SlideShare a Scribd company logo
1 of 28
Hoarding
Presentation by:
Sanjay Kumar (Special Officer )
Jamshedpur Notified Area Committee, Jamshedpur, Jharkhand
Jamshedpur
Steel City: a City of Tomorrow
Manhole turned into Machine Hole
(Elimination of Manual Scavenging in Sewer Cleaning)
Since 1st Jan 2021
CITY BACKGROUND
• Population covered- 7.7lakhs (Estimated)
• Avg. daily water supply - 80 MLD
• Length of Water Mains: - 640 Km
• Length of Sewer Lines- 579 Km
• 4 Sewage Treatment Plant : 64 MLD
• 10 sewage pumping stations: Automated
Operation
• 20000 Manhole
• Total number of SafaiMitras Engaged : 133
• Area- 64 Sq Km
• No of wards -10
• Population (2011)- 6.3 lakhs
• Green Cover-37% (Approx)
• Road Length:- 713 Km
89%
11%
SANITATION SYSTEM
households connected to sewerage
network:
Challenges: The conventional method of sewer cleaning requires manual entry.
THE GREATER SOCIETAL PROBLEM
4
ZERO MANUAL ENTRY
CHALLENGES:
• Technical
• Safety
• Social
THOUGHT:
• Design
• Mechanization
• Social Stigma
IDEAS:
• Design Change
• Study the application of
various cleaning equipment
• Create a healthy and safe
work environment for all
and create a “sense of
pride” amongst the
workmen involved in
cleaning
BEFORE SAFAIMITRA SURAKSHA CHALLENGE
ISSUES /CHALLENGES FACED DURING SEWER LINE DESILTING
Technical problem :
•Non-Uniform manhole designs
•Unavailability of Approach for cleaning of
manholes
•Unplanned construction of manholes
•One solution(machine) does not address all
maintenance requirements
Safety problem:
• Sewer line desilting required manual entry
• Exposure to poisonous gases inside manholes
• Exposure to unhygienic condition leading to
health hazard
• Depth of manholes were different
Social Problems:
• Work Dignity and Self Respect
Item Depth in Mtr. Quantity Cleaning Frequency
Removing Sewer Obstruction 6000 Nos. Compt. Based
Desilting of Branch Sewer Up to 2.0 213 KM. Compt. / Requirement Based
Desilting of Main Sewer >1.5 to 3 235 KM.
2-3 Times/Year
Desilting of Trunk Sewer >1.5 to 8 102 KM.
Desilting of Manhole
Up to 1.5 12194 Nos. Compt. / Requirement Based
>1.5 to 2.5 6779 Nos.
2-3 Times/Year
>2.5 to 8 1030 Nos
7
PROCESS FOLLOWED BEFORE SmSC
1. Opening cover
2. Checking Gases
3. Placing Rope Ladder
4.Workmen Entry 5.Workmen Entry
6. Desilting work
AVERAGE ACTIVITY TIME & ASSOCIATED RISK
Approx Time line activity for Manhole Cleaning/ Each Manhole
Sr.
No.
Activity Approx. Time in Min Risk
1 Opening of Manhole 1 Low
2 Visual Inspection of Man Hole from outside 1 Low
3 Checking of Gas 1 Low
4 Fixing of Entry Ladder 1 Low
5 Entry of Work Men 1 Low
6 Desilting of Manhole (Worker Inside manhole) 60 High
7 Exit of Work Men from Manhole 1 Low
8 Removal of Entry Ladder 1 Low
9 Closing of Manhole 1 Low
Average Cleaning time/ Each Manhole 68
Worker has to work in side the Manhole = 60 Min
MH
MH
SEWER PIPE
SILT SILT
OXYGEN AVAILABILITY INSIDE MANHOLE (DEPTH WISE)
The availability of oxygen inside manhole decreases with increase in depth
9
Sanitation Infrastructure “Pre-SmSC”
S.No Name of Maintenance Machine
Number of
Vehicles
(Nov 2020)
Requirement as
per CPHEEO
Manual
Number of
Vehicles
(July 2022)
1. Combination Hydrovac Equipment 2 3 3
2. Number of Grabbers/Desilting
Machines
2 4 4
3. Number of standard de-sludging
vehicles
2 2 8
4. Sewer Inspection Camera Apparatus 6 6 6
5. Hydro Jetting Machines 3 5 5
6. Power Bucket machine 1 2 2
7. Power Rodding Apparatus 16 16 16
8. Hydraulic Sewer Root cutters 1 3 3
SANITATION INFRASTRUCTURE “PRESENT DAY”
Super Sucker Jetting Machine Jetting Machine
Jetting
Machine
Suction cum
Jetting Machine Grabber
Jetting
Machine
Desludging Machine
Desludging Machine
MANHOLE TO MACHINE-HOLE SINCE JAN 2021
Grab Machine
Power Bucket
Machine
Suction cum
Jetting Machine
Super Sucker Machine Power Bucket Machine
Super Sucker
Machine
Power Bucket
Machine
DEPLOYMENT OF SMALL SUCTION AND JETTING MACHINE
13
1. Maximum Manhole up to 2 Mtr Situated at back alley or non road
area
2. No approach for big vehicle due to encroachment.
3. Unsafe condition at non road area for movement of big vehicle.
4. Demand of customer for mechanized cleaning.
Benefits :-
After deployment of small suction and small jetting
machine developed on TATA Intra it is easily reached up
to narrow alley / non road area and not required to
enter workmen inside manhole for cleaning.
Challenges:
Small
Jetting
Machine
(New)
Small
Suction
Machine
(New)
HAND MADE EQUIPMENT TO STOP HUMAN ENTRY
14
Hand Grab for
removing
Silt/Material
Hand Tools for removing Silt/Material from
deep Manhole
Hand Tools for
removing
Plastics, Thermos
coal
Hand Tools for removing
Plastics, Thermos coal from Sewer
ACTIVITY TIME AFTER FINAL IMPLEMENTATION
15
Approx Time line activity for Manhole Cleaning/ Each Manhole`
Sr.
No.
Activity
Earlier Activity Time
in Min (R0)
Final Activity Time in
Min (R2)
1 Opening of Manhole 1 1*
2 Visual Inspection of Manhole 1 1*
3 Checking of Gas 1 Not Required
4 Fixing of Entry Ladder 1 Not Required
5 Entry of Work Men 1.00 Not Required
6
Desilting of Manhole (Worker Inside
manhole)
60 0
7 Exit of Work Men from Manhole 1 Not Required
8 Removal of Entry Ladder 1 Not Required
9 Closing of Manhole 1 1*
Average Cleaning time/ Each Manhole
68 3
No Worker required to work inside the Manhole
* Risk of fall of person mitigated by immediate placing of M S Grill on opening.
16
ISSUES WITH DIFFERENT TYPES OF MANHOLES
The chockage of Sewer lines are cleared through
downstream manhole. Cleaning can only be
ensured from the areas marked with This
requires manual entry for access
Point of
manual
entry
Point of
manual
entry
Point of
manual
entry
17
To further aid the
cleaning mechanism 3
Nos opening were
provided in T shape & 2
Nos in L Shape, after
dismantling and recasting
of manhole top slab
CHANGE IN DESIGN OF EXISTING MANHOLES
Point of
manual
entry
AFTER
BEFORE
Point of
manual
entry
point of machine
pipe entry
CONVERSION OF L & T TYPE MANHOLE
18
BEFORE
AFTER
AFTER
MANUAL METHOD OF SEWER PIPE CLEANING
MH
MH
SEWER PIPE
SILT SILT
MECHANIZED CLEANING OF SEWER PIPE USING POWER BUCKET
THEN
NOW
MECHANIZATION JOURNEY UNDER SMSC
• Formation of Responsible Sanitation
Authority (RSA), Sanitation Response Unit
(SRU)
• Establishment of Call Centre
• Establishment of Safety Training Centre
• For handling of mechanized equipment
special training to SafaiMitras
• Public sensitization on safety measures
• Purchase of Mechanized Equipment
• Ban on Manual Scavenging
PROMOTING SAFETY, DIGNITY AND SOCIAL SECURITY
• Daily Tool Box Talk
• Mandatory PPE uses
• Mandatory Safety Training
• Converting Manhole to Machine Hole
• Geo-Tagging of all the septic tanks
Daily Tool Box Talk
Mandatory Safety Training
Converting Manhole to Machine Hole
Feast for SafaiMitras
PROMOTING SAFETY, DIGNITY AND SOCIAL SECURITY
Recognition of Best Workers on monthly basis
Regular Health Checkup Camps for SafaiMitras
CAPACITY BUILDING AND WELFARE MEASURES FOR SAFAIMITRAS
• Linkage to Social Welfare Schemes
• Regular Mass Meeting
• Linkage with PM Jivan Jyoti Bima
• Regular Health Check-up Camp
PRACTICES : CONNECTING WITH THE FAMILY MEMBERS
“CITIZEN CONNECTS” TO SPREAD AWARENESS FOR SAFETY OF SAFAIMITRAS
• More safety to SafaiMitras
• Strategic IEC outreach
• Customer contact program in every 2
months in each locality
• Two app's of TSUISL are used i.e
Zimmedaar Nagrik and JUSCO Sahyog as
customer support
MONITORING OF WORKMEN ENTRY
We achieved “ZERO” workmen entry for manhole cleaning
From 1st January 2021
55
100 100 100
Dec-20 Jan-21 Feb-21 Mar-21
% Elimination of Manual entry in
Manhole < 2m depth
5.45
18.66
33.33
80
51.82
100 100 100
% Elimination of Manual Scavenging
Manhole Depth >2 mtr.
Phase 1 Phase 2
OTHER BENEFITS
Customer KPI FY-19 FY-20 FY-21 FY-22
Compliance within SLG 94% 95% 95% 98%
Customer Satisfaction performance score for
Waste water services
89% 90% 94% 95%
TESTIMONIAL
For SafaiMitras
• Man hole worker to a mechanized sewer
worker
• No Life at Risk
• Better working condition
• Social Security- Linked with schemes
• Recognition- Working with Dignity
• Uplifted SafaiMitras for a better and
healthy life
Safety Dignity Social Security
Name: Mr. Baset Hasda
Occupation: Sewer Worker Working Zone: West
City: Jamshedpur State: Jharkhand
SAFAIMITRAS are the backbone of the
City, they are our Responsibility:
Some Sewer Operators & Sewer Men feeling dignified…
Thank You
Vinod Jha Atisher Bhumiz Aazadi Bagti Kuna Hembrom

More Related Content

Similar to SafaiMitra_Suraksha_Webinar_Jamshedpur.pptx

AUTOMATIC PNEUMATIC INTERNAL PIPE SCRAP REMOVING MACHINE2.pptx
AUTOMATIC PNEUMATIC INTERNAL PIPE SCRAP REMOVING MACHINE2.pptxAUTOMATIC PNEUMATIC INTERNAL PIPE SCRAP REMOVING MACHINE2.pptx
AUTOMATIC PNEUMATIC INTERNAL PIPE SCRAP REMOVING MACHINE2.pptxVishahanVenthan
 
IRJET- Development in Floor Cleaner Machine
IRJET- Development in Floor Cleaner MachineIRJET- Development in Floor Cleaner Machine
IRJET- Development in Floor Cleaner MachineIRJET Journal
 
Semi-Automatic Night Soil Cleaner in Railways and Multipurpose Applications
Semi-Automatic Night Soil Cleaner  in Railways and Multipurpose ApplicationsSemi-Automatic Night Soil Cleaner  in Railways and Multipurpose Applications
Semi-Automatic Night Soil Cleaner in Railways and Multipurpose ApplicationsIRJET Journal
 
Micro-Tunnelling: Productivity improvement for Asset and Apparatus Owners.
Micro-Tunnelling: Productivity improvement for Asset and Apparatus Owners.Micro-Tunnelling: Productivity improvement for Asset and Apparatus Owners.
Micro-Tunnelling: Productivity improvement for Asset and Apparatus Owners.Carlo Gabriele Borri MACostE AMICE
 
Trenchless Technology for Laying Underground pipes.
Trenchless Technology for  Laying Underground pipes.Trenchless Technology for  Laying Underground pipes.
Trenchless Technology for Laying Underground pipes.Himanshu Rao
 
Drycake Headworks V2303.pptx
Drycake Headworks V2303.pptxDrycake Headworks V2303.pptx
Drycake Headworks V2303.pptxmarkvanderbeken
 
IRJET - Design and Development of Automatic Urinal Flushing System
IRJET - Design and Development of Automatic Urinal Flushing SystemIRJET - Design and Development of Automatic Urinal Flushing System
IRJET - Design and Development of Automatic Urinal Flushing SystemIRJET Journal
 
Auto feed hydro drill , clamp index 2013 adv akt ignov
Auto feed hydro drill  , clamp index 2013 adv akt ignovAuto feed hydro drill  , clamp index 2013 adv akt ignov
Auto feed hydro drill , clamp index 2013 adv akt ignovchockalingam athilingam
 
IRJET- Moss Removal Machine
IRJET- Moss Removal MachineIRJET- Moss Removal Machine
IRJET- Moss Removal MachineIRJET Journal
 
Barredoras mecanicas - Rendimiento y recomendaciones
Barredoras mecanicas - Rendimiento y recomendaciones Barredoras mecanicas - Rendimiento y recomendaciones
Barredoras mecanicas - Rendimiento y recomendaciones Martin Bañuelos
 
STUDY AND DESIGN OF SEMI-AUTOMATIC ROAD CLEANING MACHINE
STUDY AND DESIGN OF SEMI-AUTOMATIC ROAD CLEANING MACHINESTUDY AND DESIGN OF SEMI-AUTOMATIC ROAD CLEANING MACHINE
STUDY AND DESIGN OF SEMI-AUTOMATIC ROAD CLEANING MACHINEIRJET Journal
 
IRJET- A Review Paper on Fabrication of Automatic Sewage Monitoring System
IRJET- A Review Paper on Fabrication of Automatic Sewage Monitoring SystemIRJET- A Review Paper on Fabrication of Automatic Sewage Monitoring System
IRJET- A Review Paper on Fabrication of Automatic Sewage Monitoring SystemIRJET Journal
 
NMPT-_PPT-_SHIRISH.pptx
NMPT-_PPT-_SHIRISH.pptxNMPT-_PPT-_SHIRISH.pptx
NMPT-_PPT-_SHIRISH.pptxVortexBolthe
 
IRJET- Design and Fabrication of River Cleaning Machine
IRJET- Design and Fabrication of River Cleaning MachineIRJET- Design and Fabrication of River Cleaning Machine
IRJET- Design and Fabrication of River Cleaning MachineIRJET Journal
 
Kelani River Water Treatment Plant in Colombo
Kelani River Water Treatment Plant in ColomboKelani River Water Treatment Plant in Colombo
Kelani River Water Treatment Plant in ColomboAnton Ricalovskis
 
IRJET- Water Supply through Underground Tunnel from Thane to Bhandup using TBM
IRJET- Water Supply through Underground Tunnel from Thane to Bhandup using TBMIRJET- Water Supply through Underground Tunnel from Thane to Bhandup using TBM
IRJET- Water Supply through Underground Tunnel from Thane to Bhandup using TBMIRJET Journal
 

Similar to SafaiMitra_Suraksha_Webinar_Jamshedpur.pptx (20)

8445806
84458068445806
8445806
 
AUTOMATIC PNEUMATIC INTERNAL PIPE SCRAP REMOVING MACHINE2.pptx
AUTOMATIC PNEUMATIC INTERNAL PIPE SCRAP REMOVING MACHINE2.pptxAUTOMATIC PNEUMATIC INTERNAL PIPE SCRAP REMOVING MACHINE2.pptx
AUTOMATIC PNEUMATIC INTERNAL PIPE SCRAP REMOVING MACHINE2.pptx
 
IRJET- Development in Floor Cleaner Machine
IRJET- Development in Floor Cleaner MachineIRJET- Development in Floor Cleaner Machine
IRJET- Development in Floor Cleaner Machine
 
Abhigyan
AbhigyanAbhigyan
Abhigyan
 
Semi-Automatic Night Soil Cleaner in Railways and Multipurpose Applications
Semi-Automatic Night Soil Cleaner  in Railways and Multipurpose ApplicationsSemi-Automatic Night Soil Cleaner  in Railways and Multipurpose Applications
Semi-Automatic Night Soil Cleaner in Railways and Multipurpose Applications
 
Micro-Tunnelling: Productivity improvement for Asset and Apparatus Owners.
Micro-Tunnelling: Productivity improvement for Asset and Apparatus Owners.Micro-Tunnelling: Productivity improvement for Asset and Apparatus Owners.
Micro-Tunnelling: Productivity improvement for Asset and Apparatus Owners.
 
Trenchless Technology for Laying Underground pipes.
Trenchless Technology for  Laying Underground pipes.Trenchless Technology for  Laying Underground pipes.
Trenchless Technology for Laying Underground pipes.
 
Drycake Headworks V2303.pptx
Drycake Headworks V2303.pptxDrycake Headworks V2303.pptx
Drycake Headworks V2303.pptx
 
IRJET - Design and Development of Automatic Urinal Flushing System
IRJET - Design and Development of Automatic Urinal Flushing SystemIRJET - Design and Development of Automatic Urinal Flushing System
IRJET - Design and Development of Automatic Urinal Flushing System
 
Engr,imran cv.cement.
Engr,imran cv.cement.Engr,imran cv.cement.
Engr,imran cv.cement.
 
Auto feed hydro drill , clamp index 2013 adv akt ignov
Auto feed hydro drill  , clamp index 2013 adv akt ignovAuto feed hydro drill  , clamp index 2013 adv akt ignov
Auto feed hydro drill , clamp index 2013 adv akt ignov
 
IRJET- Moss Removal Machine
IRJET- Moss Removal MachineIRJET- Moss Removal Machine
IRJET- Moss Removal Machine
 
Barredoras mecanicas - Rendimiento y recomendaciones
Barredoras mecanicas - Rendimiento y recomendaciones Barredoras mecanicas - Rendimiento y recomendaciones
Barredoras mecanicas - Rendimiento y recomendaciones
 
STUDY AND DESIGN OF SEMI-AUTOMATIC ROAD CLEANING MACHINE
STUDY AND DESIGN OF SEMI-AUTOMATIC ROAD CLEANING MACHINESTUDY AND DESIGN OF SEMI-AUTOMATIC ROAD CLEANING MACHINE
STUDY AND DESIGN OF SEMI-AUTOMATIC ROAD CLEANING MACHINE
 
IRJET- A Review Paper on Fabrication of Automatic Sewage Monitoring System
IRJET- A Review Paper on Fabrication of Automatic Sewage Monitoring SystemIRJET- A Review Paper on Fabrication of Automatic Sewage Monitoring System
IRJET- A Review Paper on Fabrication of Automatic Sewage Monitoring System
 
NMPT-_PPT-_SHIRISH.pptx
NMPT-_PPT-_SHIRISH.pptxNMPT-_PPT-_SHIRISH.pptx
NMPT-_PPT-_SHIRISH.pptx
 
IRJET- Design and Fabrication of River Cleaning Machine
IRJET- Design and Fabrication of River Cleaning MachineIRJET- Design and Fabrication of River Cleaning Machine
IRJET- Design and Fabrication of River Cleaning Machine
 
Kelani River Water Treatment Plant in Colombo
Kelani River Water Treatment Plant in ColomboKelani River Water Treatment Plant in Colombo
Kelani River Water Treatment Plant in Colombo
 
IRJET- Water Supply through Underground Tunnel from Thane to Bhandup using TBM
IRJET- Water Supply through Underground Tunnel from Thane to Bhandup using TBMIRJET- Water Supply through Underground Tunnel from Thane to Bhandup using TBM
IRJET- Water Supply through Underground Tunnel from Thane to Bhandup using TBM
 
E sewage
E  sewageE  sewage
E sewage
 

Recently uploaded

15-Minute City: A Completely New Horizon
15-Minute City: A Completely New Horizon15-Minute City: A Completely New Horizon
15-Minute City: A Completely New HorizonMorshed Ahmed Rahath
 
SLIDESHARE PPT-DECISION MAKING METHODS.pptx
SLIDESHARE PPT-DECISION MAKING METHODS.pptxSLIDESHARE PPT-DECISION MAKING METHODS.pptx
SLIDESHARE PPT-DECISION MAKING METHODS.pptxCHAIRMAN M
 
Maximizing Incident Investigation Efficacy in Oil & Gas: Techniques and Tools
Maximizing Incident Investigation Efficacy in Oil & Gas: Techniques and ToolsMaximizing Incident Investigation Efficacy in Oil & Gas: Techniques and Tools
Maximizing Incident Investigation Efficacy in Oil & Gas: Techniques and Toolssoginsider
 
21scheme vtu syllabus of visveraya technological university
21scheme vtu syllabus of visveraya technological university21scheme vtu syllabus of visveraya technological university
21scheme vtu syllabus of visveraya technological universityMohd Saifudeen
 
CLOUD COMPUTING SERVICES - Cloud Reference Modal
CLOUD COMPUTING SERVICES - Cloud Reference ModalCLOUD COMPUTING SERVICES - Cloud Reference Modal
CLOUD COMPUTING SERVICES - Cloud Reference ModalSwarnaSLcse
 
Raashid final report on Embedded Systems
Raashid final report on Embedded SystemsRaashid final report on Embedded Systems
Raashid final report on Embedded SystemsRaashidFaiyazSheikh
 
Fuzzy logic method-based stress detector with blood pressure and body tempera...
Fuzzy logic method-based stress detector with blood pressure and body tempera...Fuzzy logic method-based stress detector with blood pressure and body tempera...
Fuzzy logic method-based stress detector with blood pressure and body tempera...IJECEIAES
 
8th International Conference on Soft Computing, Mathematics and Control (SMC ...
8th International Conference on Soft Computing, Mathematics and Control (SMC ...8th International Conference on Soft Computing, Mathematics and Control (SMC ...
8th International Conference on Soft Computing, Mathematics and Control (SMC ...josephjonse
 
UNIT-2 image enhancement.pdf Image Processing Unit 2 AKTU
UNIT-2 image enhancement.pdf Image Processing Unit 2 AKTUUNIT-2 image enhancement.pdf Image Processing Unit 2 AKTU
UNIT-2 image enhancement.pdf Image Processing Unit 2 AKTUankushspencer015
 
Autodesk Construction Cloud (Autodesk Build).pptx
Autodesk Construction Cloud (Autodesk Build).pptxAutodesk Construction Cloud (Autodesk Build).pptx
Autodesk Construction Cloud (Autodesk Build).pptxMustafa Ahmed
 
Developing a smart system for infant incubators using the internet of things ...
Developing a smart system for infant incubators using the internet of things ...Developing a smart system for infant incubators using the internet of things ...
Developing a smart system for infant incubators using the internet of things ...IJECEIAES
 
Worksharing and 3D Modeling with Revit.pptx
Worksharing and 3D Modeling with Revit.pptxWorksharing and 3D Modeling with Revit.pptx
Worksharing and 3D Modeling with Revit.pptxMustafa Ahmed
 
Independent Solar-Powered Electric Vehicle Charging Station
Independent Solar-Powered Electric Vehicle Charging StationIndependent Solar-Powered Electric Vehicle Charging Station
Independent Solar-Powered Electric Vehicle Charging Stationsiddharthteach18
 
21P35A0312 Internship eccccccReport.docx
21P35A0312 Internship eccccccReport.docx21P35A0312 Internship eccccccReport.docx
21P35A0312 Internship eccccccReport.docxrahulmanepalli02
 
Artificial Intelligence in due diligence
Artificial Intelligence in due diligenceArtificial Intelligence in due diligence
Artificial Intelligence in due diligencemahaffeycheryld
 
NO1 Best Powerful Vashikaran Specialist Baba Vashikaran Specialist For Love V...
NO1 Best Powerful Vashikaran Specialist Baba Vashikaran Specialist For Love V...NO1 Best Powerful Vashikaran Specialist Baba Vashikaran Specialist For Love V...
NO1 Best Powerful Vashikaran Specialist Baba Vashikaran Specialist For Love V...Amil baba
 
litvinenko_Henry_Intrusion_Hong-Kong_2024.pdf
litvinenko_Henry_Intrusion_Hong-Kong_2024.pdflitvinenko_Henry_Intrusion_Hong-Kong_2024.pdf
litvinenko_Henry_Intrusion_Hong-Kong_2024.pdfAlexander Litvinenko
 
Passive Air Cooling System and Solar Water Heater.ppt
Passive Air Cooling System and Solar Water Heater.pptPassive Air Cooling System and Solar Water Heater.ppt
Passive Air Cooling System and Solar Water Heater.pptamrabdallah9
 
Dynamo Scripts for Task IDs and Space Naming.pptx
Dynamo Scripts for Task IDs and Space Naming.pptxDynamo Scripts for Task IDs and Space Naming.pptx
Dynamo Scripts for Task IDs and Space Naming.pptxMustafa Ahmed
 
analog-vs-digital-communication (concept of analog and digital).pptx
analog-vs-digital-communication (concept of analog and digital).pptxanalog-vs-digital-communication (concept of analog and digital).pptx
analog-vs-digital-communication (concept of analog and digital).pptxKarpagam Institute of Teechnology
 

Recently uploaded (20)

15-Minute City: A Completely New Horizon
15-Minute City: A Completely New Horizon15-Minute City: A Completely New Horizon
15-Minute City: A Completely New Horizon
 
SLIDESHARE PPT-DECISION MAKING METHODS.pptx
SLIDESHARE PPT-DECISION MAKING METHODS.pptxSLIDESHARE PPT-DECISION MAKING METHODS.pptx
SLIDESHARE PPT-DECISION MAKING METHODS.pptx
 
Maximizing Incident Investigation Efficacy in Oil & Gas: Techniques and Tools
Maximizing Incident Investigation Efficacy in Oil & Gas: Techniques and ToolsMaximizing Incident Investigation Efficacy in Oil & Gas: Techniques and Tools
Maximizing Incident Investigation Efficacy in Oil & Gas: Techniques and Tools
 
21scheme vtu syllabus of visveraya technological university
21scheme vtu syllabus of visveraya technological university21scheme vtu syllabus of visveraya technological university
21scheme vtu syllabus of visveraya technological university
 
CLOUD COMPUTING SERVICES - Cloud Reference Modal
CLOUD COMPUTING SERVICES - Cloud Reference ModalCLOUD COMPUTING SERVICES - Cloud Reference Modal
CLOUD COMPUTING SERVICES - Cloud Reference Modal
 
Raashid final report on Embedded Systems
Raashid final report on Embedded SystemsRaashid final report on Embedded Systems
Raashid final report on Embedded Systems
 
Fuzzy logic method-based stress detector with blood pressure and body tempera...
Fuzzy logic method-based stress detector with blood pressure and body tempera...Fuzzy logic method-based stress detector with blood pressure and body tempera...
Fuzzy logic method-based stress detector with blood pressure and body tempera...
 
8th International Conference on Soft Computing, Mathematics and Control (SMC ...
8th International Conference on Soft Computing, Mathematics and Control (SMC ...8th International Conference on Soft Computing, Mathematics and Control (SMC ...
8th International Conference on Soft Computing, Mathematics and Control (SMC ...
 
UNIT-2 image enhancement.pdf Image Processing Unit 2 AKTU
UNIT-2 image enhancement.pdf Image Processing Unit 2 AKTUUNIT-2 image enhancement.pdf Image Processing Unit 2 AKTU
UNIT-2 image enhancement.pdf Image Processing Unit 2 AKTU
 
Autodesk Construction Cloud (Autodesk Build).pptx
Autodesk Construction Cloud (Autodesk Build).pptxAutodesk Construction Cloud (Autodesk Build).pptx
Autodesk Construction Cloud (Autodesk Build).pptx
 
Developing a smart system for infant incubators using the internet of things ...
Developing a smart system for infant incubators using the internet of things ...Developing a smart system for infant incubators using the internet of things ...
Developing a smart system for infant incubators using the internet of things ...
 
Worksharing and 3D Modeling with Revit.pptx
Worksharing and 3D Modeling with Revit.pptxWorksharing and 3D Modeling with Revit.pptx
Worksharing and 3D Modeling with Revit.pptx
 
Independent Solar-Powered Electric Vehicle Charging Station
Independent Solar-Powered Electric Vehicle Charging StationIndependent Solar-Powered Electric Vehicle Charging Station
Independent Solar-Powered Electric Vehicle Charging Station
 
21P35A0312 Internship eccccccReport.docx
21P35A0312 Internship eccccccReport.docx21P35A0312 Internship eccccccReport.docx
21P35A0312 Internship eccccccReport.docx
 
Artificial Intelligence in due diligence
Artificial Intelligence in due diligenceArtificial Intelligence in due diligence
Artificial Intelligence in due diligence
 
NO1 Best Powerful Vashikaran Specialist Baba Vashikaran Specialist For Love V...
NO1 Best Powerful Vashikaran Specialist Baba Vashikaran Specialist For Love V...NO1 Best Powerful Vashikaran Specialist Baba Vashikaran Specialist For Love V...
NO1 Best Powerful Vashikaran Specialist Baba Vashikaran Specialist For Love V...
 
litvinenko_Henry_Intrusion_Hong-Kong_2024.pdf
litvinenko_Henry_Intrusion_Hong-Kong_2024.pdflitvinenko_Henry_Intrusion_Hong-Kong_2024.pdf
litvinenko_Henry_Intrusion_Hong-Kong_2024.pdf
 
Passive Air Cooling System and Solar Water Heater.ppt
Passive Air Cooling System and Solar Water Heater.pptPassive Air Cooling System and Solar Water Heater.ppt
Passive Air Cooling System and Solar Water Heater.ppt
 
Dynamo Scripts for Task IDs and Space Naming.pptx
Dynamo Scripts for Task IDs and Space Naming.pptxDynamo Scripts for Task IDs and Space Naming.pptx
Dynamo Scripts for Task IDs and Space Naming.pptx
 
analog-vs-digital-communication (concept of analog and digital).pptx
analog-vs-digital-communication (concept of analog and digital).pptxanalog-vs-digital-communication (concept of analog and digital).pptx
analog-vs-digital-communication (concept of analog and digital).pptx
 

SafaiMitra_Suraksha_Webinar_Jamshedpur.pptx

  • 2. Presentation by: Sanjay Kumar (Special Officer ) Jamshedpur Notified Area Committee, Jamshedpur, Jharkhand Jamshedpur Steel City: a City of Tomorrow Manhole turned into Machine Hole (Elimination of Manual Scavenging in Sewer Cleaning) Since 1st Jan 2021
  • 3. CITY BACKGROUND • Population covered- 7.7lakhs (Estimated) • Avg. daily water supply - 80 MLD • Length of Water Mains: - 640 Km • Length of Sewer Lines- 579 Km • 4 Sewage Treatment Plant : 64 MLD • 10 sewage pumping stations: Automated Operation • 20000 Manhole • Total number of SafaiMitras Engaged : 133 • Area- 64 Sq Km • No of wards -10 • Population (2011)- 6.3 lakhs • Green Cover-37% (Approx) • Road Length:- 713 Km 89% 11% SANITATION SYSTEM households connected to sewerage network: Challenges: The conventional method of sewer cleaning requires manual entry.
  • 5. ZERO MANUAL ENTRY CHALLENGES: • Technical • Safety • Social THOUGHT: • Design • Mechanization • Social Stigma IDEAS: • Design Change • Study the application of various cleaning equipment • Create a healthy and safe work environment for all and create a “sense of pride” amongst the workmen involved in cleaning
  • 6. BEFORE SAFAIMITRA SURAKSHA CHALLENGE ISSUES /CHALLENGES FACED DURING SEWER LINE DESILTING Technical problem : •Non-Uniform manhole designs •Unavailability of Approach for cleaning of manholes •Unplanned construction of manholes •One solution(machine) does not address all maintenance requirements Safety problem: • Sewer line desilting required manual entry • Exposure to poisonous gases inside manholes • Exposure to unhygienic condition leading to health hazard • Depth of manholes were different Social Problems: • Work Dignity and Self Respect Item Depth in Mtr. Quantity Cleaning Frequency Removing Sewer Obstruction 6000 Nos. Compt. Based Desilting of Branch Sewer Up to 2.0 213 KM. Compt. / Requirement Based Desilting of Main Sewer >1.5 to 3 235 KM. 2-3 Times/Year Desilting of Trunk Sewer >1.5 to 8 102 KM. Desilting of Manhole Up to 1.5 12194 Nos. Compt. / Requirement Based >1.5 to 2.5 6779 Nos. 2-3 Times/Year >2.5 to 8 1030 Nos
  • 7. 7 PROCESS FOLLOWED BEFORE SmSC 1. Opening cover 2. Checking Gases 3. Placing Rope Ladder 4.Workmen Entry 5.Workmen Entry 6. Desilting work
  • 8. AVERAGE ACTIVITY TIME & ASSOCIATED RISK Approx Time line activity for Manhole Cleaning/ Each Manhole Sr. No. Activity Approx. Time in Min Risk 1 Opening of Manhole 1 Low 2 Visual Inspection of Man Hole from outside 1 Low 3 Checking of Gas 1 Low 4 Fixing of Entry Ladder 1 Low 5 Entry of Work Men 1 Low 6 Desilting of Manhole (Worker Inside manhole) 60 High 7 Exit of Work Men from Manhole 1 Low 8 Removal of Entry Ladder 1 Low 9 Closing of Manhole 1 Low Average Cleaning time/ Each Manhole 68 Worker has to work in side the Manhole = 60 Min MH MH SEWER PIPE SILT SILT
  • 9. OXYGEN AVAILABILITY INSIDE MANHOLE (DEPTH WISE) The availability of oxygen inside manhole decreases with increase in depth 9
  • 10. Sanitation Infrastructure “Pre-SmSC” S.No Name of Maintenance Machine Number of Vehicles (Nov 2020) Requirement as per CPHEEO Manual Number of Vehicles (July 2022) 1. Combination Hydrovac Equipment 2 3 3 2. Number of Grabbers/Desilting Machines 2 4 4 3. Number of standard de-sludging vehicles 2 2 8 4. Sewer Inspection Camera Apparatus 6 6 6 5. Hydro Jetting Machines 3 5 5 6. Power Bucket machine 1 2 2 7. Power Rodding Apparatus 16 16 16 8. Hydraulic Sewer Root cutters 1 3 3
  • 11. SANITATION INFRASTRUCTURE “PRESENT DAY” Super Sucker Jetting Machine Jetting Machine Jetting Machine Suction cum Jetting Machine Grabber Jetting Machine Desludging Machine Desludging Machine
  • 12. MANHOLE TO MACHINE-HOLE SINCE JAN 2021 Grab Machine Power Bucket Machine Suction cum Jetting Machine Super Sucker Machine Power Bucket Machine Super Sucker Machine Power Bucket Machine
  • 13. DEPLOYMENT OF SMALL SUCTION AND JETTING MACHINE 13 1. Maximum Manhole up to 2 Mtr Situated at back alley or non road area 2. No approach for big vehicle due to encroachment. 3. Unsafe condition at non road area for movement of big vehicle. 4. Demand of customer for mechanized cleaning. Benefits :- After deployment of small suction and small jetting machine developed on TATA Intra it is easily reached up to narrow alley / non road area and not required to enter workmen inside manhole for cleaning. Challenges: Small Jetting Machine (New) Small Suction Machine (New)
  • 14. HAND MADE EQUIPMENT TO STOP HUMAN ENTRY 14 Hand Grab for removing Silt/Material Hand Tools for removing Silt/Material from deep Manhole Hand Tools for removing Plastics, Thermos coal Hand Tools for removing Plastics, Thermos coal from Sewer
  • 15. ACTIVITY TIME AFTER FINAL IMPLEMENTATION 15 Approx Time line activity for Manhole Cleaning/ Each Manhole` Sr. No. Activity Earlier Activity Time in Min (R0) Final Activity Time in Min (R2) 1 Opening of Manhole 1 1* 2 Visual Inspection of Manhole 1 1* 3 Checking of Gas 1 Not Required 4 Fixing of Entry Ladder 1 Not Required 5 Entry of Work Men 1.00 Not Required 6 Desilting of Manhole (Worker Inside manhole) 60 0 7 Exit of Work Men from Manhole 1 Not Required 8 Removal of Entry Ladder 1 Not Required 9 Closing of Manhole 1 1* Average Cleaning time/ Each Manhole 68 3 No Worker required to work inside the Manhole * Risk of fall of person mitigated by immediate placing of M S Grill on opening.
  • 16. 16 ISSUES WITH DIFFERENT TYPES OF MANHOLES The chockage of Sewer lines are cleared through downstream manhole. Cleaning can only be ensured from the areas marked with This requires manual entry for access Point of manual entry Point of manual entry Point of manual entry
  • 17. 17 To further aid the cleaning mechanism 3 Nos opening were provided in T shape & 2 Nos in L Shape, after dismantling and recasting of manhole top slab CHANGE IN DESIGN OF EXISTING MANHOLES Point of manual entry AFTER BEFORE Point of manual entry point of machine pipe entry
  • 18. CONVERSION OF L & T TYPE MANHOLE 18 BEFORE AFTER AFTER
  • 19. MANUAL METHOD OF SEWER PIPE CLEANING MH MH SEWER PIPE SILT SILT MECHANIZED CLEANING OF SEWER PIPE USING POWER BUCKET THEN NOW
  • 20. MECHANIZATION JOURNEY UNDER SMSC • Formation of Responsible Sanitation Authority (RSA), Sanitation Response Unit (SRU) • Establishment of Call Centre • Establishment of Safety Training Centre • For handling of mechanized equipment special training to SafaiMitras • Public sensitization on safety measures • Purchase of Mechanized Equipment • Ban on Manual Scavenging
  • 21. PROMOTING SAFETY, DIGNITY AND SOCIAL SECURITY • Daily Tool Box Talk • Mandatory PPE uses • Mandatory Safety Training • Converting Manhole to Machine Hole • Geo-Tagging of all the septic tanks Daily Tool Box Talk Mandatory Safety Training Converting Manhole to Machine Hole
  • 22. Feast for SafaiMitras PROMOTING SAFETY, DIGNITY AND SOCIAL SECURITY Recognition of Best Workers on monthly basis Regular Health Checkup Camps for SafaiMitras
  • 23. CAPACITY BUILDING AND WELFARE MEASURES FOR SAFAIMITRAS • Linkage to Social Welfare Schemes • Regular Mass Meeting • Linkage with PM Jivan Jyoti Bima • Regular Health Check-up Camp
  • 24. PRACTICES : CONNECTING WITH THE FAMILY MEMBERS
  • 25. “CITIZEN CONNECTS” TO SPREAD AWARENESS FOR SAFETY OF SAFAIMITRAS • More safety to SafaiMitras • Strategic IEC outreach • Customer contact program in every 2 months in each locality • Two app's of TSUISL are used i.e Zimmedaar Nagrik and JUSCO Sahyog as customer support
  • 26. MONITORING OF WORKMEN ENTRY We achieved “ZERO” workmen entry for manhole cleaning From 1st January 2021 55 100 100 100 Dec-20 Jan-21 Feb-21 Mar-21 % Elimination of Manual entry in Manhole < 2m depth 5.45 18.66 33.33 80 51.82 100 100 100 % Elimination of Manual Scavenging Manhole Depth >2 mtr. Phase 1 Phase 2 OTHER BENEFITS Customer KPI FY-19 FY-20 FY-21 FY-22 Compliance within SLG 94% 95% 95% 98% Customer Satisfaction performance score for Waste water services 89% 90% 94% 95%
  • 27. TESTIMONIAL For SafaiMitras • Man hole worker to a mechanized sewer worker • No Life at Risk • Better working condition • Social Security- Linked with schemes • Recognition- Working with Dignity • Uplifted SafaiMitras for a better and healthy life Safety Dignity Social Security Name: Mr. Baset Hasda Occupation: Sewer Worker Working Zone: West City: Jamshedpur State: Jharkhand
  • 28. SAFAIMITRAS are the backbone of the City, they are our Responsibility: Some Sewer Operators & Sewer Men feeling dignified… Thank You Vinod Jha Atisher Bhumiz Aazadi Bagti Kuna Hembrom