The document summarizes the key components and technical details of the Kota Super Thermal Power Station located in Kota, India. It has a total installed capacity of 1240 MW distributed across 7 units with capacities ranging from 110 MW to 210 MW. The main parts of the power station include the coal handling plant, boiler, superheater, steam turbine, economizer, generator, water treatment plant, ash handling plant, and control room. The coal handling plant handles the intake, crushing and conveying of coal to the furnace. The boiler converts the chemical energy of combustion into thermal energy to produce steam. The steam then powers the steam turbine which drives the electrical generator.
Summer Training Presentation Kota Super Thermal Power StationFellowBuddy.com
FellowBuddy.com is an innovative platform that brings students together to share notes, exam papers, study guides, project reports and presentation for upcoming exams.
We connect Students who have an understanding of course material with Students who need help.
Benefits:-
# Students can catch up on notes they missed because of an absence.
# Underachievers can find peer developed notes that break down lecture and study material in a way that they can understand
# Students can earn better grades, save time and study effectively
Our Vision & Mission – Simplifying Students Life
Our Belief – “The great breakthrough in your life comes when you realize it, that you can learn anything you need to learn; to accomplish any goal that you have set for yourself. This means there are no limits on what you can be, have or do.”
Like Us - https://www.facebook.com/FellowBuddycom
Summer Training Presentation Kota Super Thermal Power StationFellowBuddy.com
FellowBuddy.com is an innovative platform that brings students together to share notes, exam papers, study guides, project reports and presentation for upcoming exams.
We connect Students who have an understanding of course material with Students who need help.
Benefits:-
# Students can catch up on notes they missed because of an absence.
# Underachievers can find peer developed notes that break down lecture and study material in a way that they can understand
# Students can earn better grades, save time and study effectively
Our Vision & Mission – Simplifying Students Life
Our Belief – “The great breakthrough in your life comes when you realize it, that you can learn anything you need to learn; to accomplish any goal that you have set for yourself. This means there are no limits on what you can be, have or do.”
Like Us - https://www.facebook.com/FellowBuddycom
Presentation on Kota super thermal power station (KSTPS)Anurag Jindal
This is a presentation based on my experience of 2 months summer training at KSTPS.It broadly covers all the major aspects of KSTPS.As i am an electrical engineer so i have made it more relatable to electrical engineering students.
Presentation on Kota super thermal power station (KSTPS)Anurag Jindal
This is a presentation based on my experience of 2 months summer training at KSTPS.It broadly covers all the major aspects of KSTPS.As i am an electrical engineer so i have made it more relatable to electrical engineering students.
this ppt include an introduction about various part of super thermal power station. i.e in a plant various task are performed in different stages so it is a normal introduction about them.
A thermal power station is a power station in which heat energy is converted to electric power. In most of the places in the world the turbine is steam-driven. Water is heated, turns into steam and spins a steam turbine which drives an electrical generator.
3. It was established in 1983.
It is located at the left bank of the CHAMBAL River at the
upstream of KOTA BAIRAJ.
1st & 2nd units are of 110 MW each.
3rd ,4th &5th units are of 210 MW .
6th & 7 unit of 195 MW.
Total generation capacity
(110+110+210+210+210+195+195) =1240 MW
Favorable condition
Abundant quantity of clean cooling water.
Good transport facility
Concentration of load in Kota region due to large
number of industries.
INTRODUCTION OF THE THERMAL
POWER PLANT
5. Main Parts of Kota Super Thermal
Power Station (Content)
• Principle
• Layout
• Coal handling plant
• Boiler
• Super heater
• Steam Turbine
• Economizer
• Generator
• Water Treatment Plant
• Ash handling plant
• Control Room
8. Coal Handling Plant
• Wagon unloading system
• Crushing system
• Conveying system
Coal handling plant section
9. Wagon unloading system
Unload the coal from
wagon to hopper with
the help of wagon
Tripler.
Hopper allows to pass
coal pieces ≤ 200mm
From hopper coal fall
on vibrator which is
supported by roller.
10. Conveying system
Belt are used to convey coal
from coal handling plant to
furnace.
Specification:-
Belt width : 1400mm
Speed : 2.2m/sec
Total install power : 360kw
Capacity : 1350/750 ton/hr
No. of conveyor: 38
11. Crushing system
CRUSHER HOUSE:- It
consists of crushers which
are used to crush the coal
to 20 mm size.
Two types
Primary crusher
o Rail crusher
o Rotary breaker
Secondary crusher
12. Boiler
It is a closed vessel in which water under pressure is
converted into steam.
Hot water or steam used to transfer heat to a process.
A boiler is always designed to absorb maximum
amount of heat released in process of combustion.
Furnace:- It is primary part of boiler where the fuel is
burnt to liberate the heat energy.
Chemical
Energy of
fuel
Thermal
Energy by
combustion
14. Super heater
Super heater consists group of tubes.
The tubes are heated by the heat of combustion
gases during their passage from furnace to
chimney, so the temperature increased.
Super heater remove the moisture from the steam
leaving from the boiler tubes.
15. Steam Turbine
It is a machine in which a
shaft is rotated steadily
by reaction of steam, air
upon blades of a wheel.
When Steam is used
then it is called steam
turbine.
It works on Modified
Rankine cycle.
Kinetic
Energy
Mechanical
Energy
16. Economizer
Economizer is a device which recover
the heat from the flue gases on their
way to chimney.
It increases the 10-12% efficiency of the
plant.
17. •An electrical generator is a
machine which converts
mechanical energy into electrical
energy through electro
mechanical energy conversion .
•The generator is driven by
directly coupled steam turbine at
a speed of 3000 r.p.m.
Electrical
Energy
Mechanical
Energy
GENERATOR
18. Water Treatment Plant
Pressure filter removes
undisclosed impurities from
raw water.
Carbon filter removes excess
chlorine from clarified
water.
D.M. plant removes dissolved
impurities from clarified
water.
Conductivity ,pH & silica
content of this water must be
checked time to time.
D.M. water must be in the
ratio of 1:8
19. Ash Handling Plant
In thermal plants 25%
is furnace bottom ash
and 75% is pulverized
fuel ash.
Electrostatic
Precipitator is used in
ash handling plant to
remove fly ash.
20. water
wet ash
To coal mill
To furnace
PA Fan
FD Fan
A
P
H
ESP
ID Fan
Boiler
ASH HANDLING
Dry Ash
Fly Ash