1. The delivery date for the process water clean-up unit and associated equipment has slipped from December 25, 2023 to January 19, 2024 due to delays in finalizing engineering documents and obtaining approvals. 2. Actions required to expedite the project include expediting approval of outstanding documents, visiting the vendor facility to understand bottlenecks, and following up intensely with sub-vendors to meet delivery dates. 3. A conclusion is provided that delivery from the major vendor is constrained by delivery from its sub-vendor, Flowserve, requiring close follow-up to minimize further delays.