Surrey County Council – Quadrant Court




                   Proposal for a

   Improvements in energy performance

                          At

             Surrey County Council

            Quadrant Court, Woking




                          Page 1 of 8    18/01/11
Surrey County Council – Quadrant Court




Surrey County Council                                  Project Ref: Q0030297/KBR
County Hall                                            Date-        18/01/2011
Penrhyn Rd                                             Project: -   Opus II
Kingston upon Thames,
Surrey
KT1 2DN

Dear Sir,
Under this proposal we will examine and report on the use of the building, quality of
existing services and equipment, architecture and tenant use.

We will offer savings and identify specific issues where tCO2 can be reduced.

The report is the basis upon which we can plan the actions required against any
capital expenditure required to achieve them and will suggest a period of payback for
each activity.

Yours sincerely,




Kieron Ryan BSC Hon MIET
Energy and Control Systems
Mob: 07970 615856




                                         Page 2 of 8                            18/01/11
Surrey County Council – Quadrant Court




            Schedule of Contents



EXECUTIVE SUMMARY.................................................................................................4

      Lighting 10% saving year on year....................................................................................................................4
       ..........................................................................................................................................................................4
      Boilers and associated plant 15% saving year on year...................................................................................4
      Chillers and associated plant 15% saving year on year..................................................................................4
      Fan coil units: (FCU above ceilings) 10% saving year on year......................................................................4
      Re-Commissioning Existing Controls Costs.....................................................................................................5
   EXISTING SYSTEMS .............................................................................................................................................7
      Lighting Controls...............................................................................................................................................7
      The Building Controls Network........................................................................................................................7
       LTHW (Low Temperature Hot Water).............................................................................................................7
      Chiller (CHW)...................................................................................................................................................7
      Fan Coil Units (FCU).......................................................................................................................................7
   OBSERVATIONS ON THE DAY.................................................................................................................................7
      Lighting..............................................................................................................................................................8
      Integration.........................................................................................................................................................8
      Human Factors..................................................................................................................................................8
      Airside System...................................................................................................................................................8
      Chiller................................................................................................................................................................8
      Incoming Voltage Regulation............................................................................................................................8




                                                                                    Page 3 of 8                                                                    18/01/11
Surrey County Council – Quadrant Court




                                        Executive Summary

Surrey County Council, Quadrant Court, Leatherhead.

     Lighting 10% saving year on year
Fitting of the PIR shields will allow the lights in unoccupied rooms to be disabled, if
this where integrated in the BMS a further saving can be achieved.

   Boilers and associated plant 15% saving year on year
Correct demand matching will achieve reasonable reductions with minimal outlay.
   Chillers and associated plant 15% saving year on year
Correct demand matching will achieve reasonable reductions with minimal outlay.

      Fan coil units: (FCU above ceilings) 10% saving year on year
         Developing a thorough understanding of the buildings use will leverage Fan coil
         energy savings; this would form part of the re-commissioning process.


Remote monitoring and energy management will leverage another 10-15% across the
board. This is because we remotely analysis and observe systems in operation, lock
in setpoints and maintain the most effective solutions to specific and identifiable.
However, in order to achieve this integration of the lighting systems would be
required.

   1. In order to maximise on energy savings we can offer the following services.
   2. Installation of an ADSL modem allowing full remote access from anywhere in
       the world. Installation of a suitable network to collect data from the sub-
       metering.
   3. Download the core code in each controller and examine for potential savings.
   4. Continuous collection of additional data from the BMS and the sub metered
       systems for detailed analysis and identification of downstream energy usage.
   5. Lockdown and maintain carbon footprint through continuous monitoring and
       alarming of setpoints and onsite activity.
   6. Your access to any system based around the Trend products can be achieved
       via the existing head end , further sites can be added using the existing
                                          1


       software and this will allow you to use a single interface to any site in your
       portfolio.
Incoming Voltage Regulation
Incoming voltage regulation should be considered as an additional and separate
project.




1   The existing PC in the FM offices
                                               Page 4 of 8                       18/01/11
Surrey County Council – Quadrant Court




Proposals Costs

Generally the controllers are in excellent condition requiring no modifications to the
hardware.

Re-Commissioning Existing Controls Costs
     Re-commissioning of the existing controls; nominally 3 weeks work,
     implementing, best achievable performance installation of remote monitoring
     hardware etc

Initial survey to establish detailed scope                         £XXX (1 day)
        Will be deducted from an order to complete the works.

Re-commissioning of main plant                                   £XXXX (3 weeks)
     Pressurisation units, pumps, boilers, chillers, fan coil units. Provide report
     regarding any new information revealed by this activity.

Remote plant monitoring 24/7/365                                  £XXXX (per year)
     This work is monitoring only, on the existing equipment and therefore the
     Lock down service can not apply.
     Some degree of energy monitoring is achievable with changes being
     implemented by attending site as and when agreed.




                                         Page 5 of 8                           18/01/11
Surrey County Council – Quadrant Court




Notes




                    Intentionally left blank.




                              Page 6 of 8       18/01/11
Surrey County Council – Quadrant Court




                                  Energy Report
Existing Systems
The primary existing systems are: -
Lighting Controls, LTHW (Low Temperature Hot Water), Chiller (CHW), Fan Coil Units
(FCU).

Lighting Controls
      The lighting system consists of a Philips Lightmaster intelligent lighting system,
      consisting of a PC interface, network architecture, power architecture, lighting
      modules, PIRs, local lighting level sensors and exterior lighting sensors.
      This provides the foundation for a very powerful tool for energy savings.

The Building Controls Network
     The BMS (Building Management System) is a current generation Trend IQ3
     system consisting of a PC interface, network architecture, 4 off IQ3 controllers
     and IO modules (input output modules), sensors, actuators, switches and
     inverters as required to operate each piece of equipment.
     This provides the second very powerful tool with which to implement energy
     changes.

LTHW (Low Temperature Hot Water)
    The heating system consists of 4 off boilers (220Kw each), primary (5.5Kw)
    and secondary pumps (15 Kw, VT circuit) and subsidiary circuits. We did not
    observe a CT circuit system.

Chiller (CHW)
       Consisting of 2 off chillers, 2 CHW pumps (22 Kw approx) and subsidiary
       circuits.

Fan Coil Units (FCU)
     The FCU and perimeter heaters operate similarly in that each unit is fitted with
     heating and cooling valves a dedicated controller and are networked together
     to facilitate the formation of groups controlled be a single setpoint and
     amalgamated sensor values.
Observations on the Day
            This building, originally handed over in 2006 is, as one might expect in
     excellent condition. The controls for both lighting and M&E services are of a
     modern and well thought out design, balanced against capital expenditure.




                                          Page 7 of 8                            18/01/11
Surrey County Council – Quadrant Court




Lighting
       There are some aspects that should be investigated in order to maximise
       energy savings and these are: -
               Integration of the lighting PIRs to the BMS, this would allow the HVAC
       systems to be shut down when the rooms are not used.
Integration
       Inverters already connected to the BMS can be used to collect energy
       information about the activities of pumps and motors. Particularly as these are
       already being modulated to meet some need.
Human Factors
       The lighting PIRs should be fitted with range limiting shields, available from
       Philips. This will prevent the activation of the lighting modules from activities in
       the corridors.
Airside System
       Air supply plant in some areas in looking somewhat untidy, but generally
       remains in excellent condition since 2006. Access to some of these areas is
       restrictive and as such additional H&S aspects must be considered.
Chiller
       As the building is only 3 years old the chillers have a long life expectancy
       before we can consider any investment in hardware, however there is room for
       improvement in the supply of CHW at unnecessarily low temperatures with
       respect to ambient conditions.
LTHW
       As the building is only 3 years old the boilers and pumps have a long life
       expectancy before we can consider any investment in hardware, however there
       is room for improvement in the supply of LTHW at unnecessarily high
       temperatures with respect to ambient conditions.

Demand Control (boilers and chillers)
    Some opportunities exist for addressing the issues of demand by using the
    local sensors on FCU and perimeter heating, loop temperature sensors and
    return air in order to optimise the demands placed on the M&E services.
Submetering
    The sub-metering mounted on the main incoming switch is not used to collect
    information; this worthwhile investment will assist in the identification of high
    energy use areas around the building

Incoming Voltage Regulation
     The relatively new technique of incoming voltage regulation offers further
     savings. The device regulates down stream voltage to optimise power
     consumption. In general the claims of 20% are generous whilst a realistic
     saving of 10% - 15% is easily achievable.




                                           Page 8 of 8                             18/01/11

Proposal For Scc Quadrant Court

  • 1.
    Surrey County Council– Quadrant Court Proposal for a Improvements in energy performance At Surrey County Council Quadrant Court, Woking Page 1 of 8 18/01/11
  • 2.
    Surrey County Council– Quadrant Court Surrey County Council Project Ref: Q0030297/KBR County Hall Date- 18/01/2011 Penrhyn Rd Project: - Opus II Kingston upon Thames, Surrey KT1 2DN Dear Sir, Under this proposal we will examine and report on the use of the building, quality of existing services and equipment, architecture and tenant use. We will offer savings and identify specific issues where tCO2 can be reduced. The report is the basis upon which we can plan the actions required against any capital expenditure required to achieve them and will suggest a period of payback for each activity. Yours sincerely, Kieron Ryan BSC Hon MIET Energy and Control Systems Mob: 07970 615856 Page 2 of 8 18/01/11
  • 3.
    Surrey County Council– Quadrant Court Schedule of Contents EXECUTIVE SUMMARY.................................................................................................4 Lighting 10% saving year on year....................................................................................................................4 ..........................................................................................................................................................................4 Boilers and associated plant 15% saving year on year...................................................................................4 Chillers and associated plant 15% saving year on year..................................................................................4 Fan coil units: (FCU above ceilings) 10% saving year on year......................................................................4 Re-Commissioning Existing Controls Costs.....................................................................................................5 EXISTING SYSTEMS .............................................................................................................................................7 Lighting Controls...............................................................................................................................................7 The Building Controls Network........................................................................................................................7 LTHW (Low Temperature Hot Water).............................................................................................................7 Chiller (CHW)...................................................................................................................................................7 Fan Coil Units (FCU).......................................................................................................................................7 OBSERVATIONS ON THE DAY.................................................................................................................................7 Lighting..............................................................................................................................................................8 Integration.........................................................................................................................................................8 Human Factors..................................................................................................................................................8 Airside System...................................................................................................................................................8 Chiller................................................................................................................................................................8 Incoming Voltage Regulation............................................................................................................................8 Page 3 of 8 18/01/11
  • 4.
    Surrey County Council– Quadrant Court Executive Summary Surrey County Council, Quadrant Court, Leatherhead. Lighting 10% saving year on year Fitting of the PIR shields will allow the lights in unoccupied rooms to be disabled, if this where integrated in the BMS a further saving can be achieved. Boilers and associated plant 15% saving year on year Correct demand matching will achieve reasonable reductions with minimal outlay. Chillers and associated plant 15% saving year on year Correct demand matching will achieve reasonable reductions with minimal outlay. Fan coil units: (FCU above ceilings) 10% saving year on year Developing a thorough understanding of the buildings use will leverage Fan coil energy savings; this would form part of the re-commissioning process. Remote monitoring and energy management will leverage another 10-15% across the board. This is because we remotely analysis and observe systems in operation, lock in setpoints and maintain the most effective solutions to specific and identifiable. However, in order to achieve this integration of the lighting systems would be required. 1. In order to maximise on energy savings we can offer the following services. 2. Installation of an ADSL modem allowing full remote access from anywhere in the world. Installation of a suitable network to collect data from the sub- metering. 3. Download the core code in each controller and examine for potential savings. 4. Continuous collection of additional data from the BMS and the sub metered systems for detailed analysis and identification of downstream energy usage. 5. Lockdown and maintain carbon footprint through continuous monitoring and alarming of setpoints and onsite activity. 6. Your access to any system based around the Trend products can be achieved via the existing head end , further sites can be added using the existing 1 software and this will allow you to use a single interface to any site in your portfolio. Incoming Voltage Regulation Incoming voltage regulation should be considered as an additional and separate project. 1 The existing PC in the FM offices Page 4 of 8 18/01/11
  • 5.
    Surrey County Council– Quadrant Court Proposals Costs Generally the controllers are in excellent condition requiring no modifications to the hardware. Re-Commissioning Existing Controls Costs Re-commissioning of the existing controls; nominally 3 weeks work, implementing, best achievable performance installation of remote monitoring hardware etc Initial survey to establish detailed scope £XXX (1 day) Will be deducted from an order to complete the works. Re-commissioning of main plant £XXXX (3 weeks) Pressurisation units, pumps, boilers, chillers, fan coil units. Provide report regarding any new information revealed by this activity. Remote plant monitoring 24/7/365 £XXXX (per year) This work is monitoring only, on the existing equipment and therefore the Lock down service can not apply. Some degree of energy monitoring is achievable with changes being implemented by attending site as and when agreed. Page 5 of 8 18/01/11
  • 6.
    Surrey County Council– Quadrant Court Notes Intentionally left blank. Page 6 of 8 18/01/11
  • 7.
    Surrey County Council– Quadrant Court Energy Report Existing Systems The primary existing systems are: - Lighting Controls, LTHW (Low Temperature Hot Water), Chiller (CHW), Fan Coil Units (FCU). Lighting Controls The lighting system consists of a Philips Lightmaster intelligent lighting system, consisting of a PC interface, network architecture, power architecture, lighting modules, PIRs, local lighting level sensors and exterior lighting sensors. This provides the foundation for a very powerful tool for energy savings. The Building Controls Network The BMS (Building Management System) is a current generation Trend IQ3 system consisting of a PC interface, network architecture, 4 off IQ3 controllers and IO modules (input output modules), sensors, actuators, switches and inverters as required to operate each piece of equipment. This provides the second very powerful tool with which to implement energy changes. LTHW (Low Temperature Hot Water) The heating system consists of 4 off boilers (220Kw each), primary (5.5Kw) and secondary pumps (15 Kw, VT circuit) and subsidiary circuits. We did not observe a CT circuit system. Chiller (CHW) Consisting of 2 off chillers, 2 CHW pumps (22 Kw approx) and subsidiary circuits. Fan Coil Units (FCU) The FCU and perimeter heaters operate similarly in that each unit is fitted with heating and cooling valves a dedicated controller and are networked together to facilitate the formation of groups controlled be a single setpoint and amalgamated sensor values. Observations on the Day This building, originally handed over in 2006 is, as one might expect in excellent condition. The controls for both lighting and M&E services are of a modern and well thought out design, balanced against capital expenditure. Page 7 of 8 18/01/11
  • 8.
    Surrey County Council– Quadrant Court Lighting There are some aspects that should be investigated in order to maximise energy savings and these are: - Integration of the lighting PIRs to the BMS, this would allow the HVAC systems to be shut down when the rooms are not used. Integration Inverters already connected to the BMS can be used to collect energy information about the activities of pumps and motors. Particularly as these are already being modulated to meet some need. Human Factors The lighting PIRs should be fitted with range limiting shields, available from Philips. This will prevent the activation of the lighting modules from activities in the corridors. Airside System Air supply plant in some areas in looking somewhat untidy, but generally remains in excellent condition since 2006. Access to some of these areas is restrictive and as such additional H&S aspects must be considered. Chiller As the building is only 3 years old the chillers have a long life expectancy before we can consider any investment in hardware, however there is room for improvement in the supply of CHW at unnecessarily low temperatures with respect to ambient conditions. LTHW As the building is only 3 years old the boilers and pumps have a long life expectancy before we can consider any investment in hardware, however there is room for improvement in the supply of LTHW at unnecessarily high temperatures with respect to ambient conditions. Demand Control (boilers and chillers) Some opportunities exist for addressing the issues of demand by using the local sensors on FCU and perimeter heating, loop temperature sensors and return air in order to optimise the demands placed on the M&E services. Submetering The sub-metering mounted on the main incoming switch is not used to collect information; this worthwhile investment will assist in the identification of high energy use areas around the building Incoming Voltage Regulation The relatively new technique of incoming voltage regulation offers further savings. The device regulates down stream voltage to optimise power consumption. In general the claims of 20% are generous whilst a realistic saving of 10% - 15% is easily achievable. Page 8 of 8 18/01/11