functional Location Structural Display
                         IL07 - Functional Location List (Multi-Level)
                         IPMD - Maintain/Display Permits
                         IW23 - Display PM Notification
                         IW29 - Display Notifications
                         IW32 - Change Order
                         IW33 - Display PM Order
                         IW37N - Change Orders and Operations
                         IW38 - Change PM Orders
                         IW39 - Display PM orders
                         IW40 - Display Orders (Multi-Level)
                         IW43 - Display PM Order Confirmation
                         IW49 - Display Operations
Plant                    BGM1 - Create Master Warranty
Maintenance              BGM2 - Change Master Warranty
Master Data              CA85 - Replace Work Center
Maintainer
                         CL02 - Classes
                         CL20N - Assign Object to Class
                         CL22N - Assign Class to Superior Classes
For Official Use Only                                                              Page 36
SAP Transaction and Command Codes Job Aid                              GFEBS

     Role                                          Transaction Codes
                        CL24N - Class Assignment
                        CL26 - Mass Release of Assignments
                        CLHP - Graphical Hierarchy Maintenance
                        CN41 - Structure Overview Report
                        CR05 - Evaluations Work Center List
                        CR06 - Evaluations Cost Center Assignment
                        CR07 - Evaluations Work Center Capacity
                        CR08 - Evaluations Work Center Hierarchy
                        CR10 - Work Centers Change Documents
                        CR11 - Create Capacity
                        CR12 - Change Capacity
                        CR13 - Display Capacity
                        CR15 - Use Capacity
                        CR21 - Create Hierarchy
                        CR22 - Change Hierarchy
                        CR23 - Display Hierarchy
                        CS01 - Create Material BOM
                        CS02 - Change Material BOM
                        CS03 - Display Material BOM
                        CT04 - Characteristics
                        IA01 - Create Equipment Task List
                        IA02 - Change Equipment Task List
                        IA03 - Display Equipment Task List
                        IA05 - Create General Task List
                        IA06 - Change Material Maintenance Task List
                        IA11 - Create Functional Location Task List
                        IA12 - Change Functional Location Task List
                        IB01 - Create Equipment BOM
                        IB02 - Change Equipment BOM
                        IB11 - Create Functional Location BOM
                        IE01 - Create Equipment
                        IE02 - Change Equipment
                        IE03 - Display Equipment
                        IE05 - Change Equipment: Equipment Selection
                        IH01 - Functional Location Structural Display
                        IK01 - Create Measuring Point
                        IK02 - Change Measuring Point
                        IK03 - Display Measuring Point
                        IK07 - Display Measuring Points
                        IK11 - Create Measurement Document
                        IK12 - Change Measurement Document
For Official Use Only                                                    Page 37
SAP Transaction and Command Codes Job Aid                                              GFEBS

     Role                                            Transaction Codes
                        IK13 - Display Measurement Document
                        IK17 - Display Measurement Documents
                        IL01 - Create Functional Location
                        IL02 - Change Functional Location
                        IL03 - Display Functional Location
                        IL05 - Change Functional Location: Functional Location
                        Selection
                        IL07 - Functional Location List (Multi-Level)
                        IN04 - Change Functional Location Object Link
                        IN05 - Change Functional Location Object Link
                        IN15 - List Editing: Display Functional Location Object Links
                        IP02 - Change Maintenance Plan
                        IP19 - Maintenance Scheduling Overview
                        IP24 - Scheduling Overview List Form
                        IP31 - Maintenance Plan Cost Display
                        IPMD - Maintain/Display Permits
                        IR01 - Create Work Center
                        IR02 - Change Work Center
                        IR03 - Display Work Center
                        IW13 - Material Where-used List
                        IW23 - Display PM Notification
                        IW29 - Display Notifications
                        IW30 - Notification List (Multi-Level)
                        IW32 - Change Order
                        IW33 - Display PM Order
                        IW37N - Change Orders and Operations
                        IW38 - Change PM Orders
                        IW39 - Display PM Orders
                        IW3L - Display Order Component List
                        IW40 - Display Orders (Multi-Level)
                        IW49 - Display Operations
                        MCI1 - Object Class
                        MCI2 - Manufacturer
                        MCI4 - Planner Group
                        MCI5 - Damage Analysis
                        MCI6 - Object Statistics
                        MCI8 - Cost Analysis
                        OINI - Create Network ID
                        ZSPPE_DATALOAD - ZSPPEE_BOM
                        ZSPPE_DATALOAD - ZSPPEE_EQUIPMENT
                        ZSPPE_DATALOAD - ZSPPEE_FUNCTIONAL_LOCATION
For Official Use Only                                                                    Page 38
SAP Transaction and Command Codes Job Aid                              GFEBS

     Role                                    Transaction Codes
                        ZSPPE_DATALOAD - ZSPPEE_MAINTENANCE_PLAN
                        ZSPPE_DATALOAD - ZSPPEE_MEASURINGPT_COUNTER
                        ZSPPE_DATALOAD - ZSPPEE_TASK_LIST
                        ZSPPE_DATALOAD - ZSPPEE_WARRANTIES
Preventive              CN41 – Structure Overview Report
Maintenance             IA01 - Create Equipment Task List
Controller              IA02 - Change Equipment Task List
                        IA03 - Display Equipment Task List
                        IA06 - Change Material Maintenance Task List
                        IA11 - Create Functional Location Task List
                        IA12 - Change Functional Location Task List
                        IE02 – Change Equipment
                        IE03 - Display Equipment
                        IE05 – Change Equipment: Equipment Selection
                        IH01 – Functional Location Structural Display
                        IK01 - Create Measuring Point
                        IK02 - Change Measuring Point
                        IK03 - Display Measuring Point
                        IK07 - Display Measuring Points
                        IK12 - Change Measurement Document
                        IK14 - Collective Entry of MeasDocuments
                        IK16 - Collective Entry of MeasDocuments
                        IK41 - Display MeasDocs from Archive
                        IL07 – Functional Location List (Multi-Level)
                        IP02 - Change Maintenance Plan
                        IP03 - Display Maintenance Plan
                        IP10 - Schedule Maintenance Plan
                        IP19 - Maintenance Scheduling Overview
                        IP24 - Scheduling Overview List Form
                        IP30 - MaintSchedule Date Monitoring
                        IP31 - Maintenance Plan Cost Display
                        IP41 - Add Single Plan
                        IP42 - Add Strategy-controlled Plan
                        IP43 - Add Multiple Counter Plan
                        IW23 – Display PM Notification
                        IW29 – Display Notifications
                        IW30 – Notification List (Multi-Level)
                        IW33 – Display PM Order
                        IW39 – Display PM Orders
                        IW40 – Display Orders (Multi-Level)
                        IW49 – Display Operations
                        MCI1 - Object Class
For Official Use Only                                                    Page 39
SAP Transaction and Command Codes Job Aid                                           GFEBS

     Role                                          Transaction Codes
                        MCI2 - Manufacturer
                        MCI4 - Planner Group
                        MCI5 - Damage Analysis
                        MCI6 - Object Statistics
                        MCI8 - Cost Analysis
                        S_ALR_87013421 - Display Measurement Reading Entry
                        List
                        ZSPPE_DATALOAD – PPE-PM Front End for Loading Data
Material                CN41 - Structure Overview Report
Requirements            IH01 - Functional Location Structural Display
Planning                IW13 - Material Where-used List
Maintainer
                        IW23 - Display PM Notification
                        IW29 - Display Notifications
                        IW33 - Display PM Order
                        IW39 - Display PM Orders
                        IW3K - Change Order Component List
                        IW3L - Display Order Component List
                        IW40 - Display Orders (Multi-Level)
                        MB03 - Display Material Document
                        MB51 - Material Document List
                        MB52 – Display Warehouse Stocks of Material
                        MCI8 - Cost Analysis
                        MD01 - MRP Run
                        MD03 - MRP-Individual Planning-Single Level
                        MD04 - Display Stock/Requirements Situation
                        MD05 - Individual Display of MRP List
                        MD06 - Collective Display of MRP List
                        MD07 - Current Material Overview
                        MD11 - Create Planned Order
                        MD12 - Change Planned Order
                        MD13 - Display Planned Order
                        MD14 - Convert Planned Order to PR
                        MD15 - Collective Conversion of Planned Orders to Purchase
                        Reqs
                        ME03 – Display Source List
                        ME2B - POs by Requirement Tracking Number
                        ME2L – Purchase Order List Display by Vendor
                        ME2N – PO List Display by PO Number
                        MI22 - Display Phys. Inv. Docs. f. Material
                        MIGO - Goods Movement
                        MIQ1 – Selected Data for Physical Inventory Documents for
                        Project
For Official Use Only                                                                 Page 40
SAP Transaction and Command Codes Job Aid                                 GFEBS

     Role                                        Transaction Codes
                         MM01 - Create Material
                         MM02 - Change Material
                         MM03 - Display Material
                         MMBE - Stock Overview
                         MP30 - Execute Material Forecast
                         MP31 - Change Material Forecast
                         MP32 - Display Material Forecast
                         XK01 – Create Master
                         XK02 – Change Master
                         XK03 – Display Vendor Master
                         ZSSC_PRINT_PR – Print PR/Quote
                         ZSSC_SUPPLY_RPT – Supply Management Report
Physical                 CN41 - Structure Overview Report
Inventory                COGI - Processing Goods Movemnts w. Errors
Maintainer               IH01 - Functional Location Structural Display
                         IW13 - Material Where-used List
                         IW23 - Display PM Notification
                         IW29 - Display Notifications
                         IW33 - Display PM Order
                         IW39 - Display PM Orders
                         IW3K - Change Order Component List
                         IW3L - Display Order Component List
                         MB03 - Display Material Document
                         MB51 - Material Document List
                         ME03 – Display Source List
                         ME2N – Purchasing Documents per Document Number
                         MI01 - Create Physical Inventory Document
                         MI02 - Change Physical Inventory Document
                         MI03 - Display Physical Inventory Document
                         MI04 - Enter Inventory Count with Document
                         MI05 - Change Inventory Count
                         MI06 - Display Inventory Count
                         MI07 - Process List of Differences
                         MI08 - Create List of Differences with Doc.
                         MI20 - Print List of Differences
                         MI21 - Print Physical Inventory Document
                         MI24 - Physical Inventory List
                         MIGO - Goods Movement
Annual                  CJ40 – Change Project Cost Plan
Planner                 CJ40 – Change Project Plan
                        ZSPPE_AWP – Annual Workplan Report
                        ZSPPE_IJO – Report on IJO Ranking Requirements
For Official Use Only                                                       Page 41
SAP Transaction and Command Codes Job Aid                                  GFEBS

     Role                                          Transaction Codes
Plant                   AS03 - Display Asset
Maintenance             BGM3 - Display Master Warranty
Reporter                CA80 - Work Center Where Used: Selection
                        CJ02 - Display Work Breakdown Structure
                        CJ03 - Display Work Breakdown Structure
                        CJ08 - Display Project Definition
                        CJ13 - Display WBS Element
                        CJ22 - Display Basic Dates
                        CJ24 - Display Forecast Dates
                        CJ26 - Display Actual Dates
                        CJ41 - Display Project Cost Plan
                        CJ43 - Display Project Revenues
                        CJ80 - Run Hierarchy Report
                        CJ93 - Display Standard WBS
                        CJCS - Display Change Documents
                        CJE0 - Run Hierarchy Report
                        CJE3 - Display Hierarchy Report
                        CJI3 - Display Line Items
                        CJI4 - Display Line Items
                        CJI5 - Display Line Items
                        CJI9 - Display Line Items
                        CJIA - Display Line Items
                        CJID - Display Line Items
                        CJIF - Display Line Items
                        CJR3 - PS: Display Plan CElem/Activ. Input
                        CM01 - Cap. Planning; Work Center Load
                        CM02 - Capac. Planning; Work Center Orders
                        CM03 - Capac. Planning; Work Center Pool
                        CM04 - Capac. Planning; Work Center Backlog
                        CM05 - Capacity Plan; Work Center Overload
                        CM07 - Cap. Planning: Variable Access
                        CM28 - Individual Capacity Leveling
                        CM50 – Capacity Level: SFC Work Cntr List
                        CM51 – Cap. Level: SFC Individual Cap. List
                        CM52 – Cap. Leveling: SFC Orders List
                        CM53 - Capacity: Extended Evaluation Project View
                        CM54 - Capacity: Extended Evaluation Project View
                        CM55 - Capacity: Extended Evaluation Project View
                        CN03 - Display Standard Network
                        CN23 - Display Network
                        CN28 - Display Individual Confirmations - Network
For Official Use Only                                                        Page 42
SAP Transaction and Command Codes Job Aid                                  GFEBS

     Role                                          Transaction Codes
                        CN41 - Structure Overview Report
                        CN42N - Individual Overviews
                        CN43N - Individual Overviews
                        CN45N - Individual Overviews
                        CN46N - Individual Overviews
                        CN47N - Individual Overviews
                        CN49N - Individual Overviews
                        CN51N - Individual Overviews
                        CN52N - Material Reports
                        CN53N - Individual Overviews
                        CN54N - Individual Overviews
                        CN55N - Individual Overviews
                        CN60 - Display Change Documents
                        CN61 - Display Change Documents
                        CNR3 - Display Work Center
                        CO24 - Missing Parts
                        CR03 - Display Work Center
                        CR05 – Evaluations Work Center List
                        CR06 – Evaluations Cost Center Capacity
                        CR07 – Evaluations Work Center Capacity
                        CR08 – Evaluations Work Center Hierarchy
                        CR10 – Work Centers Change Documents
                        CR13 – Display Capacity
                        CR23 – Display Hierarchy
                        CS03 – Display Material BOM
                        CT10 - Characteristics Display
                        FB03 - Display Financial Document
                        FM_Sets_FIPEX3 - Display Commitment Item Group
                        FM_Sets_Function3 - Display Functional Area Group
                        FM5S - FIFM: Display Fund
                        FM6S - FIFM: Display Application of Funds
                        FMCIC - Display Commitment Item
                        FMEDD - Display Entry Document
                        FMMEASURE – Change Funded Program
                        FMMEASURED - Funded Program: Display
                        FMRP_RFFMEP1AX – All Postings
                        FMSC – Display Funds Center in FM Area
                        FMW3 - Display Funds Block
                        FMX3 - Display Funds Reservation
                        FMY3 - Display Funds Precommitment
                        FMZ3 - Display Funds Commitment
                        GRR3 - Funds Status Report
For Official Use Only                                                        Page 43
SAP Transaction and Command Codes Job Aid                                              GFEBS

     Role                                             Transaction Codes
                        IA03 - Display Equipment Task List
                        IA07 - General Maintenance Task List
                        IA13 – Display FunctLoc Task List
                        IB03 - Display Equipment BOM
                        IB13 - Display Functional Location BOM
                        IE03 – Display Equipment
                        IH01 - Functional Location Structural Display
                        IH06 – Display Functional Location
                        IH07 – Display Functional Location
                        IH08 – Display Equipment
                        IK03 – Display Measuring Point
                        IK07 – Display Measuring Points
                        IK13 – Display Measurement Document
                        IK17 - Display Measurement Documents
                        IK41 - Display MeasDocs from Archive
                        IL03 – Display Functional Location
                        IL07 – Functional Location List (Multi-Level)
                        IN06 - Display Functional Location Object Link
                        IN16 - List Editing: Display Functional Location Object Links
                        IP03 – Display Maintenance Plan
                        IP10 – Schedule Maintenance Plan
                        IP19 – Maintenance Scheduling Overview
                        IP24 – Scheduling Overview List Form
                        IP30 – MaintSchedule Date Monitoring
                        IP31 - Maintenance Plan Cost Display
                        IPMD – Maintain/Display Permits
                        IR03 – Display Work Center
                        IW13 – Material Where-used List
                        IW23 - Display PM Notification
                        IW29 - Display Notifications
                        IW30 - Notification List (Multi-Level)
                        IW33 - Display PM Order
                        IW39 - Display PM Orders
                        IW3D – Print Order
                        IW3L – Display Order Component List
                        IW40 - Display Orders (Multi-Level)
                        IW43 – Display PM Order Confirmation
                        IW49 – Display Operations
                        KJH3 - Display WBS Element Groups
                        KKAE - Display Worklist for Results Analysis
                        KKAL - Display Log for Results Analysis
                        KKE3 - Display Base Planning Object
                        KKG0 Display Cutoff Period for Results Analysis
                        KKRC - Display Inheritance (Summarization)
For Official Use Only                                                                    Page 44
SAP Transaction and Command Codes Job Aid                                   GFEBS

     Role                                           Transaction Codes
                        KSB5 - Display Actual Costs/Revenue Document
                        MB03 - Display Material Document
                        MB25 - Material Reports
                        MB51 - Material Document List
                        MBBS - Material Reports
                        MCI1 - Object Class
                        MCI2 - Manufacturer
                        MCI4 - Planner Group
                        MCI5 - Damage Analysis
                        MCI6 - Object Statistics
                        MCI8 - Cost Analysis
                        MD04 - Display Stock/Requirements Situation
                        MD13 – Display Planned Order
                        MD4C - Material Reports
                        MDLD - MRP Lists
                        ME23N - Display Purchase Order
                        ME2L - Purchase Order List Display by Vendor
                        ME2M - Purchase Order List Display by Material
                        ME2W - Purchase Order List Display by Plant
                        ME33K - Display Contract
                        ME53N - Display Purchase Requisition
                        ME5A - Purchase Requisitions List Display- General
                        ME5J - Purchase Requisitions by Project
                        ME5K - List Display of Purchase Requisitions
                        MI03 – Display Physical Inventory Document
                        MI06 – Display Inventory Count
                        MM03 – Display Material
                        MP32 – Display Material Forecast
                        RE80 - RE Navigator
                        REBDBE - Process BE
                        REBDBU - Process BU
                        REBDPR - Process PR
                        REBDRO - Process RO
                        RECARS – Process Dates for All Objects
                        RECARSCN – Process Dates for Contracts
                        RECN – Process Contract
                        REISBDOA - Info System: Object Assignment
                        REISBE - Info System: Business Entities
                        REISBP - Info System: Objects for Partner
                        REISBPBD – Info System: Partner for Master Data
                        REISBU – Info System: Buildings
                        REISCDBD – Info System: Conditions for RO

For Official Use Only                                                         Page 45
SAP Transaction and Command Codes Job Aid                                        GFEBS

     Role                                         Transaction Codes
                        REISCN – Info System: Contracts
                        REISMSBD – Info System: Measurements – Mast. Data
                        REISPR – Info System: Properties
                        REISRO – Info System: Rental Objects
                        S_ALR_87013421 - Display Measurement Reading Entry List
                        S_ALR_87013532 - Cost Hierarchical Plan-based
                        S_ALR_87013533 - Cost Hierarchical Plan-based
                        S_ALR_87013534 - Cost Hierarchical Plan-based
                        S_ALR_87013535 - Cost Hierarchical Plan-based
                        S_ALR_87013536 - Cost Hierarchical Plan-based
                        S_ALR_87013537 - Cost Hierarchical Plan-based
                        S_ALR_87013538 - Cost Hierarchical Plan-based
                        S_ALR_87013539 - Cost Hierarchical Plan-based
                        S_ALR_87013540 - Cost Hierarchical Plan-based
                        S_ALR_87013541 - Cost Hierarchical Plan-based
                        S_ALR_87013542 - Cost Element Plan-based
                        S_ALR_87013543 - Cost Element Plan-based
                        S_ALR_87013544 - Cost Element Plan-based
                        S_ALR_87013545 - Cost Element Plan-based
                        S_ALR_87013546 - Cost Element Plan-based
                        S_ALR_87013547 - Cost Element Plan-based
                        S_ALR_87013548 - Cost Element Plan-based
                        S_ALR_87013549 - Cost Element Plan-based
                        S_ALR_87013550 - Cost Element Plan-based
                        S_ALR_87013551 - Cost Element Plan-based
                        S_ALR_87013552 - Cost Element Plan-based
                        S_ALR_87013553 - Cost Element Plan-based
                        S_ALR_87013554 - Cost Element Plan-based
                        S_ALR_87013555 - Cost Element Plan-based
                        S_ALR_87013562 - Revenue and Earnings Hierarchical
                        S_ALR_87013563 - Revenue and Earnings Hierarchical
                        S_ALR_87013564 - Revenue and Earnings Hierarchical
                        S_ALR_87013565 - Revenue and Earnings Hierarchical
                        S_ALR_87013566 - Revenue and Earnings Hierarchical
                        S_ALR_87013567 - Revenue and Earnings Hierarchical
                        S_ALR_87013568 - Revenue and Earnings Hierarchical
                        S_ALR_87013569 - Revenue and Earnings Hierarchical
                        S_ALR_87013570 - Revenue and Earnings Cost Element
                        S_ALR_87013571 - Revenue and Earnings Cost Element
                        S_ALR_87013572 - Revenue and Earnings Cost Element
                        S_ALR_87013576 - Summarization Overview
For Official Use Only                                                              Page 46
SAP Transaction and Command Codes Job Aid                                             GFEBS

     Role                                        Transaction Codes
                        S_ALR_87013577 - Summarization Costs/Revenue
                        Expenditures/Receipt
                        S_ALR_87013578 - Summarization Plan-based Hierarchical Costs
                        S_ALR_87013579 - Summarization Plan-based Hierarchical Costs
                        S_ALR_87013580 - Summarization Plan-based Cost Element Costs
                        S_ALR_87013581 - Summarization Plan-based Cost Element Costs
                        S_ALR_87013582 - Summarization Plan-based Cost Element Costs
                        S_ALR_87013585 - Summarization Revenue and Earnings
                        Hierarchical
                        S_ALR_87100185 - Cost Hierarchical Plan-based
                        S_ALR_87100186 - Cost Hierarchical Plan-based
                        S_ALR_87100187 - Cost Hierarchical Plan-based
                        S_ALR_87100188 - Cost Hierarchical Plan-based
                        S_ALR_87100189 - Cost Hierarchical Plan-based
                        S_ALR_87100190 - Cost Hierarchical Plan-based
                        SM37 - Overview of Job Selection
                        VA03 - Display Sales Order
                        Z_OPEN_COM – FM Open Commitments
                        Z_OPEN_OB – FM Open Obligations
                        Z_RM_FUND_STATUS – Reimbursable Fund Status Report
                        ZFSC1 – Cumulative Status by FC
                        ZFSC2 – Cumulative Status by FA
                        ZFSC3 – Cumulative Status by FP
                        ZFSC4 – Cumulative Status by FC - Summary
                        ZFSC5 – Cumulative Status by FC - Detail
                        ZFSC6 – Cumulative Status by FA Group - Summary
                        ZFSC7 – Cumulative Status by FA Group - Detail
                        ZFSC8 – Cumulative Status with Open Commitments - Summary
                        ZFSC9 – Cumulative Status with Open Commitments - Detail
                        ZFSNC1 – Non- Cumulative Status by FC
                        ZFSNC2 – Non- Cumulative Status by FA
                        ZFSNC3 – Non- Cumulative Status by FP
                        ZFSNC4 – Non- Cumulative Status by FC - Summary
                        ZFSNC5 – Non- Cumulative Status by FC - Detail
                        ZFSNC6 – Non- Cumulative Status by FC Pre-Posted
                        ZRFSC1 – Reimbursable Cumulative Status by FC
                        ZRFSC2 – Reimbursable Cumulative Status by FP
                        ZRFSNC1 – Reimbursable Non-Cumulative Status by FC
                        ZRFSNC2 – Reimbursable Non-Cumulative Status by FP
                        ZSPPE_ACAPRULE - Asset Capitalization Rules
                        ZSPPE_AWP - Annual Workplan Report
                        ZSPPE_CANCEL - Cancellation Reason
                        ZSPPE_DATALOAD_PS - PPE-PM-EXT-2448
                        ZSPPE_DSIGN - Design/Execution Status
For Official Use Only                                                                   Page 47
SAP Transaction and Command Codes Job Aid                                GFEBS

     Role                                          Transaction Codes
                        ZSPPE_FSOURCE - Fund Source
                        ZSPPE_FUND_STAT - Fund Status
                        ZSPPE_IJO - Report on IJO Ranking Requirements
                        ZSPPE_PLNPRG - Planned Programmed Event Code
                        ZSPPE_PRJTYP - Project Type Code
                        ZSPPE_REGION - Region Name
                        ZSPPE_UPLOAD_ESTWRK – Upload Estimation of Work
                        ZSSC_PRINT_PR – Print PR/Quote
                        ZW39 – DPW Report – PM Orders

Click here to return to top.


                                             Project System

     Role                                          Transaction Codes
Project                 AS01 - Create Asset
Structure               AS02 - Change Asset
Controller              AS03 - Display Asset
                        CJ01 - Create Work Breakdown Structure
                        CJ02 - Change Work Breakdown Structure
                        CJ03 - Display Work Breakdown Structure
                        CJ06 - Create Project Definition
                        CJ07 - Change Project Definition
                        CJ08 - Display Project Definition
                        CJ11 - Create Single Element
                        CJ12 - Change Single Element
                        CJ13 - Display WBS Element
                        CJ20 - Change Structure Planning
                        CJ20N - Project Builder
                        CJ2A - Display Structure Planning
                        CJ2D - Create Structure Planning
                        CJ91 - Create Standard WBS
                        CJ92 - Change Standard WBS
                        CJ93 - Display Standard WBS
                        CJ9K - Network Costing
                        CJE1 - Create Hierarchy Report
                        CJE2 - Change Hierarchy Report
                        CJEB – Background Processing; Hierarchy Reports
                        CJI3 - Display Line Items
                        CJSG - Create WBS Element Groups
                        CJV4 - Transfer (Copy) Project
For Official Use Only                                                      Page 48
SAP Transaction and Command Codes Job Aid                                 GFEBS

     Role                                         Transaction Codes
                        CJV5 - Delete Simulation
                        CJV6 - Display Administrative Data for Version
                        CJV7 - Display Version Log
                        CN01 - Create Standard Network
                        CN02 - Change Standard Network
                        CN03 - Display Standard Network
                        CN04 – Edit PS Text Catalog
                        CN05 – Display PS Text Catalog
                        CN21 - Create Network
                        CN22 - Change Network
                        CN23 – Display Network
                        CN23 - Display Individual Confirmations- Network
                        CN24 – Overall Network Scheduling
                        CN40 – Project Overview
                        CN41 - Structure Overview
                        CN41N - Structure Overview
                        CN52N - Material Reports
                        CN71 - Create Version with Structure
                        CN72 - Create Version
                        CN98 - Delete Standard Network
                        CNR1 - Create Work Center
                        CNR2 - Change Work Center
                        CNR3 - Display Work Center
                        CO24 - Missing Parts
                        CR11 - Create Capacity
                        CR12 - Change Capacity
                        FMMEASURE – Change Funded Program
                        KJH2 - Change WBS Element Croups
                        KJH3 - Display WBS Element Groups
                        MB25 - Material Reports
                        MBBS - Material Reports
                        MD04 -Display Stock Requirements List
                        MD04 – Material Reports
                        MD4C - Material Reports
                        OPUM - Maintain Subprojects
                        Z_OPEN_COM – FM Open Commitments
                        Z_OPEN_OB – FM Open Obligations
                        ZFSC1 – Cumulative Status by FC
                        ZFSC2 – Cumulative Status by FA
                        ZFSC3 – Cumulative Status by FP
                        ZFSC4 – Cumulative Status by FC - Summary
                        ZFSC5 – Cumulative Status by FC - Detail
                        ZFSC6 – Cumulative Status by FA Group - Summary
For Official Use Only                                                       Page 49
SAP Transaction and Command Codes Job Aid                                                  GFEBS

     Role                                           Transaction Codes
                        ZFSC7 – Cumulative Status by FA Group - Detail
                        ZFSC8 – Cumulative Status with Open Commitments - Summary
                        ZFSC9 – Cumulative Status with Open Commitments - Detail
                        ZFSNC1 – Non- Cumulative Status by FC
                        ZFSNC2 – Non- Cumulative Status by FA
                        ZFSNC3 – Non- Cumulative Status by FP
                        ZFSNC4 – Non- Cumulative Status by FC - Summary
                        ZFSNC5 – Non- Cumulative Status by FC - Detail
                        ZFSNC6 – Non- Cumulative Status by FC Pre-Posted
                        ZRFSC1 – Reimbursable Cumulative Status by FC
                        ZRFSC2 – Reimbursable Cumulative Status by FP
                        ZRFSNC1 – Reimbursable Non-Cumulative Status by FC
                        ZRFSNC2 – Reimbursable Non-Cumulative Status by FP
                        ZSPPE_DATALOAD_PS – Program to Load Projects
Project                 CJ20N – Project Builder
Financial               CJ40 - Change Project Cost Plan
Controller              CJ40 – Change Project Plan
                        CJ42 - Create/Change Revenue Plan
                        CJ43 - Display Project Revenues
                        CJ9B - Copy Version (Mass Change)
                        CJ9BS - Copy Planning Cost Data by Version (Single Project)
                        CJ9C - Copy Actual to Plan Cost Data by Version (Mass Change)
                        CJ9CS - Copy Actual to Plan Cost Data by Version (Single Project)
                        CJ9F - Copy Planning Cost Data by Version (Mass Change)
                        CJ9FS - Copy Version for Project Def.
                        CJ9K - Network Costing
                        CJR2 - PS: Change Plan CElem/Activ. Input
                        CJR3 - PS: Display Plan CElem/Activ. Input
                        CN23 - Display Individual Confirmations- Network
                        CN23 – Display Network
                        CN24 – Overall Network Scheduling
                        CN40 – Project Overview
                        CN41 - Structure Overview
                        CN41N - Structure Overview
                        CN52N - Material Reports
                        CO24 - Missing Parts
                        FMMEASURE - Change Funded Program
                        KKAE - Display Worklist for Results Analysis
                        KKAL - Display Log for Results Analysis
                        KKE1 - Create Revenue Plan on WBS
                        KKE2 - Change Revenue Plan on WBS
                        KKE3 - Display Base Planning Object
                        KKG0 - Display Cutoff Period for Results Analysis
For Official Use Only                                                                        Page 50
SAP Transaction and Command Codes Job Aid                                             GFEBS

     Role                                         Transaction Codes
                        KP04 - Set Planner Profile
                        MB25 - Material Reports
                        MBBS - Material Reports
                        MD04 - Display Stock Requirements List
                        MD04 – Material Reports
                        MD4C - Material Reports
                        S_ALR_87013585 - Summarization Revenue and Earnings Hierarchical
                        Z_OPEN_COM – FM Open Commitments
                        Z_OPEN_OB – FM Open Obligations
                        ZFSC1 – Cumulative Status by FC
                        ZFSC2 – Cumulative Status by FA
                        ZFSC3 – Cumulative Status by FP
                        ZFSC4 – Cumulative Status by FC - Summary
                        ZFSC5 – Cumulative Status by FC - Detail
                        ZFSC6 – Cumulative Status by FA Group - Summary
                        ZFSC7 – Cumulative Status by FA Group - Detail
                        ZFSC8 – Cumulative Status with Open Commitments - Summary
                        ZFSC9 – Cumulative Status with Open Commitments - Detail
                        ZFSNC1 – Non- Cumulative Status by FC
                        ZFSNC2 – Non- Cumulative Status by FA
                        ZFSNC3 – Non- Cumulative Status by FP
                        ZFSNC4 – Non- Cumulative Status by FC - Summary
                        ZFSNC5 – Non- Cumulative Status by FC - Detail
                        ZFSNC6 – Non- Cumulative Status by FC Pre-Posted
                        ZRFSC1 – Reimbursable Cumulative Status by FC
                        ZRFSC2 – Reimbursable Cumulative Status by FP
                        ZRFSNC1 – Reimbursable Non-Cumulative Status by FC
                        ZRFSNC2 – Reimbursable Non-Cumulative Status by FP
                        ZSPPE_UPLOAD_ESTWRK – Upload Estimation of Work
Project                 CJ20N - Project Builder
Schedule                CJ21 - Change Basic Dates
Controller              CJ22 - Display Basic Dates
                        CJ23 - Change Forecast Dates
                        CJ24 - Display Forecast Dates
                        CJ25 - Change Actual Dates
                        CJ26 - Display Actual Dates
                        CJ27 – Project Planning Board
                        CJ29 - Update WBS (Forecast)
                        CJ2B - Change Project Planning Board
                        CM01 – Cap. Planning; Work Center Load
                        CM02 - Capac. Planning; Work Center Orders
                        CM03 - Capac. Planning; Work Center Pool
                        CM04 - Capac. Planning; Work Center Backlog
                        CM05 - Capacity Plan; Work Center Overload
For Official Use Only                                                                      Page 51
SAP Transaction and Command Codes Job Aid                                          GFEBS

     Role                                         Transaction Codes
                        CM50 – Capacity Level: SFC Work Cntr List
                        CM51 – Cap. Level: SFC Individual Cap. List
                        CM52 – Cap. Leveling: SFC Orders List
                        CM53 - Capacity: Extended Evaluation Project View
                        CM54 - Capacity: Extended Evaluation Project View
                        CN23 - Display Individual Confirmations- Network
                        CN23 – Display Network
                        CN24 - Overall Network Scheduling
                        CN24N - Overall Network Scheduling (new)
                        CN40 – Project Overview
                        CN41 - Structure Overview
                        CN41N - Structure Overview
                        CN52N - Material Reports
                        CNR1 - Create Work Center
                        CNR2 - Change Work Center
                        CNR3 - Display Work Center
                        CO24 - Missing Parts
                        CR11 - Create Capacity
                        CR12 - Change Capacity
                        CR13 - Display Capacity
                        FMMEASURE - Change Funded Program
                        MB25 - Material Reports
                        MBBS - Material Reports
                        MD04 - Display Stock Requirements List
                        MD04 – Material Reports
                        MD4C - Material Reports
                        Z_OPEN_COM – FM Open Commitments
                        Z_OPEN_OB – FM Open Obligations
                        ZFSC1 – Cumulative Status by FC
                        ZFSC2 – Cumulative Status by FA
                        ZFSC3 – Cumulative Status by FP
                        ZFSC4 – Cumulative Status by FC - Summary
                        ZFSC5 – Cumulative Status by FC - Detail
                        ZFSC6 – Cumulative Status by FA Group - Summary
                        ZFSC7 – Cumulative Status by FA Group - Detail
                        ZFSC8 – Cumulative Status with Open Commitments - Summary
                        ZFSC9 – Cumulative Status with Open Commitments - Detail
                        ZFSNC1 – Non- Cumulative Status by FC
                        ZFSNC2 – Non- Cumulative Status by FA
                        ZFSNC3 – Non- Cumulative Status by FP
                        ZFSNC4 – Non- Cumulative Status by FC - Summary
                        ZFSNC5 – Non- Cumulative Status by FC - Detail
                        ZFSNC6 – Non- Cumulative Status by FC Pre-Posted

For Official Use Only                                                                Page 52
SAP Transaction and Command Codes Job Aid                                   GFEBS

     Role                                          Transaction Codes
                        ZRFSC1 – Reimbursable Cumulative Status by FC
                        ZRFSC2 – Reimbursable Cumulative Status by FP
                        ZRFSNC1 – Reimbursable Non-Cumulative Status by FC
                        ZRFSNC2 – Reimbursable Non-Cumulative Status by FP
Project                 CN41 – Structure Overview
Maintainer              CN41N – Structure Overview
                        CJ02 - Display Work Breakdown Structure
                        CJE1 - Create Hierarchy Report
                        CJE2 - Change Hierarchy Report
                        CM01 - Cap. Planning; Work Center Load
                        CM02 - Capac. Planning; Work Center Orders
                        CM03 - Capac. Planning; Work Center Pool
                        CM04 - Capac. Planning; Work Center Backlog
                        CM05 - Capacity Plan; Work Center Overload
                        CM50 – Capacity Level: SFC Work Cntr List
                        CM51 – Cap. Level: SFC Individual Cap. List
                        CM52 – Cap. Leveling: SFC Orders List
                        CM53 - Capacity: Extended Evaluation Project View
                        CM54 - Capacity: Extended Evaluation Project View
                        CM55 - Capacity: Extended Evaluation Project View
                        CN23 - Display Individual Confirmations- Network
                        CN24 – Overall Network Scheduling
                        CN40 – Project Overview
                        CN52N - Material Reports
                        CO24 - Missing Parts
                        KKAE - Display Worklist for Results Analysis
                        KKAL - Display Log for Results Analysis
                        KKG0 - Display Cutoff Period for Results Analysis
                        MB25 - Material Reports
                        MBBS - Material Reports
                        MD04 - Display Stock Requirements List
                        MD04 – Material Reports
                        MD4C - Material Reports
                        Z_OPEN_COM – FM Open Commitments
                        Z_OPEN_OB – FM Open Obligations
                        ZFSC1 – Cumulative Status by FC
                        ZFSC2 – Cumulative Status by FA
                        ZFSC3 – Cumulative Status by FP
                        ZFSC4 – Cumulative Status by FC - Summary
                        ZFSC5 – Cumulative Status by FC - Detail
                        ZFSC6 – Cumulative Status by FA Group - Summary
                        ZFSC7 – Cumulative Status by FA Group - Detail

For Official Use Only                                                         Page 53
SAP Transaction and Command Codes Job Aid                                          GFEBS

     Role                                         Transaction Codes
                        ZFSC8 – Cumulative Status with Open Commitments - Summary
                        ZFSC9 – Cumulative Status with Open Commitments - Detail
                        ZFSNC1 – Non- Cumulative Status by FC
                        ZFSNC2 – Non- Cumulative Status by FA
                        ZFSNC3 – Non- Cumulative Status by FP
                        ZFSNC4 – Non- Cumulative Status by FC - Summary
                        ZFSNC5 – Non- Cumulative Status by FC - Detail
                        ZFSNC6 – Non- Cumulative Status by FC Pre-Posted
                        ZRFSC1 – Reimbursable Cumulative Status by FC
                        ZRFSC2 – Reimbursable Cumulative Status by FP
                        ZRFSNC1 – Reimbursable Non-Cumulative Status by FC
                        ZRFSNC2 – Reimbursable Non-Cumulative Status by FP
                        ZW39 – DPW Report – PM Orders
Project                 AS03 - Display Asset
Interface               CJ03 – Display Work Breakdown Structure
Processing              CJ08 - Display Project Definition
Monitor                 CJ13 - Display WBS Element
                        CJ20N – Project Builder
                        CJ2A - Display Structure Planning
                        CJV6 - Display Administrative Data for Version
                        CJV7 - Display Version Log
                        CN23 - Display Individual Confirmations- Network
                        CN23 – Display Network
                        CN24 – Overall Network Scheduling
                        CN40 – Project Overview
                        CN41 - Structure Overview
                        CN41N - Structure Overview
                        CN52N - Material Reports
                        CNR3 - Display Work Center
                        CO24 - Missing Parts
                        CR13 - Display Capacity
                        KJH3 - Display WBS Element Groups
                        KKAE - Display Worklist for Results Analysis
                        KKAL - Display Log for Results Analysis
                        KKG0 - Display Cutoff Period for Results Analysis
                        MB25 - Material Reports
                        MBBS - Material Reports
                        MD04 - Display Stock Requirements List
                        MD04 – Material Reports
                        MD4C - Material Reports
                        WE02 - Display IDoc List
                        Z_OPEN_COM – FM Open Commitments
                        Z_OPEN_OB – FM Open Obligations
For Official Use Only                                                                Page 54
SAP Transaction and Command Codes Job Aid                                          GFEBS

     Role                                         Transaction Codes
                        ZFSC1 – Cumulative Status by FC
                        ZFSC2 – Cumulative Status by FA
                        ZFSC3 – Cumulative Status by FP
                        ZFSC4 – Cumulative Status by FC - Summary
                        ZFSC5 – Cumulative Status by FC - Detail
                        ZFSC6 – Cumulative Status by FA Group - Summary
                        ZFSC7 – Cumulative Status by FA Group - Detail
                        ZFSC8 – Cumulative Status with Open Commitments - Summary
                        ZFSC9 – Cumulative Status with Open Commitments - Detail
                        ZFSNC1 – Non- Cumulative Status by FC
                        ZFSNC2 – Non- Cumulative Status by FA
                        ZFSNC3 – Non- Cumulative Status by FP
                        ZFSNC4 – Non- Cumulative Status by FC - Summary
                        ZFSNC5 – Non- Cumulative Status by FC - Detail
                        ZFSNC6 – Non- Cumulative Status by FC Pre-Posted
                        ZOS_IST – IDoc Status Report
                        ZRFSC1 – Reimbursable Cumulative Status by FC
                        ZRFSC2 – Reimbursable Cumulative Status by FP
                        ZRFSNC1 – Reimbursable Non-Cumulative Status by FC
                        ZRFSNC2 – Reimbursable Non-Cumulative Status by FP
                        ZSPPE_ACAPRULE - Asset Capitalization Rules
                        ZSPPE_AUTH_TYPCD - Update Authorization Type Code Table
                        ZSPPE_CANCEL - Cancellation Reason
                        ZSPPE_DSIGN - Design/Execution Status
                        ZSPPE_FSOURCE - Fund Source
                        ZSPPE_FUND_STAT - Fund Status
                        ZSPPE_PLNPRG - Planned Programmed Event Code
                        ZSPPE_PRJTYP - Project Type Code
                        ZSPPE_REGION - Region Name
                        ZSPPE_REISROOC – Rental Objects
Project                 CJ02 – Change Work Breakdown Structure
Report                  CJ02 - Display Work Breakdown Structure
Reviewer                CJ03 – Display Work Breakdown Structure
                        CJ08 – Display Project Definition
                        CJ13 – Display WBS Element
                        CJ2A – Display Structure Planning
                        CJ43 – Display Project Revenues
                        CJ93 – Display Standard WBS
                        CJR3 – PS: Display Plan CElem/Activ. Input
                        CM01 – Cap. Planning; Work Center Load
                        CM02 – Capac Planning; Work Center Orders
                        CM03 – Capac. Planning; Work Center Pool
                        CM04 - Capac. Planning; Work Center Backlog
                        CM05 - Capacity Plan; Work Center Overload
                        CM50 – Capacity Level: SFC Work Cntr List
For Official Use Only                                                                Page 55
SAP Transaction and Command Codes Job Aid                                          GFEBS

     Role                                         Transaction Codes
                        CM51 – Cap. Level: SFC Individual Cap. List
                        CM52 – Cap. Leveling: SFC Orders List
                        CM53 – Capacity: Extended Evaluation Project View
                        CM54 – Capacity: Extended Evaluation Project View
                        CM55 – Capacity: Extended Evaluation Project View
                        CN03 – Display Standard Network
                        CN23 – Display Network
                        CN23 - Display Individual Confirmations - Network
                        CN41 - Structure Overview
                        CN41N - Structure Overview
                        CN52N - Material Reports
                        CN61 - Display Change Documents
                        CO24 - Missing Parts
                        FMMEASURE – Change Funded Program
                        KJH3 – Display WBS Element Groups
                        KKAL – Display Log for Results Analysis
                        KKE3 – Display Base Planning Object
                        KKG0 – Display Cutoff Period for Results Analysis
                        MB25 - Material Reports
                        MBBS - Material Reports
                        MD04 - Display Stock Requirements List
                        MD04 – Material Reports
                        WE02 – Display IDoc List
                        Z_OPEN_COM – FM Open Commitments
                        Z_OPEN_OB – FM Open Obligations
                        ZFSC1 – Cumulative Status by FC
                        ZFSC2 – Cumulative Status by FA
                        ZFSC3 – Cumulative Status by FP
                        ZFSC4 – Cumulative Status by FC - Summary
                        ZFSC5 – Cumulative Status by FC - Detail
                        ZFSC6 – Cumulative Status by FA Group - Summary
                        ZFSC7 – Cumulative Status by FA Group - Detail
                        ZFSC8 – Cumulative Status with Open Commitments - Summary
                        ZFSC9 – Cumulative Status with Open Commitments - Detail
                        ZFSNC1 – Non- Cumulative Status by FC
                        ZFSNC2 – Non- Cumulative Status by FA
                        ZFSNC3 – Non- Cumulative Status by FP
                        ZFSNC4 – Non- Cumulative Status by FC - Summary
                        ZFSNC5 – Non- Cumulative Status by FC - Detail
                        ZFSNC6 – Non- Cumulative Status by FC Pre-Posted
                        ZRFSC1 – Reimbursable Cumulative Status by FC
                        ZRFSC2 – Reimbursable Cumulative Status by FP
                        ZRFSNC1 – Reimbursable Non-Cumulative Status by FC
                        ZRFSNC2 – Reimbursable Non-Cumulative Status by FP
                        ZSPPE_UO – Report on UO Ranking Requirements
For Official Use Only                                                                Page 56
SAP Transaction and Command Codes Job Aid                                          GFEBS

     Role                                         Transaction Codes
Project                 CN41 - Structure Overview
Workflow                CN41N - Structure Overview
Monitor                 CN52N - Material Reports
                        CO24 - Missing Parts
                        MB25 - Material Reports
                        MBBS - Material Reports
                        MD04 - Display Stock Requirements List
                        MD04 – Material Reports
                        MD4C - Material Reports
                        SWI11 - Tasks and Workflows
                        SWI2_DEAD - Workflow Deadline Monitoring
                        SWI2_DURA - Work Items by Duration
                        SWI2_FREQ - Workflow Items Analysis
                        SWI5 - Workflow Analysis
                        Z_OPEN_COM – FM Open Commitments
                        Z_OPEN_OB – FM Open Obligations
                        ZFSC1 – Cumulative Status by FC
                        ZFSC2 – Cumulative Status by FA
                        ZFSC3 – Cumulative Status by FP
                        ZFSC4 – Cumulative Status by FC - Summary
                        ZFSC5 – Cumulative Status by FC - Detail
                        ZFSC6 – Cumulative Status by FA Group - Summary
                        ZFSC7 – Cumulative Status by FA Group - Detail
                        ZFSC8 – Cumulative Status with Open Commitments - Summary
                        ZFSC9 – Cumulative Status with Open Commitments - Detail
                        ZFSNC1 – Non- Cumulative Status by FC
                        ZFSNC2 – Non- Cumulative Status by FA
                        ZFSNC3 – Non- Cumulative Status by FP
                        ZFSNC4 – Non- Cumulative Status by FC - Summary
                        ZFSNC5 – Non- Cumulative Status by FC - Detail
                        ZFSNC6 – Non- Cumulative Status by FC Pre-Posted
                        ZRFSC1 – Reimbursable Cumulative Status by FC
                        ZRFSC2 – Reimbursable Cumulative Status by FP
                        ZRFSNC1 – Reimbursable Non-Cumulative Status by FC
                        ZRFSNC2 – Reimbursable Non-Cumulative Status by FP
Project Time            CJ40 – Change Project Plan
Processor               CN24 – Overall Network Scheduling
                        CN25 - Create Network Individual Confirmations
                        CN27 - Collective Confirmation - Network
                        CN29 - Cancel Network Individual Confirmations
                        CN40 – Project Overview
                        CN41 - Structure Overview
                        CN41N - Structure Overview
                        CN52N - Material Reports
For Official Use Only                                                                Page 57
SAP Transaction and Command Codes Job Aid                                          GFEBS

     Role                                         Transaction Codes
                        CO24 - Missing Parts
                        MB25 - Material Reports
                        MBBS - Material Reports
                        MD04 - Display Stock Requirements List
                        MD04 – Material Reports
                        MD4C - Material Reports
                        Z_OPEN_COM – FM Open Commitments
                        Z_OPEN_OB – FM Open Obligations
                        ZFSC1 – Cumulative Status by FC
                        ZFSC2 – Cumulative Status by FA
                        ZFSC3 – Cumulative Status by FP
                        ZFSC4 – Cumulative Status by FC - Summary
                        ZFSC5 – Cumulative Status by FC - Detail
                        ZFSC6 – Cumulative Status by FA Group - Summary
                        ZFSC7 – Cumulative Status by FA Group - Detail
                        ZFSC8 – Cumulative Status with Open Commitments - Summary
                        ZFSC9 – Cumulative Status with Open Commitments - Detail
                        ZFSNC1 – Non- Cumulative Status by FC
                        ZFSNC2 – Non- Cumulative Status by FA
                        ZFSNC3 – Non- Cumulative Status by FP
                        ZFSNC4 – Non- Cumulative Status by FC - Summary
                        ZFSNC5 – Non- Cumulative Status by FC - Detail
                        ZFSNC6 – Non- Cumulative Status by FC Pre-Posted
                        ZRFSC1 – Reimbursable Cumulative Status by FC
                        ZRFSC2 – Reimbursable Cumulative Status by FP
                        ZRFSNC1 – Reimbursable Non-Cumulative Status by FC
                        ZRFSNC2 – Reimbursable Non-Cumulative Status by FP
Project Funds           CJ20 – Change Structure Planning
Approver                CJ20N - Project Builder
                        CJ41 - Display Project Cost Plan
                        CJ41 – Display Project Plan
                        CN24 – Overall Network Scheduling
                        CN40 – Project Overview
                        CN41 - Structure Overview
                        CN41N - Structure Overview
                        CN52N - Material Reports
                        CO24 - Missing Parts
                        MB25 - Material Reports
                        MBBS - Material Reports
                        MD04 - Display Stock Requirements List
                        MD04 – Material Reports
                        MD4C - Material Reports
                        Z_OPEN_COM – FM Open Commitments
                        Z_OPEN_OB – FM Open Obligations
For Official Use Only                                                                Page 58
SAP Transaction and Command Codes Job Aid                                          GFEBS

     Role                                         Transaction Codes
                        ZFSC1 – Cumulative Status by FC
                        ZFSC2 – Cumulative Status by FA
                        ZFSC3 – Cumulative Status by FP
                        ZFSC4 – Cumulative Status by FC - Summary
                        ZFSC5 – Cumulative Status by FC - Detail
                        ZFSC6 – Cumulative Status by FA Group - Summary
                        ZFSC7 – Cumulative Status by FA Group - Detail
                        ZFSC8 – Cumulative Status with Open Commitments - Summary
                        ZFSC9 – Cumulative Status with Open Commitments - Detail
                        ZFSNC1 – Non- Cumulative Status by FC
                        ZFSNC2 – Non- Cumulative Status by FA
                        ZFSNC3 – Non- Cumulative Status by FP
                        ZFSNC4 – Non- Cumulative Status by FC - Summary
                        ZFSNC5 – Non- Cumulative Status by FC - Detail
                        ZFSNC6 – Non- Cumulative Status by FC Pre-Posted
                        ZRFSC1 – Reimbursable Cumulative Status by FC
                        ZRFSC2 – Reimbursable Cumulative Status by FP
                        ZRFSNC1 – Reimbursable Non-Cumulative Status by FC
                        ZRFSNC2 – Reimbursable Non-Cumulative Status by FP
Project                 AS03 - Display Asset
Approver                CJ20 – Change Structure Planning
                        CJ20N - Project Builder
                        CJ41 - Display Project Cost Plan
                        CN24 – Overall Network Scheduling
                        CN40 – Project Overview
                        CN41 - Structure Overview
                        CN41N - Structure Overview
                        CN52N - Material Reports
                        CO24 - Missing Parts
                        MB25 - Material Reports
                        MBBS - Material Reports
                        MD04 - Display Stock Requirements List
                        MD04 – Material Reports
                        MD4C - Material Reports
                        Z_OPEN_COM – FM Open Commitments
                        Z_OPEN_OB – FM Open Obligations
                        ZFSC1 – Cumulative Status by FC
                        ZFSC2 – Cumulative Status by FA
                        ZFSC3 – Cumulative Status by FP
                        ZFSC4 – Cumulative Status by FC - Summary
                        ZFSC5 – Cumulative Status by FC - Detail
                        ZFSC6 – Cumulative Status by FA Group - Summary
                        ZFSC7 – Cumulative Status by FA Group - Detail
                        ZFSC8 – Cumulative Status with Open Commitments - Summary
                        ZFSC9 – Cumulative Status with Open Commitments - Detail
For Official Use Only                                                                Page 59
SAP Transaction and Command Codes Job Aid                                        GFEBS

     Role                                           Transaction Codes
                        ZFSNC1 – Non- Cumulative Status by FC
                        ZFSNC2 – Non- Cumulative Status by FA
                        ZFSNC3 – Non- Cumulative Status by FP
                        ZFSNC4 – Non- Cumulative Status by FC - Summary
                        ZFSNC5 – Non- Cumulative Status by FC - Detail
                        ZFSNC6 – Non- Cumulative Status by FC Pre-Posted
                        ZRFSC1 – Reimbursable Cumulative Status by FC
                        ZRFSC2 – Reimbursable Cumulative Status by FP
                        ZRFSNC1 – Reimbursable Non-Cumulative Status by FC
                        ZRFSNC2 – Reimbursable Non-Cumulative Status by FP
Project Period          CJ20N – Project Builder
End Close               CJ44 - Project Apply Overhead Actual Individual
Processor               CJ45 - Project Apply Overhead Actual Collective
                        CJ88 - Project Settlement Individual
                        CJ8G - Project Settlement Collective
                        CJB1 - Project Auto Generate Settlement Rule Collective
                        CJB2 - Project Auto Generate Settlement Rule Individual
                        KKA0 - Results Analysis Cutoff Period Change
                        KKA2 - Project Execute Results Analysis - Individual
                        KKAJ - Project Execute Results Analysis - Collective
                        KKAL - Display Log for Results Analysis
                        KKG0 - Display Cutoff Period for Results Analysis
                        Z_OPEN_COM – FM Open Commitments
                        Z_OPEN_OB – FM Open Obligations
                        ZFSC1 – Cumulative Status by FC
                        ZFSC2 – Cumulative Status by FA
                        ZFSC3 – Cumulative Status by FP
                        ZFSC4 – Cumulative Status by FC - Summary
                        ZFSC5 – Cumulative Status by FC - Detail
                        ZFSC6 – Cumulative Status by FA Group - Summary
                        ZFSC7 – Cumulative Status by FA Group - Detail
                        ZFSC8 – Cumulative Status with Open Commitments -
                        Summary
                        ZFSC9 – Cumulative Status with Open Commitments -
                        Detail
                        ZFSNC1 – Non- Cumulative Status by FC
                        ZFSNC2 – Non- Cumulative Status by FA
                        ZFSNC3 – Non- Cumulative Status by FP
                        ZFSNC4 – Non- Cumulative Status by FC - Summary
                        ZFSNC5 – Non- Cumulative Status by FC - Detail
                        ZFSNC6 – Non- Cumulative Status by FC Pre-Posted
                        ZRFSC1 – Reimbursable Cumulative Status by FC
                        ZRFSC2 – Reimbursable Cumulative Status by FP
                        ZRFSNC1 – Reimbursable Non-Cumulative Status by FC
                        ZRFSNC2 – Reimbursable Non-Cumulative Status by FP
For Official Use Only                                                              Page 60
SAP Transaction and Command Codes Job Aid                                        GFEBS


Click here to return to top.


                                        Real Property Inventory

     Role                                         Transaction Codes
Real Property           BP – Edit Business Partner
Maintainer              RE80 - RE Navigator
                        REBDBE - Process BE
                        REBDBU - Process BU
                        REBDPR - Process PR
                        REBDRO - Process RO
                        RECARS - Process Dates for All Objects
                        RECARSCN - Process Dates for Contracts
                        RECARSGEN - Generate Resubmission Dates
                        RECN - Process Contract
                        RECPA130 - Master Data Summary (BE)
                        RECPA150 - Master Data Summary (Land)
                        RECPA170 - Master Data Summary (Buildings)
                        RECPA190 - Master Data Summary (Rental Objects)
                        RECPA410 - Master Data Summary
                        REEXSET - Edit Set
                        REEXSETGENBD - Generate Sets for Usage Objects
                        REISBDOA - Info System: Object Assignment
                        REISBE - Info System: Business Entities
                        REISBP - Info System: Objects for Partner
                        REISBPBD - Info System: Partner for Master Data
                        REISBU - Info System: Buildings
                        REISCDBD - Info System: Conditions for RO
                        REISCN - Info System: Contracts
                        REISMSBD – Info System: Measurements - Mast.Data
                        REISPR - Info System: Properties
                        REISRO - Info System: Rental Objects
                        REISROOC - Info System: Occupancy of ROs
                        REORRR - Find by Objects
                        ZSPPE_CCTR_CAT_LKP – Cost Center Lookup by CAT Site
                        Spec.
                        ZSPPE_DA337 – Approval for Disposal of Buildings
                        ZSPPE_DD1354 – Trans & Accept of Military Property
                        ZSPPE_RE_INST – Maintain Installation Data Table
                        ZSPPE_RPUID_STATUS - Table for Unique Identifier Status


For Official Use Only                                                              Page 61
SAP Transaction and Command Codes Job Aid                                GFEBS

     Role                                         Transaction Codes
Real Property           RE80 - RE Navigator
Interface               REBDBE - Process BE
Processing              REBDBU - Process BU
Monitor
                        REBDPR - Process PR
                        REBDRO - Process RO
                        RECN - Process Contract
                        RECPA130 - Master Data Summary (BE)
                        RECPA150 - Master Data Summary (Land)
                        RECPA170 - Master Data Summary (Buildings)
                        RECPA190 - Master Data Summary (Rental Objects)
                        RECPA410 - Master Data Summary
                        REEXSET - Edit Set
                        REORRR - Find by Objects
                        WE02 - IDoc List
                        ZOS_IST – IDoc Status Report
Real Property           RE80 - RE Navigator
Inventory               REBDBU - Process BU
Inspection              REBDPR - Process PR
Processor
                        REORRR - Find by objects
Real Estate             RE80 - RE Navigator
Contracts/              REBDBE - Process BE
Space                   REBDBU - Process BU
Utilization
Maintainer              REBDPR - Process PR
                        REBDRO - Process RO
                        RECARS – Process Dates for All Objects
                        RECARSCN - Process Dates for Contracts
                        RECN - Process Contract
                        RECPA130 - Master Data Summary (BE)
                        RECPA150 - Master Data Summary (Land)
                        RECPA170 - Master Data Summary (Buildings)
                        RECPA190 - Master Data Summary (Rental Objects)
                        RECPA410 - Master Data Summary
                        REEXSET - Edit Set
                        REEXSETGENCN - Set Generation - Contract
                        REISBDOA - Info System: Object Assignment
                        REISBE - Info System: Business Entities
                        REISBP - Info System: Objects for Partner
                        REISBPBD - Info System: Partner for Master Data
                        REISBU - Info System: Buildings
                        REISCDBD - Info System: Conditions for RO
                        REISCN - Info System: Contracts
For Official Use Only                                                      Page 62
SAP Transaction and Command Codes Job Aid                                 GFEBS

     Role                                        Transaction Codes
                        REISMSBD – Info System: Measurements - Mast.Data
                        REISPR - Info System: Properties
                        REISRO - Info System: Rental Objects
                        REISROOC - Info System: Occupancy of ROs
                        REORRR - Find by Objects
                        XD03 – Display Customer (Centrally)
                        XK03 – Display Vendor Master
                        ZRFREISROOC - Space Utilization Report
Real Property           AR01 - Call Asset List
Viewer                  AR02 - Call Up Asset History Sheet
                        AR03 - Call Up Depreciation List
                        OARP - Call Up AM Report Overview
                        RE80 - RE Navigator
                        REBDBE - Process BE
                        REBDBU - Process BU
                        REBDPR - Process PR
                        REBDRO - Process RO
                        RECARS – Process Dates for All Objects
                        RECN - Process Contract
                        RECPA130 - Master Data Summary (BE)
                        RECPA150 - Master Data Summary (Land)
                        RECPA170 - Master Data Summary (Buildings)
                        RECPA190 - Master Data Summary (Rental Objects)
                        RECPA410 - Master Data Summary
                        REEXSET - Edit Set
                        REISBDOA – Info System: Object Assignment
                        REISBE – Info System: Business Entities
                        REISBP – Info System: Objects for Partner
                        REISBPBD – Info System: Partner for Master Data
                        REISBU – Info System: Buildings
                        REISCDBD – Info System: Conditions for RO
                        REISCN – Info System: Contracts
                        REISMSBD – Info System: Measurements – Mast Data
                        REISPR – Info System: Properties
                        REISRO – Info System: Rental Objects
                        REISROOC – Info System: Occupancy of ROs
                        REORRR - Find by Objects
                        ZSPPE_ASSET_PFOLIO – Asset Management Portfolio
                        Report
Business                BP - Edit Business Partner
Partner                 FLBPC1 - Create BP from Vendor
Maintainer              FLBPD1 - Create BP from Customer
                        XD03 – Display Customer (Centrally)
For Official Use Only                                                       Page 63
SAP Transaction and Command Codes Job Aid                                          GFEBS

     Role                                        Transaction Codes
                        XK03 – Display Vendor Master
                        ZSPPEE_UICDATA – Maintain UIC Data Table



Click here to return to top.


                                            Reimbursables

     Role                                        Transaction Codes
Accounts             FAGLL03 – G/L Account Line Items
Receivable           FB03 – Display Document
Reporter             FB04 – Display Changes
                     FBL5N – Customer Line Item Display
                     FD10N - Customer Balance Display
                     FD11 - Customer Account Analysis
                     FMFG_E_TRANS_REG - Transaction Register
                     FMFG_E_ZFZALI00 - Display a Payment Settlement List
                     FMST - Evaluation of Penalty Interest
                     GD23 - FI-SL: Local Actual Document Display
                     KSB5 - Controlling Documents: Actual.
                     S_ALR_87012077 - Vendor Information System
                     S_ALR_87012083 - List of Vendor Open Item
                     S_ALR_87012167 - Accounts Receivable Information System.
                     S_ALR_87012168 - Due Date Analysis for Open Items
                     S_ALR_87012169 - Transaction Figures: Account Balance
                     S_ALR_87012173 - List of Customer Open Items
                     S_ALR_87012174 - List of Customer Open Items
                     S_ALR_87012175 - Open Items: Customer Due Date Forec.
                     S_ALR_87012178 - Customer Open Item Analysis by Balance of Overdue Items
                     S_ALR_87012179 - Customer List
                     XD03 – Customer Display
                     ZSFI_TROR – TROR Report Interface
Customer            XD01 - Create Customer (Centrally)
Master Data         XD02 - Change Customer (Centrally)
Controller          XD03 – Display Customer (Centrally)
                    XD05 - Block Customer (Centrally)
                    ZSRM_DEBTCUS – Customer Master Extension Table

Customer            OV51 - Display of Changes for Customer
Master Data         XD03 - Display Customer (Centrally)
Reporter            XD04 - Display Customer Change (Centrally)

For Official Use Only                                                                 Page 64
SAP Transaction and Command Codes Job Aid                                       GFEBS

     Role                                        Transaction Codes
Customer            Transaction - Monitor IDocs of Customer Master Interfaces
Interface           WE02 - IDoc List
Monitor             ZOS_IST - IDoc Status Report

Customer            XD99 - Customer Master Mass Maintenance
Master Mass         ZSRM_DEBTCUS – Customer Master Extension Table
Maintainer
Customer             CJ13 - Display WBS Element
Order                CJ20N – Project Builder
Processor            CJI3 – Project Actual Costs/Revenues
                     FB03 – Display Document
                     FB50 - G/L Acct. Posting - Single Screen Trans. Document
                    Type ZW
                     FBM3 – Display Sample Document
                     FD03 – Display Customer (Accounting)
                     FMMEASURE – Change Funded Program
                     VA01 - Create Sales Order
                     VA02 - Change Sales Order
                     VA03 - Display Sales Order
                     VD03 – Display Customer (Sales)
                     ZSSC_COSTRNFR_LOAD – Cost Transfer Upload Extension from Load Template
Customer             CJ13 - Display WBS Element
Order                CJ20N – Project Builder
Approver             CJI3 – Project Actual Costs/Revenues
                     FD03 – Display Customer (Accounting)
                     FMBB- Budgeting Workbench
                     FMMEASURE – Change Funded Program
                     VA02- Change Sales Order
                     VA03 – Display Sales Order
                     VA05 – List of Sales Orders
                     VD03 – Display Customer (Sales)
Customer             DP91 - SD: Resource-Related Billing Doc.
Invoicing            DP96 - Res-Rel. Billing Collect. Proc - Sales
Processor            DP99B - Doc Flow for Res. Rel. Bill - SD
                     F.14 - Create Posting Documents from Recurring Documents
                     F.15 - Recurring Entry Document
                     FB00 - Accounting Editing Options
                     FB50 - G/L Acct. Posting - Single Screen Trans. Document Type
                     ZW
                     FBD1 - Create Recurring Document
                     FBD5 - Realize Recurring Entry
                     FBM3 – Display Sample Document
                     FBR2 - Post Document

For Official Use Only                                                             Page 65
SAP Transaction and Command Codes Job Aid                                            GFEBS

     Role                                        Transaction Codes
                        SHD0 - Transaction and Screen Variants
                        SM35 - Batch Input Monitoring
                        VA02 – Change Sales Order
                        ZSCC_COSTRNFR_LOAD – Cost Transfer Upload Extension
                        from Load Template
Customer                FMFG_IPAC - IPAC Upload File Creation Process
Billing                 SM37 - Overview of Job Selection
Processor/              SP01 - Output Controller
Certifier
                        VF01 - Create Billing Document
                        VF02 - Change Billing Document
                        VF03 - Display Billing Document
                        VF04 - Maintain Billing Due List
                        VF05 - List Billing Documents
                        VF06 - Batch Billing
                        VF11 - Cancel Billing Document
                        VF31 - Output from Billing Documents
                        VFX3 - List Blocked Billing Documents
                        ZSRM_DCAS1080_EXTRCT - Generate Outbound 1080 Batch File to
                        DCAS
Debt                    F150 - Dunning
Management              FB00 - Accounting Editing Options
Processor
                        FB01 - Post Document
                        FB02 - Change Document
                        FB08 – Reverse Document
                        FB70 - Enter Customer Invoice
                        FB75 – Customer Credit Memo
                        FBR2 – Post Document
                        FBRA – Reset Cleared Items
                        FINT - Item Interest Calculation
                        FINTSHOW - Interest Run Display
                        FMFEE – Fee Calculation
                        FMZ3 - Funds Commitment: Display InitScrn
                        MEAN- Address Maintenance
                        RTREAS_OFFSET_UPDATE - Treasury Offset Update Report
                        S_ALR_87002510 - Enter Time Interest Terms
                        S_ALR_87002678 - Enter Reference Interest Values
                        SBWP – Business Workplace
                        SP01 – Output Controller
                        XD03 - Display Customer (Centrally)
                        XK03 - Display Vendor Master
                        ZSRM_ACCTEXT – Account Receivable Extension Table
                        ZSRM_ASR - For RM-RPT-2071: Installment Plan/Amortization
                        ZSRM_DEBTCUS – Customer Master Extension Table
For Official Use Only                                                                  Page 66
SAP Transaction and Command Codes Job Aid                                             GFEBS

     Role                                         Transaction Codes
                        ZSRM_DEBTREF - Outbound Delinquent Debt to Treasury Frontend


Debt                F103- ABAP/ 4 Reporting: Trnsfr Receivables
Allowance           F104- ABAP/ 4 Reporting: Receivables Prov.
Processor           FB01 – Post Document
                    FB02 – Change Document
                    FB05 – Post with Clearing
                    FBB1 – Post Foreign Currency Valn
                    SBWP – Business Workplace
                    SM35- Batch Input: Session
Debt                F.80 – Mass Reversal of Documents
Reversal            FB08 - Reverse Document
Processor           FBRA – Reset Cleared Items
Debt Write    F-04- Post with Clearing
Off Processor F-32 – Customer Clearing
              F.80 – Mass Reversal of Documents
              FB02 – Change Document
Debt          FAGLL03 – G/L Account Line Items
Interface     FB03 – Document Display
Monitor       FBL5N – Customer Line Item
              SWI1 – Selection Report for Work Items
              SWI5 – Workflow Analysis
              WE02 – IDoc List
              WE09 – IDoc Search for Business Content
              XD03 – Customer Display
Reimbursable CJI3 - Project Actual Costs/Revenues
Reporter       GRR3 - Reimbursable Funds Status Report
               V23 - Sales Documents Blocked for Billing
               VA05 - List of Sales Orders
               Z_OPEN_COM – FM Open Commitments
               Z_OPEN_OB – FM Open Obligations
               Z_RM_FUND_STATUS – Reimbursable Fund Status Report
               ZFSC1 – Cumulative Status by FC
               ZFSC2 – Cumulative Status by FA
               ZFSC3 – Cumulative Status by FP
               ZFSC4 – Cumulative Status by FC - Summary
               ZFSC5 – Cumulative Status by FC - Detail
               ZFSC6 – Cumulative Status by FA Group - Summary
               ZFSC7 – Cumulative Status by FA Group - Detail
               ZFSC8 – Cumulative Status with Open Commitments - Summary
               ZFSC9 – Cumulative Status with Open Commitments - Detail
               ZFSNC1 – Non- Cumulative Status by FC
               ZFSNC2 – Non- Cumulative Status by FA
               ZFSNC3 – Non- Cumulative Status by FP
For Official Use Only                                                                   Page 67
SAP Transaction and Command Codes Job Aid                                           GFEBS

     Role                                        Transaction Codes
                        ZFSNC4 – Non- Cumulative Status by FC - Summary
                        ZFSNC5 – Non- Cumulative Status by FC - Detail
                        ZFSNC6 – Non- Cumulative Status by FC Pre-Posted
                        ZRFSC1 – Reimbursable Cumulative Status by FC
                        ZRFSC2 – Reimbursable Cumulative Status by FP
                        ZRFSNC1 – Reimbursable Non-Cumulative Status by FC
                        ZRFSNC2 – Reimbursable Non-Cumulative Status by FP
                        ZSRM_TAS_DSP - Display Treasury Accounting Symbol Table
TAS Table               ZSRM_TAS_DSP- Display Treasury Accounting Symbol Table
Master Data             ZSRM_TAS_MNT- Maintain Treasury Accounting Symbol Table
Controller
RM Periodic             SM35 - Batch Input Monitoring
Processor               SM37 - Overview of Job Selection
                        SP01 - Output Controller
                        VA02 - Change Sales Order
                        ZSFI_1081N – Create Internal 1081 Transfer
                        ZSFM_RPT_E_UNFILLED - Year End Closing Operations: Update Sales Order

Click here to return to top.




                                            Spending Chain

     Role                                        Transaction Codes
Material                MB5L - List of Stock Values: Balances
Master Data             ME01 – Maintain Source List
Controller              ME02 – Change Source List
                        ME03 – Display Source List
                        ME11 - Create PIR
                        ME12 - Change PIR
                        ME13 - Display PIR
                        MM01 - Create Material Master
                        MM02 - Change Material Master
                        MM03 - Display Material Master
                        MR21 - Change Price of Material
                        SBWP - Business Workplace
                        SO01 - Business Workplace: Inbox
                        ZSPPE_ASSET_PFOLIO – Asset Management Portfolio Report




For Official Use Only                                                                  Page 68
SAP Transaction and Command Codes Job Aid                                       GFEBS

     Role                                       Transaction Codes
Material                MB5L - List of Stock Values: Balances
Master Data             MM03 - Display Material Master
Interface               SBWP - Business Workplace
Processing
Monitor                 SO01 - Business Workplace: Inbox
                        WE02 - IDoc List
                        ZOS_IST - IDoc Status Report
                        ZSPPE_ASSET_PFOLIO – Asset Management Portfolio Report
Vendor                  FB03 - Display Document
Master Data             FBD3 - Display Recurring Document
Controller              FI03 - Display Bank: Initial Screen
                        FK05 - Block/Unblock Vendor
                        GD23 - FI-SL: Local Actual Document Display
                        MB5L - List of Stock Values: Balances
                        ME01 – Maintain Source List
                        ME02 – Change Source List
                        ME03 – Display Source List
                        ME11 - Create PIR
                        ME12 - Change PIR
                        ME13 - Display PIR
                        MKVZ - List of Vendors: Purchasing
                        MM03 - Display Material Master
                        S_ALR_87012082 - Vendor Balance Display
                        S_ALR_87012086 - Vendor List
                        SBWP - Business Workplace
                        SO01 - Business Workplace: Inbox
                        XD03 - Display Customer (Centrally)
                        XK01 - Create Master
                        XK02 - Change Master
                        XK03 - Display Vendor Master
                        XK04 - Process Vendor Master Data
                        XK05 - Block Vendor Centrally
                        XK06 - Flag for Deletion: Vendor
                        ZSPPE_ASSET_PFOLIO – Asset Management Portfolio Report
Vendor                  S_ALR_87012082 - Vendor Balance Display
Master Data             S_ALR_87012086 - Vendor List
Interface               SBWP - Business Workplace
Processing
                        SO01 - Business Workplace: Inbox
Monitor
                        WE02 - IDoc List
                        XD03 - Display Customer (Centrally)
                        XK03 - Display Vendor Master
                        ZOS_IST - IDoc Status Report
                        ZSPPE_ASSET_PFOLIO – Asset Management Portfolio Report
For Official Use Only                                                             Page 69
SAP Transaction and Command Codes Job Aid                                         GFEBS

     Role                                        Transaction Codes
Commitment              FB03 - Display Document
Processor               FBD3 - Display Recurring Document
                        FMY1 - Funds Precommitment: Create InitScrn
                        FMY2 - Change Funds Commitment
                        FMY3 - Funds Precommitment: Display InitScrn
                        SBWP - Business Workplace
                        SO01 - Business Workplace: Inbox
                        ZSPPE_ASSET_PFOLIO – Asset Management Portfolio Report
                        ZSSC_FCM_FP – FCM Financial Position Report
                        ZSSC_FCM_OUT - FCM Financial Position Outbound Interface
                        Trigger
Purchase                FB03 - Display Document
Requisition             FBD3 - Display Recurring Document
Processor               FMFG_PR_POST - Post Held Purchase Requisition
                        GD23 - FI-SL: Local Actual Document Display
                        IW33 - Display PM Order
                        MB03 - Display Material Document
                        MB51 – Material Document List
                        ME23N - Display Purchase Order
                        ME2J - PO List Display by Project/WBS
                        ME2K - PO List Display by Account Assignment – General
                        ME2L - PO List Display by Vendor
                        ME2N - PO List Display by PO Number
                        ME51N - Create Purchase Requisition
                        ME52N - Change Purchase Requisition
                        ME53N - Display Purchase Requisition
                        ME5A - PR List Display - General
                        ME5J - PR List Display by Project/WBS
                        ME5K - PR List Display by Account Assignment – General
                        MIR4 - Display Invoice Document
                        MIR5 - Display List of Invoice Documents
                        S_ALR_87012082 - Vendor Balance Display
                        SBWP - Business Workplace
                        SO01 - Business Workplace: Inbox
                        ZSPPE_ASSET_PFOLIO – Asset Management Portfolio Report
                        ZSSC_DD448 - Create DD448 Form
                        ZSSC_PRINT_PR – Print PR/Quote
Purchase                BD87 - Status Monitor for ALE Messages
Requisition             FB03 - Display Document
Interface               FBD3 - Display Recurring Document
Processing
Monitor                 GD23 - FI-SL: Local Actual Document Display
                        IW33 - Display PM Order
                        MB03 - Display Material Document
                        MB51 - Material Document List

For Official Use Only                                                               Page 70
SAP Transaction and Command Codes Job Aid                                       GFEBS

     Role                                       Transaction Codes
                        ME23N - Display Purchase Order
                        ME2J - PO List Display by Project/WBS
                        ME2K - PO List Display by Account Assignment – General
                        ME2L - PO List Display by Vendor
                        ME2N - PO List Display by PO Number
                        ME53N - Display Purchase Requisition
                        ME5A - PR List Display - General
                        ME5J - PR List Display by Project/WBS
                        ME5K - PR List Display by Account Assignment – General
                        MIR4 - Display Invoice Document
                        MIR5 - Display List of Invoice Documents
                        S_ALR_87012082 - Vendor Balance Display
                        SBWP - Business Workplace
                        SO01 - Business Workplace: Inbox
                        WE02 - IDoc List
                        WE09 - Search for IDoc in Database
                        ZOS_IST - IDoc Status Report
                        ZSPPE_ASSET_PFOLIO – Asset Management Portfolio Report
                        ZSSC_PRINT_PR – Print PR/Quote
                        ZSSC_SPS_PR – PR ACK NCK ALV Report
Purchase                FB03 - Display Document
Requisition             FBD3 - Display Recurring Document
Approver                GD23 - FI-SL: Local Actual Document Display
                        IW33 - Display PM Order
                        MB03 - Display Material Document
                        MB51 – Material Document List
                        ME23N - Display Purchase Order
                        ME2J - PO List Display by Project/WBS
                        ME2K - PO List Display by Account Assignment – General
                        ME2L - PO List Display by Vendor
                        ME2N - PO List Display by PO Number
                        ME52N - Change Purchase Requisition
                        ME53N - Display Purchase Requisition
                        ME5A - PR List Display - General
                        ME5J - PR List Display by Project/WBS
                        ME5K - PR List Display by Account Assignment – General
                        MIR4 - Display Invoice Document
                        MIR5 - Display List of Invoice Documents
                        S_ALR_87012082 - Vendor Balance Display
                        SBWP - Business Workplace
                        SO01 - Business Workplace: Inbox
                        ZSPPE_ASSET_PFOLIO – Asset Management Portfolio Report
                        ZSSC_DD448 - Create DD448 Form
                        ZSSC_PRINT_PR – Print PR/Quote
For Official Use Only                                                             Page 71
SAP Transaction and Command Codes Job Aid                                            GFEBS

     Role                                         Transaction Codes
                        ZSSC_SPS_PR - PR ACK NCK ALV Report
Purchase                FB03 - Display Document
Requisition             FBD3 - Display Recurring Document
Funds                   FMSK - Commitment Item Check
Certifier
                        GD23 - FI-SL: Local Actual Document Display
                        IW33 - Display PM Order
                        MB03 - Display Material Document
                        MB51 – Material Document List
                        ME23N - Display Purchase Order
                        ME2J - PO List Display by Project/WBS
                        ME2K - PO List Display by Account Assignment – General
                        ME2L - PO List Display by Vendor
                        ME2N - PO List Display by PO Number
                        ME52N - Change Purchase Requisition
                        ME53N - Display Purchase Requisition
                        ME5A - PR List Display - General
                        ME5J - PR List Display by Project/WBS
                        ME5K - PR List Display by Account Assignment – General
                        MIR4 - Display Invoice Document
                        MIR5 - Display List of Invoice Documents
                        S_ALR_87012082 - Vendor Balance Display
                        SBWP - Business Workplace
                        SO01 - Business Workplace: Inbox
                        ZSFM_FCTR_SECURITY – Funds Center Security Report
                        ZSPPE_ASSET_PFOLIO – Asset Management Portfolio Report
                        ZSSC_PRINT_PR – Print PR/Quote
                        ZSSCF_DD448 - Create DD448 Form
                        ZSSC_SPS_PR - PR ACK NCK ALV Report
Purchase                FB03 - Display Document
Order                   FBD3 - Display Recurring Document
Processor               FMFG_PO_HISTORY - Display a List of Accounting Document for Purchase
                        Orders
                        FMFG_PO_POST - Post Held Purchase Orders
                        FMZ1 - Funds Commitment: Create InitScrn
                        FMZ2 - Change Funds Commitment
                        FMZ3 - Funds Commitment: Display InitScrn
                        GD23 - FI-SL: Local Actual Document Display
                        IW33 - Display PM Order
                        MB03 - Display Material Document
                        MB51 – Material Document List
                        ME21N- Create Purchase Order

For Official Use Only                                                                   Page 72
SAP Transaction and Command Codes Job Aid                                             GFEBS

     Role                                         Transaction Codes
                        ME22N - Change Purchase Order
                        ME23N - Display Purchase Order
                        ME2J - PO List Display by Project/WBS
                        ME2K - PO List Display by Account Assignment – General
                        ME2L - PO List Display by Vendor
                        ME2N - PO List Display by PO Number
                        ME53N - Display Purchase Requisition
                        ME5A - PR List Display - General
                        ME5J - PR List Display by Project/WBS
                        ME5K - PR List Display by Account Assignment – General
                        MIR4 - Display Invoice Document
                        MIR5 - Display List of Invoice Documents
                        S_ALR_87012082 - Vendor Balance Display
                        S_ALR_87012086 - Vendor List
                        S_P99_41000147 - Funds Commitment: Display InitScrn
                        SBWP - Business Workplace
                        SO01 - Business Workplace: Inbox
                        XD03 - Display Customer (Centrally)
                        XK03 - Display Vendor Master
                        ZSPPE_ASSET_PFOLIO – Asset Management Portfolio Report
                        ZSSC_FCM_FP – FCM Financial Position Report
                        ZSSC_FCM_OUT - FCM Financial Position Outbound Interface Trigger
Purchase                BD87 - Status Monitor for ALE Messages
Order                   FB03 - Display Document
Interface
                        FBD3 - Display Recurring Document
Processing
Monitor                 FMY3 - Funds Precommitment: Display InitScrn
                        FMZ2 - Change Funds Commitment
                        FMZ3 - Funds Commitment: Display InitScrn
                        GD23 - FI-SL: Local Actual Document Display
                        IW33 - Display PM Order
                        MB03 - Display Material Document
                        MB51 – Material Document List
                        ME23N - Display Purchase Order
                        ME2J - PO List Display by Project/WBS
                        ME2K - PO List Display by Account Assignment – General
                        ME2L - PO List Display by Vendor
                        ME2N - PO List Display by PO Number
                        ME53N - Display Purchase Requisition
                        ME5A - PR List Display – General
                        ME5J - PR List Display by Project/WBS
                        ME5K - PR List Display by Account Assignment – General
For Official Use Only                                                                      Page 73
SAP Transaction and Command Codes Job Aid                                       GFEBS

     Role                                       Transaction Codes
                        MIR4 - Display Invoice Document
                        MIR5 - Display List of Invoice Documents
                        S_ALR_87012082 - Vendor Balance Display
                        S_ALR_87012086 - Vendor List
                        SBWP - Business Workplace
                        SO01 - Business Workplace: Inbox
                        WE02 - IDoc List
                        WE09 - Search for IDoc in Database
                        XD03 - Display Customer (Centrally)
                        XK03 - Display Vendor Master
                        ZOS_IST - IDoc Status Report
                        ZSPPE_ASSET_PFOLIO – Asset Management Portfolio Report
                        ZSSC_SPS_PR - PR ACK NCK ALV Report
Goods                   FB03 - Display Document
Receipt                 FBD3 - Display Recurring Document
Processor
                        GD23 - FI-SL: Local Actual Document Display
                        IW33 - Display PM Order
                        MB02 – Change Material Document
                        MB03 - Display Material Document
                        MB1A – Goods Issue
                        MB51 – Material Document List
                        MBST – Cancel Material Document
                        ME23N - Display Purchase Order
                        ME2J - PO List Display by Project/WBS
                        ME2K - PO List Display by Account Assignment – General
                        ME2L - PO List Display by Vendor
                        ME2N - PO List Display by PO Number
                        ME53N - Display Purchase Requisition
                        ME5A - PR List Display - General
                        ME5J - PR List Display by Project/WBS
                        ME5K - PR List Display by Account Assignment – General
                        MIGO – Create Goods Receipt
                        MIR4 - Display Invoice Document
                        MIR5 - Display List of Invoice Documents
                        ML81N – Service Entry Sheet
                        MM03 – Display Material Master
                        SBWP - Business Workplace
                        SO01 - Business Workplace: Inbox
                        ZSPPE_ASSET_PFOLIO – Asset Management Portfolio Report
                        ZSSC_PRINT_PR – Print PR/Quote



For Official Use Only                                                             Page 74
SAP Transaction and Command Codes Job Aid                                         GFEBS

     Role                                        Transaction Codes
Goods                   FB03 - Display Document
Receipt                 FBD3 - Display Recurring Document
Interface               GD23 - FI-SL: Local Actual Document Display
Processing
Monitor                 IW33 - Display PM Order
                        MB03 - Display Material Document
                        MB51 – Material Document List
                        ME23N - Display Purchase Order
                        ME2J - PO List Display by Project/WBS
                        ME2K - PO List Display by Account Assignment – General
                        ME2L - PO List Display by Vendor
                        ME2N - PO List Display by PO Number
                        ME53N - Display Purchase Requisition
                        ME5A - PR List Display - General
                        ME5J - PR List Display by Project/WBS
                        ME5K - PR List Display by Account Assignment – General
                        MIR4 - Display Invoice Document
                        MIR5 - Display List of Invoice Documents
                        S_ALR_87012082 - Vendor Balance Display
                        SBWP - Business Workplace
                        SO01 - Business Workplace: Inbox
                        WE02 - IDoc List
                        ZOS_IST - IDoc Status Report
                        ZSPPE_ASSET_PFOLIO – Asset Management Portfolio Report
Invoice                 F.14 - Create Posting Documents from Recurring Documents
Processor               F.15 - List of Recurring Documents
                        F.42 - Vendor Balances in Local Currency
                        F-44 - Clear Vendor
                        F-47 - Down Payment Request
                        F-48 - Post Vendor Down Payment
                        F-54 - Down Payment Clearing
                        FB02 - Change Document
                        FB03 - Display Document
                        FB08 - Reverse Document
                        FB60 - Enter Incoming Invoice (FI)
                        FB65 - Enter Incoming Credit Memo (FI)
                        FBD1 - Create Recurring Document
                        FBD2 - Change Recurring Document
                        FBD3 - Display Recurring Document
                        FBD5 - Realize Recurring Payment
                        FBL1N - Vendor Line Item Display
                        FBR2 - Post Document
For Official Use Only                                                               Page 75
SAP Transaction and Command Codes Job Aid                                           GFEBS

     Role                                        Transaction Codes
                        FBRA - Reset Cleared Items
                        FK10 - Vendor Balance Display
                        FK10N - Vendor Balance Display
                        FMDPREF – Down Payment Request
                        FMFG_E_TRANS_REG - Federal Transaction Register
                        FMRC – Penalty Reason Codes Report in ALV
                        GD23 - FI-SL: Local Actual Document Display
                        IW33 - Display PM Order
                        MB03 - Display Material Document
                        MB51 – Material Document List
                        ME23N - Display Purchase Order
                        ME2J - PO List Display by Project/WBS
                        ME2K - PO List Display by Account Assignment – General
                        ME2L - PO List Display by Vendor
                        ME2N - PO List Display by PO Number
                        ME53N - Display Purchase Requisition
                        ME5A - PR List Display - General
                        ME5J - PR List Display by Project/WBS
                        ME5K - PR List Display by Account Assignment – General
                        MIR4 - Display Invoice Document
                        MIR5 - Display List of Invoice Documents
                        MIRO - Enter Incoming Invoice (MM)
                        MR8M - Cancel Invoice Document
                        MRKO - Consignment and Pipeline Settlement
                        S_ALR_87012078 - Due Date Analysis for Open Items
                        S_ALR_87012082 - Vendor Balance Display
                        S_ALR_87012085 - Vendor Appraisal with OI Sorted List
                        S_ALR_87012086 - Vendor List
                        S_P00_07000134 – Generic Withholding Tax Reporting
                        SBWP - Business Workplace
                        SM35 - Batch Input Monitoring
                        SO01 - Business Workplace: Inbox
                        XD03 - Display Customer (Centrally)
                        XK03 - Display Vendor Master
                        ZPMT_WAREHOUSE – Payment Warehouse
                        ZSPPE_ASSET_PFOLIO – Asset Management Portfolio Report
                        ZSSC_1099_WH_LOAD – 1099 Withholding Tax Extension
                        ZSSC_CAPSRPT - Invoice Entered By Day Report
                        ZSSC_FCM_FP – FCM Financial Position Report
                        ZSSC_FLUX_MTCE - Flux Rate Table Maintenance
                        ZSSC_GET_FLUX_RATE - Get Flux Rate
                        ZSSC_INVOICE_LOAD – Invoice Upload Extension from Load Template
For Official Use Only                                                                 Page 76
SAP Transaction and Command Codes Job Aid                                           GFEBS

     Role                                        Transaction Codes
Site Invoice            F.14 - Create Posting Documents from Recurring Documents
Processor               F.15 - List of Recurring Documents
                        F.42 - Vendor Balances in Local Currency
                        F-47 - Down Payment Request
                        FB02 - Change Document
                        FB08 - Reverse Document
                        FB60 - Enter Incoming Invoice (FI)
                        FB65 - Enter Incoming Credit Memo (FI)
                        FBD1 - Create Recurring Document
                        FBD2 - Change Recurring Document
                        FBD5 - Realize Recurring Payment
                        FBL1N - Vendor Line Item Display
                        FBR2 - Post Document
                        FK10 - Vendor Balance Display
                        FK10N - Vendor Balance Display
                        FMFG_E_TRANS_REG - Federal Transaction Register
                        MB03 – Display Material Document
                        S_ALR_87012078 - Due Date Analysis for Open Items
                        S_ALR_87012082 - Vendor Balance Display
                        S_ALR_87012085 - Vendor Appraisal with OI Sorted List
                        S_ALR_87012086 - Vendor List
                        S_P00_07000134 – Generic Withholding Tax Reporting
                        XD03 - Display Customer (Centrally)
                        XK03 - Display Vendor Master
                        ZSSC_CAPSRPT - Invoice Entered By Day Report
                        ZSSC_FCM_FP – FCM Financial Position Report
                        ZSSC_INVOICE_LOAD – Invoice Upload Extension from Load Template
Invoice                 BD87 - Status Monitor for ALE Messages
Interface               F.42 - Vendor Balances in Local Currency
Processing              FB03 - Display Document
Monitor                 FBD3 - Display Recurring Document
                        FBL1N - Vendor Line Item Display
                        FK10 - Vendor Balance Display
                        FK10N - Vendor Balance Display
                        GD23 - FI-SL: Local Actual Document Display
                        IW33 - Display PM Order
                        MB03 - Display Material Document
                        MB51 – Material Document List
                        ME23N - Display Purchase Order
                        ME2J - PO List Display by Project/WBS
                        ME2K - PO List Display by Account Assignment – General
                        ME2L - PO List Display by Vendor
                        ME2N - PO List Display by PO Number
                        ME53N - Display Purchase Requisition
For Official Use Only                                                                 Page 77
SAP Transaction and Command Codes Job Aid                                       GFEBS

     Role                                        Transaction Codes
                        ME5A - PR List Display - General
                        ME5J - PR List Display by Project/WBS
                        ME5K - PR List Display by Account Assignment – General
                        MIR4 - Display Invoice Document
                        MIR5 - Display List of Invoice Documents
                        S_ALR_87012082 - Vendor Balance Display
                        S_ALR_87012086 - Vendor List
                        SBWP - Business Workplace
                        SO01 - Business Workplace: Inbox
                        WE02 - IDoc List
                        XD03 - Display Customer (Centrally)
                        XK03 - Display Vendor Master
                        ZOS_IST - IDoc Status Report
                        ZSPPE_ASSET_PFOLIO – Asset Management Portfolio Report
Site Invoice            BD87 – Status Monitor for ALE Messages
Interface               FB03 – Display Document
Processing              MB03 – Display Material Document
Monitor                 ME23N – Display Purchase Order
                        ME53N – Display Purchase Requisition
                        MIR4 – Display Invoice Document
                        MIR5 – Display List of Invoice Documents
                        S_ALR_87012086 – Vendor List
                        SBWP – Business Workplace
                        WE02 – IDoc List
GPC Account             CRS1 – Create Credit Card Master Record
Maintainer              CRS2 – Change Credit Card Master Record
                        CRS3 – Display Credit Card Master Record

Release                 MRBR – Manage Blocked Invoices
Blocked
Invoice
Processor




For Official Use Only                                                             Page 78
SAP Transaction and Command Codes Job Aid                                                  GFEBS

     Role                                            Transaction Codes
PR Approval             FB03 - Display Document
Maintainer              FBD3 - Display Recurring Document
                        GD23 - FI-SL: Local Actual Document Display
                        IW33 - Display PM Order
                        ME23N - Display Purchase Order
                        ME2J - PO List Display by Project/WBS
                        ME2K - PO List Display by Account Assignment – General
                        ME2L - PO List Display by Vendor
                        ME2N - PO List Display by PO Number
                        ME53N - Display Purchase Requisition
                        ME5A - PR List Display - General
                        ME5J - PR List Display by Project/WBS
                        ME5K - PR List Display by Account Assignment – General
                        MIR4 - Display Invoice Document
                        MIR5 - Display List of Invoice Documents
                        S_ALR_87012082 - Vendor Balance Display
                        SBWP - Business Workplace
                        SO01 - Business Workplace: Inbox
                        ZSPPE_ASSET_PFOLIO – Asset Management Portfolio Report
                        ZSSC_WF_USERS - Custom Report

GR/IR                   F.13 – Automatic Clearing without Definition of Clearing Currency
Processor               MR11 - GR/IR Account Balance
                        MR11SHOW - Carryout Goods Receipt
                        ZSPPE_ASSET_PFOLIO – Asset Management Portfolio Report
Payment                 F110 - Automatic Payment Transactions
Processor               F-47 - Down Payment Request
                        F-48 - Post Vendor Down Payment
                        F-54 - Down Payment Clearing
                        FB03 - Display Document
                        FBD3 - Display Recurring Document
                        FBL1N - Vendor Line Item Display
                        FBZ0 - Payment Proposal
                        FCH1 - Display Check
                        FMDPEF – Down Payment
                        FMFG_E_ZFZALI00 - Display a Payment Settlement List
                        FMRC - Penalty Reason Codes Report in ALV
                        FMST - Evaluation of Penalty Interest
                        GD23 - FI-SL: Local Actual Document Display
                        IW33 - Display PM Order
                        MB03 - Display Material Document
                        MB51 – Material Document List
For Official Use Only                                                                        Page 79
SAP Transaction and Command Codes Job Aid                                       GFEBS

     Role                                       Transaction Codes
                        ME23N - Display Purchase Order
                        ME2J - PO List Display by Project/WBS
                        ME2K - PO List Display by Account Assignment – General
                        ME2L - PO List Display by Vendor
                        ME2N - PO List Display by PO Number
                        ME53N - Display Purchase Requisition
                        ME5A - PR List Display - General
                        ME5J - PR List Display by Project/WBS
                        ME5K - PR List Display by Account Assignment – General
                        MIR4 - Display Invoice Document
                        MIR5 - Display List of Invoice Documents
                        S_ALR_87012078 - Due Date Analysis for Open Items
                        S_ALR_87012082 - Vendor Balance Display
                        S_ALR_87012085 - Vendor Appraisal with OI Sorted List
                        S_ALR_87012086 - Vendor List
                        S_P00_07000134 – Generic Withholding Tax Reporting
                        S_P99_41000099 - Payment List
                        SBWP - Business Workplace
                        SO01 - Business Workplace: Inbox
                        XD03 - Display Customer (Centrally)
                        XK03 - Display Vendor Master
                        ZPMT_WAREHOUSE – Payment Warehouse
                        ZSPPE_ASSET_PFOLIO – Asset Management Portfolio Report
                        ZSSC_CAPSRPT - Invoice Entered By Day Report
Payment                 F110 - Automatic Payment Transactions
Certifier               FB03 - Display Document
                        FBD3 - Display Recurring Document
                        FBL1N - Vendor Line Item Display
                        FBZ0 - Payment Proposal
                        FCH1 - Display Check
                        FMFG_E_ZFZALI00 - Display a Payment Settlement List
                        GD23 - FI-SL: Local Actual Document Display
                        IW33 - Display PM Order
                        MB03 - Display Material Document
                        MB51 – Material Document List
                        ME23N - Display Purchase Order
                        ME2J - PO List Display by Project/WBS
                        ME2K - PO List Display by Account Assignment – General
                        ME2L - PO List Display by Vendor
                        ME2N - PO List Display by PO Number
                        ME53N - Display Purchase Requisition
                        ME5A - PR List Display - General
                        ME5J - PR List Display by Project/WBS
For Official Use Only                                                             Page 80
SAP Transaction and Command Codes Job Aid                                       GFEBS

     Role                                       Transaction Codes
                        ME5K - PR List Display by Account Assignment – General
                        MIR4 - Display Invoice Document
                        MIR5 - Display List of Invoice Documents
                        S_ALR_87012082 - Vendor Balance Display
                        S_ALR_87012086 - Vendor List
                        S_P99_41000099 - Payment List
                        SBWP - Business Workplace
                        SO01 - Business Workplace: Inbox
                        XD03 - Display Customer (Centrally)
                        XK03 - Display Vendor Master
                        ZPMT_WAREHOUSE – Payment Warehouse
                        ZSPPE_ASSET_PFOLIO – Asset Management Portfolio Report
                        ZSSC_CAPSRPT - Invoice Entered By Day Report
Vendor                  FB03 - Display Document
Master Data             FBD3 - Display Recurring Document
Display                 FI01 – Create Bank: Initial Screen
                        FI02 – Change Bank: Initial Screen
                        FI03 - Display Bank: Initial Screen
                        GD23 - FI-SL: Local Actual Document Display
                        MB5L - List of Stock Values: Balances
                        ME13 - Display PIR
                        MKVZ - List of Vendors: Purchasing
                        MM03 - Display Material Master
                        S_ALR_87012082 - Vendor Balance Display
                        S_ALR_87012086 - Vendor List
                        XD03 - Display Customer (Centrally)
                        XK03 - Display Vendor Master
                        ZSPPE_ASSET_PFOLIO – Asset Management Portfolio Report
Contract                FB03 – Display Document
Viewer                  FBD3 – Display Recurring Document
                        GD23 – FI-SL: Local Actual Document Display
                        IW33 - Display PM Order
                        MB03 – Display Material Document
                        MB51 – Material Document List
                        ME23N - Display Purchase Order
                        ME2J - PO List Display by Project/WBS
                        ME2K - PO List Display by Account Assignment – General
                        ME2L - PO List Display by Vendor
                        ME2N - PO List Display by PO Number
                        ME53N - Display Purchase Requisition
                        ME5A - PR List Display – General
                        ME5J - PR List Display by Project/WBS
                        ME5K - PR List Display by Account Assignment – General
For Official Use Only                                                             Page 81
SAP Transaction and Command Codes Job Aid                                       GFEBS

     Role                                          Transaction Codes
                        MIR4 – Display Invoice Document
                        MIR5 – Display List of Invoice Documents
                        S_ALR_87012082 – Vendor Balance Display
                        S_ALR_87012086 - Vendor List
                        SBWP - Business Workplace
                        SO01 - Business Workplace: Inbox
                        WE02 - IDoc List
                        WE09 - Search for IDoc in Database
                        XK03 - Display Vendor Master
                        ZOS_IFV – IDoc Field Values Report
                        ZOS_IST – IDoc Status Report
                        ZSPPE_ASSET_PFOLIO – Asset Management Portfolio Report
                        ZSSC_CAPSRPT – Invoice Entered by Day Report
                        ZSSC_SPS_PR - PR ACK NCK ALV Report
Exchange                BD87 - Status Monitor for ALE Messages
Rate Monitor            OB08 - Change View: Currency Exchange Rates
                        WE02 - IDoc List
                        ZSSC_FLUX_MTCE - Flux Rate Table
                        Maintenance
Non-ITS                 OB08 – Change View: Currency Exchange Rates
Exchange
Rate Monitor
Default Pay         ZSSC_USER_PAY_OFFICE – Maintenance of Pay Office DoDAAC Table
Office
DoDAAC
Table
Maintainer
1099                    FB02 - Change Document
Reporter                FB03 – Display Document
                        FBL1N – Vendor Line Item Display
                        ZSSC_1099_REPORT - Outbound 1099 Report to DFAS
103 ARNG                FB03 - Display Document
Movement                FBD3 - Display Recurring Document
Type Goods
                        GD23 - FI-SL: Local Actual Document Display
Receipt
                        IW33 - Display PM Order
Processor
                        MB02 – Change Material Document
                        MB03 - Display Material Document
                        MB1A – Goods Issue
                        MB51 – Material Document List
                        MBST – Cancel Material Document
                        ME23N - Display Purchase Order
                        ME2J - PO List Display by Project/WBS
                        ME2K - PO List Display by Account Assignment – General
                        ME2L - PO List Display by Vendor
For Official Use Only                                                             Page 82
SAP Transaction and Command Codes Job Aid                                       GFEBS

     Role                                       Transaction Codes
                        ME2N - PO List Display by PO Number
                        ME53N - Display Purchase Requisition
                        ME5A - PR List Display - General
                        ME5J - PR List Display by Project/WBS
                        ME5K - PR List Display by Account Assignment – General
                        MIGO – Create Goods Receipt
                        MIR4 - Display Invoice Document
                        MIR5 - Display List of Invoice Documents
                        MM03 – Display Material Master
                        S_ALR_87012082 - Vendor Balance Display
                        S_ALR_87012086 - Vendor List
                        SBWP - Business Workplace
                        SO01 - Business Workplace: Inbox
                        ZSPPE_ASSET_PFOLIO – Asset Management Portfolio Report
105 ARNG                FB02 – Change Document
Movement                FB03 - Display Document
Type Goods
                        FBD3 - Display Recurring Document
Acceptance
Processor               GD23 - FI-SL: Local Actual Document Display
                        IW33 - Display PM Order
                        MB02 – Change Material Document
                        MB03 - Display Material Document
                        MB1A – Goods Issue
                        MB51 - List Display of Material Documents (GRs)
                        MBST – Cancel Material Document
                        ME23N - Display Purchase Order
                        ME2J - PO List Display by Project/WBS
                        ME2K - PO List Display by Account Assignment – General
                        ME2L - PO List Display by Vendor
                        ME2N - PO List Display by PO Number
                        ME53N - Display Purchase Requisition
                        ME5A - PR List Display - General
                        ME5J - PR List Display by Project/WBS
                        ME5K - PR List Display by Account Assignment – General
                        MIGO – Create Goods Receipt
                        MIR4 - Display Invoice Document
                        MIR5 - Display List of Invoice Documents
                        ML81N – Service Entry Sheet
                        MM03 – Display Material Master
                        S_ALR_87012082 - Vendor Balance Display
                        SBWP - Business Workplace
                        SO01 - Business Workplace: Inbox
                        ZPMT_WAREHOUSE – Payment Warehouse
For Official Use Only                                                             Page 83
SAP Transaction and Command Codes Job Aid                                       GFEBS

     Role                                         Transaction Codes
                        ZSPPE_ASSET_PFOLIO – Asset Management Portfolio Report

ARNG                    MB02 – Change Material Document
Service Entry           MB03 – Display Material Document
Sheet                   ML81N – Service Entry Sheet
Processor
FMS                 BD87 - Status Monitor for ALE Messages
Interface           SBWP - Business Workplace
Processing          SP01 - Output Controller
Monitor             WE02 - IDoc List
                    WE09 - Search for IDoc in Database
                    ZOS_IFV - IDoc Field Values Report
                    ZOS_IST - IDoc Status Report

Click here to return to top.




For Official Use Only                                                             Page 84

Sap transaction codes

  • 1.
    GENERAL FUND ENTERPRISEBUSINESS SYSTEM SAP Transaction and Command Codes Job Aid Prepared by Accenture June 27, 2011 Department of the Army United States of America
  • 2.
    SAP Transaction andCommand Codes Job Aid GFEBS Transaction and Command Codes Job Aid Overview Purpose: • The purpose of this job aid is to provide transaction codes and command codes that end users can use to easily navigate through the various screens of the SAP application. These transaction codes are listed by business process area and by role. • Transaction codes and command codes are slightly different: o A transaction code is a unique identifier attached to each transaction in SAP. o A command code is the text typed into the command field in order to access a transaction. It consists of the transaction code when the user is on the home screen (the SAP Easy Access Menu), or the transaction code and a prefix if the user is currently working within a transaction. • Command codes are entered into the command field as follows: o “<transaction code>” takes the user to the associated transaction if one is currently at the SAP Easy Access Menu. o “/N” ends the current transaction and returns the user to the main SAP Easy Access Menu. o “/N<transaction code>” ends the current transaction and starts the new specified transaction. o “/O” displays an overview of the open sessions. o “/O<transaction code>” starts a new session with the specified transaction while keeping the current session open. o “/I” closes the active session. o “/Nend” ends the current transaction and prompts the user to log off of SAP. Audience: • All GFEBS end users will utilize this job aid. For Official Use Only Page 2
  • 3.
    SAP Transaction andCommand Codes Job Aid GFEBS Transaction Codes by Business Process Area Click on the following Business Process Areas to be taken directly to that section: • Cost Management • Equipment & Assets • Financial Management • Funds Management • Plant Maintenance • Project System • Real Property Inventory • Reimbursables • Spending Chain Cost Management Role Transaction Codes Centralized CM-EXT-2055- Add Custom Fields to Cost Center Master Controlling CP01 - Create Business Process Master Data CP02 - Change Business Process Maintainer CP04 - Delete Business Process CP12 - Edit Business Processes CP14 - Delete Business Processes CPH1 - Create Business Process Group CPH2 - Change Business Process Group CPH4N - Change Standard Hierarchy FMDERIVER - Object Assignment - Maintenance IM01 - Create Investment Program Definition IM02 - Change Investment Program Definition IM11 - Create Investment Program Position IM12 - Change Investment Program Position IM13 - Display Investment Program Position IM22 - Change Investment Program Structure IM27 - Open New Approval Year IM27_CLOSE- Close Old Approval Year KA01 - Create Cost Element KA02 - Change Cost Element KA04 - Delete Cost Element KA06 - Create Secondary Cost Element KA24 - Delete Cost Elements For Official Use Only Page 3
  • 4.
    SAP Transaction andCommand Codes Job Aid GFEBS Role Transaction Codes KAH1- Create Cost Element Group KAH2 - Change Cost Element Group KAK2 - Change Statistical Key Figures KBH1 - Create Statistical Key Figure Group KBH2 - Change Statistical Key Figure Group KK01- Create Statistical Figure KK02- Change Statistical Figure KK03DEL - Delete Statistical Key Figures KL01 - Create Activity Type KL02 - Change Activity Type KL04 - Delete Activity Type KL14 - Delete Activity Types KLH1 - Create Activity Type Group KLH2 - Change Activity Type Group KO01 - Create Internal Order KO02 - Change Internal Order KO04 - Order Manager KOH1 - Create Order Group KOH2 - Change Order Group KOK6 - Collect. Printing of Internal Orders KOSRLIST_OR - Internal Orders: Coll. Displ. SettRu KP97 - Copy Planning for Cost Centers KP98 - Copy Actual to Plan for Cost Center KS01 - Create Cost Center KS02- Change Cost Center KS04 - Delete Cost Center KS12 - Change Cost Centers KS14- Delete Cost Centers KSH1- Create Cost Center Group KSH2- Change Cost Center Group OKEON - Change Standard Hierarchy S_ALR_87005263 - IMG Activity: SIMG_CFMENUORKAOK02 ZSCM_BIZ_PROC_LOAD - Business Process Upload Extension ZSCM_GPR_ACCT_DERIVE - GL Account Derivation Table ZSCM_HOUR_CODE - Change View "Hour Code Indicators" ZSCM_INTERN_ORD_LOAD - Internal Order Upload Extension ZSCM_TABLE_AREARESP – Check Table – Area of Responsibility ZSCM_TABLE_ATTRIB1 – Check Table - Attribute 1 ZSCM_TABLE_ATTRIB2 – Check Table - Attribute 2 ZSCM_TABLE_DMISID – Check Table - Defense Medical Sys For Official Use Only Page 4
  • 5.
    SAP Transaction andCommand Codes Job Aid GFEBS Role Transaction Codes ID ZSCM_TABLE_FCACD – Check Table - Functnl Cost Acct Code ZSCM_TABLE_FDC – Table for Custom Field FDC ZSCM_TABLE_INTIND – Check Table – Interface Indicator ZSCM_TABLE_OUID – Check Table – Organizational Unit ID ZSCM_TABLE_PRGAREA – Check Table – Program Area ZSCM_TABLE_TDA – Check Table – TDA/TOE Paragraph ZSCM_TABLE_UIC – Check Table – Unit ID Code ZSCM_CC_MAINT – Upload Cost Center Master Data Decentralized IM01 - Create Investment Program Definition Controlling IM02- Change Investment Program Definition Master Data IM11 - Create Investment Program Position Maintainer IM12 - Change Investment Program Position IM22 - Change Investment Program Structure IM27 - Open New Approval Year IM27_CLOSE- Close Old Approval Year KO01 - Create Internal Order KO02 - Change Internal Order KO04 - Order Manager KOH1 - Create Order Group KOH2 - Change Order Group KOK6 - Collect. Printing of Internal Orders ZSCM_INTERN_ORD_LOAD - Internal Order Upload Extension Cost CPP1 - Create Actual Assess. for Processes Allocation CPP2 - Change Actual Assess. for Processes Processor CPP4 - Delete Actual Assess. for Processes CPP6 - Actual Assess. Processes: Overview CPP7 - Create Plan Assess. for Processes CPP8 - Change Plan Assess. for Processes CPPA - Delete Plan Assessment for Processes CPT1 - Create Template CPT2 - Change Template CPT4 - Delete Template CPV1 - Create Actual Process Distribution CPV2 - Change Actual Distribution Process CPV4 - Delete Actual Process Distribution CPV6 - Actual Process Distribution Overview CPV7 - Create Plan Process Distribution CPV8 - Change Plan Process Distribution CPVA - Delete Plan Process Distribution KSC1 – Create Actual Indirect Acty Alloc. For Official Use Only Page 5
  • 6.
    SAP Transaction andCommand Codes Job Aid GFEBS Role Transaction Codes KSC2 – Change Actual Indirect Acty Alloc. KSC4 – Delete Actual Indirect Acty Alloc. KSC7 – Create Indirect Activity Alloc. Plan KSC8 – Change Indirect Activity Alloc. Plan KSCA – Delete Indirect Activity Alloc. Plan KSU1 - Create Actual Assessment KSU2 - Change Actual Assessment KSU4 - Delete Actual Assessment KSU7 – Create Plan Assessment KSU8 - Change Plan Assessment KSUA - Delete Plan Assessment KSUC - Plan Assessment: Overview KSV1 - Create Actual Distribution KSV2 - Change Actual Distribution KSV4 - Delete Actual Distribution KSV6 - Actual Distribution: Overview KSV7 - Create Plan Distribution KSV8 - Change Plan Distribution KSVA - Delete Plan Distribution KSVC - Plan Distribution: Overview KSW1 - Create Periodic Reposting KSW2 - Change Periodic Reposting KSW4 - Delete Periodic Reposting KZA1 - Maintain Overhead Tables KZB2 - Calculation Base: Cost Element/Origin KZB4 - Calculation Base: Cost Center/Activity Type KZE2 – Credit KZM2 - Maintain Quantity Based Overhead KZS2 - Costing Sheet KZZ2 - Maintain Percentage Overhead OKOZ - Maintain Overhead Tables S_ALR_87005104 - IMG Activity: SIMG_CFMENUORKAKZS2 Cost Plan CJZ7 - Planned Int.Calc: Indiv.CO Ord.Proc. Maintainer CJZ9 - Plan Int.Calc.: Coll.CO Order Prc. CP06 - Activity Inputs CP26 - Change Plan Data for Business Processes CP46 - Statistical Key Figures CPCB - Execute Plan Indirect Acty Alloc. CPP7 - Create Plan Assess. for Processes CPP8 - Change Plan Assess. for Processes CPPA - Delete Plan Assessment for Processes CPPB - Execute Plan Assess. for Processes CPPS - Plan Template Allocation: Process For Official Use Only Page 6
  • 7.
    SAP Transaction andCommand Codes Job Aid GFEBS Role Transaction Codes CPUA - Plan Template Allocation: Order CPUB - Plan Template Allocation: Orders CPV7 - Create Plan Process Distribution CPV8 - Change Plan Process Distribution CPVA - Delete Plan Process Distribution CPVB - Execute Plan Process Distribution CPZP - Plan Overhead: Business Processes KGP2 - Overhead Plan.: Int.Orders Ind.Pro. KGP4 - Overhead Plan.: Int.Orders Col.Pro. KO12 - Change Order Plan (Overall, Year) KO9E - Plan Settlement: Internal Order KO9G - Plan Settlement: Internal Orders KP04 - Set Planner Profile KP06 - Change CElem/Activity Input Planning KP26 - Change Plan Data for Activity Types KP46 - Change Stat. Key Figure Plan Data KPD6 - Change Stat. Key Figure Plan Data KPF6 - Change CElem/Activity Input Planning KPPS - Allocation Templ. Plan: CCtr/ATyp KSC7 - Create Indirect Activity Alloc. Plan KSC8 - Change Indirect Activity Alloc. Plan KSCA - Delete Indirect Activity Alloc. Plan KSCB - Execute Plan Indirect Acty Alloc. KSP4 - Plan Overhead: Cost Centers KSPI – Iterative Plan Price Calculation KSU7 – Create Plan Assessment KSU8 - Change Plan Assessment KSUA - Delete Plan Assessment KSUB - Execute Plan Assessment KSUC - Plan Assessment: Overview KSV7 - Create Plan Distribution KSV8 - Change Plan Distribution KSVA - Delete Plan Distribution KSVB - Execute Plan Distribution KSVC - Plan Distribution: Overview KSWB - Execute Plan Periodic Reposting ZSCM_ATBP - Activity Type and Business Process Rates Extension from Load Spreadsheet Payroll BD87 - Status Monitor for ALE Messages Interface CM-INT-2014- DCPS Unfunded Leave Processing CM-INT-2015 - DCPS GPF Monitor SM35 - Batch Input Monitoring WE02 - Display IDoc ZOS_IST - IDoc Status Report For Official Use Only Page 7
  • 8.
    SAP Transaction andCommand Codes Job Aid GFEBS Role Transaction Codes ZSCA_TT_ERR_MAINT - Maintain Error Tracking Table ZSCM_ATAAPS_OP_AGNCY - Maintain Operations Agency Table ZSCM_ATAAPS_OUTBOUND - View Outbound Cost Master Data Tables ZSCM_DISB_ALLOC – Disbursement Extension for Time Trac ZSCM_GL_ACCRUAL- Accrual GL Account Derivation Table ZSCM_GPR_ACCT_DERIVE - GL Account Derivation Table ZSCM_GPR_RECONCILE – Gross Pay Reconcilliation (GPR) ZSCM_PAYROLL_ACCRUAL - Payroll Accrual Process DTS BD87 - Reprocess Failed IDocs Interface BD87 - Status Monitor for ALE Messages Processing WE02 - Display IDoc Monitor WE09 - Search for IDoc in Database ZOS_IST - IDoc Status Report Controlling KB15N - Enter Manual Allocations Close KGI2 - Actual Overhead Calcuation: Order Processor KGI4 - Actual Overhead: Int.Ord. Coll. Proc. KO88 - Individual Processing KO8G - Act. Settlment: Int.-/Maint. Orders KOC4 - Cost Analysis KOK2 - Collective Proc. Internal Orders KOK3 – Collective Disp. Internal Orders KOK4 - Aut. Collect. Proc. Internal Orders KON1 - Actual Reval.: Int.Orders Ind.Pro. KON2 - Actual Reval.: Int.Orders Col.Pro. KOSRLIST_OR- Internal Orders: Coll. Displ. SettRu KSII - Actual Price Determination: CCtrs KSS2 - Actual Cost Splitting: Cost Centers KSU5 – Assessment KSV5 - Execute Actual Distribution KSW5 - Execute Actual Periodic Reposting RECOSEVAR – Collective Processing-Settlement of Line Items ZSCM_ACTUP - Manual Activity and Business Process Allocation Upload from Load Spreadsheet Cost ECC CP03 - Display Business Process Display and CP07 - Display Activity Inputs Reporter CP13 - Business Processes: Master Data Rep. CP27 - Display Plan Data for Business Processes CP47 - Display Statistical Key Figures CPB1 - Business Processes: Actual Line Items CPBT - Business Process Price Report CPH3 - Display Business Process Group CPH5N - Display Std Hierarchy/Business Proc. CPP3 - Display Actual Assess. for Processes For Official Use Only Page 8
  • 9.
    SAP Transaction andCommand Codes Job Aid GFEBS Role Transaction Codes CPP9 - Display Plan Assess. for Processes CPT3 - Display Template CPV3 - Display Actual Process Distribution CPV9 - Display Plan Process Distribution IM03 - Display Investment Program Definition IM23 - Display Investment Program Structure KA03 - Display Cost Element KA05 - Cost Element: Display Changes KA23 - Cost Elements: Master Data Report KABL - Order: Planning Overview KABP - Controlling Documents: Plan KAH3 - Display Cost Element Group KAK3- Display Statistical Key Figures KB16N – View Manual Cost Allocations KB23N - Display Direct Activity Allocation KB33N - Display Statistical Key Figures KB53N - Display Services KBH3 - Display Statistical Key Figure Group KK03 - Display Statistical Key Figures KK04 - Stat.Key Figures: Master Data Report KL03 - Display Activity Type KL05 - Activity type: Display Changes KL13 - Activity Types: Master Data Report KL20 - Templ. Alloc. Struct. CCTR/Acty Type KLH3 - Display Activity Type Group KO03 - Display Internal Order KO13 - Display Order Plan (Overall, Year) KOB1 - Orders: Actual Line Items KOB2 - Orders: Commitment Line Items KOBP - Orders: Plan Line Items KOC4 - Cost Analysis KOH3 - Display Order Group KOK3 - Collective Disp. Internal Orders KOK5 - Master Data List Internal Orders KOSRLIST_OR - Internal Orders: Coll. Displ. SettRu KP07 - Display Planning CElem/Act. Input KP27 - Display Plan Data for Activity Types KP47 - Display Stat. Key Figure Plan Data KPD7 - Display Stat. Key Figure Plan Data KPF7 - Display CElem./Acty Input Planning KS03 - Display Cost Center KS05 - Cost Center: Display Changes KS13 - Cost Centers: Master Data Report KSB1 - Cost Centers: Actual Line Items KSB2 - Cost Centers: Commitment Line Items For Official Use Only Page 9
  • 10.
    SAP Transaction andCommand Codes Job Aid GFEBS Role Transaction Codes KSB5 - Controlling Documents: Actual KSBL - Cost Centers: Planning overview KSBP - Cost Centers: Plan Line Items KSBT - Cost centers: Activity Prices KSC3 - Display Actual Indirect Acty Alloc. KSC9 - Display Indirect Acty Alloc. Plan KSH3 - Display Cost Center Group KSU3 - Display Actual Assessment KSU6 - Actual Assessment: Overview KSU9 - Display Plan Assessment KSV3 - Display Actual Distribution KSV9 - Display Plan Distribution KSW3 - Display Periodic Reposting OKENN - Display Standard Hierarchy RECOSEVAR - Collective Processing-Settlement of Line Items REISCOCSTACT - Report for Costs/Revenue: Period Overview – Actual (RE Cost Objects) REISCOCSTACTPLN - Report for Costs/Revenue: Plan/Actual Comparison (RE Cost Objects) REISCOCSTACTPRE - Report for Costs/Revenue: Plan/Actual Comparison Previous Year (RE Cost Objects) REISCOLIBD - Information System: Actual Line Items Master Data (RE Cost Objects) S_ALR_87005104 - IMG Activity: SIMG_CFMENUORKAKZS2 S_ALR_87012105 - Down Payment Made to Vendor Report S_ALR_87012805 - Structure and Value List for Investment Program S_ALR_87012806 - Structure and Value List for Investment Program S_ALR_87012808- Overall Plan/Annual Plan in Program Title S_ALR_87012993 - Orders: Actual/Plan/Variance S_ALR_87012994 - Orders: Current Period/Cumulative S_ALR_87012995 - List: Orders S_ALR_87012996 - List: Orders by Cost Element S_ALR_87012997 - List: Cost Elements by Order S_ALR_87012998 - Orders: Breakdown by Partner S_ALR_87012999 - Orders: Actual/Plan/Commitments S_ALR_87013000 - List: Actual/Plan/Commitments S_ALR_87013001 - Orders: Yearly Comparison - Actual S_ALR_87013002 - Orders: Quarterly Comparison - Act. S_ALR_87013003 - Orders: Period Comparison - Actual S_ALR_87013004 - Orders: Yearly Comparison - Plan S_ALR_87013005 - Orders: Quarterly Comparison - Plan S_ALR_87013006 - Orders: Period Comparison - Plan For Official Use Only Page 10
  • 11.
    SAP Transaction andCommand Codes Job Aid GFEBS Role Transaction Codes S_ALR_87013010 - Orders: Breakdown by Period S_ALR_87013011 - Orders: Actual/Plan/Price Variance S_ALR_87013012 - Orders: Actual/Plan/Consumption S_ALR_87013013 - Orders: Actual TCrcy/OCrcy/CAcrcy S_ALR_87013014 - List: Cost Elements (True Postings) S_ALR_87013015 - List: Actual Debit/Credit S_ALR_87013016 - List: Plan Debit/Credit S_ALR_87013017 - List: Actual/Plan/Var. Cumulative S_ALR_87013018 - List: Total Plan/Actual/Commitments S_ALR_87013019 - List: Budget/Actual/Commitments S_ALR_87013611 - Cost Centers: Actual/Plan/Variance S_ALR_87013612 - Area: Cost Centers S_ALR_87013613 - Range: Cost Elements S_ALR_87013614 - CCtrs: Current Period / Cumulative S_ALR_87013615 - Cost Centers: Breakdown by Partner S_ALR_87013616 - Cost Centers: Breakdown by BusTrans S_ALR_87013617 - Range: Activity Types S_ALR_87013618 - Range: Statistical Key Figures S_ALR_87013619 - Areas: Assigned Orders/WBS Elements S_ALR_87013620 - Cost Centers: Act./Plan/Commitments S_ALR_87013621 - Range: Actual/Plan/Commitments S_ALR_87013622 - Cost Centers: Projection S_ALR_87013623 - Cost Centers: Quarterly Comparison S_ALR_87013624 - Cost Ctrs: Fiscal Year Comparison S_ALR_87013625 - Cost Centers: Actual/Target/Variance S_ALR_87013626 - Range: Cost Elements S_ALR_87013627 - Cost Centers: Variances S_ALR_87013628 - Cost Centers: Splitting S_ALR_87013629 - Activity Types: Reconciliation S_ALR_87013630 - Activity Types: Plan receivers S_ALR_87013631 - Cost Centers: Rolling Year S_ALR_87013632 - Cost Centers: Average Costs S_ALR_87013633 - Cost Centers: Act./Plan/Var./Prev.Yr S_ALR_87013636 - Cost Centers: Object Comparison S_ALR_87013637 - Area: Internal Business Volume S_ALR_87013638 - Cost Centers: Curr./Cum./Total Year S_ALR_87013639 - Cost Centers: Act/Target from Summ. S_ALR_87013640 - CCtrs: Period Breakdown Actual/Plan S_ALR_87013641 - CCtrs: Period Breakdown Act./Target S_ALR_87013643 - Range: Orders S_ALR_87013645 - Stat. Key Figs: Period Breakdown For Official Use Only Page 11
  • 12.
    SAP Transaction andCommand Codes Job Aid GFEBS Role Transaction Codes S_ALR_87013646 - Activity Types: Period Breakdown S_ALR_87013647 - Activity Types: Scheduled/Plan S_ALR_87013648 - Range: Actual/Budget/Commitments ZSPPE_ASSET_PFOLIO – Asset Management Portfolio Report Payroll FB50 – G/L Acct. Posting – Single Screen Trans. Document Type ZW Corrections ZSCM_TT_ERRORS - View Partner (ATAAPS, AWPS) System Errors Processor ZSCM_DCPS_ERROR – Process DCPS Errors Cost Driver KB21N - Enter Direct Activity Allocation Controller KB24N - Reverse Direct Activity Allocation KB31N - Enter Statistical Key Figures KB34N - Reverse Statistical Key Figures KB51N - Enter Services KB54N - Reverse Activities ZSCM_ACTUP - Manual Activity and Business Process Allocation Upload from Load Spreadsheet ZSCM_STATKEY - Statistical Key Figure Value Upload from Load Spreadsheet HR Master S_AHR_61016369 - Employee List Report Data Verifier Manual Time- SM37 – Overview of Job Selection Tracking SP01 – Output Controller Extension ZSCM_MAN_TIMETRACK - Manual Time-Tracking Extension Processor Cost Driver BD87 - Reprocess Failed IDocs Interface SM35 - Batch Input Monitoring Processing WE02 - Display IDoc Monitor WE09 - Search for IDoc in Database ZOS_IST - IDoc Status Report ZSCM_OSMIS_2005 - Display Error Log for OSMIS Interface ZSCMT_DODIC_ACT – WARS DODIC Crosswalk DMLSS SP01 - Output Controller Interface WE02 - Display IDoc Processing WE09 - Search for IDoc in Database Monitor ZOS_IST - IDoc Status Report CIMS SBWP - Business Workplace Interface WE02 - Display IDoc Processing WE09- Search for IDoc in Database Monitor ZOS_IST- IDoc Status Report ZSCM_TT_ERRORS - View Partner (ATAAPS, AWPS) System Errors Cost Rate CP26 – Change Plan Data for Business Processes Maintainer KP26 – Change Plan Data for Activity Types ZSCM_ATBP – Activity Type and Business Process Rates For Official Use Only Page 12
  • 13.
    SAP Transaction andCommand Codes Job Aid GFEBS Role Transaction Codes Extension from Load Spreadsheet Cost KB15N - Enter Manual Allocations Recovery Processor EASI SBWP - Business Workplace Interface SP01- Output Controller Processing ZOS_IST - IDoc Status Report Monitor ZSCM_COST_EASI - Outbound Cost Data Interface to EASI NMP BD87 – Status Monitor for ALE Messages Interface WE02 – Display IDoc Processing WE09 – Search for IDoc in Database Monitor German LN CJ20N – Project Builder Payroll FB03 – Display Document Corrections FB50 – G/L Account Pstg: Single Screen Transaction Processor FMZ1 – Create Funds Commitment FMZ2 – Change Funds Commitment FMZ3 – Display Funds Commitment SBWP – SAP Business Workplace VA01 – Create Sales Order VA02 – Change Sales Order VA03 – Display Sales Order Z_FUND_STATUS – Fund Status Report in ECC ZSCM_FFPO_ERROR – Process Error Corrections for German LN Payroll ZSCM_FFPO_OBLG – Create Funds Commitment for German LN Payroll ZSCM_FFPO_HIST – Display FFPO History Table German LN F-04 – Post with Clearing Payroll FB02 – Change Document Processor FB03 – Display Document FB08 – Reverse Document FB50 – G/L Account Pstg: Single Screen Transaction FB65 – Enter Incoming Credit Memos FMDPREF – Enter Down Payment Request SBWP – SAP Business Workplace SM35 – Batch Input Monitoring SP01 – Output Controller WE02 – Display IDoc Z_FUND_STATUS – Fund Status Report in ECC ZSCM_FFPO_DPR – Enter Down Payment Request for German LN Payroll ZSCM_FFPO_HIST – Display FFPO History Table ZSCM_FFPO_INT – Reverse DPR and Post Actuals for German LN Payroll ZSCM_LNPAY_1081 – Generate 1081 for LN Payroll ZSSC_GET_FLUX_RATE – Maintain Budget Rate Table Italian LN FB01 – Post Document Payroll FB02 – Change Document For Official Use Only Page 13
  • 14.
    SAP Transaction andCommand Codes Job Aid GFEBS Role Transaction Codes Processor FB03 – Display Document FB08 – Reverse Document FB50 – G/L Account Pstg: Single Screen Transaction FB60 – Enter Incoming Invoices SBWP – SAP Business Workplace SP01 – Output Controller Z_FUND_STATUS – Fund Status Report in ECC ZSSC_GET_FLUX_RATE – Maintain Budget Rate Table Italian LN CJ20N – Project Builder Payroll F.81 – Mass Reversal of Accruals Obligation FB02 – Change Document and Accrual FB03 – Display Document Processor FBS1 – Enter Accrual/Deferral Document FMZ1 – Create Funds Commitment FMZ2 – Change Funds Commitment FMZ3 – Display Funds Commitment SBWP – SAP Business Workplace SP01 – Output Controller VA01 – Create Sales Order VA02 – Change Sales Order VA03 – Display Sales Order Z_FUND_STATUS – Fund Status Report in ECC ZSCM_LNP_ACCRUAL – Initiate Accrual Postings for LN Payroll ZSCM_OBLIG_UPLOAD – Initiate Obligation Postings for LN Payroll Korean LN F.81 – Mass Reversal of Accruals Payroll FB01 – Post Document Processor FB02 – Change Document FB03 – Display Document FB08 – Reverse Document FB50 – G/L Account Pstg: Single Screen Transaction FB60 – Enter Incoming Invoices SBWP – SAP Business Workplace SP01 – Output Controller Z_FUND_STATUS – Fund Status Report in ECC ZSCM_KNPS_ORGFC – Display KNP Org to Fund Custom Table ZSSC_GET_FLUX_RATE – Maintain Budget Rate Table Korean LN CJ20N – Project Builder Payroll F.81 – Mass Reversal of Accruals Obligation FB02 – Change Document and Accrual FB03 – Display Document Processor FBS1 – Enter Accrual/Deferral Document FMZ1 – Create Funds Commitment FMZ2 – Change Funds Commitment FMZ3 – Display Funds Commitment SBWP – SAP Business Workplace SP01 – Output Controller For Official Use Only Page 14
  • 15.
    SAP Transaction andCommand Codes Job Aid GFEBS Role Transaction Codes VA01 – Create Sales Order VA02 – Change Sales Order VA03 – Display Sales Order Z_FUND_STATUS – Fund Status Report in ECC ZSCM_LNP_ACCRUAL – Initiate Accrual Postings for LN Payroll ZSCM_OBLIG_UPLOAD – Initiate Obligation Postings for LN Payroll Belgian FB02 – Change Document Manual LN FB03 – Display Document Payroll FB08 – Reverse Document Processor FB50 – G/L Account Pstg: Single Screen Transaction FB60 – Enter Incoming Invoices FB65 – Enter Incoming Credit Memos FBL1N – Vendor Line Item Display SBWP – SAP Business Workplace SP02 – Output Controller Z_FUND_STATUS – Fund Status Report in ECC ZSCM_LOCL_PAYROLL – Custom Tcode for CM_EXT-2046 to access Manual Payroll Upload File screen ZSSC_COSTRNFR_LOAD – Custom Tcode for CM-EXT-4319 to access Manual Cost Transfers Upload from Load Sheet screen ZSSC_GET_FLUX_RATE – Maintain Budget Rate Table Belgian CJ20N – Project Builder Manual LN F.81 – Mass Reversal of Accruals Payroll FB02 – Change Document Obligation FB03 – Display Document and Accrual FBS1 – Enter Accrual/Deferral Document Processor FMZ1 – Create Funds Commitment FMZ2 – Change Funds Commitment FMZ3 – Display Funds Commitment SBWP – SAP Business Workplace SP02 – Output Controller VA01 – Create Sales Order VA02 – Change Sales Order VA03 – Display Sales Order Z_FUND_STATUS – Fund Status Report in ECC ZSCM_LNP_ACCRUAL – Initiate Accrual Postings for LN Payroll ZSCM_OBLIG_UPLOAD – Initiate Obligation Postings for LN Payroll Dutch FB02 – Change Document Manual LN FB03 – Display Document Payroll FB08 – Reverse Document Processor FB50 – G/L Account Pstg: Single Screen Transaction FB60 – Enter Incoming Invoices FBL1N – Vendor Line Item Display SBWP – SAP Business Workplace SP02 – Output Controller For Official Use Only Page 15
  • 16.
    SAP Transaction andCommand Codes Job Aid GFEBS Role Transaction Codes Z_FUND_STATUS – Fund Status Report in ECC ZSCM_LOCL_PAYROLL _ Custom Tcode for CM-EXT-2046 to access Manual Payroll Upload File screen ZSSC_COSTRNFR_LOAD – Custom Tcode for CM-EXT-4319 to access Manual Cost Transfers Upload from Load Sheet screen ZSSC_GET_FLUX_RATE – Maintain Budget Rate Table Dutch FBS1 – Enter Accrual/Deferral Document Manual LN FB02 – Change Document Payroll FB03 – Display Document Accrual CJ20N – Project Builder Processor VA01 – Create Sales Order VA02 – Change Sales Order VA03 – Display Sales Order SBWP – SAP Business Workplace Dutch CJ20N – Project Builder Manual LN Custom Tcode for CM-EXT-4305 – Initiate Accrual Postings for LN Payroll Payroll F.81 – Mass Reversal of Accruals Obligation FB02 – Change Document and Accrual FB03 – Display Document Processor FBS1 – Enter Accrual/Deferral Document FMZ1 – Create Funds Commitment FMZ2 – Change Funds Commitment FMZ3 – Display Funds Commitment SBWP – SAP Business Workplace SP02 – Output Controller VA01 – Create Sales Order VA02 – Change Sales Order VA03 – Display Sales Order Z_FUND_STATUS – Fund Status Report in ECC ZSCM_OBLIG_UPLOAD – Custom Tcode for CM-EXT-4306 for Manual Upload Extension to Create/Change Obligation from Load Sheet screen Click here to return to top. For Official Use Only Page 16
  • 17.
    SAP Transaction andCommand Codes Job Aid GFEBS Equipment & Assets Role Transaction Codes Asset Master AB08 - Reverse Line Items Data ABAA - Write-Down/Unplanned Depreciation Maintainer ABAVN - Asset Retirement by Scrapping ABSO - Miscellaneous Transactions ABUMN - Transfer within Company Code ABZU - Write-Up AFABN - Post Depreciation AR01 - Call Asset List AR02- Call Up Asset History Sheet AR03 - Call Up Depreciation List AS01 - Create Asset Master Record AS02- Change Asset Master Record AS06 - Delete Asset Record/Mark for Delete AS11 - Create Asset Subnumber CJ20N - Project Builder CJ88 - Settle Projects and Networks CJ8G - Actual Settlement: Projects/Networks OARP- Call Up AM Report Overview RE80 – RE Navigator S_ALR_87010173- Revaluation S_ALR_87010175 - Depreciation Posted to Cost Center S_ALR_87011963 - Asset Balances S_ALR_87011966 - Asset Balances S_ALR_87011967 - Asset Balances S_ALR_87011969 - Asset Balances S_ALR_87011990 - Asset History Sheet S_ALR_87011992- Liabilities from Leasing Agreements S_ALR_87011994 - Asset Balances S_ALR_87012004 – Depreciation S_ALR_87012006 – Depreciation S_ALR_87012008 – Depreciation S_ALR_87012011 - Write-Ups S_ALR_87012013 - Depreciation Comparison S_ALR_87012015 - Manual Depreciation S_ALR_87012018 - Depreciation and Interest S_ALR_87012048 - Asset Transactions S_ALR_87012056 - Directory of Unposted Assets For Official Use Only Page 17
  • 18.
    SAP Transaction andCommand Codes Job Aid GFEBS Role Transaction Codes S_P99_41000192 - SAP Standard Variant SM37 - Overview of Job Selection ZSPPE_ASSET_PFOLIO – Asset Management Portfolio Report ZSPPET_GEQUIP - Create/Update/Deactivate General Equipment Federal Supply Class/Federal Supply Group to Asset Class Mapping ZSPPET_MEQUIP - Create/Update/Deactivate Military Equipment Federal Supply Class/Federal Supply Group to Asset Class Mapping ZSPPET_NSN - Update the National Stock Number to Asset Class Mapping as well as the Usage Based Depreciation Data Asset AW01N – Asset Explorer Interface BD87- Status Monitor for ALE Messages Processing S_ALR_87011963 - Asset Balances Monitor SM37 - Overview of Job Selection WE02 - Display IDoc WE07- IDoc Statistics ZOS_IST - IDoc Status Report ZSPPE_ASSET_PFOLIO – Asset Management Portfolio Report ZSPPE_DELE_IDOC_ERR - Work/Evaluate PBUSE IDoc Errors Asset Close AB03 - Display Asset Document Processor AFABN - Post Depreciation AFAR - Usage Based Depreciation AFBP – Create Depreciation Posting Log AJAB – Year End Closing AJRW - Fiscal Year Change AS03 - Display Asset Master Record AUVA - FI-AA Incomplete Assets AW01N – Asset Explorer GD23 – FI-SL: Local Actual Document Display S_ALR_87011964 – Asset Balances S_ALR_87012050 – Asset Acquisitions S_ALR_87012052 – Asset Retirements SM37 - Overview of Job Selection ZSPPE_ASSET_PFOLIO – Asset Management Portfolio Report AMIS ABAVN - Asset Retirement by Scrapping Interface ABSO - Miscellaneous Transactions Processor AS01 - Create Asset Master Record AS02 - Change Asset Master Record AS06 - Delete Asset Record/Mark for Delete AS11 - Create Asset Subnumber BD87 - Status Monitor for ALE Messages S_ALR_87010173 – Revaluation S_ALR_87010175 - Depreciation Posted to Cost Center For Official Use Only Page 18
  • 19.
    SAP Transaction andCommand Codes Job Aid GFEBS Role Transaction Codes S_ALR_87011963 - Asset Balances S_ALR_87011964 – Asset Balances S_ALR_87011966 - Asset Balances S_ALR_87011967 - Asset Balances S_ALR_87011969 - Asset Balances S_ALR_87011990 - Asset History Sheet S_ALR_87011992 - Liabilities from Leasing Agreements S_ALR_87011994 - Asset Balances S_ALR_87012004 - Depreciation S_ALR_87012006 - Depreciation S_ALR_87012008 - Depreciation S_ALR_87012011 - Write-Ups S_ALR_87012013 - Depreciation Comparison S_ALR_87012015 - Manual Depreciation S_ALR_87012018 - Depreciation and Interest S_ALR_87012048 - Asset Transactions S_ALR_87012050 – Asset Acquisitions S_ALR_87012052 – Asset Retirements S_ALR_87012056 - Directory of Unposted Assets S_P99_41000192 - SAP Standard Variant SM37 - Overview of Job Selection WE02 - Display IDoc WE07 - IDoc Statistics ZSPPE_ASSET_PFOLIO – Asset Management Portfolio Report Click here to return to top. Financials Role Transaction Codes General FS00 - G/L Acct. Master Record Maintenance Ledger S_ALR_87012326 - Chart of Accounts Master Data Approver General FS00 - G/L Acct. Master Record Maintenance Ledger FS01 - Edit G/L Account Centrally Master Data S_ALR_87012308 - Display Audit Trail Maintainer S_ALR_87012326 - Chart of Accounts S_ALR_87012328 – G/L Account List For Official Use Only Page 19
  • 20.
    SAP Transaction andCommand Codes Job Aid GFEBS Role Transaction Codes General FB03 - Display Document Ledger FS00 - G/L Acct. Master Record Maintenance Master Data GD23 - FI-SL: Local Actual Document Display Reviewer S_ALR_87012326 - Chart of Accounts Journal ZSFI_JV_UPLOAD - JV Upload Tool Voucher Master Processor Journal FB02 - Change Document Voucher FB50 - G/L Acct. Posting - Single Screen Trans. Document Type Processor ZW FBV2 - Change Parked Document FBV3 - Display Parked Document FV50 - Park G/L Account Items FV53 - Display Parked G/L Account Document S_ALR_87012293 – Display of Changed Documents SHD0 - Transaction and Screen Variants ZSCC_COSTRNFR_LOAD – Cost Transfer Upload Extension from Load Template Journal FBV3 - Display Parked Document Voucher FV53 - Display Parked G/L Account Document Reviewer Journal FBV0 - Post Parked Document Voucher FBV3- Display Parked Document Approver FV53 - Display Parked G/L Account Document GRR3 - Status of Funds S_ALR_87012293 – Display of Changed Documents Journal ZSFI_JV_EDIT_ORG - Edit JV Processor ID Table Voucher ZSFI_JV_EDIT_RA - Edit JV Reviewer/Approver ID and Dollar Threshold Workflow Table Maintainer ZSFI_JV_LOAD_ORG - Load via File JV Processor ID Table ZSFI_JV_LOAD_RA - Load via File JV Reviewer/Approver Period FMAVCR01 - Display Annual Values of Control Objects Close FMAVCR02 - Display Overall Values of Control Objects Schedule SCMA- Schedule Manager Processor Period FMAVCR01 - Display Annual Values of Control Objects Close FMAVCR02 - Display Overall Values of Control Objects Schedule S_ALR_87012277 - G/L Account Balance Monitor SCMA - Schedule Manager For Official Use Only Page 20
  • 21.
    SAP Transaction andCommand Codes Job Aid GFEBS Role Transaction Codes Open_Close FMIR - Detail Maintenance of Open Int Rules Processor FMMI - Mass Maintenance of Open Intervals MMPV - Close Periods MMRV - Allow Posting to Previous Period OB52 - C FI Maintain Table T001B OKP1 - Maintain Period Lock Accounting F.81 - Reverse Accrual/Deferral Document Processor FAGL_FC_TRANS - Currency Translation of Balance. FAGL_FC_VAL- Foreign Currency Valuation FB03 - Display Document FBS1 - Enter Accrual/Deferral Document GD23 - FI-SL: Local Actual Document Display RFMFGRCN_RP1 - Reconciliation Analysis Report RFMFGRCN_RP2 - Batch Reconciliation Check ZSFI_ABNORMAL_BALRPT - Abnormal Balance Report Year End FMFG_RCV - Treasury Report on Receivable Certifier FS10N - Balance Display S_ALR_87012277 - G/L Account Balance S_KI4_38000323 - Trial Balance by SGL Level S_KI4_38000323 – Trial Balance by Fund at SGL Level S_KI4_38000325 - Trial Balance by Fund SM37 - Overview of Job Selection ZSFI_SFISREPORT- SFIS Report Year End AJAB – Year End Closing Processor AJRW - Fiscal Year Change AUVA – FI-AA Incomplete Assets CO99 - Set Status Closed F.05 – Foreign Currency Valuation F.07 – G/L: Balance Carryforward F.16 – ABAP/4 Report: G/L Bal Carryforward F.80 – Mass Reversal of Documents FAGLGVTR - G/L: Balance Carried Forward FMAVCR02 - Display Overall Values of Control Objects FMAVCREINIT – Re-initialize AVC Ledger FMBB - Budgeting Workbench FMFG_CANCELED_AP – Canceled Fund for Account Payable - FI FMFG_CANCELED_AP_MM – Canceled Fund for Account Payable - MM FMFG_CANCELED_AR - Account Receivables FMFG_E_TRANS_REG - Federal Transaction Register FMFG_YEAR_END_CLOSE - Close Budget Accounts with Residual Balance FMIR - Detail Maintenance of Open Int Rules For Official Use Only Page 21
  • 22.
    SAP Transaction andCommand Codes Job Aid GFEBS Role Transaction Codes FMMC - Close Commitment Items FMRP_RFFMEP1AX- All Postings FMSU - Change Status FMY2 – Change Funds Commitment FMZ2 - Change Funds Commitment GVTR - FI-SL: Balance Carryforward ME23N- Display Purchase Order ME52N- Change Purchase Requisition ME53N- Display Purchase Requisition MMPV - Close Periods MMRV - Allow Posting to Previous Period OB52 – C FI Maintain Table T001B OKP1 - Maintain Period Lock S_KI4_38000039 – Index of Funds S_KI4_38000325 - Trial Balance by Fund VA02 - Change Sales Order Z_OPEN_COM – FM Open Commitments Z_OPEN_OB – FM Open Obligations Z_RM_FUND_STATUS – Reimbursable Fund Status Report ZFSC1 – Cumulative Status by FC ZFSC2 – Cumulative Status by FA ZFSC3 – Cumulative Status by FP ZFSC4 – Cumulative Status by FC - Summary ZFSC5 – Cumulative Status by FC - Detail ZFSC6 – Cumulative Status by FA Group - Summary ZFSC7 – Cumulative Status by FA Group - Detail ZFSC8 – Cumulative Status with Open Commitments - Summary ZFSC9 – Cumulative Status with Open Commitments - Detail ZFSNC1 – Non- Cumulative Status by FC ZFSNC2 – Non- Cumulative Status by FA ZFSNC3 – Non- Cumulative Status by FP ZFSNC4 – Non- Cumulative Status by FC - Summary ZFSNC5 – Non- Cumulative Status by FC - Detail ZFSNC6 – Non- Cumulative Status by FC Pre-Posted ZRFSC1 – Reimbursable Cumulative Status by FC ZRFSC2 – Reimbursable Cumulative Status by FP ZRFSNC1 – Reimbursable Non-Cumulative Status by FC ZRFSNC2 – Reimbursable Non-Cumulative Status by FP ZSFI_DDRS_TRL_BAL2 - DDRS Trial Balance Exact Program ZSFI_SFISREPORT - SFIS Report ZSFM_RPT_E_UNFILLED – Year End Closing Operations: Update Sales Order For Official Use Only Page 22
  • 23.
    SAP Transaction andCommand Codes Job Aid GFEBS Role Transaction Codes Balance FAGLGVTR - G/L: Balance Carried Forward Forward FB03 - Display Document Processor GD23 - FI-SL: Local Actual Document Display GVTR - FI-SL: Balance Carryforward Financial FAGLL03 – G/L Account Line Items Reviewer FB03 - Display Document FBL1N - Vendor Line Item Display FBL3N - G/L Account Line Items FBV3 - Display Parked Document FMB_B01 – Budget View by Document Type FMEDDW - Drilldown For Budget Entry Documents FMFG_E_TRANS_REG - Federal Transaction Register FMFG_E_ZFZALI00 - Display a Payment Settlement List FMFG_RCV - Treasury Report on Receivable FMRP_RFFMEP1AX – All Postings FMRP_RFFMEP1FX – FI Posting. Individual Items According to Document Number. FMST - Evaluation of Penalty Interest FMY3 - Display Funds Precommitment FMZ3 - Display Funds Commitment FS10N - Balance Display GD23 - FI-SL: Local Actual Document Display GRR3 - Status of Funds ME23N - Display Purchase Order ME2K - PO List Display by Account Assignment – General ME2L - PO List Display by Vendor ME2N - PO List Display by PO Number ME53N - Display Purchase Requisition ME5A - PR List Display - General RFMFGRCN_RP1 - Reconciliation Analysis Report RFMFGRCN_RP2 - Batch Reconciliation Check S_ALR_87012077 - Vendor Information System S_ALR_87012082 – Vendor Balance Display S_ALR_87012083 - List of Vendor Open Item S_ALR_87012086 – Vendor List S_ALR_87012105 - Down Payment Made to Vendor Report S_ALR_87012167 - Accounts Receivable Information System S_ALR_87012174 – List of Customer Open Items S_ALR_87012277 - G/L Account Balance S_ALR_87012308 - Display Audit Trail S_ALR_87012326 - Chart of Accounts S_KI4_38000323 - Trial Balance by Fund at SGL level For Official Use Only Page 23
  • 24.
    SAP Transaction andCommand Codes Job Aid GFEBS Role Transaction Codes S_KI4_38000323 – Trial Balance by SGL Level S_KI4_38000325 - Trial Balance by Fund S_P99_41000099 – Payment List S_P99_41000147 - Funds Commitment: Display InitScrn SE16N - Edit Table SM37 - Simple Overview of Job Selection VF03 - Display Billing Document WE09 - Search for IDoc in Database Z_OPEN_COM – FM - Open Commitments Z_OPEN_OB – FM - Open Obligations ZFSC1 – Cumulative Status by FC ZFSC2 – Cumulative Status by FA ZFSC3 – Cumulative Status by FP ZFSC4 – Cumulative Status by FC - Summary ZFSC5 – Cumulative Status by FC - Detail ZFSC6 – Cumulative Status by FA Group - Summary ZFSC7 – Cumulative Status by FA Group - Detail ZFSC8 – Cumulative Status with Open Commitments - Summary ZFSC9 – Cumulative Status with Open Commitments - Detail ZFSNC1 – Non- Cumulative Status by FC ZFSNC2 – Non- Cumulative Status by FA ZFSNC3 – Non- Cumulative Status by FP ZFSNC4 – Non- Cumulative Status by FC - Summary ZFSNC5 – Non- Cumulative Status by FC - Detail ZFSNC6 – Non- Cumulative Status by FC Pre-Posted ZRFSC1 – Reimbursable Cumulative Status by FC ZRFSC2 – Reimbursable Cumulative Status by FP ZRFSNC1 – Reimbursable Non-Cumulative Status by FC ZRFSNC2 – Reimbursable Non-Cumulative Status by FP ZOS_IFV - IDoc Field Values Report ZSCM_DCPS_ERROR – Process DCPS Errors ZSFI_ABNORMAL_BALRPT - Abnormal Balance Report ZSFI_DCAS_ID – DCAS ID Table ZSFI_REP_1081 – Query for 1081 Table ZSFI_SFISREPORT - SFIS Report External FB03 - Display Document Information FMFG_RCV - Treasury Report on Receivable Monitor GD23 - FI-SL: Local Actual Document Display S_KI4_38000323 - Trial Balance by SGL Level S_KI4_38000325 - Trial Balance by Fund SM37 - Overview of Job Selection ZSFI_DDRS_TRL_BAL - DDRS layout file ZSFI_DDRS_TRL_BAL2 – DDRS Trial Balance Exact Program ZSFI_SFIS_TRLBAL_EXT - SFIS Trial Balance For Official Use Only Page 24
  • 25.
    SAP Transaction andCommand Codes Job Aid GFEBS Role Transaction Codes ZSFI_SFISREPORT - SFIS Report ZSFI_TROR - TROR Report Interface ZSFI_TROR_DDRS – DDRS Trial Balance Extract Program Cash FAGLL03 - G/L Account Line Items Balancing FB03 - Display Document Approver FBL1N - Vendor Line Item Display FBL5N - Customer Line Item FMRP_RFFMEP1AX – All Postings FMY3 - Display Funds Precommitment FMZ3 - Display Funds Commitment GD23 - FI-SL: Local Actual Document Display ME23N - Display Purchase Order ME2K - PO List Display by Account Assignment – General ME2L - PO List Display by Vendor ME2N - PO List Display by PO Number ME53N - Display Purchase Requisition ME5A - PR List Display - General S_ALR_87012083 - List of Vendor Open Item S_ALR_87012105 - Down Payment Made to Vendor Report S_P99_41000147 - Funds Commitment: Display InitScrn SE16N - Edit Table VF03 - Display Billing Document ZOS_IFV - IDoc Field Values Report ZOS_IST - IDoc Status Report ZSFI_Auto_Sweep – Auto Sweep Program ZSSC_DCAS1081_EXTRCT – 1081 Outbound Interface Cash F-03 – Clear G/L Account Balancing F-04 - Post with Clearing Processor F-28 – Collections F-44 - Clear Vendor FAGLL03 - G/L Account Line Items FB01 - Post Document FB02 – Change Document FB03 - Display Document FB08 - Reverse Document FBL1N - Vendor Line Item Display FBL3N - G/L Account Line Items FBL5N - Customer Line Item FMEDDW - Drilldown for Budget Entry Documents FMFG_E_ZFZALI00 - Display a Payment Settlement List For Official Use Only Page 25
  • 26.
    SAP Transaction andCommand Codes Job Aid GFEBS Role Transaction Codes FMRP_RFFMEP1AX – All Postings FMST - Evaluation of Penalty Interest FMY3 - Display Funds Precommitment FMZ3 - Display Funds Commitment GD23 - FI-SL: Local Actual Document Display ME23N - Display Purchase Order ME2K - PO List Display by Account Assignment – General ME2L - PO List Display by Vendor ME2N - PO List Display by PO Number ME53N - Display Purchase Requisition ME5A - PR List Display - General S_ALR_87012077 - Vendor Information System S_ALR_87012083 - List of Vendor Open Item S_ALR_87012105 - Down Payment Made to Vendor Report S_ALR_87012167 - Accounts Receivable Information System. S_ALR_87012174 - List of Customer Open Items S_P99_41000147 - Funds Commitment: Display InitScrn SE16N - Edit Table VF03 - Display Billing Document WE09 - Search for IDoc in Database ZOS_IFV - IDoc Field Values Report ZOS_IST - IDoc Status Report ZSFI_1081 - Post 1081 Adjustment transaction ZSFI_Auto_Sweep – Auto Sweep Program ZSFI_DCAS_ID – DCAS ID Table ZSFI_REP_1081 – Query for 1081 Table LMP FB03 - Display Document Depreciation Reviewer Cross-Code ZSFI_LOAXREFLOAD – Load Data File into LOA XREF Tables Maintainer ZSFI_LOA – Maintain Table ZSFIT_LOAXREF Payment BD87 - Status Monitor for ALE Messages Interface FB03 - Display Document Processing FBD3 - Display Recurring Document Monitor FBL1N - Vendor Line Item Display FBZ0 - Payment Proposal GD23 - FI-SL: Local Actual Document Display IW33 - Display PM Order MB03 - Display Material Document MB51 – Material Document List ME23N - Display Purchase Order For Official Use Only Page 26
  • 27.
    SAP Transaction andCommand Codes Job Aid GFEBS Role Transaction Codes ME2J - PO List Display by Project/WBS ME2K - PO List Display by Account Assignment – General ME2L - PO List Display by Vendor ME2N - PO List Display by PO Number ME53N - Display Purchase Requisition ME5A - PR List Display - General ME5J - PR List Display by Project/WBS ME5K - PR List Display by Account Assignment – General MIR4 - Display Invoice Document MIR5 - Display List of Invoice Documents S_ALR_87012082 - Vendor Balance Display S_ALR_87012086 - Vendor List S_P99_41000099 - Payment List SBWP - Business Workplace SM37 - Overview of Job Selection SO01 - Business Workplace: Inbox WE02 - IDoc List XK03 - Display Vendor Master ZOS_IST - IDoc Status Report Click here to return to top. Funds Management Role Transaction Codes Funds BD87 - Status Monitor for ALE Messages Management FB03 – Display Document Interface FM_Function – FM: Functional Area Processing FM_Sets_FIPEX3 – Display Commitment Item Group Monitor FM_Sets_Function3 – Display Functional Area Group FM5S – FIFM: Display Fund FM6S – FIFM: Display Application of Funds FMBB – Budgeting Workbench FMCIC – Display Commitment Item FMEDD – Display Entry Document FMMEASURED – Funded Program Display FMSC – Display Funds Center in FM area FMSE – Display Funds Center Hierarchy WE02 - IDoc List Z_OPEN_COM – FM - Open Commitments Z_OPEN_OB – FM - Open Obligations ZFSC1 – Cumulative Status by FC For Official Use Only Page 27
  • 28.
    SAP Transaction andCommand Codes Job Aid GFEBS Role Transaction Codes ZFSC2 – Cumulative Status by FA ZFSC3 – Cumulative Status by FP ZFSC4 – Cumulative Status by FC - Summary ZFSC5 – Cumulative Status by FC - Detail ZFSC6 – Cumulative Status by FA Group - Summary ZFSC7 – Cumulative Status by FA Group - Detail ZFSC8 – Cumulative Status with Open Commitments - Summary ZFSC9 – Cumulative Status with Open Commitments - Detail ZFSNC1 – Non- Cumulative Status by FC ZFSNC2 – Non- Cumulative Status by FA ZFSNC3 – Non- Cumulative Status by FP ZFSNC4 – Non- Cumulative Status by FC - Summary ZFSNC5 – Non- Cumulative Status by FC - Detail ZFSNC6 – Non- Cumulative Status by FC Pre-Posted ZOS_IST - IDoc Status Report ZRFSC1 – Reimbursable Cumulative Status by FC ZRFSC2 – Reimbursable Cumulative Status by FP ZRFSNC1 – Reimbursable Non-Cumulative Status by FC ZRFSNC2 – Reimbursable Non-Cumulative Status by FP ZSBF_AFP_RETRACTION – AFP Retraction ZSFM_ASN_MAINT – Update Period of Availability Z-Table ZSFM_POA_MAINT – Update Allotment Serial Number Table ZSFM_THRESHOLD – Update Threshold Table ECC Budget FB03 - Display Document Reporter FM_Function - FM: Functional Area FM_Sets_FIPEX3 - Display Commitment Item Group FM_Sets_Function3 - Display Functional Area Group FM5S - FIFM: Display Fund FM6S - FIFM: Display Application of Funds FMAVCR02 - Display Overall Values of Control Objects FMCIC - Display Commitment Item FMMEASURED - Funded Program: Display FMSC - Display Funds Center in FM Area FMSE - Display Funds Center Hierarchy ME23N - Display Purchase Order ME53N - Display Purchase Requisition ME5A - PR List Display - General S_ALR_87012105 - Down Payment Made to Vendor Report Z_FUND_STATUS – Status of Funds Report - Cumulative Z_OPEN_COM – FM Open Commitments Z_OPEN_OB – FM Open Obligations ZFSC1 – Cumulative Status by FC ZFSC2 – Cumulative Status by FA ZFSC3 – Cumulative Status by FP For Official Use Only Page 28
  • 29.
    SAP Transaction andCommand Codes Job Aid GFEBS Role Transaction Codes ZFSC4 – Cumulative Status by FC - Summary ZFSC5 – Cumulative Status by FC - Detail ZFSC6 – Cumulative Status by FA Group - Summary ZFSC7 – Cumulative Status by FA Group - Detail ZFSC8 – Cumulative Status with Open Commitments - Summary ZFSC9 – Cumulative Status with Open Commitments - Detail ZFSNC1 – Non- Cumulative Status by FC ZFSNC2 – Non- Cumulative Status by FA ZFSNC3 – Non- Cumulative Status by FP ZFSNC4 – Non- Cumulative Status by FC - Summary ZFSNC5 – Non- Cumulative Status by FC - Detail ZFSNC6 – Non- Cumulative Status by FC Pre-Posted ZRFSC1 – Reimbursable Cumulative Status by FC ZRFSC2 – Reimbursable Cumulative Status by FP ZRFSNC1 – Reimbursable Non-Cumulative Status by FC ZRFSNC2 – Reimbursable Non-Cumulative Status by FP ZSFM_SFISLOAREPORT – SFIS LOA Report Funds FMBB - Budgeting Workbench Management FMEDDW - Drilldown for Budget Entry Documents Maintainer FMMEASURE - Change Funded Program VA03 - Display Sales Order Z_FUND_STATUS - Status of Funds Report – Cumulative Z_OPEN_COM – FM Open Commitments Z_OPEN_OB – FM Open Obligations ZFSC1 – Cumulative Status by FC ZFSC2 – Cumulative Status by FA ZFSC3 – Cumulative Status by FP ZFSC4 – Cumulative Status by FC - Summary ZFSC5 – Cumulative Status by FC - Detail ZFSC6 – Cumulative Status by FA Group - Summary ZFSC7 – Cumulative Status by FA Group - Detail ZFSC8 – Cumulative Status with Open Commitments - Summary ZFSC9 – Cumulative Status with Open Commitments - Detail ZFSNC1 – Non- Cumulative Status by FC ZFSNC2 – Non- Cumulative Status by FA ZFSNC3 – Non- Cumulative Status by FP ZFSNC4 – Non- Cumulative Status by FC - Summary ZFSNC5 – Non- Cumulative Status by FC - Detail ZFSNC6 – Non- Cumulative Status by FC Pre-Posted ZRFSC1 – Reimbursable Cumulative Status by FC ZRFSC2 – Reimbursable Cumulative Status by FP ZRFSNC1 – Reimbursable Non-Cumulative Status by FC ZRFSNC2 – Reimbursable Non-Cumulative Status by FP For Official Use Only Page 29
  • 30.
    SAP Transaction andCommand Codes Job Aid GFEBS Role Transaction Codes Funds FMBB - Budgeting Workbench Management FMEDDW - Drilldown for Budget Entry Documents Approver FMMEASURE - Change Funded Program VA03 - Display Sales Order Z_FUND_STATUS - Status of Funds Report – Cumulative Z_OPEN_COM – FM Open Commitments Z_OPEN_OB – FM Open Obligations ZFSC1 – Cumulative Status by FC ZFSC2 – Cumulative Status by FA ZFSC3 – Cumulative Status by FP ZFSC4 – Cumulative Status by FC - Summary ZFSC5 – Cumulative Status by FC - Detail ZFSC6 – Cumulative Status by FA Group - Summary ZFSC7 – Cumulative Status by FA Group - Detail ZFSC8 – Cumulative Status with Open Commitments - Summary ZFSC9 – Cumulative Status with Open Commitments - Detail ZFSNC1 – Non- Cumulative Status by FC ZFSNC2 – Non- Cumulative Status by FA ZFSNC3 – Non- Cumulative Status by FP ZFSNC4 – Non- Cumulative Status by FC - Summary ZFSNC5 – Non- Cumulative Status by FC - Detail ZFSNC6 – Non- Cumulative Status by FC Pre-Posted ZRFSC1 – Reimbursable Cumulative Status by FC ZRFSC2 – Reimbursable Cumulative Status by FP ZRFSNC1 – Reimbursable Non-Cumulative Status by FC ZRFSNC2 – Reimbursable Non-Cumulative Status by FP Funds FB03 - Display Document Execution FB50 - G/L Acct. Posting - Single Screen Trans. Document Type ZW Controller FMBB - Budgeting Workbench FMEDDW - Drilldown for Budget Entry Documents FMZ3 - Display Funds Commitment MB03 - Display Material Document ME23N - Display Purchase Order VA03 - Display Sales Order Z_FUND_STATUS - Status of Funds Report - Cumulative Z_OPEN_COM – FM Open Commitments Z_OPEN_OB – FM Open Obligations ZFSC1 – Cumulative Status by FC ZFSC2 – Cumulative Status by FA ZFSC3 – Cumulative Status by FP ZFSC4 – Cumulative Status by FC - Summary ZFSC5 – Cumulative Status by FC - Detail ZFSC6 – Cumulative Status by FA Group - Summary ZFSC7 – Cumulative Status by FA Group - Detail ZFSC8 – Cumulative Status with Open Commitments - Summary For Official Use Only Page 30
  • 31.
    SAP Transaction andCommand Codes Job Aid GFEBS Role Transaction Codes ZFSC9 – Cumulative Status with Open Commitments - Detail ZFSNC1 – Non- Cumulative Status by FC ZFSNC2 – Non- Cumulative Status by FA ZFSNC3 – Non- Cumulative Status by FP ZFSNC4 – Non- Cumulative Status by FC - Summary ZFSNC5 – Non- Cumulative Status by FC - Detail ZFSNC6 – Non- Cumulative Status by FC Pre-Posted ZRFSC1 – Reimbursable Cumulative Status by FC ZRFSC2 – Reimbursable Cumulative Status by FP ZRFSNC1 – Reimbursable Non-Cumulative Status by FC ZRFSNC2 – Reimbursable Non-Cumulative Status by FP ZSFM_DISTBUDGET – Inbound Distribute Budget Interface ZSFM_THRESHOLD – Update Threshold Table ZSSC_FCM_FP - FCM Financial Position Report Funds FM_Function - FM: Functional Area Management FM_Sets_FIPEX1 - Create Commitment Item Group Master Data FM_Sets_FIPEX2 - Change Commitment Item Group Maintainer FM_Sets_Function1 - Create Functional Area Group FM_Sets_Function2 - Change Functional Area Group FM4M – Directory of Functional Areas FM5I - FIFM: Create Fund FM5M – Index of Funds FM5U - FIFM: Change Fund FM6I - FIFM: Create Application of Funds FM6M – Index of Application of Funds FM6U - FIFM: Change Application of Funds FM7M – Directory of Funded Programs FMCIA - Edit Commitment Item FMDERIVATIONANALYSIS – Analysis Report on FM Derivations FMDERIVER - Object Assignment - Maintenance FMMEASURE - Change Funded Program FMMEASURED - Funded Program: Display FMSA - Create Funds Center in FM Area FMSB - Change Funds Center in FM Area FMWHEREUSED – Where-Used FM Assignments FRFNSUB1 - PPB BOS Transaction to Pull Data from Legacy System to GFEBS FRFNSUB2 - PPB BOS Transaction to Pull Data from Legacy System to GFEBS FRFNSUB3 - PPB BOS Transaction to Pull Data from Legacy System to GFEBS WE02 - IDoc List Z_FUND_STATUS – Status of Funds Report - Cumulative Z_OPEN_COM – FM Open Commitments Z_OPEN_OB – FM Open Obligations For Official Use Only Page 31
  • 32.
    SAP Transaction andCommand Codes Job Aid GFEBS Role Transaction Codes ZFSC1 – Cumulative Status by FC ZFSC2 – Cumulative Status by FA ZFSC3 – Cumulative Status by FP ZFSC4 – Cumulative Status by FC - Summary ZFSC5 – Cumulative Status by FC - Detail ZFSC6 – Cumulative Status by FA Group - Summary ZFSC7 – Cumulative Status by FA Group - Detail ZFSC8 – Cumulative Status with Open Commitments - Summary ZFSC9 – Cumulative Status with Open Commitments - Detail ZFSNC1 – Non- Cumulative Status by FC ZFSNC2 – Non- Cumulative Status by FA ZFSNC3 – Non- Cumulative Status by FP ZFSNC4 – Non- Cumulative Status by FC - Summary ZFSNC5 – Non- Cumulative Status by FC - Detail ZFSNC6 – Non- Cumulative Status by FC Pre-Posted ZRFSC1 – Reimbursable Cumulative Status by FC ZRFSC2 – Reimbursable Cumulative Status by FP ZRFSNC1 – Reimbursable Non-Cumulative Status by FC ZRFSNC2 – Reimbursable Non-Cumulative Status by FP ZSFM_ASN – Table Maintenance for ZSFMT_PBAS_ASN ZSFM_ASN_MAINT – Update Period of Availability Z-Table ZSFM_POA – Upload Data for ZSFMT_PBAS_POA ZSFM_POA_MAINT - Update Allotment Serial Number Table Click here to return to top. Plant Maintenance Role Transaction Codes Work CA85 – Replace Work Center Notification IW21 - Create PM Notification - General Processor IW22 - Change PM Notification IW28 - Change Notifications IW30 - Notification List (Multi-Level) IW32 – Change Order IW34 - PM Order for PM Notification IW36 - Create PM Sub-Order IW37N – Change Orders and Operations IW38 - Change PM Orders IW3D - Print Order IW41 - Enter PM Order Confirmation For Official Use Only Page 32
  • 33.
    SAP Transaction andCommand Codes Job Aid GFEBS Role Transaction Codes IW42 - Overall Completion Confirmation IW44 - PM Order Collective Confirmation Order CN41 - Structure Overview Report Maintainer I_GRAPH_MONITOR - Monitor for Jobs IE02 – Change Equipment IE03 - Display Equipment IE05 – Change Equipment: Equipment Selection IH01 - Functional Location Structural Display IK07 - Display Measuring Points IK11 - Create Measurement Document IK12 - Change Measurement Document IK13 - Display Measurement Document IK14 - Collective Entry of MeasDocuments IK16 - Collective Entry of MeasDocuments IK17 - Display Measurement Documents IK18 - Change Measurement Documents IK21 - Collective Entry of MeasDocuments IK22 - Collective Entry of MeasDocuments IK34 - Collective Entry of MeasDocuments IL07 - Functional Location List (Multi-Level) IPMD - Maintain/Display Permits IR01 – Create Work Center IR02 – Change Work Center IW13 - Material Where-used List IW22 - Change PM Notification IW23 - Display PM Notification IW28 - Change Notifications IW29 - Display Notifications IW30 - Notification List (Multi-Level) IW32 - Change Order IW33 - Display PM Order IW37 - Change Operations IW37N – Change Orders and Operations IW38 - Change PM Orders IW39 - Display PM orders IW3D - Print Order IW3K - Change Order Component List IW3L - Display Order Component List IW40 - Display Orders (Multi-Level) IW41 - Enter PM Order Confirmation For Official Use Only Page 33
  • 34.
    SAP Transaction andCommand Codes Job Aid GFEBS Role Transaction Codes IW42 - Overall Completion Confirmation IW43 - Display PM Order Confirmation IW44 - PM Order Collective Confirmation IW48 – Confirmation Using Operation List IW49 - Display Operations IW70 - Orders Overall Network Scheduling KGI2 - Actual Overhead Calculation: Order KGI4 - Actual Overhead Calculation: Internal/Maintenance Orders KO8G - Act. Settlment: Int.-/Maint. Orders MIGO - Goods Movement S_ALR_87013421 - Display Measurement Reading Entry List ZSSC_PRINT_PR – Print PR/Quote Order CJ2B - Project Scheduling Board Approver CM01 - Cap. Planning; Work Center Load CM02 - Capac. Planning; Work Center Orders CM03 - Capac. Planning; Work Center Pool CM04 - Capac. Planning; Work Center Backlog CM05 - Capacity Plan; Work Center Overload CM07 - Cap. Planning: Variable Access CM24 - Capacity Leveling: PM Indiv. Tab. CM25 - Capacity Leveling: Variable CM30 - Cap. Leveling: PM Indiv. Cap. Graph. CM33 - Cap. Leveling: PM Work Cntr. Graphic CM34 - Cap. Leveling: PM Work Cntr. Tab. CM50 – Capacity Level: SFC Work Cntr List CM51 – Cap. Level: SFC Individual Cap. List CM52 – Cap. Leveling: SFC Orders List CN41 - Structure Overview Report CO99 - Set Status "Closed" COGI - Processing Goods Movemnts w. Errors IA01 - Create Equipment Task List IA02 - Change Equipment Task List IA03 - Display Equipment Task List IA05 - Create General Task List IA06 - Change Material Maintenance Task List IA11 - Create Functional Location Task List IA12 - Change Functional Location Task List IE02 – Change Equipment IE03 - Display Equipment IE05 – Change Equipment: Equipment Selection For Official Use Only Page 34
  • 35.
    SAP Transaction andCommand Codes Job Aid GFEBS Role Transaction Codes IH01 - Functional Location Structural Display IK07 - Display Measuring Points IK11 - Create Measurement Document IK12 - Change Measurement Document IK13 - Display Measurement Document IK16 - Collective Entry of MeasDocuments IK17 - Display Measurement Documents IK18 - Change Measurement Documents IK21 - Collective Entry of MeasDocuments IK22 - Collective Entry of MeasDocuments IK34 - Collective Entry of MeasDocuments IK41 - Display MeasDocs From Archive IL07 - Functional Location List (Multi-Level) IP19 - Maintenance Scheduling Overview IP24 - Scheduling Overview List Form IP30 - MaintSchedule Date Monitoring IP31 - Maintenance Plan Cost Display IPMD - Maintain/Display Permits IQS8 - Worklist: Notifications (General) IQS9 - Worklist: Tasks (General) IW12 - Document Flow List IW13 - Material Where-used List IW21 - Create PM Notification - General IW22 - Change PM Notification IW23 - Display PM Notification IW28 - Change Notifications IW29 - Display Notifications IW30 - Notification List (Multi-Level) IW31 -Create Order IW32 - Change Order IW33 - Display PM Order IW34 - PM Order for PM Notification IW36 - Create PM Sub-Order IW37 - Change Operations IW37N - Change Orders and Operations IW38 - Change PM Orders IW39 - Display PM Orders IW3D - Print Order IW3K - Change Order Component List For Official Use Only Page 35
  • 36.
    SAP Transaction andCommand Codes Job Aid GFEBS Role Transaction Codes IW3L - Display Order Component List IW3M - Lists of Good Movements for Order IW40 - Display Orders (Multi-Level) IW41 - Enter PM Order Confirmation IW42 - Overall Completion Confirmation IW43 - Display PM Order Confirmation IW44 - PM Order Collective Confirmation IW45 - Cancel PM Order Confirmation IW47 - Confirmation List IW48 - Confirmation Using Operation List IW49 - Display Operations IW70 - Orders Overall Network Scheduling MCI1 - Object Class MCI2 - Manufacturer MCI4 - Planner Group MCI5 - Damage Analysis MCI6 - Object Statistics MCI8 - Cost Analysis MD04 - Display Stock/Requirements Situation S_ALR_87013421 - Display Measurement Reading Entry List Permit CN41 - Structure Overview Report Approver IH01 - Functional Location Structural Display IL07 - Functional Location List (Multi-Level) IPMD - Maintain/Display Permits IW23 - Display PM Notification IW29 - Display Notifications IW32 - Change Order IW33 - Display PM Order IW37N - Change Orders and Operations IW38 - Change PM Orders IW39 - Display PM orders IW40 - Display Orders (Multi-Level) IW43 - Display PM Order Confirmation IW49 - Display Operations Plant BGM1 - Create Master Warranty Maintenance BGM2 - Change Master Warranty Master Data CA85 - Replace Work Center Maintainer CL02 - Classes CL20N - Assign Object to Class CL22N - Assign Class to Superior Classes For Official Use Only Page 36
  • 37.
    SAP Transaction andCommand Codes Job Aid GFEBS Role Transaction Codes CL24N - Class Assignment CL26 - Mass Release of Assignments CLHP - Graphical Hierarchy Maintenance CN41 - Structure Overview Report CR05 - Evaluations Work Center List CR06 - Evaluations Cost Center Assignment CR07 - Evaluations Work Center Capacity CR08 - Evaluations Work Center Hierarchy CR10 - Work Centers Change Documents CR11 - Create Capacity CR12 - Change Capacity CR13 - Display Capacity CR15 - Use Capacity CR21 - Create Hierarchy CR22 - Change Hierarchy CR23 - Display Hierarchy CS01 - Create Material BOM CS02 - Change Material BOM CS03 - Display Material BOM CT04 - Characteristics IA01 - Create Equipment Task List IA02 - Change Equipment Task List IA03 - Display Equipment Task List IA05 - Create General Task List IA06 - Change Material Maintenance Task List IA11 - Create Functional Location Task List IA12 - Change Functional Location Task List IB01 - Create Equipment BOM IB02 - Change Equipment BOM IB11 - Create Functional Location BOM IE01 - Create Equipment IE02 - Change Equipment IE03 - Display Equipment IE05 - Change Equipment: Equipment Selection IH01 - Functional Location Structural Display IK01 - Create Measuring Point IK02 - Change Measuring Point IK03 - Display Measuring Point IK07 - Display Measuring Points IK11 - Create Measurement Document IK12 - Change Measurement Document For Official Use Only Page 37
  • 38.
    SAP Transaction andCommand Codes Job Aid GFEBS Role Transaction Codes IK13 - Display Measurement Document IK17 - Display Measurement Documents IL01 - Create Functional Location IL02 - Change Functional Location IL03 - Display Functional Location IL05 - Change Functional Location: Functional Location Selection IL07 - Functional Location List (Multi-Level) IN04 - Change Functional Location Object Link IN05 - Change Functional Location Object Link IN15 - List Editing: Display Functional Location Object Links IP02 - Change Maintenance Plan IP19 - Maintenance Scheduling Overview IP24 - Scheduling Overview List Form IP31 - Maintenance Plan Cost Display IPMD - Maintain/Display Permits IR01 - Create Work Center IR02 - Change Work Center IR03 - Display Work Center IW13 - Material Where-used List IW23 - Display PM Notification IW29 - Display Notifications IW30 - Notification List (Multi-Level) IW32 - Change Order IW33 - Display PM Order IW37N - Change Orders and Operations IW38 - Change PM Orders IW39 - Display PM Orders IW3L - Display Order Component List IW40 - Display Orders (Multi-Level) IW49 - Display Operations MCI1 - Object Class MCI2 - Manufacturer MCI4 - Planner Group MCI5 - Damage Analysis MCI6 - Object Statistics MCI8 - Cost Analysis OINI - Create Network ID ZSPPE_DATALOAD - ZSPPEE_BOM ZSPPE_DATALOAD - ZSPPEE_EQUIPMENT ZSPPE_DATALOAD - ZSPPEE_FUNCTIONAL_LOCATION For Official Use Only Page 38
  • 39.
    SAP Transaction andCommand Codes Job Aid GFEBS Role Transaction Codes ZSPPE_DATALOAD - ZSPPEE_MAINTENANCE_PLAN ZSPPE_DATALOAD - ZSPPEE_MEASURINGPT_COUNTER ZSPPE_DATALOAD - ZSPPEE_TASK_LIST ZSPPE_DATALOAD - ZSPPEE_WARRANTIES Preventive CN41 – Structure Overview Report Maintenance IA01 - Create Equipment Task List Controller IA02 - Change Equipment Task List IA03 - Display Equipment Task List IA06 - Change Material Maintenance Task List IA11 - Create Functional Location Task List IA12 - Change Functional Location Task List IE02 – Change Equipment IE03 - Display Equipment IE05 – Change Equipment: Equipment Selection IH01 – Functional Location Structural Display IK01 - Create Measuring Point IK02 - Change Measuring Point IK03 - Display Measuring Point IK07 - Display Measuring Points IK12 - Change Measurement Document IK14 - Collective Entry of MeasDocuments IK16 - Collective Entry of MeasDocuments IK41 - Display MeasDocs from Archive IL07 – Functional Location List (Multi-Level) IP02 - Change Maintenance Plan IP03 - Display Maintenance Plan IP10 - Schedule Maintenance Plan IP19 - Maintenance Scheduling Overview IP24 - Scheduling Overview List Form IP30 - MaintSchedule Date Monitoring IP31 - Maintenance Plan Cost Display IP41 - Add Single Plan IP42 - Add Strategy-controlled Plan IP43 - Add Multiple Counter Plan IW23 – Display PM Notification IW29 – Display Notifications IW30 – Notification List (Multi-Level) IW33 – Display PM Order IW39 – Display PM Orders IW40 – Display Orders (Multi-Level) IW49 – Display Operations MCI1 - Object Class For Official Use Only Page 39
  • 40.
    SAP Transaction andCommand Codes Job Aid GFEBS Role Transaction Codes MCI2 - Manufacturer MCI4 - Planner Group MCI5 - Damage Analysis MCI6 - Object Statistics MCI8 - Cost Analysis S_ALR_87013421 - Display Measurement Reading Entry List ZSPPE_DATALOAD – PPE-PM Front End for Loading Data Material CN41 - Structure Overview Report Requirements IH01 - Functional Location Structural Display Planning IW13 - Material Where-used List Maintainer IW23 - Display PM Notification IW29 - Display Notifications IW33 - Display PM Order IW39 - Display PM Orders IW3K - Change Order Component List IW3L - Display Order Component List IW40 - Display Orders (Multi-Level) MB03 - Display Material Document MB51 - Material Document List MB52 – Display Warehouse Stocks of Material MCI8 - Cost Analysis MD01 - MRP Run MD03 - MRP-Individual Planning-Single Level MD04 - Display Stock/Requirements Situation MD05 - Individual Display of MRP List MD06 - Collective Display of MRP List MD07 - Current Material Overview MD11 - Create Planned Order MD12 - Change Planned Order MD13 - Display Planned Order MD14 - Convert Planned Order to PR MD15 - Collective Conversion of Planned Orders to Purchase Reqs ME03 – Display Source List ME2B - POs by Requirement Tracking Number ME2L – Purchase Order List Display by Vendor ME2N – PO List Display by PO Number MI22 - Display Phys. Inv. Docs. f. Material MIGO - Goods Movement MIQ1 – Selected Data for Physical Inventory Documents for Project For Official Use Only Page 40
  • 41.
    SAP Transaction andCommand Codes Job Aid GFEBS Role Transaction Codes MM01 - Create Material MM02 - Change Material MM03 - Display Material MMBE - Stock Overview MP30 - Execute Material Forecast MP31 - Change Material Forecast MP32 - Display Material Forecast XK01 – Create Master XK02 – Change Master XK03 – Display Vendor Master ZSSC_PRINT_PR – Print PR/Quote ZSSC_SUPPLY_RPT – Supply Management Report Physical CN41 - Structure Overview Report Inventory COGI - Processing Goods Movemnts w. Errors Maintainer IH01 - Functional Location Structural Display IW13 - Material Where-used List IW23 - Display PM Notification IW29 - Display Notifications IW33 - Display PM Order IW39 - Display PM Orders IW3K - Change Order Component List IW3L - Display Order Component List MB03 - Display Material Document MB51 - Material Document List ME03 – Display Source List ME2N – Purchasing Documents per Document Number MI01 - Create Physical Inventory Document MI02 - Change Physical Inventory Document MI03 - Display Physical Inventory Document MI04 - Enter Inventory Count with Document MI05 - Change Inventory Count MI06 - Display Inventory Count MI07 - Process List of Differences MI08 - Create List of Differences with Doc. MI20 - Print List of Differences MI21 - Print Physical Inventory Document MI24 - Physical Inventory List MIGO - Goods Movement Annual CJ40 – Change Project Cost Plan Planner CJ40 – Change Project Plan ZSPPE_AWP – Annual Workplan Report ZSPPE_IJO – Report on IJO Ranking Requirements For Official Use Only Page 41
  • 42.
    SAP Transaction andCommand Codes Job Aid GFEBS Role Transaction Codes Plant AS03 - Display Asset Maintenance BGM3 - Display Master Warranty Reporter CA80 - Work Center Where Used: Selection CJ02 - Display Work Breakdown Structure CJ03 - Display Work Breakdown Structure CJ08 - Display Project Definition CJ13 - Display WBS Element CJ22 - Display Basic Dates CJ24 - Display Forecast Dates CJ26 - Display Actual Dates CJ41 - Display Project Cost Plan CJ43 - Display Project Revenues CJ80 - Run Hierarchy Report CJ93 - Display Standard WBS CJCS - Display Change Documents CJE0 - Run Hierarchy Report CJE3 - Display Hierarchy Report CJI3 - Display Line Items CJI4 - Display Line Items CJI5 - Display Line Items CJI9 - Display Line Items CJIA - Display Line Items CJID - Display Line Items CJIF - Display Line Items CJR3 - PS: Display Plan CElem/Activ. Input CM01 - Cap. Planning; Work Center Load CM02 - Capac. Planning; Work Center Orders CM03 - Capac. Planning; Work Center Pool CM04 - Capac. Planning; Work Center Backlog CM05 - Capacity Plan; Work Center Overload CM07 - Cap. Planning: Variable Access CM28 - Individual Capacity Leveling CM50 – Capacity Level: SFC Work Cntr List CM51 – Cap. Level: SFC Individual Cap. List CM52 – Cap. Leveling: SFC Orders List CM53 - Capacity: Extended Evaluation Project View CM54 - Capacity: Extended Evaluation Project View CM55 - Capacity: Extended Evaluation Project View CN03 - Display Standard Network CN23 - Display Network CN28 - Display Individual Confirmations - Network For Official Use Only Page 42
  • 43.
    SAP Transaction andCommand Codes Job Aid GFEBS Role Transaction Codes CN41 - Structure Overview Report CN42N - Individual Overviews CN43N - Individual Overviews CN45N - Individual Overviews CN46N - Individual Overviews CN47N - Individual Overviews CN49N - Individual Overviews CN51N - Individual Overviews CN52N - Material Reports CN53N - Individual Overviews CN54N - Individual Overviews CN55N - Individual Overviews CN60 - Display Change Documents CN61 - Display Change Documents CNR3 - Display Work Center CO24 - Missing Parts CR03 - Display Work Center CR05 – Evaluations Work Center List CR06 – Evaluations Cost Center Capacity CR07 – Evaluations Work Center Capacity CR08 – Evaluations Work Center Hierarchy CR10 – Work Centers Change Documents CR13 – Display Capacity CR23 – Display Hierarchy CS03 – Display Material BOM CT10 - Characteristics Display FB03 - Display Financial Document FM_Sets_FIPEX3 - Display Commitment Item Group FM_Sets_Function3 - Display Functional Area Group FM5S - FIFM: Display Fund FM6S - FIFM: Display Application of Funds FMCIC - Display Commitment Item FMEDD - Display Entry Document FMMEASURE – Change Funded Program FMMEASURED - Funded Program: Display FMRP_RFFMEP1AX – All Postings FMSC – Display Funds Center in FM Area FMW3 - Display Funds Block FMX3 - Display Funds Reservation FMY3 - Display Funds Precommitment FMZ3 - Display Funds Commitment GRR3 - Funds Status Report For Official Use Only Page 43
  • 44.
    SAP Transaction andCommand Codes Job Aid GFEBS Role Transaction Codes IA03 - Display Equipment Task List IA07 - General Maintenance Task List IA13 – Display FunctLoc Task List IB03 - Display Equipment BOM IB13 - Display Functional Location BOM IE03 – Display Equipment IH01 - Functional Location Structural Display IH06 – Display Functional Location IH07 – Display Functional Location IH08 – Display Equipment IK03 – Display Measuring Point IK07 – Display Measuring Points IK13 – Display Measurement Document IK17 - Display Measurement Documents IK41 - Display MeasDocs from Archive IL03 – Display Functional Location IL07 – Functional Location List (Multi-Level) IN06 - Display Functional Location Object Link IN16 - List Editing: Display Functional Location Object Links IP03 – Display Maintenance Plan IP10 – Schedule Maintenance Plan IP19 – Maintenance Scheduling Overview IP24 – Scheduling Overview List Form IP30 – MaintSchedule Date Monitoring IP31 - Maintenance Plan Cost Display IPMD – Maintain/Display Permits IR03 – Display Work Center IW13 – Material Where-used List IW23 - Display PM Notification IW29 - Display Notifications IW30 - Notification List (Multi-Level) IW33 - Display PM Order IW39 - Display PM Orders IW3D – Print Order IW3L – Display Order Component List IW40 - Display Orders (Multi-Level) IW43 – Display PM Order Confirmation IW49 – Display Operations KJH3 - Display WBS Element Groups KKAE - Display Worklist for Results Analysis KKAL - Display Log for Results Analysis KKE3 - Display Base Planning Object KKG0 Display Cutoff Period for Results Analysis KKRC - Display Inheritance (Summarization) For Official Use Only Page 44
  • 45.
    SAP Transaction andCommand Codes Job Aid GFEBS Role Transaction Codes KSB5 - Display Actual Costs/Revenue Document MB03 - Display Material Document MB25 - Material Reports MB51 - Material Document List MBBS - Material Reports MCI1 - Object Class MCI2 - Manufacturer MCI4 - Planner Group MCI5 - Damage Analysis MCI6 - Object Statistics MCI8 - Cost Analysis MD04 - Display Stock/Requirements Situation MD13 – Display Planned Order MD4C - Material Reports MDLD - MRP Lists ME23N - Display Purchase Order ME2L - Purchase Order List Display by Vendor ME2M - Purchase Order List Display by Material ME2W - Purchase Order List Display by Plant ME33K - Display Contract ME53N - Display Purchase Requisition ME5A - Purchase Requisitions List Display- General ME5J - Purchase Requisitions by Project ME5K - List Display of Purchase Requisitions MI03 – Display Physical Inventory Document MI06 – Display Inventory Count MM03 – Display Material MP32 – Display Material Forecast RE80 - RE Navigator REBDBE - Process BE REBDBU - Process BU REBDPR - Process PR REBDRO - Process RO RECARS – Process Dates for All Objects RECARSCN – Process Dates for Contracts RECN – Process Contract REISBDOA - Info System: Object Assignment REISBE - Info System: Business Entities REISBP - Info System: Objects for Partner REISBPBD – Info System: Partner for Master Data REISBU – Info System: Buildings REISCDBD – Info System: Conditions for RO For Official Use Only Page 45
  • 46.
    SAP Transaction andCommand Codes Job Aid GFEBS Role Transaction Codes REISCN – Info System: Contracts REISMSBD – Info System: Measurements – Mast. Data REISPR – Info System: Properties REISRO – Info System: Rental Objects S_ALR_87013421 - Display Measurement Reading Entry List S_ALR_87013532 - Cost Hierarchical Plan-based S_ALR_87013533 - Cost Hierarchical Plan-based S_ALR_87013534 - Cost Hierarchical Plan-based S_ALR_87013535 - Cost Hierarchical Plan-based S_ALR_87013536 - Cost Hierarchical Plan-based S_ALR_87013537 - Cost Hierarchical Plan-based S_ALR_87013538 - Cost Hierarchical Plan-based S_ALR_87013539 - Cost Hierarchical Plan-based S_ALR_87013540 - Cost Hierarchical Plan-based S_ALR_87013541 - Cost Hierarchical Plan-based S_ALR_87013542 - Cost Element Plan-based S_ALR_87013543 - Cost Element Plan-based S_ALR_87013544 - Cost Element Plan-based S_ALR_87013545 - Cost Element Plan-based S_ALR_87013546 - Cost Element Plan-based S_ALR_87013547 - Cost Element Plan-based S_ALR_87013548 - Cost Element Plan-based S_ALR_87013549 - Cost Element Plan-based S_ALR_87013550 - Cost Element Plan-based S_ALR_87013551 - Cost Element Plan-based S_ALR_87013552 - Cost Element Plan-based S_ALR_87013553 - Cost Element Plan-based S_ALR_87013554 - Cost Element Plan-based S_ALR_87013555 - Cost Element Plan-based S_ALR_87013562 - Revenue and Earnings Hierarchical S_ALR_87013563 - Revenue and Earnings Hierarchical S_ALR_87013564 - Revenue and Earnings Hierarchical S_ALR_87013565 - Revenue and Earnings Hierarchical S_ALR_87013566 - Revenue and Earnings Hierarchical S_ALR_87013567 - Revenue and Earnings Hierarchical S_ALR_87013568 - Revenue and Earnings Hierarchical S_ALR_87013569 - Revenue and Earnings Hierarchical S_ALR_87013570 - Revenue and Earnings Cost Element S_ALR_87013571 - Revenue and Earnings Cost Element S_ALR_87013572 - Revenue and Earnings Cost Element S_ALR_87013576 - Summarization Overview For Official Use Only Page 46
  • 47.
    SAP Transaction andCommand Codes Job Aid GFEBS Role Transaction Codes S_ALR_87013577 - Summarization Costs/Revenue Expenditures/Receipt S_ALR_87013578 - Summarization Plan-based Hierarchical Costs S_ALR_87013579 - Summarization Plan-based Hierarchical Costs S_ALR_87013580 - Summarization Plan-based Cost Element Costs S_ALR_87013581 - Summarization Plan-based Cost Element Costs S_ALR_87013582 - Summarization Plan-based Cost Element Costs S_ALR_87013585 - Summarization Revenue and Earnings Hierarchical S_ALR_87100185 - Cost Hierarchical Plan-based S_ALR_87100186 - Cost Hierarchical Plan-based S_ALR_87100187 - Cost Hierarchical Plan-based S_ALR_87100188 - Cost Hierarchical Plan-based S_ALR_87100189 - Cost Hierarchical Plan-based S_ALR_87100190 - Cost Hierarchical Plan-based SM37 - Overview of Job Selection VA03 - Display Sales Order Z_OPEN_COM – FM Open Commitments Z_OPEN_OB – FM Open Obligations Z_RM_FUND_STATUS – Reimbursable Fund Status Report ZFSC1 – Cumulative Status by FC ZFSC2 – Cumulative Status by FA ZFSC3 – Cumulative Status by FP ZFSC4 – Cumulative Status by FC - Summary ZFSC5 – Cumulative Status by FC - Detail ZFSC6 – Cumulative Status by FA Group - Summary ZFSC7 – Cumulative Status by FA Group - Detail ZFSC8 – Cumulative Status with Open Commitments - Summary ZFSC9 – Cumulative Status with Open Commitments - Detail ZFSNC1 – Non- Cumulative Status by FC ZFSNC2 – Non- Cumulative Status by FA ZFSNC3 – Non- Cumulative Status by FP ZFSNC4 – Non- Cumulative Status by FC - Summary ZFSNC5 – Non- Cumulative Status by FC - Detail ZFSNC6 – Non- Cumulative Status by FC Pre-Posted ZRFSC1 – Reimbursable Cumulative Status by FC ZRFSC2 – Reimbursable Cumulative Status by FP ZRFSNC1 – Reimbursable Non-Cumulative Status by FC ZRFSNC2 – Reimbursable Non-Cumulative Status by FP ZSPPE_ACAPRULE - Asset Capitalization Rules ZSPPE_AWP - Annual Workplan Report ZSPPE_CANCEL - Cancellation Reason ZSPPE_DATALOAD_PS - PPE-PM-EXT-2448 ZSPPE_DSIGN - Design/Execution Status For Official Use Only Page 47
  • 48.
    SAP Transaction andCommand Codes Job Aid GFEBS Role Transaction Codes ZSPPE_FSOURCE - Fund Source ZSPPE_FUND_STAT - Fund Status ZSPPE_IJO - Report on IJO Ranking Requirements ZSPPE_PLNPRG - Planned Programmed Event Code ZSPPE_PRJTYP - Project Type Code ZSPPE_REGION - Region Name ZSPPE_UPLOAD_ESTWRK – Upload Estimation of Work ZSSC_PRINT_PR – Print PR/Quote ZW39 – DPW Report – PM Orders Click here to return to top. Project System Role Transaction Codes Project AS01 - Create Asset Structure AS02 - Change Asset Controller AS03 - Display Asset CJ01 - Create Work Breakdown Structure CJ02 - Change Work Breakdown Structure CJ03 - Display Work Breakdown Structure CJ06 - Create Project Definition CJ07 - Change Project Definition CJ08 - Display Project Definition CJ11 - Create Single Element CJ12 - Change Single Element CJ13 - Display WBS Element CJ20 - Change Structure Planning CJ20N - Project Builder CJ2A - Display Structure Planning CJ2D - Create Structure Planning CJ91 - Create Standard WBS CJ92 - Change Standard WBS CJ93 - Display Standard WBS CJ9K - Network Costing CJE1 - Create Hierarchy Report CJE2 - Change Hierarchy Report CJEB – Background Processing; Hierarchy Reports CJI3 - Display Line Items CJSG - Create WBS Element Groups CJV4 - Transfer (Copy) Project For Official Use Only Page 48
  • 49.
    SAP Transaction andCommand Codes Job Aid GFEBS Role Transaction Codes CJV5 - Delete Simulation CJV6 - Display Administrative Data for Version CJV7 - Display Version Log CN01 - Create Standard Network CN02 - Change Standard Network CN03 - Display Standard Network CN04 – Edit PS Text Catalog CN05 – Display PS Text Catalog CN21 - Create Network CN22 - Change Network CN23 – Display Network CN23 - Display Individual Confirmations- Network CN24 – Overall Network Scheduling CN40 – Project Overview CN41 - Structure Overview CN41N - Structure Overview CN52N - Material Reports CN71 - Create Version with Structure CN72 - Create Version CN98 - Delete Standard Network CNR1 - Create Work Center CNR2 - Change Work Center CNR3 - Display Work Center CO24 - Missing Parts CR11 - Create Capacity CR12 - Change Capacity FMMEASURE – Change Funded Program KJH2 - Change WBS Element Croups KJH3 - Display WBS Element Groups MB25 - Material Reports MBBS - Material Reports MD04 -Display Stock Requirements List MD04 – Material Reports MD4C - Material Reports OPUM - Maintain Subprojects Z_OPEN_COM – FM Open Commitments Z_OPEN_OB – FM Open Obligations ZFSC1 – Cumulative Status by FC ZFSC2 – Cumulative Status by FA ZFSC3 – Cumulative Status by FP ZFSC4 – Cumulative Status by FC - Summary ZFSC5 – Cumulative Status by FC - Detail ZFSC6 – Cumulative Status by FA Group - Summary For Official Use Only Page 49
  • 50.
    SAP Transaction andCommand Codes Job Aid GFEBS Role Transaction Codes ZFSC7 – Cumulative Status by FA Group - Detail ZFSC8 – Cumulative Status with Open Commitments - Summary ZFSC9 – Cumulative Status with Open Commitments - Detail ZFSNC1 – Non- Cumulative Status by FC ZFSNC2 – Non- Cumulative Status by FA ZFSNC3 – Non- Cumulative Status by FP ZFSNC4 – Non- Cumulative Status by FC - Summary ZFSNC5 – Non- Cumulative Status by FC - Detail ZFSNC6 – Non- Cumulative Status by FC Pre-Posted ZRFSC1 – Reimbursable Cumulative Status by FC ZRFSC2 – Reimbursable Cumulative Status by FP ZRFSNC1 – Reimbursable Non-Cumulative Status by FC ZRFSNC2 – Reimbursable Non-Cumulative Status by FP ZSPPE_DATALOAD_PS – Program to Load Projects Project CJ20N – Project Builder Financial CJ40 - Change Project Cost Plan Controller CJ40 – Change Project Plan CJ42 - Create/Change Revenue Plan CJ43 - Display Project Revenues CJ9B - Copy Version (Mass Change) CJ9BS - Copy Planning Cost Data by Version (Single Project) CJ9C - Copy Actual to Plan Cost Data by Version (Mass Change) CJ9CS - Copy Actual to Plan Cost Data by Version (Single Project) CJ9F - Copy Planning Cost Data by Version (Mass Change) CJ9FS - Copy Version for Project Def. CJ9K - Network Costing CJR2 - PS: Change Plan CElem/Activ. Input CJR3 - PS: Display Plan CElem/Activ. Input CN23 - Display Individual Confirmations- Network CN23 – Display Network CN24 – Overall Network Scheduling CN40 – Project Overview CN41 - Structure Overview CN41N - Structure Overview CN52N - Material Reports CO24 - Missing Parts FMMEASURE - Change Funded Program KKAE - Display Worklist for Results Analysis KKAL - Display Log for Results Analysis KKE1 - Create Revenue Plan on WBS KKE2 - Change Revenue Plan on WBS KKE3 - Display Base Planning Object KKG0 - Display Cutoff Period for Results Analysis For Official Use Only Page 50
  • 51.
    SAP Transaction andCommand Codes Job Aid GFEBS Role Transaction Codes KP04 - Set Planner Profile MB25 - Material Reports MBBS - Material Reports MD04 - Display Stock Requirements List MD04 – Material Reports MD4C - Material Reports S_ALR_87013585 - Summarization Revenue and Earnings Hierarchical Z_OPEN_COM – FM Open Commitments Z_OPEN_OB – FM Open Obligations ZFSC1 – Cumulative Status by FC ZFSC2 – Cumulative Status by FA ZFSC3 – Cumulative Status by FP ZFSC4 – Cumulative Status by FC - Summary ZFSC5 – Cumulative Status by FC - Detail ZFSC6 – Cumulative Status by FA Group - Summary ZFSC7 – Cumulative Status by FA Group - Detail ZFSC8 – Cumulative Status with Open Commitments - Summary ZFSC9 – Cumulative Status with Open Commitments - Detail ZFSNC1 – Non- Cumulative Status by FC ZFSNC2 – Non- Cumulative Status by FA ZFSNC3 – Non- Cumulative Status by FP ZFSNC4 – Non- Cumulative Status by FC - Summary ZFSNC5 – Non- Cumulative Status by FC - Detail ZFSNC6 – Non- Cumulative Status by FC Pre-Posted ZRFSC1 – Reimbursable Cumulative Status by FC ZRFSC2 – Reimbursable Cumulative Status by FP ZRFSNC1 – Reimbursable Non-Cumulative Status by FC ZRFSNC2 – Reimbursable Non-Cumulative Status by FP ZSPPE_UPLOAD_ESTWRK – Upload Estimation of Work Project CJ20N - Project Builder Schedule CJ21 - Change Basic Dates Controller CJ22 - Display Basic Dates CJ23 - Change Forecast Dates CJ24 - Display Forecast Dates CJ25 - Change Actual Dates CJ26 - Display Actual Dates CJ27 – Project Planning Board CJ29 - Update WBS (Forecast) CJ2B - Change Project Planning Board CM01 – Cap. Planning; Work Center Load CM02 - Capac. Planning; Work Center Orders CM03 - Capac. Planning; Work Center Pool CM04 - Capac. Planning; Work Center Backlog CM05 - Capacity Plan; Work Center Overload For Official Use Only Page 51
  • 52.
    SAP Transaction andCommand Codes Job Aid GFEBS Role Transaction Codes CM50 – Capacity Level: SFC Work Cntr List CM51 – Cap. Level: SFC Individual Cap. List CM52 – Cap. Leveling: SFC Orders List CM53 - Capacity: Extended Evaluation Project View CM54 - Capacity: Extended Evaluation Project View CN23 - Display Individual Confirmations- Network CN23 – Display Network CN24 - Overall Network Scheduling CN24N - Overall Network Scheduling (new) CN40 – Project Overview CN41 - Structure Overview CN41N - Structure Overview CN52N - Material Reports CNR1 - Create Work Center CNR2 - Change Work Center CNR3 - Display Work Center CO24 - Missing Parts CR11 - Create Capacity CR12 - Change Capacity CR13 - Display Capacity FMMEASURE - Change Funded Program MB25 - Material Reports MBBS - Material Reports MD04 - Display Stock Requirements List MD04 – Material Reports MD4C - Material Reports Z_OPEN_COM – FM Open Commitments Z_OPEN_OB – FM Open Obligations ZFSC1 – Cumulative Status by FC ZFSC2 – Cumulative Status by FA ZFSC3 – Cumulative Status by FP ZFSC4 – Cumulative Status by FC - Summary ZFSC5 – Cumulative Status by FC - Detail ZFSC6 – Cumulative Status by FA Group - Summary ZFSC7 – Cumulative Status by FA Group - Detail ZFSC8 – Cumulative Status with Open Commitments - Summary ZFSC9 – Cumulative Status with Open Commitments - Detail ZFSNC1 – Non- Cumulative Status by FC ZFSNC2 – Non- Cumulative Status by FA ZFSNC3 – Non- Cumulative Status by FP ZFSNC4 – Non- Cumulative Status by FC - Summary ZFSNC5 – Non- Cumulative Status by FC - Detail ZFSNC6 – Non- Cumulative Status by FC Pre-Posted For Official Use Only Page 52
  • 53.
    SAP Transaction andCommand Codes Job Aid GFEBS Role Transaction Codes ZRFSC1 – Reimbursable Cumulative Status by FC ZRFSC2 – Reimbursable Cumulative Status by FP ZRFSNC1 – Reimbursable Non-Cumulative Status by FC ZRFSNC2 – Reimbursable Non-Cumulative Status by FP Project CN41 – Structure Overview Maintainer CN41N – Structure Overview CJ02 - Display Work Breakdown Structure CJE1 - Create Hierarchy Report CJE2 - Change Hierarchy Report CM01 - Cap. Planning; Work Center Load CM02 - Capac. Planning; Work Center Orders CM03 - Capac. Planning; Work Center Pool CM04 - Capac. Planning; Work Center Backlog CM05 - Capacity Plan; Work Center Overload CM50 – Capacity Level: SFC Work Cntr List CM51 – Cap. Level: SFC Individual Cap. List CM52 – Cap. Leveling: SFC Orders List CM53 - Capacity: Extended Evaluation Project View CM54 - Capacity: Extended Evaluation Project View CM55 - Capacity: Extended Evaluation Project View CN23 - Display Individual Confirmations- Network CN24 – Overall Network Scheduling CN40 – Project Overview CN52N - Material Reports CO24 - Missing Parts KKAE - Display Worklist for Results Analysis KKAL - Display Log for Results Analysis KKG0 - Display Cutoff Period for Results Analysis MB25 - Material Reports MBBS - Material Reports MD04 - Display Stock Requirements List MD04 – Material Reports MD4C - Material Reports Z_OPEN_COM – FM Open Commitments Z_OPEN_OB – FM Open Obligations ZFSC1 – Cumulative Status by FC ZFSC2 – Cumulative Status by FA ZFSC3 – Cumulative Status by FP ZFSC4 – Cumulative Status by FC - Summary ZFSC5 – Cumulative Status by FC - Detail ZFSC6 – Cumulative Status by FA Group - Summary ZFSC7 – Cumulative Status by FA Group - Detail For Official Use Only Page 53
  • 54.
    SAP Transaction andCommand Codes Job Aid GFEBS Role Transaction Codes ZFSC8 – Cumulative Status with Open Commitments - Summary ZFSC9 – Cumulative Status with Open Commitments - Detail ZFSNC1 – Non- Cumulative Status by FC ZFSNC2 – Non- Cumulative Status by FA ZFSNC3 – Non- Cumulative Status by FP ZFSNC4 – Non- Cumulative Status by FC - Summary ZFSNC5 – Non- Cumulative Status by FC - Detail ZFSNC6 – Non- Cumulative Status by FC Pre-Posted ZRFSC1 – Reimbursable Cumulative Status by FC ZRFSC2 – Reimbursable Cumulative Status by FP ZRFSNC1 – Reimbursable Non-Cumulative Status by FC ZRFSNC2 – Reimbursable Non-Cumulative Status by FP ZW39 – DPW Report – PM Orders Project AS03 - Display Asset Interface CJ03 – Display Work Breakdown Structure Processing CJ08 - Display Project Definition Monitor CJ13 - Display WBS Element CJ20N – Project Builder CJ2A - Display Structure Planning CJV6 - Display Administrative Data for Version CJV7 - Display Version Log CN23 - Display Individual Confirmations- Network CN23 – Display Network CN24 – Overall Network Scheduling CN40 – Project Overview CN41 - Structure Overview CN41N - Structure Overview CN52N - Material Reports CNR3 - Display Work Center CO24 - Missing Parts CR13 - Display Capacity KJH3 - Display WBS Element Groups KKAE - Display Worklist for Results Analysis KKAL - Display Log for Results Analysis KKG0 - Display Cutoff Period for Results Analysis MB25 - Material Reports MBBS - Material Reports MD04 - Display Stock Requirements List MD04 – Material Reports MD4C - Material Reports WE02 - Display IDoc List Z_OPEN_COM – FM Open Commitments Z_OPEN_OB – FM Open Obligations For Official Use Only Page 54
  • 55.
    SAP Transaction andCommand Codes Job Aid GFEBS Role Transaction Codes ZFSC1 – Cumulative Status by FC ZFSC2 – Cumulative Status by FA ZFSC3 – Cumulative Status by FP ZFSC4 – Cumulative Status by FC - Summary ZFSC5 – Cumulative Status by FC - Detail ZFSC6 – Cumulative Status by FA Group - Summary ZFSC7 – Cumulative Status by FA Group - Detail ZFSC8 – Cumulative Status with Open Commitments - Summary ZFSC9 – Cumulative Status with Open Commitments - Detail ZFSNC1 – Non- Cumulative Status by FC ZFSNC2 – Non- Cumulative Status by FA ZFSNC3 – Non- Cumulative Status by FP ZFSNC4 – Non- Cumulative Status by FC - Summary ZFSNC5 – Non- Cumulative Status by FC - Detail ZFSNC6 – Non- Cumulative Status by FC Pre-Posted ZOS_IST – IDoc Status Report ZRFSC1 – Reimbursable Cumulative Status by FC ZRFSC2 – Reimbursable Cumulative Status by FP ZRFSNC1 – Reimbursable Non-Cumulative Status by FC ZRFSNC2 – Reimbursable Non-Cumulative Status by FP ZSPPE_ACAPRULE - Asset Capitalization Rules ZSPPE_AUTH_TYPCD - Update Authorization Type Code Table ZSPPE_CANCEL - Cancellation Reason ZSPPE_DSIGN - Design/Execution Status ZSPPE_FSOURCE - Fund Source ZSPPE_FUND_STAT - Fund Status ZSPPE_PLNPRG - Planned Programmed Event Code ZSPPE_PRJTYP - Project Type Code ZSPPE_REGION - Region Name ZSPPE_REISROOC – Rental Objects Project CJ02 – Change Work Breakdown Structure Report CJ02 - Display Work Breakdown Structure Reviewer CJ03 – Display Work Breakdown Structure CJ08 – Display Project Definition CJ13 – Display WBS Element CJ2A – Display Structure Planning CJ43 – Display Project Revenues CJ93 – Display Standard WBS CJR3 – PS: Display Plan CElem/Activ. Input CM01 – Cap. Planning; Work Center Load CM02 – Capac Planning; Work Center Orders CM03 – Capac. Planning; Work Center Pool CM04 - Capac. Planning; Work Center Backlog CM05 - Capacity Plan; Work Center Overload CM50 – Capacity Level: SFC Work Cntr List For Official Use Only Page 55
  • 56.
    SAP Transaction andCommand Codes Job Aid GFEBS Role Transaction Codes CM51 – Cap. Level: SFC Individual Cap. List CM52 – Cap. Leveling: SFC Orders List CM53 – Capacity: Extended Evaluation Project View CM54 – Capacity: Extended Evaluation Project View CM55 – Capacity: Extended Evaluation Project View CN03 – Display Standard Network CN23 – Display Network CN23 - Display Individual Confirmations - Network CN41 - Structure Overview CN41N - Structure Overview CN52N - Material Reports CN61 - Display Change Documents CO24 - Missing Parts FMMEASURE – Change Funded Program KJH3 – Display WBS Element Groups KKAL – Display Log for Results Analysis KKE3 – Display Base Planning Object KKG0 – Display Cutoff Period for Results Analysis MB25 - Material Reports MBBS - Material Reports MD04 - Display Stock Requirements List MD04 – Material Reports WE02 – Display IDoc List Z_OPEN_COM – FM Open Commitments Z_OPEN_OB – FM Open Obligations ZFSC1 – Cumulative Status by FC ZFSC2 – Cumulative Status by FA ZFSC3 – Cumulative Status by FP ZFSC4 – Cumulative Status by FC - Summary ZFSC5 – Cumulative Status by FC - Detail ZFSC6 – Cumulative Status by FA Group - Summary ZFSC7 – Cumulative Status by FA Group - Detail ZFSC8 – Cumulative Status with Open Commitments - Summary ZFSC9 – Cumulative Status with Open Commitments - Detail ZFSNC1 – Non- Cumulative Status by FC ZFSNC2 – Non- Cumulative Status by FA ZFSNC3 – Non- Cumulative Status by FP ZFSNC4 – Non- Cumulative Status by FC - Summary ZFSNC5 – Non- Cumulative Status by FC - Detail ZFSNC6 – Non- Cumulative Status by FC Pre-Posted ZRFSC1 – Reimbursable Cumulative Status by FC ZRFSC2 – Reimbursable Cumulative Status by FP ZRFSNC1 – Reimbursable Non-Cumulative Status by FC ZRFSNC2 – Reimbursable Non-Cumulative Status by FP ZSPPE_UO – Report on UO Ranking Requirements For Official Use Only Page 56
  • 57.
    SAP Transaction andCommand Codes Job Aid GFEBS Role Transaction Codes Project CN41 - Structure Overview Workflow CN41N - Structure Overview Monitor CN52N - Material Reports CO24 - Missing Parts MB25 - Material Reports MBBS - Material Reports MD04 - Display Stock Requirements List MD04 – Material Reports MD4C - Material Reports SWI11 - Tasks and Workflows SWI2_DEAD - Workflow Deadline Monitoring SWI2_DURA - Work Items by Duration SWI2_FREQ - Workflow Items Analysis SWI5 - Workflow Analysis Z_OPEN_COM – FM Open Commitments Z_OPEN_OB – FM Open Obligations ZFSC1 – Cumulative Status by FC ZFSC2 – Cumulative Status by FA ZFSC3 – Cumulative Status by FP ZFSC4 – Cumulative Status by FC - Summary ZFSC5 – Cumulative Status by FC - Detail ZFSC6 – Cumulative Status by FA Group - Summary ZFSC7 – Cumulative Status by FA Group - Detail ZFSC8 – Cumulative Status with Open Commitments - Summary ZFSC9 – Cumulative Status with Open Commitments - Detail ZFSNC1 – Non- Cumulative Status by FC ZFSNC2 – Non- Cumulative Status by FA ZFSNC3 – Non- Cumulative Status by FP ZFSNC4 – Non- Cumulative Status by FC - Summary ZFSNC5 – Non- Cumulative Status by FC - Detail ZFSNC6 – Non- Cumulative Status by FC Pre-Posted ZRFSC1 – Reimbursable Cumulative Status by FC ZRFSC2 – Reimbursable Cumulative Status by FP ZRFSNC1 – Reimbursable Non-Cumulative Status by FC ZRFSNC2 – Reimbursable Non-Cumulative Status by FP Project Time CJ40 – Change Project Plan Processor CN24 – Overall Network Scheduling CN25 - Create Network Individual Confirmations CN27 - Collective Confirmation - Network CN29 - Cancel Network Individual Confirmations CN40 – Project Overview CN41 - Structure Overview CN41N - Structure Overview CN52N - Material Reports For Official Use Only Page 57
  • 58.
    SAP Transaction andCommand Codes Job Aid GFEBS Role Transaction Codes CO24 - Missing Parts MB25 - Material Reports MBBS - Material Reports MD04 - Display Stock Requirements List MD04 – Material Reports MD4C - Material Reports Z_OPEN_COM – FM Open Commitments Z_OPEN_OB – FM Open Obligations ZFSC1 – Cumulative Status by FC ZFSC2 – Cumulative Status by FA ZFSC3 – Cumulative Status by FP ZFSC4 – Cumulative Status by FC - Summary ZFSC5 – Cumulative Status by FC - Detail ZFSC6 – Cumulative Status by FA Group - Summary ZFSC7 – Cumulative Status by FA Group - Detail ZFSC8 – Cumulative Status with Open Commitments - Summary ZFSC9 – Cumulative Status with Open Commitments - Detail ZFSNC1 – Non- Cumulative Status by FC ZFSNC2 – Non- Cumulative Status by FA ZFSNC3 – Non- Cumulative Status by FP ZFSNC4 – Non- Cumulative Status by FC - Summary ZFSNC5 – Non- Cumulative Status by FC - Detail ZFSNC6 – Non- Cumulative Status by FC Pre-Posted ZRFSC1 – Reimbursable Cumulative Status by FC ZRFSC2 – Reimbursable Cumulative Status by FP ZRFSNC1 – Reimbursable Non-Cumulative Status by FC ZRFSNC2 – Reimbursable Non-Cumulative Status by FP Project Funds CJ20 – Change Structure Planning Approver CJ20N - Project Builder CJ41 - Display Project Cost Plan CJ41 – Display Project Plan CN24 – Overall Network Scheduling CN40 – Project Overview CN41 - Structure Overview CN41N - Structure Overview CN52N - Material Reports CO24 - Missing Parts MB25 - Material Reports MBBS - Material Reports MD04 - Display Stock Requirements List MD04 – Material Reports MD4C - Material Reports Z_OPEN_COM – FM Open Commitments Z_OPEN_OB – FM Open Obligations For Official Use Only Page 58
  • 59.
    SAP Transaction andCommand Codes Job Aid GFEBS Role Transaction Codes ZFSC1 – Cumulative Status by FC ZFSC2 – Cumulative Status by FA ZFSC3 – Cumulative Status by FP ZFSC4 – Cumulative Status by FC - Summary ZFSC5 – Cumulative Status by FC - Detail ZFSC6 – Cumulative Status by FA Group - Summary ZFSC7 – Cumulative Status by FA Group - Detail ZFSC8 – Cumulative Status with Open Commitments - Summary ZFSC9 – Cumulative Status with Open Commitments - Detail ZFSNC1 – Non- Cumulative Status by FC ZFSNC2 – Non- Cumulative Status by FA ZFSNC3 – Non- Cumulative Status by FP ZFSNC4 – Non- Cumulative Status by FC - Summary ZFSNC5 – Non- Cumulative Status by FC - Detail ZFSNC6 – Non- Cumulative Status by FC Pre-Posted ZRFSC1 – Reimbursable Cumulative Status by FC ZRFSC2 – Reimbursable Cumulative Status by FP ZRFSNC1 – Reimbursable Non-Cumulative Status by FC ZRFSNC2 – Reimbursable Non-Cumulative Status by FP Project AS03 - Display Asset Approver CJ20 – Change Structure Planning CJ20N - Project Builder CJ41 - Display Project Cost Plan CN24 – Overall Network Scheduling CN40 – Project Overview CN41 - Structure Overview CN41N - Structure Overview CN52N - Material Reports CO24 - Missing Parts MB25 - Material Reports MBBS - Material Reports MD04 - Display Stock Requirements List MD04 – Material Reports MD4C - Material Reports Z_OPEN_COM – FM Open Commitments Z_OPEN_OB – FM Open Obligations ZFSC1 – Cumulative Status by FC ZFSC2 – Cumulative Status by FA ZFSC3 – Cumulative Status by FP ZFSC4 – Cumulative Status by FC - Summary ZFSC5 – Cumulative Status by FC - Detail ZFSC6 – Cumulative Status by FA Group - Summary ZFSC7 – Cumulative Status by FA Group - Detail ZFSC8 – Cumulative Status with Open Commitments - Summary ZFSC9 – Cumulative Status with Open Commitments - Detail For Official Use Only Page 59
  • 60.
    SAP Transaction andCommand Codes Job Aid GFEBS Role Transaction Codes ZFSNC1 – Non- Cumulative Status by FC ZFSNC2 – Non- Cumulative Status by FA ZFSNC3 – Non- Cumulative Status by FP ZFSNC4 – Non- Cumulative Status by FC - Summary ZFSNC5 – Non- Cumulative Status by FC - Detail ZFSNC6 – Non- Cumulative Status by FC Pre-Posted ZRFSC1 – Reimbursable Cumulative Status by FC ZRFSC2 – Reimbursable Cumulative Status by FP ZRFSNC1 – Reimbursable Non-Cumulative Status by FC ZRFSNC2 – Reimbursable Non-Cumulative Status by FP Project Period CJ20N – Project Builder End Close CJ44 - Project Apply Overhead Actual Individual Processor CJ45 - Project Apply Overhead Actual Collective CJ88 - Project Settlement Individual CJ8G - Project Settlement Collective CJB1 - Project Auto Generate Settlement Rule Collective CJB2 - Project Auto Generate Settlement Rule Individual KKA0 - Results Analysis Cutoff Period Change KKA2 - Project Execute Results Analysis - Individual KKAJ - Project Execute Results Analysis - Collective KKAL - Display Log for Results Analysis KKG0 - Display Cutoff Period for Results Analysis Z_OPEN_COM – FM Open Commitments Z_OPEN_OB – FM Open Obligations ZFSC1 – Cumulative Status by FC ZFSC2 – Cumulative Status by FA ZFSC3 – Cumulative Status by FP ZFSC4 – Cumulative Status by FC - Summary ZFSC5 – Cumulative Status by FC - Detail ZFSC6 – Cumulative Status by FA Group - Summary ZFSC7 – Cumulative Status by FA Group - Detail ZFSC8 – Cumulative Status with Open Commitments - Summary ZFSC9 – Cumulative Status with Open Commitments - Detail ZFSNC1 – Non- Cumulative Status by FC ZFSNC2 – Non- Cumulative Status by FA ZFSNC3 – Non- Cumulative Status by FP ZFSNC4 – Non- Cumulative Status by FC - Summary ZFSNC5 – Non- Cumulative Status by FC - Detail ZFSNC6 – Non- Cumulative Status by FC Pre-Posted ZRFSC1 – Reimbursable Cumulative Status by FC ZRFSC2 – Reimbursable Cumulative Status by FP ZRFSNC1 – Reimbursable Non-Cumulative Status by FC ZRFSNC2 – Reimbursable Non-Cumulative Status by FP For Official Use Only Page 60
  • 61.
    SAP Transaction andCommand Codes Job Aid GFEBS Click here to return to top. Real Property Inventory Role Transaction Codes Real Property BP – Edit Business Partner Maintainer RE80 - RE Navigator REBDBE - Process BE REBDBU - Process BU REBDPR - Process PR REBDRO - Process RO RECARS - Process Dates for All Objects RECARSCN - Process Dates for Contracts RECARSGEN - Generate Resubmission Dates RECN - Process Contract RECPA130 - Master Data Summary (BE) RECPA150 - Master Data Summary (Land) RECPA170 - Master Data Summary (Buildings) RECPA190 - Master Data Summary (Rental Objects) RECPA410 - Master Data Summary REEXSET - Edit Set REEXSETGENBD - Generate Sets for Usage Objects REISBDOA - Info System: Object Assignment REISBE - Info System: Business Entities REISBP - Info System: Objects for Partner REISBPBD - Info System: Partner for Master Data REISBU - Info System: Buildings REISCDBD - Info System: Conditions for RO REISCN - Info System: Contracts REISMSBD – Info System: Measurements - Mast.Data REISPR - Info System: Properties REISRO - Info System: Rental Objects REISROOC - Info System: Occupancy of ROs REORRR - Find by Objects ZSPPE_CCTR_CAT_LKP – Cost Center Lookup by CAT Site Spec. ZSPPE_DA337 – Approval for Disposal of Buildings ZSPPE_DD1354 – Trans & Accept of Military Property ZSPPE_RE_INST – Maintain Installation Data Table ZSPPE_RPUID_STATUS - Table for Unique Identifier Status For Official Use Only Page 61
  • 62.
    SAP Transaction andCommand Codes Job Aid GFEBS Role Transaction Codes Real Property RE80 - RE Navigator Interface REBDBE - Process BE Processing REBDBU - Process BU Monitor REBDPR - Process PR REBDRO - Process RO RECN - Process Contract RECPA130 - Master Data Summary (BE) RECPA150 - Master Data Summary (Land) RECPA170 - Master Data Summary (Buildings) RECPA190 - Master Data Summary (Rental Objects) RECPA410 - Master Data Summary REEXSET - Edit Set REORRR - Find by Objects WE02 - IDoc List ZOS_IST – IDoc Status Report Real Property RE80 - RE Navigator Inventory REBDBU - Process BU Inspection REBDPR - Process PR Processor REORRR - Find by objects Real Estate RE80 - RE Navigator Contracts/ REBDBE - Process BE Space REBDBU - Process BU Utilization Maintainer REBDPR - Process PR REBDRO - Process RO RECARS – Process Dates for All Objects RECARSCN - Process Dates for Contracts RECN - Process Contract RECPA130 - Master Data Summary (BE) RECPA150 - Master Data Summary (Land) RECPA170 - Master Data Summary (Buildings) RECPA190 - Master Data Summary (Rental Objects) RECPA410 - Master Data Summary REEXSET - Edit Set REEXSETGENCN - Set Generation - Contract REISBDOA - Info System: Object Assignment REISBE - Info System: Business Entities REISBP - Info System: Objects for Partner REISBPBD - Info System: Partner for Master Data REISBU - Info System: Buildings REISCDBD - Info System: Conditions for RO REISCN - Info System: Contracts For Official Use Only Page 62
  • 63.
    SAP Transaction andCommand Codes Job Aid GFEBS Role Transaction Codes REISMSBD – Info System: Measurements - Mast.Data REISPR - Info System: Properties REISRO - Info System: Rental Objects REISROOC - Info System: Occupancy of ROs REORRR - Find by Objects XD03 – Display Customer (Centrally) XK03 – Display Vendor Master ZRFREISROOC - Space Utilization Report Real Property AR01 - Call Asset List Viewer AR02 - Call Up Asset History Sheet AR03 - Call Up Depreciation List OARP - Call Up AM Report Overview RE80 - RE Navigator REBDBE - Process BE REBDBU - Process BU REBDPR - Process PR REBDRO - Process RO RECARS – Process Dates for All Objects RECN - Process Contract RECPA130 - Master Data Summary (BE) RECPA150 - Master Data Summary (Land) RECPA170 - Master Data Summary (Buildings) RECPA190 - Master Data Summary (Rental Objects) RECPA410 - Master Data Summary REEXSET - Edit Set REISBDOA – Info System: Object Assignment REISBE – Info System: Business Entities REISBP – Info System: Objects for Partner REISBPBD – Info System: Partner for Master Data REISBU – Info System: Buildings REISCDBD – Info System: Conditions for RO REISCN – Info System: Contracts REISMSBD – Info System: Measurements – Mast Data REISPR – Info System: Properties REISRO – Info System: Rental Objects REISROOC – Info System: Occupancy of ROs REORRR - Find by Objects ZSPPE_ASSET_PFOLIO – Asset Management Portfolio Report Business BP - Edit Business Partner Partner FLBPC1 - Create BP from Vendor Maintainer FLBPD1 - Create BP from Customer XD03 – Display Customer (Centrally) For Official Use Only Page 63
  • 64.
    SAP Transaction andCommand Codes Job Aid GFEBS Role Transaction Codes XK03 – Display Vendor Master ZSPPEE_UICDATA – Maintain UIC Data Table Click here to return to top. Reimbursables Role Transaction Codes Accounts FAGLL03 – G/L Account Line Items Receivable FB03 – Display Document Reporter FB04 – Display Changes FBL5N – Customer Line Item Display FD10N - Customer Balance Display FD11 - Customer Account Analysis FMFG_E_TRANS_REG - Transaction Register FMFG_E_ZFZALI00 - Display a Payment Settlement List FMST - Evaluation of Penalty Interest GD23 - FI-SL: Local Actual Document Display KSB5 - Controlling Documents: Actual. S_ALR_87012077 - Vendor Information System S_ALR_87012083 - List of Vendor Open Item S_ALR_87012167 - Accounts Receivable Information System. S_ALR_87012168 - Due Date Analysis for Open Items S_ALR_87012169 - Transaction Figures: Account Balance S_ALR_87012173 - List of Customer Open Items S_ALR_87012174 - List of Customer Open Items S_ALR_87012175 - Open Items: Customer Due Date Forec. S_ALR_87012178 - Customer Open Item Analysis by Balance of Overdue Items S_ALR_87012179 - Customer List XD03 – Customer Display ZSFI_TROR – TROR Report Interface Customer XD01 - Create Customer (Centrally) Master Data XD02 - Change Customer (Centrally) Controller XD03 – Display Customer (Centrally) XD05 - Block Customer (Centrally) ZSRM_DEBTCUS – Customer Master Extension Table Customer OV51 - Display of Changes for Customer Master Data XD03 - Display Customer (Centrally) Reporter XD04 - Display Customer Change (Centrally) For Official Use Only Page 64
  • 65.
    SAP Transaction andCommand Codes Job Aid GFEBS Role Transaction Codes Customer Transaction - Monitor IDocs of Customer Master Interfaces Interface WE02 - IDoc List Monitor ZOS_IST - IDoc Status Report Customer XD99 - Customer Master Mass Maintenance Master Mass ZSRM_DEBTCUS – Customer Master Extension Table Maintainer Customer CJ13 - Display WBS Element Order CJ20N – Project Builder Processor CJI3 – Project Actual Costs/Revenues FB03 – Display Document FB50 - G/L Acct. Posting - Single Screen Trans. Document Type ZW FBM3 – Display Sample Document FD03 – Display Customer (Accounting) FMMEASURE – Change Funded Program VA01 - Create Sales Order VA02 - Change Sales Order VA03 - Display Sales Order VD03 – Display Customer (Sales) ZSSC_COSTRNFR_LOAD – Cost Transfer Upload Extension from Load Template Customer CJ13 - Display WBS Element Order CJ20N – Project Builder Approver CJI3 – Project Actual Costs/Revenues FD03 – Display Customer (Accounting) FMBB- Budgeting Workbench FMMEASURE – Change Funded Program VA02- Change Sales Order VA03 – Display Sales Order VA05 – List of Sales Orders VD03 – Display Customer (Sales) Customer DP91 - SD: Resource-Related Billing Doc. Invoicing DP96 - Res-Rel. Billing Collect. Proc - Sales Processor DP99B - Doc Flow for Res. Rel. Bill - SD F.14 - Create Posting Documents from Recurring Documents F.15 - Recurring Entry Document FB00 - Accounting Editing Options FB50 - G/L Acct. Posting - Single Screen Trans. Document Type ZW FBD1 - Create Recurring Document FBD5 - Realize Recurring Entry FBM3 – Display Sample Document FBR2 - Post Document For Official Use Only Page 65
  • 66.
    SAP Transaction andCommand Codes Job Aid GFEBS Role Transaction Codes SHD0 - Transaction and Screen Variants SM35 - Batch Input Monitoring VA02 – Change Sales Order ZSCC_COSTRNFR_LOAD – Cost Transfer Upload Extension from Load Template Customer FMFG_IPAC - IPAC Upload File Creation Process Billing SM37 - Overview of Job Selection Processor/ SP01 - Output Controller Certifier VF01 - Create Billing Document VF02 - Change Billing Document VF03 - Display Billing Document VF04 - Maintain Billing Due List VF05 - List Billing Documents VF06 - Batch Billing VF11 - Cancel Billing Document VF31 - Output from Billing Documents VFX3 - List Blocked Billing Documents ZSRM_DCAS1080_EXTRCT - Generate Outbound 1080 Batch File to DCAS Debt F150 - Dunning Management FB00 - Accounting Editing Options Processor FB01 - Post Document FB02 - Change Document FB08 – Reverse Document FB70 - Enter Customer Invoice FB75 – Customer Credit Memo FBR2 – Post Document FBRA – Reset Cleared Items FINT - Item Interest Calculation FINTSHOW - Interest Run Display FMFEE – Fee Calculation FMZ3 - Funds Commitment: Display InitScrn MEAN- Address Maintenance RTREAS_OFFSET_UPDATE - Treasury Offset Update Report S_ALR_87002510 - Enter Time Interest Terms S_ALR_87002678 - Enter Reference Interest Values SBWP – Business Workplace SP01 – Output Controller XD03 - Display Customer (Centrally) XK03 - Display Vendor Master ZSRM_ACCTEXT – Account Receivable Extension Table ZSRM_ASR - For RM-RPT-2071: Installment Plan/Amortization ZSRM_DEBTCUS – Customer Master Extension Table For Official Use Only Page 66
  • 67.
    SAP Transaction andCommand Codes Job Aid GFEBS Role Transaction Codes ZSRM_DEBTREF - Outbound Delinquent Debt to Treasury Frontend Debt F103- ABAP/ 4 Reporting: Trnsfr Receivables Allowance F104- ABAP/ 4 Reporting: Receivables Prov. Processor FB01 – Post Document FB02 – Change Document FB05 – Post with Clearing FBB1 – Post Foreign Currency Valn SBWP – Business Workplace SM35- Batch Input: Session Debt F.80 – Mass Reversal of Documents Reversal FB08 - Reverse Document Processor FBRA – Reset Cleared Items Debt Write F-04- Post with Clearing Off Processor F-32 – Customer Clearing F.80 – Mass Reversal of Documents FB02 – Change Document Debt FAGLL03 – G/L Account Line Items Interface FB03 – Document Display Monitor FBL5N – Customer Line Item SWI1 – Selection Report for Work Items SWI5 – Workflow Analysis WE02 – IDoc List WE09 – IDoc Search for Business Content XD03 – Customer Display Reimbursable CJI3 - Project Actual Costs/Revenues Reporter GRR3 - Reimbursable Funds Status Report V23 - Sales Documents Blocked for Billing VA05 - List of Sales Orders Z_OPEN_COM – FM Open Commitments Z_OPEN_OB – FM Open Obligations Z_RM_FUND_STATUS – Reimbursable Fund Status Report ZFSC1 – Cumulative Status by FC ZFSC2 – Cumulative Status by FA ZFSC3 – Cumulative Status by FP ZFSC4 – Cumulative Status by FC - Summary ZFSC5 – Cumulative Status by FC - Detail ZFSC6 – Cumulative Status by FA Group - Summary ZFSC7 – Cumulative Status by FA Group - Detail ZFSC8 – Cumulative Status with Open Commitments - Summary ZFSC9 – Cumulative Status with Open Commitments - Detail ZFSNC1 – Non- Cumulative Status by FC ZFSNC2 – Non- Cumulative Status by FA ZFSNC3 – Non- Cumulative Status by FP For Official Use Only Page 67
  • 68.
    SAP Transaction andCommand Codes Job Aid GFEBS Role Transaction Codes ZFSNC4 – Non- Cumulative Status by FC - Summary ZFSNC5 – Non- Cumulative Status by FC - Detail ZFSNC6 – Non- Cumulative Status by FC Pre-Posted ZRFSC1 – Reimbursable Cumulative Status by FC ZRFSC2 – Reimbursable Cumulative Status by FP ZRFSNC1 – Reimbursable Non-Cumulative Status by FC ZRFSNC2 – Reimbursable Non-Cumulative Status by FP ZSRM_TAS_DSP - Display Treasury Accounting Symbol Table TAS Table ZSRM_TAS_DSP- Display Treasury Accounting Symbol Table Master Data ZSRM_TAS_MNT- Maintain Treasury Accounting Symbol Table Controller RM Periodic SM35 - Batch Input Monitoring Processor SM37 - Overview of Job Selection SP01 - Output Controller VA02 - Change Sales Order ZSFI_1081N – Create Internal 1081 Transfer ZSFM_RPT_E_UNFILLED - Year End Closing Operations: Update Sales Order Click here to return to top. Spending Chain Role Transaction Codes Material MB5L - List of Stock Values: Balances Master Data ME01 – Maintain Source List Controller ME02 – Change Source List ME03 – Display Source List ME11 - Create PIR ME12 - Change PIR ME13 - Display PIR MM01 - Create Material Master MM02 - Change Material Master MM03 - Display Material Master MR21 - Change Price of Material SBWP - Business Workplace SO01 - Business Workplace: Inbox ZSPPE_ASSET_PFOLIO – Asset Management Portfolio Report For Official Use Only Page 68
  • 69.
    SAP Transaction andCommand Codes Job Aid GFEBS Role Transaction Codes Material MB5L - List of Stock Values: Balances Master Data MM03 - Display Material Master Interface SBWP - Business Workplace Processing Monitor SO01 - Business Workplace: Inbox WE02 - IDoc List ZOS_IST - IDoc Status Report ZSPPE_ASSET_PFOLIO – Asset Management Portfolio Report Vendor FB03 - Display Document Master Data FBD3 - Display Recurring Document Controller FI03 - Display Bank: Initial Screen FK05 - Block/Unblock Vendor GD23 - FI-SL: Local Actual Document Display MB5L - List of Stock Values: Balances ME01 – Maintain Source List ME02 – Change Source List ME03 – Display Source List ME11 - Create PIR ME12 - Change PIR ME13 - Display PIR MKVZ - List of Vendors: Purchasing MM03 - Display Material Master S_ALR_87012082 - Vendor Balance Display S_ALR_87012086 - Vendor List SBWP - Business Workplace SO01 - Business Workplace: Inbox XD03 - Display Customer (Centrally) XK01 - Create Master XK02 - Change Master XK03 - Display Vendor Master XK04 - Process Vendor Master Data XK05 - Block Vendor Centrally XK06 - Flag for Deletion: Vendor ZSPPE_ASSET_PFOLIO – Asset Management Portfolio Report Vendor S_ALR_87012082 - Vendor Balance Display Master Data S_ALR_87012086 - Vendor List Interface SBWP - Business Workplace Processing SO01 - Business Workplace: Inbox Monitor WE02 - IDoc List XD03 - Display Customer (Centrally) XK03 - Display Vendor Master ZOS_IST - IDoc Status Report ZSPPE_ASSET_PFOLIO – Asset Management Portfolio Report For Official Use Only Page 69
  • 70.
    SAP Transaction andCommand Codes Job Aid GFEBS Role Transaction Codes Commitment FB03 - Display Document Processor FBD3 - Display Recurring Document FMY1 - Funds Precommitment: Create InitScrn FMY2 - Change Funds Commitment FMY3 - Funds Precommitment: Display InitScrn SBWP - Business Workplace SO01 - Business Workplace: Inbox ZSPPE_ASSET_PFOLIO – Asset Management Portfolio Report ZSSC_FCM_FP – FCM Financial Position Report ZSSC_FCM_OUT - FCM Financial Position Outbound Interface Trigger Purchase FB03 - Display Document Requisition FBD3 - Display Recurring Document Processor FMFG_PR_POST - Post Held Purchase Requisition GD23 - FI-SL: Local Actual Document Display IW33 - Display PM Order MB03 - Display Material Document MB51 – Material Document List ME23N - Display Purchase Order ME2J - PO List Display by Project/WBS ME2K - PO List Display by Account Assignment – General ME2L - PO List Display by Vendor ME2N - PO List Display by PO Number ME51N - Create Purchase Requisition ME52N - Change Purchase Requisition ME53N - Display Purchase Requisition ME5A - PR List Display - General ME5J - PR List Display by Project/WBS ME5K - PR List Display by Account Assignment – General MIR4 - Display Invoice Document MIR5 - Display List of Invoice Documents S_ALR_87012082 - Vendor Balance Display SBWP - Business Workplace SO01 - Business Workplace: Inbox ZSPPE_ASSET_PFOLIO – Asset Management Portfolio Report ZSSC_DD448 - Create DD448 Form ZSSC_PRINT_PR – Print PR/Quote Purchase BD87 - Status Monitor for ALE Messages Requisition FB03 - Display Document Interface FBD3 - Display Recurring Document Processing Monitor GD23 - FI-SL: Local Actual Document Display IW33 - Display PM Order MB03 - Display Material Document MB51 - Material Document List For Official Use Only Page 70
  • 71.
    SAP Transaction andCommand Codes Job Aid GFEBS Role Transaction Codes ME23N - Display Purchase Order ME2J - PO List Display by Project/WBS ME2K - PO List Display by Account Assignment – General ME2L - PO List Display by Vendor ME2N - PO List Display by PO Number ME53N - Display Purchase Requisition ME5A - PR List Display - General ME5J - PR List Display by Project/WBS ME5K - PR List Display by Account Assignment – General MIR4 - Display Invoice Document MIR5 - Display List of Invoice Documents S_ALR_87012082 - Vendor Balance Display SBWP - Business Workplace SO01 - Business Workplace: Inbox WE02 - IDoc List WE09 - Search for IDoc in Database ZOS_IST - IDoc Status Report ZSPPE_ASSET_PFOLIO – Asset Management Portfolio Report ZSSC_PRINT_PR – Print PR/Quote ZSSC_SPS_PR – PR ACK NCK ALV Report Purchase FB03 - Display Document Requisition FBD3 - Display Recurring Document Approver GD23 - FI-SL: Local Actual Document Display IW33 - Display PM Order MB03 - Display Material Document MB51 – Material Document List ME23N - Display Purchase Order ME2J - PO List Display by Project/WBS ME2K - PO List Display by Account Assignment – General ME2L - PO List Display by Vendor ME2N - PO List Display by PO Number ME52N - Change Purchase Requisition ME53N - Display Purchase Requisition ME5A - PR List Display - General ME5J - PR List Display by Project/WBS ME5K - PR List Display by Account Assignment – General MIR4 - Display Invoice Document MIR5 - Display List of Invoice Documents S_ALR_87012082 - Vendor Balance Display SBWP - Business Workplace SO01 - Business Workplace: Inbox ZSPPE_ASSET_PFOLIO – Asset Management Portfolio Report ZSSC_DD448 - Create DD448 Form ZSSC_PRINT_PR – Print PR/Quote For Official Use Only Page 71
  • 72.
    SAP Transaction andCommand Codes Job Aid GFEBS Role Transaction Codes ZSSC_SPS_PR - PR ACK NCK ALV Report Purchase FB03 - Display Document Requisition FBD3 - Display Recurring Document Funds FMSK - Commitment Item Check Certifier GD23 - FI-SL: Local Actual Document Display IW33 - Display PM Order MB03 - Display Material Document MB51 – Material Document List ME23N - Display Purchase Order ME2J - PO List Display by Project/WBS ME2K - PO List Display by Account Assignment – General ME2L - PO List Display by Vendor ME2N - PO List Display by PO Number ME52N - Change Purchase Requisition ME53N - Display Purchase Requisition ME5A - PR List Display - General ME5J - PR List Display by Project/WBS ME5K - PR List Display by Account Assignment – General MIR4 - Display Invoice Document MIR5 - Display List of Invoice Documents S_ALR_87012082 - Vendor Balance Display SBWP - Business Workplace SO01 - Business Workplace: Inbox ZSFM_FCTR_SECURITY – Funds Center Security Report ZSPPE_ASSET_PFOLIO – Asset Management Portfolio Report ZSSC_PRINT_PR – Print PR/Quote ZSSCF_DD448 - Create DD448 Form ZSSC_SPS_PR - PR ACK NCK ALV Report Purchase FB03 - Display Document Order FBD3 - Display Recurring Document Processor FMFG_PO_HISTORY - Display a List of Accounting Document for Purchase Orders FMFG_PO_POST - Post Held Purchase Orders FMZ1 - Funds Commitment: Create InitScrn FMZ2 - Change Funds Commitment FMZ3 - Funds Commitment: Display InitScrn GD23 - FI-SL: Local Actual Document Display IW33 - Display PM Order MB03 - Display Material Document MB51 – Material Document List ME21N- Create Purchase Order For Official Use Only Page 72
  • 73.
    SAP Transaction andCommand Codes Job Aid GFEBS Role Transaction Codes ME22N - Change Purchase Order ME23N - Display Purchase Order ME2J - PO List Display by Project/WBS ME2K - PO List Display by Account Assignment – General ME2L - PO List Display by Vendor ME2N - PO List Display by PO Number ME53N - Display Purchase Requisition ME5A - PR List Display - General ME5J - PR List Display by Project/WBS ME5K - PR List Display by Account Assignment – General MIR4 - Display Invoice Document MIR5 - Display List of Invoice Documents S_ALR_87012082 - Vendor Balance Display S_ALR_87012086 - Vendor List S_P99_41000147 - Funds Commitment: Display InitScrn SBWP - Business Workplace SO01 - Business Workplace: Inbox XD03 - Display Customer (Centrally) XK03 - Display Vendor Master ZSPPE_ASSET_PFOLIO – Asset Management Portfolio Report ZSSC_FCM_FP – FCM Financial Position Report ZSSC_FCM_OUT - FCM Financial Position Outbound Interface Trigger Purchase BD87 - Status Monitor for ALE Messages Order FB03 - Display Document Interface FBD3 - Display Recurring Document Processing Monitor FMY3 - Funds Precommitment: Display InitScrn FMZ2 - Change Funds Commitment FMZ3 - Funds Commitment: Display InitScrn GD23 - FI-SL: Local Actual Document Display IW33 - Display PM Order MB03 - Display Material Document MB51 – Material Document List ME23N - Display Purchase Order ME2J - PO List Display by Project/WBS ME2K - PO List Display by Account Assignment – General ME2L - PO List Display by Vendor ME2N - PO List Display by PO Number ME53N - Display Purchase Requisition ME5A - PR List Display – General ME5J - PR List Display by Project/WBS ME5K - PR List Display by Account Assignment – General For Official Use Only Page 73
  • 74.
    SAP Transaction andCommand Codes Job Aid GFEBS Role Transaction Codes MIR4 - Display Invoice Document MIR5 - Display List of Invoice Documents S_ALR_87012082 - Vendor Balance Display S_ALR_87012086 - Vendor List SBWP - Business Workplace SO01 - Business Workplace: Inbox WE02 - IDoc List WE09 - Search for IDoc in Database XD03 - Display Customer (Centrally) XK03 - Display Vendor Master ZOS_IST - IDoc Status Report ZSPPE_ASSET_PFOLIO – Asset Management Portfolio Report ZSSC_SPS_PR - PR ACK NCK ALV Report Goods FB03 - Display Document Receipt FBD3 - Display Recurring Document Processor GD23 - FI-SL: Local Actual Document Display IW33 - Display PM Order MB02 – Change Material Document MB03 - Display Material Document MB1A – Goods Issue MB51 – Material Document List MBST – Cancel Material Document ME23N - Display Purchase Order ME2J - PO List Display by Project/WBS ME2K - PO List Display by Account Assignment – General ME2L - PO List Display by Vendor ME2N - PO List Display by PO Number ME53N - Display Purchase Requisition ME5A - PR List Display - General ME5J - PR List Display by Project/WBS ME5K - PR List Display by Account Assignment – General MIGO – Create Goods Receipt MIR4 - Display Invoice Document MIR5 - Display List of Invoice Documents ML81N – Service Entry Sheet MM03 – Display Material Master SBWP - Business Workplace SO01 - Business Workplace: Inbox ZSPPE_ASSET_PFOLIO – Asset Management Portfolio Report ZSSC_PRINT_PR – Print PR/Quote For Official Use Only Page 74
  • 75.
    SAP Transaction andCommand Codes Job Aid GFEBS Role Transaction Codes Goods FB03 - Display Document Receipt FBD3 - Display Recurring Document Interface GD23 - FI-SL: Local Actual Document Display Processing Monitor IW33 - Display PM Order MB03 - Display Material Document MB51 – Material Document List ME23N - Display Purchase Order ME2J - PO List Display by Project/WBS ME2K - PO List Display by Account Assignment – General ME2L - PO List Display by Vendor ME2N - PO List Display by PO Number ME53N - Display Purchase Requisition ME5A - PR List Display - General ME5J - PR List Display by Project/WBS ME5K - PR List Display by Account Assignment – General MIR4 - Display Invoice Document MIR5 - Display List of Invoice Documents S_ALR_87012082 - Vendor Balance Display SBWP - Business Workplace SO01 - Business Workplace: Inbox WE02 - IDoc List ZOS_IST - IDoc Status Report ZSPPE_ASSET_PFOLIO – Asset Management Portfolio Report Invoice F.14 - Create Posting Documents from Recurring Documents Processor F.15 - List of Recurring Documents F.42 - Vendor Balances in Local Currency F-44 - Clear Vendor F-47 - Down Payment Request F-48 - Post Vendor Down Payment F-54 - Down Payment Clearing FB02 - Change Document FB03 - Display Document FB08 - Reverse Document FB60 - Enter Incoming Invoice (FI) FB65 - Enter Incoming Credit Memo (FI) FBD1 - Create Recurring Document FBD2 - Change Recurring Document FBD3 - Display Recurring Document FBD5 - Realize Recurring Payment FBL1N - Vendor Line Item Display FBR2 - Post Document For Official Use Only Page 75
  • 76.
    SAP Transaction andCommand Codes Job Aid GFEBS Role Transaction Codes FBRA - Reset Cleared Items FK10 - Vendor Balance Display FK10N - Vendor Balance Display FMDPREF – Down Payment Request FMFG_E_TRANS_REG - Federal Transaction Register FMRC – Penalty Reason Codes Report in ALV GD23 - FI-SL: Local Actual Document Display IW33 - Display PM Order MB03 - Display Material Document MB51 – Material Document List ME23N - Display Purchase Order ME2J - PO List Display by Project/WBS ME2K - PO List Display by Account Assignment – General ME2L - PO List Display by Vendor ME2N - PO List Display by PO Number ME53N - Display Purchase Requisition ME5A - PR List Display - General ME5J - PR List Display by Project/WBS ME5K - PR List Display by Account Assignment – General MIR4 - Display Invoice Document MIR5 - Display List of Invoice Documents MIRO - Enter Incoming Invoice (MM) MR8M - Cancel Invoice Document MRKO - Consignment and Pipeline Settlement S_ALR_87012078 - Due Date Analysis for Open Items S_ALR_87012082 - Vendor Balance Display S_ALR_87012085 - Vendor Appraisal with OI Sorted List S_ALR_87012086 - Vendor List S_P00_07000134 – Generic Withholding Tax Reporting SBWP - Business Workplace SM35 - Batch Input Monitoring SO01 - Business Workplace: Inbox XD03 - Display Customer (Centrally) XK03 - Display Vendor Master ZPMT_WAREHOUSE – Payment Warehouse ZSPPE_ASSET_PFOLIO – Asset Management Portfolio Report ZSSC_1099_WH_LOAD – 1099 Withholding Tax Extension ZSSC_CAPSRPT - Invoice Entered By Day Report ZSSC_FCM_FP – FCM Financial Position Report ZSSC_FLUX_MTCE - Flux Rate Table Maintenance ZSSC_GET_FLUX_RATE - Get Flux Rate ZSSC_INVOICE_LOAD – Invoice Upload Extension from Load Template For Official Use Only Page 76
  • 77.
    SAP Transaction andCommand Codes Job Aid GFEBS Role Transaction Codes Site Invoice F.14 - Create Posting Documents from Recurring Documents Processor F.15 - List of Recurring Documents F.42 - Vendor Balances in Local Currency F-47 - Down Payment Request FB02 - Change Document FB08 - Reverse Document FB60 - Enter Incoming Invoice (FI) FB65 - Enter Incoming Credit Memo (FI) FBD1 - Create Recurring Document FBD2 - Change Recurring Document FBD5 - Realize Recurring Payment FBL1N - Vendor Line Item Display FBR2 - Post Document FK10 - Vendor Balance Display FK10N - Vendor Balance Display FMFG_E_TRANS_REG - Federal Transaction Register MB03 – Display Material Document S_ALR_87012078 - Due Date Analysis for Open Items S_ALR_87012082 - Vendor Balance Display S_ALR_87012085 - Vendor Appraisal with OI Sorted List S_ALR_87012086 - Vendor List S_P00_07000134 – Generic Withholding Tax Reporting XD03 - Display Customer (Centrally) XK03 - Display Vendor Master ZSSC_CAPSRPT - Invoice Entered By Day Report ZSSC_FCM_FP – FCM Financial Position Report ZSSC_INVOICE_LOAD – Invoice Upload Extension from Load Template Invoice BD87 - Status Monitor for ALE Messages Interface F.42 - Vendor Balances in Local Currency Processing FB03 - Display Document Monitor FBD3 - Display Recurring Document FBL1N - Vendor Line Item Display FK10 - Vendor Balance Display FK10N - Vendor Balance Display GD23 - FI-SL: Local Actual Document Display IW33 - Display PM Order MB03 - Display Material Document MB51 – Material Document List ME23N - Display Purchase Order ME2J - PO List Display by Project/WBS ME2K - PO List Display by Account Assignment – General ME2L - PO List Display by Vendor ME2N - PO List Display by PO Number ME53N - Display Purchase Requisition For Official Use Only Page 77
  • 78.
    SAP Transaction andCommand Codes Job Aid GFEBS Role Transaction Codes ME5A - PR List Display - General ME5J - PR List Display by Project/WBS ME5K - PR List Display by Account Assignment – General MIR4 - Display Invoice Document MIR5 - Display List of Invoice Documents S_ALR_87012082 - Vendor Balance Display S_ALR_87012086 - Vendor List SBWP - Business Workplace SO01 - Business Workplace: Inbox WE02 - IDoc List XD03 - Display Customer (Centrally) XK03 - Display Vendor Master ZOS_IST - IDoc Status Report ZSPPE_ASSET_PFOLIO – Asset Management Portfolio Report Site Invoice BD87 – Status Monitor for ALE Messages Interface FB03 – Display Document Processing MB03 – Display Material Document Monitor ME23N – Display Purchase Order ME53N – Display Purchase Requisition MIR4 – Display Invoice Document MIR5 – Display List of Invoice Documents S_ALR_87012086 – Vendor List SBWP – Business Workplace WE02 – IDoc List GPC Account CRS1 – Create Credit Card Master Record Maintainer CRS2 – Change Credit Card Master Record CRS3 – Display Credit Card Master Record Release MRBR – Manage Blocked Invoices Blocked Invoice Processor For Official Use Only Page 78
  • 79.
    SAP Transaction andCommand Codes Job Aid GFEBS Role Transaction Codes PR Approval FB03 - Display Document Maintainer FBD3 - Display Recurring Document GD23 - FI-SL: Local Actual Document Display IW33 - Display PM Order ME23N - Display Purchase Order ME2J - PO List Display by Project/WBS ME2K - PO List Display by Account Assignment – General ME2L - PO List Display by Vendor ME2N - PO List Display by PO Number ME53N - Display Purchase Requisition ME5A - PR List Display - General ME5J - PR List Display by Project/WBS ME5K - PR List Display by Account Assignment – General MIR4 - Display Invoice Document MIR5 - Display List of Invoice Documents S_ALR_87012082 - Vendor Balance Display SBWP - Business Workplace SO01 - Business Workplace: Inbox ZSPPE_ASSET_PFOLIO – Asset Management Portfolio Report ZSSC_WF_USERS - Custom Report GR/IR F.13 – Automatic Clearing without Definition of Clearing Currency Processor MR11 - GR/IR Account Balance MR11SHOW - Carryout Goods Receipt ZSPPE_ASSET_PFOLIO – Asset Management Portfolio Report Payment F110 - Automatic Payment Transactions Processor F-47 - Down Payment Request F-48 - Post Vendor Down Payment F-54 - Down Payment Clearing FB03 - Display Document FBD3 - Display Recurring Document FBL1N - Vendor Line Item Display FBZ0 - Payment Proposal FCH1 - Display Check FMDPEF – Down Payment FMFG_E_ZFZALI00 - Display a Payment Settlement List FMRC - Penalty Reason Codes Report in ALV FMST - Evaluation of Penalty Interest GD23 - FI-SL: Local Actual Document Display IW33 - Display PM Order MB03 - Display Material Document MB51 – Material Document List For Official Use Only Page 79
  • 80.
    SAP Transaction andCommand Codes Job Aid GFEBS Role Transaction Codes ME23N - Display Purchase Order ME2J - PO List Display by Project/WBS ME2K - PO List Display by Account Assignment – General ME2L - PO List Display by Vendor ME2N - PO List Display by PO Number ME53N - Display Purchase Requisition ME5A - PR List Display - General ME5J - PR List Display by Project/WBS ME5K - PR List Display by Account Assignment – General MIR4 - Display Invoice Document MIR5 - Display List of Invoice Documents S_ALR_87012078 - Due Date Analysis for Open Items S_ALR_87012082 - Vendor Balance Display S_ALR_87012085 - Vendor Appraisal with OI Sorted List S_ALR_87012086 - Vendor List S_P00_07000134 – Generic Withholding Tax Reporting S_P99_41000099 - Payment List SBWP - Business Workplace SO01 - Business Workplace: Inbox XD03 - Display Customer (Centrally) XK03 - Display Vendor Master ZPMT_WAREHOUSE – Payment Warehouse ZSPPE_ASSET_PFOLIO – Asset Management Portfolio Report ZSSC_CAPSRPT - Invoice Entered By Day Report Payment F110 - Automatic Payment Transactions Certifier FB03 - Display Document FBD3 - Display Recurring Document FBL1N - Vendor Line Item Display FBZ0 - Payment Proposal FCH1 - Display Check FMFG_E_ZFZALI00 - Display a Payment Settlement List GD23 - FI-SL: Local Actual Document Display IW33 - Display PM Order MB03 - Display Material Document MB51 – Material Document List ME23N - Display Purchase Order ME2J - PO List Display by Project/WBS ME2K - PO List Display by Account Assignment – General ME2L - PO List Display by Vendor ME2N - PO List Display by PO Number ME53N - Display Purchase Requisition ME5A - PR List Display - General ME5J - PR List Display by Project/WBS For Official Use Only Page 80
  • 81.
    SAP Transaction andCommand Codes Job Aid GFEBS Role Transaction Codes ME5K - PR List Display by Account Assignment – General MIR4 - Display Invoice Document MIR5 - Display List of Invoice Documents S_ALR_87012082 - Vendor Balance Display S_ALR_87012086 - Vendor List S_P99_41000099 - Payment List SBWP - Business Workplace SO01 - Business Workplace: Inbox XD03 - Display Customer (Centrally) XK03 - Display Vendor Master ZPMT_WAREHOUSE – Payment Warehouse ZSPPE_ASSET_PFOLIO – Asset Management Portfolio Report ZSSC_CAPSRPT - Invoice Entered By Day Report Vendor FB03 - Display Document Master Data FBD3 - Display Recurring Document Display FI01 – Create Bank: Initial Screen FI02 – Change Bank: Initial Screen FI03 - Display Bank: Initial Screen GD23 - FI-SL: Local Actual Document Display MB5L - List of Stock Values: Balances ME13 - Display PIR MKVZ - List of Vendors: Purchasing MM03 - Display Material Master S_ALR_87012082 - Vendor Balance Display S_ALR_87012086 - Vendor List XD03 - Display Customer (Centrally) XK03 - Display Vendor Master ZSPPE_ASSET_PFOLIO – Asset Management Portfolio Report Contract FB03 – Display Document Viewer FBD3 – Display Recurring Document GD23 – FI-SL: Local Actual Document Display IW33 - Display PM Order MB03 – Display Material Document MB51 – Material Document List ME23N - Display Purchase Order ME2J - PO List Display by Project/WBS ME2K - PO List Display by Account Assignment – General ME2L - PO List Display by Vendor ME2N - PO List Display by PO Number ME53N - Display Purchase Requisition ME5A - PR List Display – General ME5J - PR List Display by Project/WBS ME5K - PR List Display by Account Assignment – General For Official Use Only Page 81
  • 82.
    SAP Transaction andCommand Codes Job Aid GFEBS Role Transaction Codes MIR4 – Display Invoice Document MIR5 – Display List of Invoice Documents S_ALR_87012082 – Vendor Balance Display S_ALR_87012086 - Vendor List SBWP - Business Workplace SO01 - Business Workplace: Inbox WE02 - IDoc List WE09 - Search for IDoc in Database XK03 - Display Vendor Master ZOS_IFV – IDoc Field Values Report ZOS_IST – IDoc Status Report ZSPPE_ASSET_PFOLIO – Asset Management Portfolio Report ZSSC_CAPSRPT – Invoice Entered by Day Report ZSSC_SPS_PR - PR ACK NCK ALV Report Exchange BD87 - Status Monitor for ALE Messages Rate Monitor OB08 - Change View: Currency Exchange Rates WE02 - IDoc List ZSSC_FLUX_MTCE - Flux Rate Table Maintenance Non-ITS OB08 – Change View: Currency Exchange Rates Exchange Rate Monitor Default Pay ZSSC_USER_PAY_OFFICE – Maintenance of Pay Office DoDAAC Table Office DoDAAC Table Maintainer 1099 FB02 - Change Document Reporter FB03 – Display Document FBL1N – Vendor Line Item Display ZSSC_1099_REPORT - Outbound 1099 Report to DFAS 103 ARNG FB03 - Display Document Movement FBD3 - Display Recurring Document Type Goods GD23 - FI-SL: Local Actual Document Display Receipt IW33 - Display PM Order Processor MB02 – Change Material Document MB03 - Display Material Document MB1A – Goods Issue MB51 – Material Document List MBST – Cancel Material Document ME23N - Display Purchase Order ME2J - PO List Display by Project/WBS ME2K - PO List Display by Account Assignment – General ME2L - PO List Display by Vendor For Official Use Only Page 82
  • 83.
    SAP Transaction andCommand Codes Job Aid GFEBS Role Transaction Codes ME2N - PO List Display by PO Number ME53N - Display Purchase Requisition ME5A - PR List Display - General ME5J - PR List Display by Project/WBS ME5K - PR List Display by Account Assignment – General MIGO – Create Goods Receipt MIR4 - Display Invoice Document MIR5 - Display List of Invoice Documents MM03 – Display Material Master S_ALR_87012082 - Vendor Balance Display S_ALR_87012086 - Vendor List SBWP - Business Workplace SO01 - Business Workplace: Inbox ZSPPE_ASSET_PFOLIO – Asset Management Portfolio Report 105 ARNG FB02 – Change Document Movement FB03 - Display Document Type Goods FBD3 - Display Recurring Document Acceptance Processor GD23 - FI-SL: Local Actual Document Display IW33 - Display PM Order MB02 – Change Material Document MB03 - Display Material Document MB1A – Goods Issue MB51 - List Display of Material Documents (GRs) MBST – Cancel Material Document ME23N - Display Purchase Order ME2J - PO List Display by Project/WBS ME2K - PO List Display by Account Assignment – General ME2L - PO List Display by Vendor ME2N - PO List Display by PO Number ME53N - Display Purchase Requisition ME5A - PR List Display - General ME5J - PR List Display by Project/WBS ME5K - PR List Display by Account Assignment – General MIGO – Create Goods Receipt MIR4 - Display Invoice Document MIR5 - Display List of Invoice Documents ML81N – Service Entry Sheet MM03 – Display Material Master S_ALR_87012082 - Vendor Balance Display SBWP - Business Workplace SO01 - Business Workplace: Inbox ZPMT_WAREHOUSE – Payment Warehouse For Official Use Only Page 83
  • 84.
    SAP Transaction andCommand Codes Job Aid GFEBS Role Transaction Codes ZSPPE_ASSET_PFOLIO – Asset Management Portfolio Report ARNG MB02 – Change Material Document Service Entry MB03 – Display Material Document Sheet ML81N – Service Entry Sheet Processor FMS BD87 - Status Monitor for ALE Messages Interface SBWP - Business Workplace Processing SP01 - Output Controller Monitor WE02 - IDoc List WE09 - Search for IDoc in Database ZOS_IFV - IDoc Field Values Report ZOS_IST - IDoc Status Report Click here to return to top. For Official Use Only Page 84