 Strongform specializes in industrial structural concrete
construction; rebar placement, steel buildings, & structural steel
erection and civil work. Services to industries include alternative
energy, agriculture, mining, cement, fertilizer, food and beverage,
power, and other industrial projects. Strongform achieves
excellent workmanship on aggressive schedules and maintains an
excellent safety standard. From expansions to greenfield projects
we can be of service to you and, as we are a nationwide
contractor, our services are available to you wherever your
business may take you.
ABOUT US
CORPORATE PROFILE
•Strongform is a general contractor that specializes in industrial structural concrete construction; rebar placement, steel
buildings and structural steel erection.
•Strongform is a licensed nationwide contractor.
•Strongform has extensive Bio-refining foundation, structural steel, equipment installation experience.
•Strongform has vast experience in import/export terminal construction.
MAJOR INDUSTRIES SERVED
•Alternative Energy
Ethanol
Biodiesel
Methane Digesters
•Agriculture – Feed and Process
•Agriculture – Bulk Storage
•Mining – Metal and Non-metal
•Cement – Storage and Process
•Fertilizer – Storage and Process
•Food and Beverage
•Power Industry
TYPES OF CONSTRUCTION
•Civil
•Footings
•Walls
Gang Form
Jump Form
Hand Set
•Flatwork and Floors
•Concrete Paving
•Concrete Tanks and Silos
•Structural Concrete Beams and Columns
•Structural Steel and Equipment Installation
CAST-IN-PLACE
CIRCULAR
CONCRETE TANKS
Pouring and Finishing Tank Base Slab
Finished Tank Base Slab ready for Wall forms
Assembly of Steel Gang Forms – Assembly of Walk-way is
done on the ground and lifted into place attached to a
section of forms
Workers will work from a safe location and platform mobile
man-lifts are used as needed.
Section of Gang Form and Walk-way being hoisted into place with Crane.
Note: All workers are tied-off 100% and the use of Load Tag lines is Company
Policy
Competed Gang Form Wall section
Installing Wall Reinforcing bar – Note: Rebar is tied in mats on the
ground with the correct splicing and then hoisted into place with
crane.
Extra Reinforcing being set in the splice sections. Note:
Workers are 100% tied-off at all times. Spotters and Safety
personal watching at all times.
Closing Up outside wall form of wall section. Note
Workers using man-lifts and spotters guiding form
section into place.
Pouring Concrete in Wall section. Note: Workers work from walk-
ways on the inside of the wall section.
Finished Tank Wall section
Gang Form wall section on inside of tank after finishing
pouring. Note: Squares on the concrete are from the pour
doors in the form panels with allows concrete to be poured
into the forms per the ACI specifications.
Finished Tank Inside
Finished Tank Outside
Tank finished filled and tested ready for production
3+ Million Gallon Square Tank – WTP
Crew Size – 8
Duration – 2 Months to Finish
3+ Million Gallon Square Tank – WTP
Crew Size – 8
Duration – 2 Months to Finish
MBR Tank – Alabama
Crew Size 5
Duration – 6 Weeks
Grain Receiving Tunnel Base - Poet
Pouring Receiving Tunnel Base - Poet
Receiving Pit – 12’ Deep
Tunnels and Silo Foundations – Mobile Alabama Export Facility.
12’x 12’ Tunnels and 12’ Stem Walls.
UWGP office floor – Note: In-slab heating
Layout lines for Saw cutting control joints
Base Slab pour and finish
Elevated Slab Pour and Finish – Hand Finish and Power Trowels used
FERTILIZER AND BULK
MATERIALS STORAGE
Complete and Cleaned up and Ready for Dome America to build wood dome
Interior walls – rebar and installed Interior walls – Complete ready for
columns
Port of Mobile - Alabama
Port of Mobile – Alabama
Interior wood divider walls going up and forming and pouring Interior
columns going on at the same time.
Port of Alabama – Setting interior columns
Port of Mobile – Alabama
Exterior Columns formed
Port of Mobile – Alabama
Exterior Columns Poured and
finished
Port of Mobile – Alabama
Building Framework going Up
Contact:
Duane Thomes –
(209) 480-0301 – Cell
P: 218.462.2607
F: 218.462.2508
208 Baker St. N. / P.O. Box 315/
Deer Creek, MN 56527
dthomes@strongform.net

PRESENTATION 10-Reduced

  • 2.
     Strongform specializesin industrial structural concrete construction; rebar placement, steel buildings, & structural steel erection and civil work. Services to industries include alternative energy, agriculture, mining, cement, fertilizer, food and beverage, power, and other industrial projects. Strongform achieves excellent workmanship on aggressive schedules and maintains an excellent safety standard. From expansions to greenfield projects we can be of service to you and, as we are a nationwide contractor, our services are available to you wherever your business may take you.
  • 3.
    ABOUT US CORPORATE PROFILE •Strongformis a general contractor that specializes in industrial structural concrete construction; rebar placement, steel buildings and structural steel erection. •Strongform is a licensed nationwide contractor. •Strongform has extensive Bio-refining foundation, structural steel, equipment installation experience. •Strongform has vast experience in import/export terminal construction. MAJOR INDUSTRIES SERVED •Alternative Energy Ethanol Biodiesel Methane Digesters •Agriculture – Feed and Process •Agriculture – Bulk Storage •Mining – Metal and Non-metal •Cement – Storage and Process •Fertilizer – Storage and Process •Food and Beverage •Power Industry TYPES OF CONSTRUCTION •Civil •Footings •Walls Gang Form Jump Form Hand Set •Flatwork and Floors •Concrete Paving •Concrete Tanks and Silos •Structural Concrete Beams and Columns •Structural Steel and Equipment Installation
  • 4.
  • 6.
    Pouring and FinishingTank Base Slab
  • 7.
    Finished Tank BaseSlab ready for Wall forms
  • 8.
    Assembly of SteelGang Forms – Assembly of Walk-way is done on the ground and lifted into place attached to a section of forms Workers will work from a safe location and platform mobile man-lifts are used as needed.
  • 9.
    Section of GangForm and Walk-way being hoisted into place with Crane. Note: All workers are tied-off 100% and the use of Load Tag lines is Company Policy
  • 10.
    Competed Gang FormWall section
  • 11.
    Installing Wall Reinforcingbar – Note: Rebar is tied in mats on the ground with the correct splicing and then hoisted into place with crane.
  • 12.
    Extra Reinforcing beingset in the splice sections. Note: Workers are 100% tied-off at all times. Spotters and Safety personal watching at all times.
  • 13.
    Closing Up outsidewall form of wall section. Note Workers using man-lifts and spotters guiding form section into place.
  • 14.
    Pouring Concrete inWall section. Note: Workers work from walk- ways on the inside of the wall section.
  • 15.
  • 16.
    Gang Form wallsection on inside of tank after finishing pouring. Note: Squares on the concrete are from the pour doors in the form panels with allows concrete to be poured into the forms per the ACI specifications.
  • 17.
  • 18.
  • 19.
    Tank finished filledand tested ready for production
  • 27.
    3+ Million GallonSquare Tank – WTP Crew Size – 8 Duration – 2 Months to Finish
  • 28.
    3+ Million GallonSquare Tank – WTP Crew Size – 8 Duration – 2 Months to Finish
  • 29.
    MBR Tank –Alabama Crew Size 5 Duration – 6 Weeks
  • 36.
  • 37.
  • 38.
  • 39.
    Tunnels and SiloFoundations – Mobile Alabama Export Facility. 12’x 12’ Tunnels and 12’ Stem Walls.
  • 42.
    UWGP office floor– Note: In-slab heating
  • 44.
    Layout lines forSaw cutting control joints
  • 45.
    Base Slab pourand finish
  • 47.
    Elevated Slab Pourand Finish – Hand Finish and Power Trowels used
  • 54.
  • 57.
    Complete and Cleanedup and Ready for Dome America to build wood dome
  • 58.
    Interior walls –rebar and installed Interior walls – Complete ready for columns Port of Mobile - Alabama
  • 59.
    Port of Mobile– Alabama Interior wood divider walls going up and forming and pouring Interior columns going on at the same time.
  • 60.
    Port of Alabama– Setting interior columns
  • 61.
    Port of Mobile– Alabama Exterior Columns formed Port of Mobile – Alabama Exterior Columns Poured and finished
  • 62.
    Port of Mobile– Alabama Building Framework going Up
  • 70.
    Contact: Duane Thomes – (209)480-0301 – Cell P: 218.462.2607 F: 218.462.2508 208 Baker St. N. / P.O. Box 315/ Deer Creek, MN 56527 dthomes@strongform.net