This project plan summarizes the supply, installation, certification, testing and commissioning of a flight simulator for an aviation training program. It outlines activities such as procurement, installation at three sites, testing and certification over 117 days. Key activities include market research, developing training and maintenance plans, procuring hardware and software, installation taking 45 days per site, testing for 15 days, certification for 30 days and commissioning for 10 days. It estimates manpower needs of 1608 man-days from teams of technicians, managers and regulators to complete the scope of work.