Unit-based personnel costs can be calculated using an amount per unit determined by the beneficiary's usual cost accounting practices, such as for SME owners. Actual personnel costs must be calculated based on the actual hours worked on a project by employees or equivalent contracted individuals. Several factors must be considered when calculating personnel costs such as productive hours, annual leave, overtime, and salary components according to national tax rules. Documentation such as timesheets and pay slips must be retained to justify actual personnel costs charged to Horizon 2020 projects.
Kontrak ialah suatu perjanjian yang dimeterai apabila satu pihak bersetuju menerima tawaran daripada satu pihak yang lain. Kontrak akan dimeterai apabila kedua-dua belah pihak, klien/majikan dan kontraktor mengikat perjanjian.
MRP is a materials requirements planning system developed in 1964 to help manufacturing companies manage inventory. It uses a master production schedule, bill of materials, and inventory records as inputs to determine when to release new orders and reschedule open orders. The objectives of MRP are to ensure materials and products are available when needed, maintain low inventory levels, and plan manufacturing, delivery, and purchasing activities. It operates by processing input files through the MRP system to generate outputs like planned order schedules. Potential issues include lot sizing, safety stock, scrap allowance, and updating inaccurate files.
Kontrak ialah suatu perjanjian yang dimeterai apabila satu pihak bersetuju menerima tawaran daripada satu pihak yang lain. Kontrak akan dimeterai apabila kedua-dua belah pihak, klien/majikan dan kontraktor mengikat perjanjian.
MRP is a materials requirements planning system developed in 1964 to help manufacturing companies manage inventory. It uses a master production schedule, bill of materials, and inventory records as inputs to determine when to release new orders and reschedule open orders. The objectives of MRP are to ensure materials and products are available when needed, maintain low inventory levels, and plan manufacturing, delivery, and purchasing activities. It operates by processing input files through the MRP system to generate outputs like planned order schedules. Potential issues include lot sizing, safety stock, scrap allowance, and updating inaccurate files.
Dokumen tersebut membahas teknik-teknik analisis masalah untuk menghasilkan tulang ikan (diagram masalah) yang dapat mengidentifikasi punca-punca utama masalah di sebuah jabatan, termasuk menggunakan gambarajah afini, why-why analysis, smart analysis, dan verifikasi punca masalah."
Africa has a diverse array of musical styles and traditions across its regions. Traditional African music is often communal, with call-and-response and polyrhythmic drumming as key features. Common instruments include drums like the djembe and talking drums, as well as harp-lutes, xylophones, and shakers. African music has had a significant influence on genres like blues, gospel, and jazz.
1. Studi ini mengkaji standar desain dan produksi U-ditch pracetak untuk meningkatkan kualitas produk. 2. Dilakukan perhitungan beban desain dan dimensi penampang U-ditch untuk mendapatkan desain yang efisien. 3. Hasilnya adalah desain U-ditch berukuran 500x500x1000 mm yang mampu menahan momen 6,76 kNm.
[Ringkasan]
Dokumen tersebut membahas mengenai masalah kehadiran dan ketiadaan guru dalam kelas di sebuah sekolah. Kumpulan inovasi sekolah melakukan analisis terhadap masalah tersebut untuk menemukan penyelesaian, meliputi langkah-langkah seperti pemilihan masalah, analisis akar masalah, dan cadangan penyelesaian. Masalah kehadiran dan ketiadaan guru dalam kelas dipilih karena berdampak besar terhadap proses pem
A bill of material (BOM) is a list that contains the components, quantities, and costs needed to produce an item or assembly. It includes the item ID, description, cost per item, and total cost of all items. The key information in a BOM allows users to identify the correct parts, order the necessary quantities, and calculate the total materials cost of a project.
Beberapa poin penting dari dokumen tersebut adalah:
1) Dokumen tersebut membahas tentang daya-daya pada bahan, termasuk jenis-jenis daya, tegasan, dan terikan.
2) Ada beberapa jenis daya seperti daya statik, dinamik, hentaman, dan lesu/ulang alik.
3) Terdapat daya terus dan ricih, serta tegasan terus, ricih, tegangan, dan mampatan.
Dokumen tersebut merupakan ringkasan proses sand casting, yaitu teknik pembuatan produk logam dengan mencairkan logam dan menuangkannya ke dalam cetakan pasir. Prosesnya meliputi pembuatan cetakan pasir, penuangan logam cair, pendinginan hingga pelepasan produk logam yang telah memejal. Teknik ini murah dan bahan mentahnya mudah didapat, meski dapat menghasilkan kecacatan akibat gas atau ketidaksempurnaan cet
Ringkasan dokumen:
1. Dokumen memberikan informasi tentang lima jenis tender yang umum digunakan dalam industri konstruksi di Malaysia yaitu tender terbuka, tender terhad, tender terpilih, tender perundingan, dan tender pra-kualifikasi.
2. Definisi dan kelebihan serta kekurangan masing-masing jenis tender dijelaskan. Contoh iklan tender juga disertakan.
The document provides guidance to beneficiaries of EU research grants on avoiding common errors in cost claims. It lists the 10 most frequent errors, including: costs not substantiated or linked to the project; unapproved use of third parties; improper depreciation charges; incorrect use of indirect cost models; including ineligible costs in indirect cost pools; improper calculation of personnel productive hours; and incorrectly charging hours worked. Beneficiaries are advised to carefully review financial rules and check that all claimed costs are real, paid, project-related, and properly calculated and documented to avoid errors and ensure timely reimbursement.
EASME webinar to GEO-CRADLE partners on project financial management and repo...geocradle1
This document discusses guidelines for avoiding common errors in project financial management and reporting. It covers errors related to personnel costs, procurement, and other budget categories. The key points are:
- Personnel costs errors include incorrect calculations of hourly rates and annual productive hours, lack of timesheets, and ineligible salary elements.
- Procurement errors involve lack of evidence for best value in purchases and subcontracts.
- Other errors are amounts that don't reconcile with accounting, declaring estimates instead of actual costs, and costs outside the eligibility period.
The document provides tips on compliant practices like using the last closed financial year for hourly rate calculations and ensuring timely record keeping of hours worked on the project. It also outlines
Dokumen tersebut membahas teknik-teknik analisis masalah untuk menghasilkan tulang ikan (diagram masalah) yang dapat mengidentifikasi punca-punca utama masalah di sebuah jabatan, termasuk menggunakan gambarajah afini, why-why analysis, smart analysis, dan verifikasi punca masalah."
Africa has a diverse array of musical styles and traditions across its regions. Traditional African music is often communal, with call-and-response and polyrhythmic drumming as key features. Common instruments include drums like the djembe and talking drums, as well as harp-lutes, xylophones, and shakers. African music has had a significant influence on genres like blues, gospel, and jazz.
1. Studi ini mengkaji standar desain dan produksi U-ditch pracetak untuk meningkatkan kualitas produk. 2. Dilakukan perhitungan beban desain dan dimensi penampang U-ditch untuk mendapatkan desain yang efisien. 3. Hasilnya adalah desain U-ditch berukuran 500x500x1000 mm yang mampu menahan momen 6,76 kNm.
[Ringkasan]
Dokumen tersebut membahas mengenai masalah kehadiran dan ketiadaan guru dalam kelas di sebuah sekolah. Kumpulan inovasi sekolah melakukan analisis terhadap masalah tersebut untuk menemukan penyelesaian, meliputi langkah-langkah seperti pemilihan masalah, analisis akar masalah, dan cadangan penyelesaian. Masalah kehadiran dan ketiadaan guru dalam kelas dipilih karena berdampak besar terhadap proses pem
A bill of material (BOM) is a list that contains the components, quantities, and costs needed to produce an item or assembly. It includes the item ID, description, cost per item, and total cost of all items. The key information in a BOM allows users to identify the correct parts, order the necessary quantities, and calculate the total materials cost of a project.
Beberapa poin penting dari dokumen tersebut adalah:
1) Dokumen tersebut membahas tentang daya-daya pada bahan, termasuk jenis-jenis daya, tegasan, dan terikan.
2) Ada beberapa jenis daya seperti daya statik, dinamik, hentaman, dan lesu/ulang alik.
3) Terdapat daya terus dan ricih, serta tegasan terus, ricih, tegangan, dan mampatan.
Dokumen tersebut merupakan ringkasan proses sand casting, yaitu teknik pembuatan produk logam dengan mencairkan logam dan menuangkannya ke dalam cetakan pasir. Prosesnya meliputi pembuatan cetakan pasir, penuangan logam cair, pendinginan hingga pelepasan produk logam yang telah memejal. Teknik ini murah dan bahan mentahnya mudah didapat, meski dapat menghasilkan kecacatan akibat gas atau ketidaksempurnaan cet
Ringkasan dokumen:
1. Dokumen memberikan informasi tentang lima jenis tender yang umum digunakan dalam industri konstruksi di Malaysia yaitu tender terbuka, tender terhad, tender terpilih, tender perundingan, dan tender pra-kualifikasi.
2. Definisi dan kelebihan serta kekurangan masing-masing jenis tender dijelaskan. Contoh iklan tender juga disertakan.
The document provides guidance to beneficiaries of EU research grants on avoiding common errors in cost claims. It lists the 10 most frequent errors, including: costs not substantiated or linked to the project; unapproved use of third parties; improper depreciation charges; incorrect use of indirect cost models; including ineligible costs in indirect cost pools; improper calculation of personnel productive hours; and incorrectly charging hours worked. Beneficiaries are advised to carefully review financial rules and check that all claimed costs are real, paid, project-related, and properly calculated and documented to avoid errors and ensure timely reimbursement.
EASME webinar to GEO-CRADLE partners on project financial management and repo...geocradle1
This document discusses guidelines for avoiding common errors in project financial management and reporting. It covers errors related to personnel costs, procurement, and other budget categories. The key points are:
- Personnel costs errors include incorrect calculations of hourly rates and annual productive hours, lack of timesheets, and ineligible salary elements.
- Procurement errors involve lack of evidence for best value in purchases and subcontracts.
- Other errors are amounts that don't reconcile with accounting, declaring estimates instead of actual costs, and costs outside the eligibility period.
The document provides tips on compliant practices like using the last closed financial year for hourly rate calculations and ensuring timely record keeping of hours worked on the project. It also outlines
The document discusses the implications of the UK's Pensions Act, which introduced automatic pension enrollment for workers starting in 2012. It will require employers to automatically enroll eligible workers into a qualifying pension scheme if they are not already in one. This affects agencies and contractors, as agencies are responsible for enrolling contractors they employ directly via PAYE.
The implications include additional costs for employers to fund pension contributions, as well as significant administrative burdens to manage the pension schemes and enrollment process. There are also challenges around who will bear the financial responsibility - the agency, client, or umbrella company. The document provides options for agencies and contractors to prepare, including agreeing an approach, choosing a pension provider, and complying with their staging date
THE LABOUR MARKET IN ITALY: WILL REFORMS ALONE CREATE EMPLOYMENT?telosaes
The document discusses labour market reforms in Italy from 2012-2014, including the Fornero Reform law of 2012 and the Jobs Act law of 2014. The reforms aimed to increase flexibility around hiring and firing while providing more protections for unemployed workers. Key changes included making fixed-term contracts easier for employers but with limits, expanding apprenticeships, and reducing reinstatement of unjustly fired workers to compensation. Critics argue this may increase precarious employment without addressing lack of economic growth and demand. The full effects of the reforms on unemployment are still unclear.
Deeltijd ww in the netherlands costs and benefitsPeterMachielse
The Deeltijd WW (part-time unemployment benefits) program in the Netherlands ran from April 2009 to July 2011. It aimed to prevent layoffs during the economic downturn by subsidizing employers to cut employee hours rather than jobs. Under the program, employers and employees could agree to reduce hours to 70% of normal, with unemployment benefits making up lost wages. This allowed employers to retain skilled workers and employees to keep their jobs and income. Evaluations found the program saved an estimated 5,000-6,000 jobs but cost nearly 1 billion euros, with around half the spending considered "deadweight loss" going to companies that would not have otherwise laid people off. Debate centered on whether the program slowed structural adjustment or
Off Payroll Working In Private Sector | Makesworth Accountants in HarrowMakesworth Accountants
New tax rules for individuals working via their own companies for medium or large business. From 6 April 2020, new tax rules are proposed for individuals who provide their personal services via an ‘intermediary’ to medium or large business. An intermediary may be another individual, a partnership, an unincorporated association or a company. The most common structure is a worker providing their services via their own company (PSC) which is the term used in this letter to summarise the rules which will apply to all intermediaries. Similar rules were introduced in 2017 for public sector organisations receiving services from PSCs. The 2020 rules will use the 2017 rules as a starting point which means, in practical terms, that the principles have already been decided but some aspects of the detailed operation of the rules will be decided in a consultation process. Draft legislation has been published which will, subject to consultation, be included in the next Finance Bill.
Investment calculations and production automation in weldingOlli-Pekka Holamo
This document discusses factors to consider when evaluating investments in production automation, such as robots, using net present value calculations. It emphasizes that total costs, including indirect costs associated with current manual production processes, must be considered rather than just comparing direct labor costs to investment costs. Three categories of costs are identified: direct costs, indirect costs caused by current operations, and costs associated with resources over time like increasing labor costs. Key performance indicators should be used to compare the total costs per unit of current and proposed automated production concepts to determine the most profitable option.
Govology Webinar: PPP Forgiveness, Indirect Rates and the Incurred Cost ProposalRobert E Jones
The accurate calculation of indirect rates is critical to budgets, proposals, provisional billing rates, and ultimately to company profitability. And the timely determination of final rates, final invoices and contract close-out is dependent on proper completion of the incurred cost proposal. By adding in PPP loans and Section 3610 funds you create another layer of complexity to an already confusing process for small business owners. This doesn't even consider the tax implications of PPP loans and other CARES Act or FFCRA COVID-19 relief options. Did you know according to FAR 31.201-5, contractors must accrue to the government the benefit of any refunds, rebates or credits received in the form of cost reductions or cash refunds? During this webinar we will discuss why contractors may or may not want to apply for forgiveness as well as provide technical guidance on the proper calculation on rates and completion of the incurred cost proposal.
The document discusses subleasing and HR services in Vietnam. It provides an overview of the HR services industry globally and in Vietnam. It explains key HR terminology like temporary workers, outsourcing, and contract workers. It outlines the process that led to the introduction of subleasing in Vietnam's Labor Code and the requirements for obtaining a subleasing license. The document also discusses the risks for clients of subleasing and proposes two options for clients: a managed business service provider or subleased services.
The document provides information about the UK government's COVID-19 Job Retention Scheme, which provides grants to employers to pay employees who are furloughed. Key details include: employers can claim 80% of wages up to £2,500 per month for furloughed employees; directors, agency workers, and employees hired before February 28 are eligible; and employers must discuss furloughing with employees and keep records of agreements. Employers can claim reimbursement for wages, National Insurance contributions, and pension contributions through an online portal opening in mid-April.
DIRECTED READING THREE PERCEPTIONS OF PROJECT COST D.H. Hamburg.docxduketjoy27252
DIRECTED READING: THREE PERCEPTIONS OF PROJECT COST*: D.H. Hamburger
Project cost seems to be a relatively simple expression, but “cost” is more than a four letter word. Different elements of the organization perceive cost differently, as the timing ofprojectcost identification affects their particular organizational function. The project manager charged with on-time, on-cost, on-spec execution of a project views the “on cost” component of his responsibility as a requirement to stay within the allocated budget, while satisfying a given setof specified conditions (scope of work), within a required time frame (schedule). To mostproject managers this simply means a commitment to project funds in 328329accordance with a prescribed plan (time-based budget). Others in the organization are less concerned with the commitment of funds. The accounting department addresses expense recognition related to aproject or an organizational profit and loss statement. The accountant’s ultimate goal is reporting profitability, while positively influencing the firm’s tax liability. The comptroller (finance department) is primarily concerned with the organization’s cash flow. It is that person’s responsibility to provide the funds for paying the bills, and putting the unused or available money to work for the company.
To be an effective project manager, one must understand each cost, and also realize that the timing of cost identification can affect both project and corporate financial performance. Theproject manager must be aware of the different cost perceptions and the manner in which they are reported. With this knowledge, the project manager can control more than theproject’s cost of goods sold (a function often viewed as the project manager’s sole financial responsibility). The project manager can also influence the timing of cost to improve cash flow and the cost of financing the work, in addition to affecting revenue and expense reporting in the P&L statement.
Three Perceptions of Cost
To understand the three perceptionsof cost—commitments, expenses, and cash flow—consider the purchase of a major project component. Assume that a $120,000 compressor with delivery quoted at six months was purchased. Figure 1 depicts the order execution cycle. At time 0 an order is placed. Six months later the vendor makes two shipments, a large box containing the compressor and a small envelope containing an invoice. The received invoice is processed immediately, but payment is usually delayed to comply with corporate payment policy (30, 60, 90, or more days may pass before a check is actually mailed to the vendor). In this example, payment was made 60 days after receipt of the invoice or 8 months after the order for the compressor was given to the vendor.
Figure 1: Three perceptions of project cost.
Commitments—The Project Manager’s Concern
Placement of the purchase order represents a commitment to pay the vendor $120,000 following satisfactory delivery of the compressor..
34565 Finance Bill Update flyer Jan 2017Tony Nevin
The document summarizes upcoming changes to optional remuneration arrangements under UK tax law. Beginning April 2017, salary sacrificed amounts for benefits will be taxed based on the higher of the sacrificed amount or benefit value. Exemptions include pension contributions, childcare vouchers, and ultra-low emission company cars. Employers must review existing benefit programs, consider changes to remain advantageous, and communicate changes to employees who may be financially impacted.
This document provides information about setting up a business and VAT rates in the Netherlands. It discusses:
1) Several legal forms a business can take such as sole proprietorship, partnership, or private limited company.
2) VAT rates of 19% for luxury goods and 21% for air travel which includes a 2% environmental tax.
3) Requirements for setting up a business including registering with the Chamber of Commerce and obtaining necessary permits from the tax authorities.
Question and Answers from - A benefits management framework for prioritising programmes webinar
Monday 17 February 2020
presented by:
Dr Hugo Minney
The link to the write up page and resources of this webinar:
https://www.apm.org.uk/news/a-benefits-management-framework-for-prioritising-programmes-webinar/
This supports the APM publication “A guide to using a benefits management framework” and takes participants through the implementation process:
https://www.apm.org.uk/book-shop/a-guide-to-using-a-benefits-management-framework/
Presentation slides:
https://www.slideshare.net/assocpm/a-benefits-management-framework-for-prioritising-programmes-webinar-17-february-2020
CSIS 375
Final Project Instructions
Instructions:
General Background Information:
CMS Systems, Inc. is a company that provides information systems consulting services to companies in the telecom industry in the United States and the United Kingdom. Due to its success, CMS is hoping to expand its operations into other parts of Europe. Despite its large size, CMS currently uses a manual/spreadsheet-based process for maintaining employee hours worked, employee benefits, employee payroll, project management, and customer billing. It also uses a file based system to manage its legal documents and other client information.
Management has now decided to implement a company-wide application that will keep track of all of its employee, project, and client information. Employee information will include such items as employee name, address, hire date, and salary. It will also keep track of employee hours spent working on various projects, employee benefits, employee payroll, and produce invoices for clients based on hours worked by employees. Client information will include such items as client name, legal location (i.e., country), billing address, office locations, client contact information , and contracts associated with each client. Project information will also have to be maintained, which will keep track of employee assignments to projects.
Employee Management
CMS currently employs 1,500 individuals (900 in the US and 600 in the UK) who serve as systems analysts, developers, managers, testers, maintenance engineers, accountants, lawyers, sales representatives, and office staff.
The new system will enable the Human Resources department to maintain all employee information such as name, address, hire date, termination date, emergency contact information, marital status, tax withholding information, 401 K participation, insurance participation, other tax-related deductions, and salary/wage rates.
Only members of the Human Resources department will be allowed to edit employee information.
Recording Hours Worked
All CMS employees must keep a record of the time they spend working for each client on a weekly basis. Because employees can work for more than one client and perform different functions for each client, CMS utilizes “project management” to keep track of employee assignments to client contracts. Employees can be assigned to work on more than one project at a given time. In fact, it is not unusual for an employee to spend time on two or more different projects within the same day.
The number of hours worked for each employee on each project must be recorded on a weekly basis. Employees currently log their time using an Excel worksheet. An example of this worksheet is presented below. Notice that the employee’s supervisor is listed on the worksheet. A supervisor is currently required to approve his employees’ timesheets by placing his initials beside his name.
All employees in the company should be allowed to enter information on their timesh.
The perverse effects of job security provisions on job security: results from...EUROsociAL II
This document summarizes a study that uses a regression discontinuity design to analyze the effects of job security provisions in Italy on outcomes like job composition and firm productivity. It finds that while employment protection may help job security, it can also reduce job creation and reallocation. The study exploits a threshold in Italy where regulations are less stringent for firms with 15 employees or fewer. It presents descriptive statistics and tests that validate the regression discontinuity approach. Regressions are estimated to examine impacts on various outcomes and whether effects differ across sectors with varying output volatility. The results provide evidence on the complex tradeoffs of employment protection policies.
MGT 3302, Introduction to Project Management 1 Cou.docxmadlynplamondon
MGT 3302, Introduction to Project Management 1
Course Learning Outcomes for Unit VI
Upon completion of this unit, students should be able to:
5. Analyze factors impacting control of project costs.
5.1 Discuss creating a budget for a project.
Course/Unit
Learning Outcomes
Learning Activity
5.1
Unit Lesson
Chapter 7, pp. 242–269
Unit VI Course Project
Required Unit Resources
Chapter 7: Determining Costs, Budget, and Earned Value, pp. 242–269
Unit Lesson
In the previous unit, we discussed resource planning, resource utilization, and creating and managing a Gantt
chart. If you remember from Unit I, the three main constraints of the project are scope, time, and budget.
Activities and resources fit under the scope component. However, resources also fit under the budget
component. One of our biggest expenses for a project involves the resources we use. Regardless, we have to
calculate our total project cost.
Estimating Activity Cost
Estimating activity cost is a very important part of the budgeting process. Once we have identified our specific
activities, then we can estimate the resources needed and the cost for those activities. Until now, we have
referred to employees who will perform the activities as resources. However, for the purpose of budgeting,
resources could be people, materials, equipment, facilities, or licenses. Any activity could have multiple costs
associated with it. For example, painting a room would have labor costs, material costs, and equipment costs.
Other types of costs are facility costs, travel costs, or contingency costs. As another example, let’s suppose
we need to send an information technology (IT) professional to training. The cost associated with this
resource’s activities would be labor costs and travel costs.
Let’s discuss some of the details of these different costs.
Labor costs: As mentioned, labor cost can be one of the highest costs in a budget. How many people will we
need to work on this project? How many hours will each person need for the project? How much will we pay
each individual person? How will we account for technical experts or skilled workers versus administrative
personnel? Will we have overhead? Overhead costs are those costs that are not specifically attributed to work
performed. For example, how will we account for health benefits or 401(k) donations? What about training
costs?
Materials costs: In our fair project, the cost of materials might be fairly high. But let’s suppose we were
undertaking an IT project. The cost of materials might be fairly low. If our project involved building a house,
the cost materials would definitely be high.
UNIT VI STUDY GUIDE
The Project Budget
MGT 3302, Introduction to Project Management 2
UNIT x STUDY GUIDE
Title
Equipment costs: What if we have to rent some machinery in order to complete our project? For example,
what if some of the activities in our project required t.
Similar to Question and Answer catalogue: Horizon 2020 Personnel Cost calculation and Reporting (20)
This webinar discusses best practices for disseminating EU-funded project results. The presentation covers developing a dissemination and communication plan that includes defining target audiences, appropriate communication tools and channels, timeline, key performance indicators (KPIs), and monitoring and reporting. The target audience should follow the "quadruple helix model" of policymakers, academia, industry, and society. Visual identity, citizen engagement activities, collaboration with other projects, and qualitative and quantitative KPIs are also addressed.
This document outlines the agenda and content for a webinar on the first and final steps in writing Horizon Europe proposals. The webinar will cover filling out key sections of Part A such as participants, budget, and ethics questions. It will also review important elements for writing proposals such as describing the consortium, work plan, and impact pathways. The speaker's contact information is provided at the end for attendees to follow up.
This document provides a summary of a webinar presentation about the financial rules of Horizon Europe compared to Horizon 2020.
The presentation covered key changes in terminology, personnel cost calculation using a daily rate approach, budgeting versus reporting, project-based remuneration replacing additional remuneration, rules around in-kind contributions, and a new System and Process Audit that could reduce ex-post audits for low-risk beneficiaries.
The presentation also discussed internally invoiced goods and services actual costs instead of a flat rate, no limits on exceeding maximum EC contributions, and a Mutual Insurance Mechanism replacing the Guarantee Fund. Q&A was taken at the end to address questions received in advance.
Research and Innovation is financed through different budget lines, we are collecting all relevant programmes in this document. At the end of the document you can find a full summary table.
A few basic issues to understand when it comes to preparing yourself to coordinate research and innovation projects. The templates we refer to are not linked in the document.
Check our Templates section on the website.
Some useful tips for those interested in submitting a Horizon 2020 proposal. What are the evaluators looking for? Hands-on approach to H2020 proposal writing.
What to expect in case your Horizon 2020 project is audited by the European Commission. How to prepare and how to avoid an EC audit. Is there a way to avoid EC audits?
The document provides information about evaluating project proposals for the Junior Project Management course taking place in Budapest, Hungary in April 2011. It discusses who the expert evaluators are and how they are selected to ensure a balanced representation. It also outlines the evaluation process, including individual and consensus evaluations, and describes the on-site and remote evaluation methods. Scoring criteria focus on scientific and technical quality, implementation plans, and potential impacts. Evaluators provide individual assessment reports with scores and recommendations to determine if proposals meet funding thresholds.
This document provides guidance for getting a project started, including establishing roles and responsibilities, developing a consortium agreement, holding a kick-off meeting, and ongoing communication and management. It emphasizes defining who is involved in the project, creating a consortium agreement to outline legal and financial obligations, and using the kick-off meeting to thoroughly plan activities, timelines, deliverables, and responsibilities for the first phases of the project. The kick-off meeting should train partners, establish reporting procedures, and implement management systems to effectively launch the collaboration.
FP7 Projects: Negotiation, management and financial rules
This document provides a summary of key aspects of FP7 projects, including [1] the basic facts about project consortiums, roles, and responsibilities; [2] the FP7 grant agreement negotiation process; and [3] basic FP7 financial rules regarding eligible costs, funding rates, and payment processes. It outlines that all FP7 projects are directly controlled by the European Commission's DG Research, with the coordinator representing the consortium and partners being jointly responsible for implementation. It also summarizes the grant agreement negotiations, eligible cost categories, reimbursement rates that vary by project type, reporting obligations, and issues addressed in the mandatory consortium agreement, including
The document provides an introduction to the EU funding system. It explains some of the key terms and acronyms used in EU funding. It outlines the different types of EU funds available, including regional support funds, agricultural funds, external support instruments, and community programs. It also discusses how to find information on funding opportunities, determine eligibility, get started in the application process, and compares indirect vs direct support.
This document provides a case study and analysis of a funding opportunity through the European Union's FP7 program. Specifically, it examines Call Identifier FP7-ENERGY-2007-1-RTD on developing a common methodology for assessing biomass potential using earth observations. The document outlines the key details of the call, including topics, funding scheme, expected impact, and deadline. It then provides suggestions on how to approach the proposal, including emphasizing coordination, past experiences, and ensuring a proposal structure that directly addresses the requirements in the call text. Finally, it summarizes the results of the proposal submitted, which received a positive score and funding for the "CEUBIOM" project.
Phenomics assisted breeding in crop improvementIshaGoswami9
As the population is increasing and will reach about 9 billion upto 2050. Also due to climate change, it is difficult to meet the food requirement of such a large population. Facing the challenges presented by resource shortages, climate
change, and increasing global population, crop yield and quality need to be improved in a sustainable way over the coming decades. Genetic improvement by breeding is the best way to increase crop productivity. With the rapid progression of functional
genomics, an increasing number of crop genomes have been sequenced and dozens of genes influencing key agronomic traits have been identified. However, current genome sequence information has not been adequately exploited for understanding
the complex characteristics of multiple gene, owing to a lack of crop phenotypic data. Efficient, automatic, and accurate technologies and platforms that can capture phenotypic data that can
be linked to genomics information for crop improvement at all growth stages have become as important as genotyping. Thus,
high-throughput phenotyping has become the major bottleneck restricting crop breeding. Plant phenomics has been defined as the high-throughput, accurate acquisition and analysis of multi-dimensional phenotypes
during crop growing stages at the organism level, including the cell, tissue, organ, individual plant, plot, and field levels. With the rapid development of novel sensors, imaging technology,
and analysis methods, numerous infrastructure platforms have been developed for phenotyping.
The ability to recreate computational results with minimal effort and actionable metrics provides a solid foundation for scientific research and software development. When people can replicate an analysis at the touch of a button using open-source software, open data, and methods to assess and compare proposals, it significantly eases verification of results, engagement with a diverse range of contributors, and progress. However, we have yet to fully achieve this; there are still many sociotechnical frictions.
Inspired by David Donoho's vision, this talk aims to revisit the three crucial pillars of frictionless reproducibility (data sharing, code sharing, and competitive challenges) with the perspective of deep software variability.
Our observation is that multiple layers — hardware, operating systems, third-party libraries, software versions, input data, compile-time options, and parameters — are subject to variability that exacerbates frictions but is also essential for achieving robust, generalizable results and fostering innovation. I will first review the literature, providing evidence of how the complex variability interactions across these layers affect qualitative and quantitative software properties, thereby complicating the reproduction and replication of scientific studies in various fields.
I will then present some software engineering and AI techniques that can support the strategic exploration of variability spaces. These include the use of abstractions and models (e.g., feature models), sampling strategies (e.g., uniform, random), cost-effective measurements (e.g., incremental build of software configurations), and dimensionality reduction methods (e.g., transfer learning, feature selection, software debloating).
I will finally argue that deep variability is both the problem and solution of frictionless reproducibility, calling the software science community to develop new methods and tools to manage variability and foster reproducibility in software systems.
Exposé invité Journées Nationales du GDR GPL 2024
hematic appreciation test is a psychological assessment tool used to measure an individual's appreciation and understanding of specific themes or topics. This test helps to evaluate an individual's ability to connect different ideas and concepts within a given theme, as well as their overall comprehension and interpretation skills. The results of the test can provide valuable insights into an individual's cognitive abilities, creativity, and critical thinking skills
The use of Nauplii and metanauplii artemia in aquaculture (brine shrimp).pptxMAGOTI ERNEST
Although Artemia has been known to man for centuries, its use as a food for the culture of larval organisms apparently began only in the 1930s, when several investigators found that it made an excellent food for newly hatched fish larvae (Litvinenko et al., 2023). As aquaculture developed in the 1960s and ‘70s, the use of Artemia also became more widespread, due both to its convenience and to its nutritional value for larval organisms (Arenas-Pardo et al., 2024). The fact that Artemia dormant cysts can be stored for long periods in cans, and then used as an off-the-shelf food requiring only 24 h of incubation makes them the most convenient, least labor-intensive, live food available for aquaculture (Sorgeloos & Roubach, 2021). The nutritional value of Artemia, especially for marine organisms, is not constant, but varies both geographically and temporally. During the last decade, however, both the causes of Artemia nutritional variability and methods to improve poorquality Artemia have been identified (Loufi et al., 2024).
Brine shrimp (Artemia spp.) are used in marine aquaculture worldwide. Annually, more than 2,000 metric tons of dry cysts are used for cultivation of fish, crustacean, and shellfish larva. Brine shrimp are important to aquaculture because newly hatched brine shrimp nauplii (larvae) provide a food source for many fish fry (Mozanzadeh et al., 2021). Culture and harvesting of brine shrimp eggs represents another aspect of the aquaculture industry. Nauplii and metanauplii of Artemia, commonly known as brine shrimp, play a crucial role in aquaculture due to their nutritional value and suitability as live feed for many aquatic species, particularly in larval stages (Sorgeloos & Roubach, 2021).
BREEDING METHODS FOR DISEASE RESISTANCE.pptxRASHMI M G
Plant breeding for disease resistance is a strategy to reduce crop losses caused by disease. Plants have an innate immune system that allows them to recognize pathogens and provide resistance. However, breeding for long-lasting resistance often involves combining multiple resistance genes
The binding of cosmological structures by massless topological defectsSérgio Sacani
Assuming spherical symmetry and weak field, it is shown that if one solves the Poisson equation or the Einstein field
equations sourced by a topological defect, i.e. a singularity of a very specific form, the result is a localized gravitational
field capable of driving flat rotation (i.e. Keplerian circular orbits at a constant speed for all radii) of test masses on a thin
spherical shell without any underlying mass. Moreover, a large-scale structure which exploits this solution by assembling
concentrically a number of such topological defects can establish a flat stellar or galactic rotation curve, and can also deflect
light in the same manner as an equipotential (isothermal) sphere. Thus, the need for dark matter or modified gravity theory is
mitigated, at least in part.
Remote Sensing and Computational, Evolutionary, Supercomputing, and Intellige...University of Maribor
Slides from talk:
Aleš Zamuda: Remote Sensing and Computational, Evolutionary, Supercomputing, and Intelligent Systems.
11th International Conference on Electrical, Electronics and Computer Engineering (IcETRAN), Niš, 3-6 June 2024
Inter-Society Networking Panel GRSS/MTT-S/CIS Panel Session: Promoting Connection and Cooperation
https://www.etran.rs/2024/en/home-english/
Travis Hills' Endeavors in Minnesota: Fostering Environmental and Economic Pr...Travis Hills MN
Travis Hills of Minnesota developed a method to convert waste into high-value dry fertilizer, significantly enriching soil quality. By providing farmers with a valuable resource derived from waste, Travis Hills helps enhance farm profitability while promoting environmental stewardship. Travis Hills' sustainable practices lead to cost savings and increased revenue for farmers by improving resource efficiency and reducing waste.
Professional air quality monitoring systems provide immediate, on-site data for analysis, compliance, and decision-making.
Monitor common gases, weather parameters, particulates.
ANAMOLOUS SECONDARY GROWTH IN DICOT ROOTS.pptxRASHMI M G
Abnormal or anomalous secondary growth in plants. It defines secondary growth as an increase in plant girth due to vascular cambium or cork cambium. Anomalous secondary growth does not follow the normal pattern of a single vascular cambium producing xylem internally and phloem externally.
Question and Answer catalogue: Horizon 2020 Personnel Cost calculation and Reporting
1. "Basic mistakes in H2020
personnel cost calculation
and reporting"
on May 22nd, 2019
www.europamediatrainings.com
www.emdesk.com
Q&A catalogue
following the live webinar
1
2. 2
# ORIGINAL PARTICIPANT QUESTION ANSWER BY EUROPA MEDIA
1 what is a unit-based personnel cost ? Direct personnel costs can be calculated on the basis of an
amount per unit calculated by the beneficiary in accordance with
its usual cost accounting practices (‘unit costs’). e.g.
Personnel costs for SME owners or beneficiaries that are natural
persons not receiving a salary must be declared on the basis of
the amount per unit set out in Annex 2a (unit costs);
2 Unit Cost are related to the CoMUC... do
you know any organization to which the
EC have approved the CoMUC?
Yes, there are several, but we are not allowed sharing these
names.
3 If the certificate is apporved, can we use
the Methodlology under FP9 prjects?
Most likely no, new certificate will be necessary for a new
programme.
4 Might get covered later on but, what are
the key differences between seconded
and subcontracted employees?
For seconded employees you pay only the costs; in case of
subcontracting you pay the profit ratio as well. No overhead
applies for subcontracting costs. IP onwership differences may
also apply.
5 Under Actual Personnel costs, you have
to use for the calculation of the cost per
hour the personnel cost of the last closed
fiscal year. How do you manage to cover
your real costs if you have to use costs of
a previous year that many times is lower?
Indeed if you use the fiscal year calculation and for several months
you have to use the previous year's data, it may happen that not all
your real costs are covered. However, using the fiscal year
calculation requires less time and effort from your administration
which saves money. In case you think that your losses are
significant with the fiscal year calculation, turn to the monthly
calculation. This is why we recommend trying out both routes to
see which is the more beneficial - considering all advantages and
disadvantages.
6 does the in-house consultant need to sign
the time-sheets?
Yes
7 I think you have said that you would send
us the slides, is that ok?
The slides were sent by EMDESK
8 Does the actual personnel costs include
all costs (salary, insurance, social costs,
etc.)?
Yes, all these listed in the brackets - all mandatory charges
9 Do empleyee contracts need to contain a
reference to the H2020 project tasks?
Not necessarily - follow your own and national rules for this. The
employees need to be assigned to the project - but not necessarily
via their contract.
10 Morning, when preparing to submit a
project most of the time we are asked for
our average personnel costs, so is this
incorrect, should leaders ask for actual
one by one personeel costs instead of
ana verage cost?
For budget development purposes you give one average rate of
the people who will work on the project. This rate is weighted by
the involvement rate of the assigned people. Then at the reporting
you report the actual costs of those people who work on the
project. Check the budget exercise on europa media training site
under knowledge base.
11 Regarding UNIT-based personnel costs: (1)
i would say standard hours of the
company (2) i would say standard hours of
the company
???? I do not understand the question
3. 3
12 When are unit-based costs used instead
of actual personnel costs?
In case the use of average personnel costs are more beneficial
and the organisation has a standard calculation for this. E.g. many
technicians work on the project or many junior researchers whose
salary is similar, and they spend a few hours here, a few hours
there. For them calculating the actual costs one by one for the
periods means also a lot of administration. So having a system for
average personnel cost calculation may be beneficial.
13 We have in-house consultants employed
under independent contracts. We are in
Belgium and you stated this is not
possible?
From AMGA: Direct personnel costs: Natural persons with direct
contract - This budget category covers typically the costs of in-
house consultants and similar persons (i.e. self-employed natural
persons) that worked on the action for the beneficiary under
conditions similar to those of an employee. Please note: The
contract cannot be with a third party legal entity (e.g. a temporary
work agency), even if that third party is a one-person company.
Legally you basically cannot have a contract with a legal entity -
but it needs to be a natural person.
14 If we have a worker with two different
kinds of labor contracts, one elegible and
the other no, which anual cost should
must we use to calcule the fee? only the
contract that is elegible?
Yes, calculate only with eligible costs
15 What, if several employees with different
salaries work in one project?
This is normally true for all organisations. For all employees you
calculate the eligible costs separately that you charge on the
project.
16 if a company has more than one H2020
project, starting in different years, is if
acceptable that the same in-house
consultant has different hourly rate form
one project to another?
Yes, if clearly justified and not significantly different.
17 is it also possible to calculate cost for an
administrative Person at our institute also
a non researcher!! (university)
yes, also admin people can work on the project on specific tasks
18 Persons recruited through temporary
work agencies, are these costs eligible?
from AMGA: Staff provided by a temporary work agency — A
contract with a temporary work agency qualifies typically as
purchase of services (unless the temporary work agency carries
out directly some task of the action — in which case it would be
considered as subcontracting). Thus, although NOT eligible as
personnel costs, the costs can be charged under other budget
categories (i.e. D.3 other goods and services or B. subcontracting),
if they comply with the eligibility conditions (especially best value
for money and no conflict of interest; see Articles 10 and 13).
19 if an employee is assigned to multiple
H2020 projects should the declaration
you mentioned be filled?
No, because the person is not fully allocated to the project, but
works on several projects. Timesheets are needed and an
assignment to each project following your own rules.
20 is holiday allowance also allowed to
calculate in the personell cost?
Yes, the part which is paid by the employer based on national
rules (and not compensated in any way later by the state)
# ORIGINAL PARTICIPANT QUESTION ANSWER BY EUROPA MEDIA
4. 4
21 A person previously employed by a
beneficiary has started his own company.
This company will be included as a third
linked party in the project. So it is possible
his personnel costs have changed from
actual direct personnel cost to SME owner
unit costs? Is there anything I need to
keep in mind in this situation?
Is this really a linked third party? What is the legal link between the
two organisations? But yes, the rates will be different - if one
project is affected by this in a reporting period - a clear justification
needs to be included in the report.
22 In Spain a lot of the time the mandatory
salary is the Minimum Salary cost and
then pluses are added to that, here our
accountant has stated that these bonuses
are part of the basic salary, although it is a
seperate part of the basic salary. So what
pluses are and aren't included?
Your accountant may be right and your additional parts of the
salary may indeed be part of the basic salary. This has to be
carefully checked. Exclude arbitrary bonuses (i.e. bonuses which
are not part of the beneficiary's usual remuneration practices and/
or which are not based on objective conditions). Also these
bonuses should have no connection to the project itself.
23 Is always needed a letter of assignment,
even if the person works only a part of his
time at the project?
Assignment is needed - no matter how low is the involvement.
Follow your own rules how this needs to be done.
24 In perssonel costs can we take into
account the costs related to courses that
have been made by the person whose
costs we are calculating?
???? I do not understand the question
25 By taxes included in the remuneration you
mean taxes paying by the employee
himself/herself?
Both paid by the employee to the state (automatically deducted
from the salary) and the taxes paid by the employer.
26 Could you just repeat the part about who
can be included - do they have to be
officially assigned in someway to the
project?
Project personnel working at the Beneficiary (assigned to the
project) ACTUAL Personnel costs
- Employees or equivalent employment contracts
- Seconded employees
- In-house consultants
UNIT-based Personnel costs
- Average personnel costs – set by the Beneficiary
- SME owner rate – set by the EC/GA
- Natural person rate – set by the EC/GA
27 Hi, about in-kind benefits: what about for
instance pension funds, health insurance,
etc,?
If allowed by internal and national rules to be part of the salary,
then also eligible in the H2020 personnel costs
28 Can HR accounting costs be included in
the personnel costs? (when using an
external service provider as a small
organisation and getting an invoice for it)
No, this will probably not be eligible - include to indirect costs.
# ORIGINAL PARTICIPANT QUESTION ANSWER BY EUROPA MEDIA
5. 5
29 And what about the number of productive
hours during maternity?
During maternity leave you do not have any productive hours. from
the AMGA: The same rules on the treatment of absences and
overtime apply as for annual hourly rates, except that time spent
on parental leave can NOT be deducted from the annual
productive hours.
However, beneficiaries may charge to the action the costs
incurred for parental leave (as personnel costs) in proportion to
the time the person worked for the action during the financial year
(time worked on the action over total productive hours for the
year). This must be done separately and on top of the personnel
costs declared by multiplying the hours worked for the action by
the monthly hourly rates.
30 We are collecting all the Personnel Cost
either on Emdesk and registering the
individual hours spent on the project on
excel forms with daily registration. How
the review process will take place at the
end of the project?
You need to archive all this documentation. The financial audit may
come within the project duration - a closed period is needed for
one or more projects. The financia audit is done on the
organisational level. All your documentation will be checked.
31 sickness leave: how can this be paid as
we do not have productive hours for that
year we have the 1720 rule in fiscal year
can we calulate also thes hours for e.g
when the person is one week sick?
1720 is the standard number of productive hours, already
deducting an average number of hours spent on sick leave. So you
add the sick-leave payment to the basic salary when it is paid and
use the 1720 where sick-leave is already considered.
32 In Italy we have the IRAP tax, Is it included
in eligible salary components?
No, it is not eligible. There is a document called country-specific
issues where the AMGA is also downloadable. See it there.
# ORIGINAL PARTICIPANT QUESTION ANSWER BY EUROPA MEDIA
6. 6
33 What happens if the emplyees work a
more than the 1720H?
The double ceiling needs to be considered. From AMGA:
Beneficiaries must ensure that:
- the total number of hours worked declared in EU and Euratom
grants for a person for a year is NOT higher than the number of
annual productive hours used for the calculation of the hourly rate
(see below)
Example: Beneficiary using 1 720 as annual productive hours.
According to the time-records, during the financial year 2017
employee Z worked 900 hours in a H2020 action and 900 hours
in another EU project. The total hours worked for EU projects by
employee Z would therefore be 1 800 (900 + 900). However, the
beneficiary cannot declare more than 1 720 hours, since this is the
number of annual productive hours it used for the calculation of
the hourly rate. Therefore, for 2017, the beneficiary can only
charge 820 hours to the H2020 action (i.e. 1 720 – 900 hours
declared to other EU grant), even if the person worked 900 hours
in the action.
- the total amount of personnel costs declared (for reimbursement
as actual costs) in EU and Euratom grants for a person for a year
is NOT higher than the total personnel costs recorded in the
beneficiary’s accounts (for that person for that year).
Example: The total personnel costs recorded in the 2017 accounts
of the beneficiary for employee Z is EUR 18 000. The beneficiary
already declared EUR 9 000 to the other EU grant. The hourly rate
for employee Z according to the formula in the H2020 Grant
Agreement is 11 EUR/hour and employee Z worked 900 hours for
the action in 2017. The eligible personnel costs for the H2020
action would therefore be: 11 EUR/hour x 900 hours = EUR 9 900.
However, since the beneficiary already declared EUR 9 000 to the
other EU grant, the maximum that it can declare to the H2020
action is: EUR 18 000 (total personnel costs for employee Z) – EUR
9 000 (already declared to other EU grant) = EUR 9 000. The
beneficiary can therefore declare only EUR 9 000, even if the
result of the formula for personnel costs would be EUR 9 900.
34 How to calculate the hourly rate when the
13th salary is paid out in a given month
and we report using the monthly hourly
rate
You need to proportionate. In each month in the reporting period
you calculate the relavant part of the 13th salary earned in that
month.
35 Is it possible to change from 1720h to
another method within a running project?
From fiscal year to fiscal year you can change - but for running
project it needs to be done retroactively (so with an adjustment to
the previous period(s)) From AMGA: Recalculations & adjustments
of financial statements (exceptional) — To benefit from this new
option (i.e. hourly rate per month) beneficiaries may apply it
retroactively for all grants on-going (i.e. for which the final report
has not been submitted) on 20 July 2016 (i.e. date of adoption of
the H2020 MGA version 3.0). The beneficiary may re-calculate
costs already declared on the basis the full financial year by using
the monthly calculation method. However, in that case it must do
the recalculation for ALL personnel costs declared for that/those
financial year(s) in ALL on-going H2020 grants. The beneficiary
must declare the differences, either positive or negative, as
adjustments in the next reporting period.
# ORIGINAL PARTICIPANT QUESTION ANSWER BY EUROPA MEDIA
7. 36 For countries out of EU, Euro currency is
changing during the year. What is the
eligible currency calculation?
Beneficiaries [and linked third parties] with accounting established
in a currency other than the euro must convert the costs recorded
in their accounts into euro, at the average of the daily exchange
rates published in the C series of the Official Journal of the
European Union, calculated over the corresponding reporting
period.
37 How about employees with contracts
without monthly hours? I.e. these
employees normally do not use
timesheets and do not track their time. If
such empoyees book hours on a H2020
project it will be the only entry in the
timesheet. Is there any problem that can
arise in such construct.
Use the 1720 for the hourly rate calculation or the pro-rata of that.
38 What happend if you use 1720 fixed hours
but the annual productive hours are 1600?
How do you calculate it with hourly rate
per month? so, we have to calculate as
follow? total personnel eligible costs/1720
but we have to put just a maximum of
1600 worked hours, right?
In case you use the 1720, but your real hours are lower, you will
charge less to the EU than you could have. You need to add up all
salary - in your case in one month and then divide by 1720/12 (143
hours). That will give your the hourly rate for the month in question.
Then multiply this hourly rate with the hours spent on the project
based on the timesheet. You do not make any mistake here, just
charge less than possible as you decided to use the 1720 standard
productive hours.
39 Would we receive the calculation as
example?
I am sorry, the excel will not be shared
40 maybe I missed it....how to include the
extra months (13 and 14) in the personal
costs? i see in the excel I see the monthly
cost is multiplied by 12
If you have 13th and 14th month salaries and it is based on national
rules, then just add it to all yearly salary costs. That is if you use
fiscal year calculation. In case of monthly calculation, you need to
distribute the two extra salaries by months throughout the year.
(when the part of these two extra salaries were earned)
41 Regarding personnel cost calculation for
hourly rate, a researcher with with a sick
leave for almost the whole year (being
2018 last closed year) (total salary paid by
the State as a public servant), how must
the cost for 2019 (not closed) be
calculated? should the remuneration cost
of 2017 or 2018 be taken?
2018 has to be taken - BUT as teh hourly rate will be probably
really high, probably the capping will be met and double ceiling
will be an issue, so you will probably charge what you paid.
42 When ypou report a future period using
the actual rate, can you correct the
reported hours when you Know the rate of
that future period? So you submit and
adjustment and that's it?
No adjustments are possible just because you know the real costs
of a closed year part of it you have reported already using the
previous year's hourly rate. You can submit adjustments to
previous periods when mistakes done are realised.
43 But if you have to audit the project at the
end of it because you need a CFS, it
would be an error for the hourly rate of
january/april 2017...
The auditor will check the hourly rate calculation considering if that
at the time of the reporting you had all information about closed
financial years or not. Mistakes will be identified if you made such
mistakes at the time of the reporting. If you did the calculation
correctly at the time of the reporting no adjustments will be
recomemnded just because at the end of the project you have the
information.
44 PD: under beneficiary standars calculation
basis
?
#
7
ORIGINAL PARTICIPANT QUESTION ANSWER BY EUROPA MEDIA
8. 8
45 Hello. Timesheets must be signed by
employees and supervisors every month,
right? Should be signed in pen, to be
more trusthworthy?
Electronic signatures are also accepted if your system allows that.
46 using the 1720 method: what if the person
works from november til december 350
hours -> calcuating with the 1720 method
he would only be allowed 286 h
(1720/12*2month) -> do I have to do that
monthly breakdown or do I look at the
yearly hours?
You can do both - depends which one you decided to use anyway
and which is beneficial for you. Also your present accounting
system should be taken into consideration. In case of monthly
calculation, the hourly rate will be the monthly payment divided by
143 (1720/12). That will be multiplied with the real hours worked
(NOT the 286!). In case of fiscal year calculation - all yearly salary is
added up, then divided by 1720. This results in a yearly hourly rate,
which you will multiply by 350 to have the personnel costs to be
reported. You cannot work more than 1720 in any consecutive 12
months, it does not mean that also pro-rata it shoudl be kept. So
you can work in 2 months also 400 hours if you do not exceed
1720 in the whole year. NB: if you started to work on 1 November at
the organisation, you use the fiscal year calculation and the 1720
then the double ceiling rule will not allow you to charge more than
the two monthly salaries.
47 There are some costs like holidays
accrued in a year but payed in the year
after
If already paid - only then you can include it to the report.
Calculating only the part that refers to the reporting period.
48 May we take that in to consideration in the
annual salary cost even the accrual is
previous to the payment time which is the
one we have to take into account?
If this is an actual accrual because the cost is booked in the
previous year's accounting even if paid next year, you may take
that into account - so particularly foreseen and accounted only the
payment is accrued then it is ok.
49 in case of 13th or 14th salary, in order to
get the total eligible salary cost per month
do we multiply the actual monthly rate by
13 or 14 and then divide by 12?
see previous replies
50 If a person works a whole year (52 weeks)
x 40 hours a week = 2080. And has 7,5
weeks of holiday = 300 hours. Total
available hours would be 2080 - 300 =
1780 hours. How does this relate to the
1720 hours. What is better to use?
holidays, sicknessleave, national holidays,
educational/maternity leave - this is taken
as an average and subtracted from 2080 -
so you get 1720
? Not sure what is your question. The productive hour calculation is
described in the AMGA: annual workable hours of the person
(according to the employment contract, applicable collective
labour agreement or national law)
plus
overtime worked
minus
absences (such as sick leave and special leave)}.
# ORIGINAL PARTICIPANT QUESTION ANSWER BY EUROPA MEDIA
9. 9
ANSWER BY EUROPA MEDIA
51 for the yearly calculation: why it is not
allowed to make an adjustment to period 1
afterwards, to correct the financial data
which were not yet available at the point
of reporting for Period 1?
this is the rule. From AMGA: Recalculations & adjustments of
financial statements (exceptional) — Adjustments to the hourly
rate are normally allowed ONLY for mistakes (e.g. incorrect
accounting information; error in the calculation; etc.) and must be
done using the hourly rate which would have had to be used at
the end of the reporting period concerned.
Examples:
1. An internal audit on the annual accounts of the beneficiary finds
later errors in the accounting information used to calculate the
hourly rates.
2. Reporting period 1 runs from 1 January 2016 to 30 June 2017.
The beneficiary used the hourly rate 2016 for the entire period (i.e.
also for the part from 01/01/2017 – 30/06/2017) because the
financial year 2017 was still on-going at the end of the reporting
period. In 2018, the beneficiary realises that the 2016 hourly rate
was incorrectly calculated and that it has to declare an adjustment
for reporting period 1. To calculate the adjustment, the beneficiary
must use the correct hourly rate for 2016 for the whole reporting
period 1, including the period from January to June 2017.
Otherwise, costs that have already been declared can normally
NOT be adjusted/changed (even if a recalculation of the hourly
rate after the closure of the financial year would give another
result).
52 To me is still not clear which bonuses are
eligible and which not. Thanks!
Basic rules from AMGA: bonuses are eligible if based on the
overall financial performance of the organisation (e.g. profitability
or surplus) may be accepted, if they fulfil the conditions set out
below, i.e. as part of the usual remuneration practices for national
projects and thus eligible as basic remuneration. OR bonus is paid
in accordance with national law, the collective labour agreement
and the employment contract/equivalent appointing act. ALWAYS
exclude arbitrary bonuses (i.e. bonuses which are not part of the
beneficiary's usual remuneration practices and/or which are not
based on objective conditions).
# ORIGINAL PARTICIPANT QUESTION
10. 10
53 Dear Gabriella, in the monthly calculation
do we need to use a capping of the 1720
hours in case the researcher worked on
the project for less than a year?
In monthly calculation you use for the hourly calculation the 1/12th
of the standard, yes. Also capping needs to be considered
because of the double ceiling. Let's suppose that the researcher
worked for 6 months. In these months he worked 150 hours on the
project each month. You need to check if you are charging more
to the project than what was actually paid to the researcher. from
AMGA about the double ceiling: Double ceiling — Beneficiaries
must ensure that:
- the total number of hours worked declared in EU and Euratom
grants for a person for a year is NOT higher than the number of
annual productive hours used for the calculation of the hourly rate
(see below)
Example: Beneficiary using 1 720 as annual productive hours.
According to the time-records, during the financial year 2017
employee Z worked 900 hours in a H2020 action and 900 hours
in another EU project. The total hours worked for EU projects by
employee Z would therefore be 1 800 (900 + 900). However, the
beneficiary cannot declare more than 1 720 hours, since this is the
number of annual productive hours it used for the calculation of
the hourly rate. Therefore, for 2017, the beneficiary can only
charge 820 hours to the H2020 action (i.e. 1 720 – 900 hours
declared to other EU grant), even if the person worked 900 hours
in the action.
- the total amount of personnel costs declared (for reimbursement
as actual costs) in EU and Euratom grants for a person for a year
is NOT higher than the total personnel costs recorded in the
beneficiary’s accounts (for that person for that year).
Example: The total personnel costs recorded in the 2017 accounts
of the beneficiary for employee Z is EUR 18 000. The beneficiary
already declared EUR 9 000 to the other EU grant. The hourly rate
for employee Z according to the formula in the H2020 Grant
Agreement is 11 EUR/hour and employee Z worked 900 hours for
the action in 2017. The eligible personnel costs for the H2020
action would therefore be: 11 EUR/hour x 900 hours = EUR 9 900.
However, since the beneficiary already declared EUR 9 000 to the
other EU grant, the maximum that it can declare to the H2020
action is: EUR 18 000 (total personnel costs for employee Z) – EUR
9 000 (already declared to other EU grant) = EUR 9 000. The
beneficiary can therefore declare only EUR 9 000, even if the
result of the formula for personnel costs would be EUR 9 900. So,
if your researcher earns 1430 EUR/month and you use 1720. Than
teh monthly hourly rate is 10 EUR. In case the researcher works for
6 months at the organisation and the project, then the max salary
will be 6x1430 = 8580 EUR. While if the researcher works 150
hours on the project each month, you count 9000 EUR: Becuase
of the double ceiling, you can charge only 8580 EUR to the
project. If on the other hand the researcher works for the
organisation the whole year, and only for this project for 6 months,
then the full 9000 could be charged to the project. BUT Nota
bene! the double ceiling still applies if the researcher works on
other EU projects as well. You still cannot charge more than what
was actually paid out in that year.
54 i didnt understand the double ceiling. can
you kindly explain again? thanks
see previous replies
# ORIGINAL PARTICIPANT QUESTION ANSWER BY EUROPA MEDIA
11. 11
55 Actual hours can often vary quite
significantly from standard hours for f/t
staff - how should this be resolved on the
timesheet when researchers are 100% on
the project?
You always report the actual hours on the timesheet. But again, be
careful with the double ceiling as explained above and check if the
total number of yearly productive hours correspond to the
standard. (the yearly total number should be watched)
56 If we use 1720/12, amounts don't
correspond with accounting. auditors
suggested: total eligible personnel costs/
1720hours. and then weig monthly hours
month by month. In this case, we have a
diferent hourly rate each month
It is not necessary to have your internal accounting numbers fully
matching with the reported numbers. As you are using actual
hours internally and the standard for the EU, the numbers will not
be the same. For internal reasons you may do what the auditor
suggested, still, the EU rules need to be followed. The accounted
numbers should be higher or equal than what you report as cost to
the EU.
57 Time recording: Is it sufficient to record
the time just on a monthly and not daily
basis?
The timesheet summarises the hours on the project on a monthly
basis. We recommend having a daily distribution with hourly
accuracy on this monthly timesheet.
58 When is a time recording system
considered "certified"?
It is certified if you apply certain principles. There is no full
description on this I think, but the basic issues are: authorisation;
accuracy; reliability; approval process etc. You do not have to
chose a certified software for time tracking. The system needs to
fulfil these principles and you can do that with printed timesheets
using excel.
59 In which situation using 1720H methode is
recommended?
In case your annual productive hours (of those people normally
working on projects) are lower or close to 1720 you can save
administration time by using 1720. If the real annual productive
hours are higher than using 1720 is beneficial, just watch the
double ceiling. If the real annual productive hours are significantly
lower than 1720, we do not recommend using the 1720 standard.
# ORIGINAL PARTICIPANT QUESTION ANSWER BY EUROPA MEDIA
12. 12
60 You mentioned that if a person works on
the project exclusively a certified
declaration is sufficient, but if this person
has some leavings due to illness, and
these days are higher than the effective
working days of the month the EC would
not pay that month. So better use a TS
record always isn't it?
In case we talk about a leave that has to be paid by your
organisation, than indeed this is an issue as in the monthly
calculation you would end up with zero costs. BUT the AMGA
states: Absences & overtime —
The same rules on the treatment of absences and overtime apply
as for annual hourly rates, except that time spent on parental
leave can NOT be deducted from the annual productive hours.
However, beneficiaries may charge to the action the costs
incurred for parental leave (as personnel costs) in proportion to
the time the person worked for the action during the financial year
(time worked on the action over total productive hours for the
year). This must be done separately and on top of the personnel
costs declared by multiplying the hours worked for the action by
the monthly hourly rates.
Example:
In 2015 Ms T has been five months in parental leave. During that
time the social security reimbursed to the beneficiary 50 % of her
salary. Her monthly salary was EUR 3 000 (reimbursement EUR 1
500). The beneficiary used option 1 (1720 fixed hours) for the
annual productive hours and Ms T worked in 2015 320 hours on
the H2020 action.
Personnel costs incurred during parental leave= {EUR 3 000 x 5} -
{EUR 1 500 x 5} = 15 000 – 7 500 = EUR 7 500
(Note: amounts reimbursed to the beneficiary by the social
security are not actual costs for it and, therefore, must be
deducted)
Proportion of time worked for the action in 2015 = Time worked for
the action / Total productive hours excluding the parental leave =
320 / {1720 - {1 720 x 5/12}} = 320 / {1 720 – 716,7} = 320 / 1 003,3 =
31,89 %
Cost of parental leave for the H2020 action = EUR 7 500 x 31,89 %
= EUR 2 391,75
61 Is the 1720 prorate (monthly calculation)
related to the months worked in the
institution or the months worked on the
project?
1720 limitation is for the hours worked on the project in a year. The
prorata of the 1720 applies if you work less in the organisation than
a full year or your contract is not a full time position. Othrwise in
monthly calculation you use always 1720/12.
62 I thought the time sheets are monthly and
not daily now in H2020
The timesheet summarises the hours on the project on a monthly
basis. We recommend having a daily distribution with hourly
accuracy on this monthly timesheet.
63 Is a "reliable and certified system"
necessarily be different from an excel
system of reporting? In other words what
is the meaning of a "certified system"?
see previous replies
64 Can I calculate the hourly rate based on
real worked hours per month?
NO, in monthly calculation you have to use the 1/12th of a standard
65 Could you please explain how to apply
the double ceiling in the monthly
calculation?
The double ceiling is applicable for any consecutive 12 months. In
montly you cannot apply that as you work different hours in
different months.
# ORIGINAL PARTICIPANT QUESTION ANSWER BY EUROPA MEDIA
13. 13
66 Our fiscal year is from 01/10/-31/09; we
need to report to fiscal authorities the
salaries from 01/01-31/12 every year -
which personell cost do I have to use for a
project that startet on 01/05 and the first
report is due after 18 months?
Use your fiscal year. If the start year e.g. is 2017 then 01/05/2017 -
31/10/2018 is your reporting period. So for 01/05/2017-31/09/2017
your use the hourly rate from the 2016-2017 fiscal year. Then for
01/10/2017-31/09/2018 you use this fiscal year's hourly rate and for
the last september 2018 month you use the previous fiscal year's
hourly rate.
67 Is there also an exception if one works on
the one project exclusively, but only part-
time, like 50%?
Yes, if all hours at the organisation are exclusively spent on one
project, it is ok.
68 in the case of a in house consultant
working on the project exclusively, is it
sufficient with a certified declaration?
They need timesheets all time as basically their contract is
exclusive on the project in each case - but that is not an
employment contract. Timesheets are a must.
69 can use one time sheet for project or only
one with all projects ?
You can have both versions for timesheets. We are recommending
having all monthly productive hours on one timesheet, but this is
not a must.
70 If you have a researcher who works only 2
days per week but exclusively for the
project. Do you need time sheets for him
If his full employment contract is for the project, no timesheet is
needed. The declaration is enough.
71 some of our researchers do not take their
full annual leave entitlement so work more
than the beneficiary's annual productive
hours. How do we deal with this?
You do not change anything in the calculation because of this. If
you use 1720, it cannot be adjusted. If we suppose that this holiday
not taken is paid out, then the yearly salary will be higher that
usual and that is ok. This is not a problem.
72 Is there any template for the certified
declaration for people that work full time
in the same project? Does it need to be
uploaded on the participant portal or just
sent by email to the PO?"
It is downloadable from the Funding and Tenders Portal - under
How to Participat - Refrence documents. You need to keep it, no
need to upload anywhere. The financial officer may ask for it.
73 Good morning. The timesheet time basis
is daily ? Could it be monthly ?
The timesheet summarises the hours on the project on a monthly
basis. We recommend having a daily distribution with hourly
accuracy on this monthly timesheet.
74 Unrelated to personnel costs: I would
really appreciate a webinar regarding
DoA changes (in EMDESK), is this
something you might consider?
Sure, we will consider
75 temporary working agency cannot been
consider an other cost "services"? it's only
subcontracting ?
from AMGA: Staff provided by another entity against a price,
including staff provided by a temporary work agency (because in
this case there is no direct contract between the person and the
beneficiary; the contract is not with the beneficiary but with the
entity hiring the person).
Staff provided by a temporary work agency — A contract with a
temporary work agency qualifies typically as purchase of services
(unless the temporary work agency carries out directly some task
of the action — in which case it would be considered as
subcontracting). Thus, although NOT eligible as personnel costs,
the costs can be charged under other budget categories (i.e. D.3
other goods and services or B. subcontracting), if they comply with
the eligibility conditions (especially best value for money and no
conflict of interest; see Articles 10 and 13).
# ORIGINAL PARTICIPANT QUESTION ANSWER BY EUROPA MEDIA
14. 14
76 Wich bonuses are elegibles? see previous replies
77 In RP1 (interim reporting over the first 18
months of the project) we have exceeded
the PM rate over what was initially
projected. How can we adjust this? Our
salaries are paid based on our national
legislation and practice for research
projects
If the calculation of your salaries is correct than the only thing to do
is to explain and justify the raise in PM rates. There is no room for
adjustment.
78 For a person contracted at some point in
a current year, how to calculate the Hourly
rate?? is this right: we contract a person 1
june, then, for a EC medium dedication,
i.e. 1720h, for this case would be 860h???
Supposing this person is hired from the 1st July and you use fiscal
year calculation with 1720, then indeed the half of 1720 should be
used for the hourly rate calculation.
79 What, if the actual personell costs differ a
lot from what was assumed in the
proposal? (i.e. due to personnel change..)
You need to give explanation on that to the officer. Still, the report
has to be based on real costs of the people allocated to the
project.
80 When does this internal e-mail to assign a
person to the grant be sent? whenever
during the project? Do we need to send a
copy to the PO as proof?
No need to send a copy to anyone. The assignment should be
following your own rules.
81 For monthly calculation - holiday
allowance and sick leave - does it have to
be proportionaly calculated for each
month
if paid at once and not monthly, yes
82 Can a company bonus or additional
remuneration given just to an employee
be charged to the project and be eligible -
it is not linked to the project
A company bonus paid to one employee - not sure this is
possible. Regarding additional remuneration, you have to fulfil all
rules, only then this cost is eligible for the project.
84 tickets restaurant are eligible? as
personnel cost?
If also in your accounting system this is part of the salary, then yes,
it could be eligible also for the project.
85 do we need any proof to apply to the 1720
methodology ?
No
86 In an EU project of ours, we get a PM of
6.150 Euros and in the DoA, it says that
we are putting 32 months into the project.
We have found out that our hourly rate is
higher than the one calculated on the
basis of he 6.150 and it is therefore not
possible for us to work 32 months. Do we
just work less than - for example 25
months? Or do we HAVE to work the
months that we can on the basis of our
own, real hourly rates?
I replied to this on the webinar, please watch this part
87 We have a single time sheet with different
columns dedictaed to the different
projects: is this ok?
Yes, we recommend however giving also reference to the WP/task
you worked on. Normally columns are days and rows are project
tasks in a timesheet.
# ORIGINAL PARTICIPANT QUESTION ANSWER BY EUROPA MEDIA
15. 15
88 How the final rewiew of the project cost
will be performed by H2020 inspectors?
We have prepared all the individual hour
registration form and also submitted all
the personnel costs on the EMdesk
platform. Waht are the official documents
cosidered by inspectors?
There is a full list of documents you need to prepare for a financial
audit. You may download it from the Funding and Tenders portal
(under Reference Documents - Templates section). In case of
technical reviews only the official reports will be reviewed by the
reviewers to conduct a financial check.
89 A person has been sick for 4 months and
the company has payed him/her as usual;
using productive hours shall we consider
all the hours of 8 months or 12 as usual
dividing for the yearly salary?
see previous replies
90 Since when is it allowed to use the
simplified time sheets? Until that date it
was compulsory to register all hours and
activities, right?
You still need to register all hours and activities on the project.
However, the timesheet template the Commission published does
not record all your hours in a month, just the project hours. The
explanation what was done in that month on the project should be
also available whenever the officer asks for it.
91 Are personnel costs regarding internships
eligible to be included? Can those intern
employees who have a agreement (but
not a contract) be included in this eligible
personnel costs?
Internship is eligible, you need to follow your own national rules
regarding payment and contractual arrangements.
92 in § 1.3 direct personal cost it is stated:
Staff provided by a temporary work
agency — A contract with a temporary
work agency qualifies typi-cally as a
purchase of services (unless the
temporary work agency carries out
directly some task of the action — in
which case it can be considered as
subcontracting). Thus, although NOT
eligible as personnel costs, the costs can
be charged under other budget
categories (i.e. D.3 other goods and
services+B64
see previous replies
93 Where do we find the national project
reference rate?
There is no common database or any link I know of. Each country if
it has this rate set - they publish it on national channels.
94 How can be diferenciated the elibigle
compliments? Are eligible costs those
compliments that the company has in
normal practice with all employees? I
mean a revision of productivity
see previous replies
95 is a bonus for "good workers" given at the
end of the year an eligible cost? or
additional remuneration?
see previous replies
96 What about if the person is working for
the project in holidays to attain the project
meetings or reporting the days that are
not holiday in other countries?
I replied to this on the webinar, please watch this part
# ORIGINAL PARTICIPANT QUESTION ANSWER BY EUROPA MEDIA
16. 16
97 Can you define what is considered
overheads?
from AMGA: ‘Indirect costs’ are costs that cannot be identified as
specific costs directly linked to the performance of the action.
In practice, they are costs whose link to the action can NOT be (or
has not been) measured directly, but only by means of cost drivers
or a proxy (i.e. parameters that apportion the total indirect costs
(overheads) among the different activities of the beneficiary).
98 What about a person who work at 80%,
should we use the 1720h*0.80 ??
yes
99 Is there (will there be ) a FAQ webpage
with the answers to the most of the above
questions ? Maybe such a page is (could
be) available from the EC ? This can
benefit many organisations and project
across the board, rather than some
project develop their own FAQ pages
We do not know about a common, EC published FAQ on these
issues. But on the Funding and Tenders portal you have the
Support section.
100 If we use a monthly rate and not a fiscal
annual rate using 1/12 1720, then in a
periodid reporting period ending in June
2019, can we use the real monthly costs
from January-JUne 2019 or would we
have tp also use 2018 costs? You have
talked about this but I still have a bit of
queries concerning this.
In case of monthly calculation you use indeed the real monthly
rates, so if the period is between May 2018 and April 2019 then
you can charge January-April 2019 monthly costs.
101 is correct to use standard hours less 10%
as non productive hours? i would say
standard hours of the company
???? I do not understand the question
102 What would be the link of the personnel
costs declared in the Financial Statement
(based on the hourly rate per person) with
the accounting system or payroll system.
In your excelfile you showed the monthly
salary, but what is actually paid per month
will differ? (vacation, sick leave, etc)
In many organisations the monthly salaries are different from each
other. Because you use a standard number of hours for calculating
the hourly rate, the numbers in the accountng system and the
personnel costs reported in the financial statement will not 100%
match.
103 when you used the actual on yearly
financial bases and you a have a new
employee that start to work for example in
2019 and when I have to made the
financial statment my fiscal year it's not
close , how we calculate the cost for the
new employee ? 2019 salary even if is not
yet closed ?
This is an exception, you need to use the actual - so 2019 salary is
used.
104 holidays and parental leaves related to
the previous year paed by the company
are included in the salry of the year ? or
we need to deduct ?
You include it. In fiscal year calculation you cannot include it next
year, so you include the holiday payment in the hourly rate
calculation even if it refers the previous year. As each year you get
the payment - but always later.
105 Is it possible to insert the hours worked
during a trip, for example an airplane, in
the timesheets?
If your travel policy allows that, then yes.
# ORIGINAL PARTICIPANT QUESTION ANSWER BY EUROPA MEDIA
17. 17
106 Can timesheets be those extracted from
SAP account or should be in a specific
format?
Yes, you can use that.
107 Can a cost related to a project incurred
after the project has ended, can be
considered as eligible cost? If yes, then
how can this cost be claimed?
Only the personnel costs related to reporting after the end of the
project or if you have a review meetings within the 60 days after
the last reporting period. These are eligible for all partners. You
claim these costs in the final report that you submit within 60 days
after the end of the project.
108 Can a PM rate be an average rate for all
workers or should if we are using actual
costs do we have to use each persons PM
rate?
Average PM rates are used only for budgetary calculation
purposes. In the report you use real costs that are based on hourly
rates.
109 If in a H2020 project, our average is 6000
and there is a variation because of a
internal re-organization or, for instance, if
a researcher leaves, how should we
proceed?
You need to justify the change and report the real costs.
110 Can yopu reestimate one period's costs
reportred before knowing the real cost for
that period?
see previous replies
111 An auditor told us that the excel
timesheets were not enough because
there were modifiable.
This is why excel timesheets need to be printed and signed. The
printed versions cannot be modified.
112 A contract for a person on a specific
project (so full time working on that
project) saying on that contract that he is
working on that project, is a valid
document or still we need an official
declaration specifying that this person is
working full time on that project?
The official declaration is needed.
113 Is it possible to make any adjustment in a
reporting period if we realize that we
made a mistake in calculating hourly rate
in previous periods?
Yes, if mistakes are realised, you can submit adjustments to
previous periods when the next reporting period is open.
114 Zdenek Broz Can you recommend
suitable publications on this subject?
Not sure which subject. If personnel cost calculation then read fully
the AMGA.
115 Related to the document associated to
exclusively dedication, as it is mentioned
in the AMGA if the declaration covers
months in which the person was absent
for more than half of the working days
those months can NOT be taken account
to calculate the hours worked in the
action. Maternal leave is inside this
exception so, the best way to avoid that
situations is to do TS althought the person
is 100% to the project?
This is quite an exceptional case, but if this absence was because
the person took the annual leave, then you can consider also that
month. You cannot take that month e.g. if the person is working
only from July till October and you still want the EC paying for full
August when the person was on holiday and working full-time on
the project. Full-time here for the EC is only four months from the
whole year, so the annual leave should not be paid from the
project. For parental leave you calculate the costs on the top of the
personnel costs (see previous replies).
# ORIGINAL PARTICIPANT QUESTION ANSWER BY EUROPA MEDIA
18. 18
116 I work full time on a H2020 project. The
total productive hours I have to work in
my institute (at Uni) per month is more
than the productive hours expected in the
H 2020 financial sheet prepared by the
Uni. What to do with the extra hours?
You cannot charge these extra hours on the project. You can do
other things in these hours.
117 If I use the fiscal year calculation and I
realise some components were wrongly
incorporated in the basic salary can I
make an adjustment?
see previous replies
118 If we declare in the first Reporting period
from January to April 2017, the hourly rate
of 2016, should we adjust the annual cost
of the 2017 presented in the M18 for the
one calculated in the second reporting for
2017? Or should we keep the cost
calculated in each period even if it is
different?
see previous replies
119 I have a question regarding salary
increase based on inflation for public
university when using project based
financing and additional remuneration. If I
understand the principles of calculating
eligible costs correctly, the methodology
doesn't allow to increase your salary over
time as it's always linked to the previous
financial year. So any extra costs, in this
case the increase based on inflation, will
be taken as additional salary. Is that
correct? This is also linked with the
national reference rate calculation. If I've
been working exclusively on H2020
projects for last 3 years, the national
reference rate will be taken from 4 years
back. Is that correct? If so, how does the
methodology enable increase of salary
based on inflation so it's not considered
as additional salary, but it's part of the
basic salary.
Your are mixing up additional remuneration scheme with salary
raise. Salary increase in your basic salary will be basic salary. It
does not matter if your salary increases because of the inflation or
other reasons. Each year you take the previous closed fianncial
year's data and each year this hourly rate will be different as your
salary increases. Indeed with fiscal year calculation you may loose
some money if your salary increased and the reporting period
includes also months when there is a raise you cannot take into
account. The national project reference rate if exists in your
country may be from last year or 5 years before you start working
on the project. Depends. In most countries there is no such
declared reference rate.
120 in the excel sheet that Gabriella
presented to calculate the hourly rate, the
year cost is divided by 12 months; how do
you incorporate the extra payment-
months (month 13 and 14)??. I guess you
can use the total year cost of the
employee (12+2 months) and then divide
by 12 to calculate the hourly rate; so, it
would not be possible to use the total
monthly salary cost, right?.
You can include it. In fiscal year you just simply add up all salary. In
monthly calculation you need to calculate how much this extra
payment was earned in each month. So simply add up the 13+14th
month salaries, divide this by 12 and this extra payment should be
added on top of each monthly salary.
# ORIGINAL PARTICIPANT QUESTION ANSWER BY EUROPA MEDIA
19. 19
121 When reporting as actual personnel costs,
If we are 5 people working on a project,
can we calculate an average PM rate to
use for all of them, say 5000 a month, if
this is a real average calculated from
adding all salaries together and dividing
them between the workers and getting a
result of 5000 or more so that in the end
the costs are actual, or below actual costs
spent but not reported, or if we are
reporting actual costs, must we use each
persons real actual costs and then add
this together?
Meaning can we use this average in the
following cases as actual costs:
CASE 1 AVERAGE PM USED IN PROJECT
AS ACTUAL COSTS: 5000 € PM
Worker 1: 6000€
Worker 2: 3000€
Worker 3: 6000€
Worker 4: 4000€
Worker 5: 6000€
Average PM= 25000€/5people = 5000€
Average PM
CASE2 AVERAGE PM USED IN PROJECT
AS ACTUAL COSTS: 5000€ PM
Worker 1: 6000€
Worker 2: 4000€
Worker 3: 6000€
Worker 4: 5000€
Worker 5: 6000€
Average PM= 27000€/5people = 5400€
Average PM, but we use 5000€PM
This question arises because in many EU
projects, when preparing them the project
leaders ask for you to give then an
average PM rate for the budget
calculations, but now we are not sure if in
the reporting we would have to use this
average PM rate provided or each
persons real monthly costs dedicated to
the projects.
For actual cost reporting you cannot use any average. For each
person you have to do the calculation of eligible personnel costs
that you want to report. None of these averages you listed can be
used. This is only for the budget development.
# ORIGINAL PARTICIPANT QUESTION ANSWER BY EUROPA MEDIA
EMDESK and Europa Media assume no responsibility for the content, accuracy or
completeness of the information presented.