This document provides a summary of Rahul Kulkarni's qualifications and experience. It outlines that he has a B.E. in Instrumentation and over 2 years of experience as a Project Application Engineer at Schneider Electric working on automation projects in oil, gas and petrochemical plants. Some of his key responsibilities included DCS logic programming, establishing communications between control systems, and engineering of control panels and network architecture. He is interested in further expanding his experience in DCS and ESD automation.
Chief maintenance engineering/Supervision & implementation on an Executive ME...Qahtan Adnan
* Regarding to my MEP works of Implementation, Finishing, Pre-opening and Operating Maintenance for a:-
1- 36 floor, +five star hotel, 256 rooms & full facilities.
2- 24,000 Square Meter Five star hotel, 135 rooms & facilities.
3- 20,000 Square Meter Villa’s with full facilities.
4- Six floors, 165 rooms/ Accommodation building.
5- Fifth floor building / Plant room for a hospital FMC.
6- Flat 500 (square Meter) /with full luxury facilities.
My briefly duties were:-
• Managing designs, researches, and analysis on a project by project and advice for the best to be implemented and maintain for future time.
• Prepare all drawings on site according to specifications.
• Proposal all the suggestion to make the project plan in easiest way to implemented.
• Study and planning to estimated costs for the projects.
• Managing project schedules and budgets, and following obtain permits for operations.
• Following up engineering calculations connection with field and office assignments.
• Investigate & follow up all problems and recommend the best solutions to be applied.
• Prepared and reviewed engineering plans, specifications required, project schedules time, designs, circuit diagrams, and estimates for construction and maintenance of projects Gradually with the sequence of the project.
• Daily provided technical support for system operations and maintenance.
• Maintained connection effective working relationships with field crews, contractors, vendors, outside agencies, the staff members.
• Prepare requests of proposals and evaluate tenders.
• Ensure that safety requirements and standards procedures are implemented.
• Following up all payment with venders.
Chief maintenance engineering/Supervision & implementation on an Executive ME...Qahtan Adnan
* Regarding to my MEP works of Implementation, Finishing, Pre-opening and Operating Maintenance for a:-
1- 36 floor, +five star hotel, 256 rooms & full facilities.
2- 24,000 Square Meter Five star hotel, 135 rooms & facilities.
3- 20,000 Square Meter Villa’s with full facilities.
4- Six floors, 165 rooms/ Accommodation building.
5- Fifth floor building / Plant room for a hospital FMC.
6- Flat 500 (square Meter) /with full luxury facilities.
My briefly duties were:-
• Managing designs, researches, and analysis on a project by project and advice for the best to be implemented and maintain for future time.
• Prepare all drawings on site according to specifications.
• Proposal all the suggestion to make the project plan in easiest way to implemented.
• Study and planning to estimated costs for the projects.
• Managing project schedules and budgets, and following obtain permits for operations.
• Following up engineering calculations connection with field and office assignments.
• Investigate & follow up all problems and recommend the best solutions to be applied.
• Prepared and reviewed engineering plans, specifications required, project schedules time, designs, circuit diagrams, and estimates for construction and maintenance of projects Gradually with the sequence of the project.
• Daily provided technical support for system operations and maintenance.
• Maintained connection effective working relationships with field crews, contractors, vendors, outside agencies, the staff members.
• Prepare requests of proposals and evaluate tenders.
• Ensure that safety requirements and standards procedures are implemented.
• Following up all payment with venders.
Στα πλαίσια του μαθήματος της Νεοελληνικής Λογοτεχνίας, οι μαθήτριες του Β2 Μαρία Χαραλαμπίδου, Αλεξάνδρα Μπουτροπούλου και Μαρία Μηνοβγήδου έκαναν μία ομαδική παρουσίαση του βιβλίου ''Το Ημερολόγιο της Άννας Φράνκ''.
1. Rahul Kulkarni
PERSONAL INFORMATION
QUALIFICATION :- B.E INSTRUMENTATION
EMPLOYMENT STATUS:- Project Application Engineer at Schneider Electric,Invensys.
AGE:- 24 yrs (June 15th
,1992)
RESIDENTIAL ADDRESS:- Kulkarni House, Subhash Rd, Vishnunagar, Opp. Punjab national
Bank , Dombivli(west), 421202
MOBILE No:-+91- 9769715996/+91-8097541884
EMAIL:- rahul.krajan01@gmail.com
Passport No:- K4807621
OBJECTIVE
To seek a job in an organization providing good exposure in the field of Automation and Control
SUMMARY
Instrumentation Engineer with 2.9 years of experience in Automation Industry(Oil & Gas,
Petrochemical).Being good at FBD Programming even during academic years, I choose to excel
my career in the same.
I have an excellent experience of both Panel hardware engineering and Software engineering
plus on many occasions I had communicated with clients to understand their technical
requirements.Apart from my professional skills I have got good Presentation skills as well and
have presented various papers in different institutions. Like to work actively in a Team.
Area of Interest:- DCS/ESD Automation, Logic Preparation and Programming(Complex Loops,
Simple Loops etc ), DCS/ESD Panel Hardware Engineering .
2. EMPLOYMENT HISTORY
Employer :- SCHNEIDER ELECTRIC
Designation :-PROJECT APPLICATION ENGINEER
Location:- NAVI MUMBAI, Maharashtra, India
Date of Joining:- September 2013
PROJECTS
Reliance J3 Oil refinery Expansion Project, Cracker Unit, MEG & ASU plant ,
Gassification.
Roles and Responsibilities :-
Software
- DCS logic preparation for MEG,ASU, Steam Super heater and other systems.
(Understanding and implementing Control narratives, Interlocks ,Complex and simple loops ,
Understanding and Implementing Control Philosophy from P&ID’s)
- Sequence logics for equipment like Dryer and ERU package
- Establishing Historian communication
- Bulk generations of simple control loops and IO tags
- System preparations.(Installing Foxboro Control Software , Historian, Wonderware
HMI , FDM for HART and FF devices
- Establishing ESD –DCS serial communication.(Triconex – Foxboro DCS)
- Foundation Fieldbus Device commissioning as a part of FAT.
- Completed logic FAT for MEG and ASU plant which were part of cracker complex
of Reliance J3 , Currently preparing for FAT at Gasification Complex .
Hardware and Documentation
- Preparing Network architecture for DCS.
-Detail System interconnections between various areas in the plant (Port wise details
of Network Equipment like Switches ,Controllers and Servers Etc.)
- I/O channel assignment of DCS tags (Assigning tags to Input Output cards ,
Assigning particular loop typical to a tag and selecting cards and termination assembly as per
typical.
- DCS panel designs after finalizing IO assignments,(System, Marshalling, Relay,
PDB ,LAN, Server )
- GA and Wiring documents of Individual Panel.
- Cross wiring and System cable scheduling
- Heat and Power calculations.
- Tracking periodic system updates like Antivirus, EEPROM versions of cards,
Software upgrades, Switch firmware updates etc.
- On Site experience of panel erectioning and Power on’s
3. EDUCATIONAL DETAILS
INSTRUMENTATION ENGINEERING:-
College:- D.Y Patil ,College of Engineering , Navi Mumabi
YEAR OF PASSING :- JULY 2013, with first grades, from Mumbai University
Projects Submitted:-
o "DATA ACQUISITION SYSTEM AND CONTROL" using various Temp.
Detectors and SOV's
o "RTD Signal conditioning"
DIPLOMA IN INSTRUMENTATION:-
College:- VPM’s Polytechnic,Thane
YEAR OF PASSING :- AUGUST 2010, with distinction , from MSBTE
Projects Submitted:-
o "Automation of Housing societies using PLC "
SSC:-
YEAR OF PASSING:- JUNE 2007 with distinction
HOBBIES AND ACHIEVEMENTS
• Vice President for ISA , technical committee in my Engineering college.
• Vice president for ISTE ,technical committee in my Diploma college.
• Had presented Technical papers as per follows
• Presented Paper on the topic 'VFD and its controlling schemes' at 'Thakur
Polytechnic,Andheri' (Feb 2010)
• Presented Paper on the topic 'Short Distance Wireless Communication' at 'L&T
Institute
Of Technology,powai' (Jan 2010)
Presented Paper on the topic 'BLU-RAY Disc' at 'PadmbhooshanVasantraodadapatil
Institute Of Technology , Sangli' (Feb 2009)
• To Gym
• To Play Cricket
CERTIFICATIONS
GOETHE-ZERTIFIKAT
GOETHE-INSTITUT
I have completed B1(level 3) German language course from Max-Mueller Bhavan,Kala Ghoda,Mumbai.
4. LANGUAGE
• German: Conversational
• English: Fluent
• Marathi: Native
• Hindi: Fluent
DECLARATIONS
I vouch for the authenticity of the aforementioned information.