Scope of Works:
• Comprehensive planned preventive maintenance (PPM) 3-years contract of
the 3-compartment 16-men hyperbaric & recompression chamber system
• Includes the planned preventive maintenance of the ETC Baramed XD
monoplace hyperbaric chamber system
• Condition survey: visual inspection, non-destructive test & hydrostatic test
• Viewports & gaskets replacement & leak testing
• Doors re-alignment & seal replacement
• Air compressor system maintenance, including air dryer, air banks & CO2
scrubber
• Gauges & analyzers calibration
• BIBS replacements
• Replacements of hyperbaric safe patients’ seat
• Supply of new hyperbaric automated chamber control system
• Communication system repair & testing
• Environmental Control Unit (ECU) refurbishment
•Documentation: Refurbishment Report (MDR) & Operator’s Manual
• Training: Hyperbaric System Assurance Training, Diving & Hyperbaric
Medicine Refresher & Operator’s Training
For more information, kindly contact:
HEALING CHAMBERS OF ASIA SDN BHD
(Co. Reg. No.: 642186-T)
No. 3, Persiaran Titiwangsa 3,
Taman Tasik Titiwangsa, Setapak
53200 Kuala Lumpur, MALAYSIA.
Tel: +603.4023.3333 Fax: +603.4023.3030
Web: www.healingchambers.com.my
INSTITUTE OF UNDERWATER & HYPERBARIC MEDICINE -
HYPERBARIC & RECOMPRESSION CHAMBER SYSTEM
COMPREHENSIVE PLANNED PREVENTIVE MAINTENANCE
CONTRACT
Job ID: #0120 - Malaysia Ministry of Defense, Jan. 2010 - Dec. 2013

More Related Content

Similar to Portfolio 5 - IPBAH small

SNGPL Industrial Training Report Presentation
SNGPL Industrial Training Report PresentationSNGPL Industrial Training Report Presentation
SNGPL Industrial Training Report PresentationShams Ul Islam
 
BUILDING ENERGY MANAGEMENT SERVICES IN HOSPITALS
BUILDING ENERGY MANAGEMENT SERVICES IN HOSPITALSBUILDING ENERGY MANAGEMENT SERVICES IN HOSPITALS
BUILDING ENERGY MANAGEMENT SERVICES IN HOSPITALSLakshmi Ravi Chandu Kolusu
 
Retrocommissioning of Existing Buildings
Retrocommissioning of Existing BuildingsRetrocommissioning of Existing Buildings
Retrocommissioning of Existing BuildingsWIGreenBuilding
 
Validation utility system
Validation utility systemValidation utility system
Validation utility systemArpitSuralkar
 
production operator
production operatorproduction operator
production operatorGURU JOY
 
One slider for qualification and validation of depyrogenation and sterilizati...
One slider for qualification and validation of depyrogenation and sterilizati...One slider for qualification and validation of depyrogenation and sterilizati...
One slider for qualification and validation of depyrogenation and sterilizati...Palash Das
 
Overview of Water cycles, wastewater treatment processes, wastewater plant en...
Overview of Water cycles, wastewater treatment processes, wastewater plant en...Overview of Water cycles, wastewater treatment processes, wastewater plant en...
Overview of Water cycles, wastewater treatment processes, wastewater plant en...AEP Ohio
 
Session_5_PSA-_USAID_RISE (1) training guide.pptx
Session_5_PSA-_USAID_RISE (1) training guide.pptxSession_5_PSA-_USAID_RISE (1) training guide.pptx
Session_5_PSA-_USAID_RISE (1) training guide.pptxMpumeleloNcube4
 
effective maintenance hvac
effective maintenance hvaceffective maintenance hvac
effective maintenance hvacAzie Syarina
 
resume-4-1.docx (1)
resume-4-1.docx (1)resume-4-1.docx (1)
resume-4-1.docx (1)Thomas Lally
 
boilers maintenance .pdf
boilers maintenance .pdfboilers maintenance .pdf
boilers maintenance .pdfssuser9a3adc
 
PTP 3111 - Hospital Air Distribution Systems (PDF).pdf
PTP 3111 - Hospital Air Distribution Systems (PDF).pdfPTP 3111 - Hospital Air Distribution Systems (PDF).pdf
PTP 3111 - Hospital Air Distribution Systems (PDF).pdfJorgeMarroquin31
 
Validation of HVAC pharma geeta TUBE (Utility Systems)
Validation of HVAC pharma geeta TUBE (Utility Systems)Validation of HVAC pharma geeta TUBE (Utility Systems)
Validation of HVAC pharma geeta TUBE (Utility Systems)Saikat Bagchi
 
Trial 2 overview of oil handling operations mc cord pipeline
Trial 2 overview of oil handling operations mc cord pipelineTrial 2 overview of oil handling operations mc cord pipeline
Trial 2 overview of oil handling operations mc cord pipelineJoel Ballou
 
Portfolio 2 - KD Sri Indera Sakti small
Portfolio 2 - KD Sri Indera Sakti smallPortfolio 2 - KD Sri Indera Sakti small
Portfolio 2 - KD Sri Indera Sakti smallMohd Amirullah Hamzah
 

Similar to Portfolio 5 - IPBAH small (20)

SNGPL Industrial Training Report Presentation
SNGPL Industrial Training Report PresentationSNGPL Industrial Training Report Presentation
SNGPL Industrial Training Report Presentation
 
BUILDING ENERGY MANAGEMENT SERVICES IN HOSPITALS
BUILDING ENERGY MANAGEMENT SERVICES IN HOSPITALSBUILDING ENERGY MANAGEMENT SERVICES IN HOSPITALS
BUILDING ENERGY MANAGEMENT SERVICES IN HOSPITALS
 
Retrocommissioning of Existing Buildings
Retrocommissioning of Existing BuildingsRetrocommissioning of Existing Buildings
Retrocommissioning of Existing Buildings
 
Pipe system
Pipe systemPipe system
Pipe system
 
Validation utility system
Validation utility systemValidation utility system
Validation utility system
 
production operator
production operatorproduction operator
production operator
 
Final report
Final reportFinal report
Final report
 
Pri Bio Product Brochure
Pri Bio Product BrochurePri Bio Product Brochure
Pri Bio Product Brochure
 
One slider for qualification and validation of depyrogenation and sterilizati...
One slider for qualification and validation of depyrogenation and sterilizati...One slider for qualification and validation of depyrogenation and sterilizati...
One slider for qualification and validation of depyrogenation and sterilizati...
 
Hvac part 3
Hvac part 3Hvac part 3
Hvac part 3
 
Overview of Water cycles, wastewater treatment processes, wastewater plant en...
Overview of Water cycles, wastewater treatment processes, wastewater plant en...Overview of Water cycles, wastewater treatment processes, wastewater plant en...
Overview of Water cycles, wastewater treatment processes, wastewater plant en...
 
Session_5_PSA-_USAID_RISE (1) training guide.pptx
Session_5_PSA-_USAID_RISE (1) training guide.pptxSession_5_PSA-_USAID_RISE (1) training guide.pptx
Session_5_PSA-_USAID_RISE (1) training guide.pptx
 
effective maintenance hvac
effective maintenance hvaceffective maintenance hvac
effective maintenance hvac
 
resume-4-1.docx (1)
resume-4-1.docx (1)resume-4-1.docx (1)
resume-4-1.docx (1)
 
boilers maintenance .pdf
boilers maintenance .pdfboilers maintenance .pdf
boilers maintenance .pdf
 
validation.pdf
validation.pdfvalidation.pdf
validation.pdf
 
PTP 3111 - Hospital Air Distribution Systems (PDF).pdf
PTP 3111 - Hospital Air Distribution Systems (PDF).pdfPTP 3111 - Hospital Air Distribution Systems (PDF).pdf
PTP 3111 - Hospital Air Distribution Systems (PDF).pdf
 
Validation of HVAC pharma geeta TUBE (Utility Systems)
Validation of HVAC pharma geeta TUBE (Utility Systems)Validation of HVAC pharma geeta TUBE (Utility Systems)
Validation of HVAC pharma geeta TUBE (Utility Systems)
 
Trial 2 overview of oil handling operations mc cord pipeline
Trial 2 overview of oil handling operations mc cord pipelineTrial 2 overview of oil handling operations mc cord pipeline
Trial 2 overview of oil handling operations mc cord pipeline
 
Portfolio 2 - KD Sri Indera Sakti small
Portfolio 2 - KD Sri Indera Sakti smallPortfolio 2 - KD Sri Indera Sakti small
Portfolio 2 - KD Sri Indera Sakti small
 

Portfolio 5 - IPBAH small

  • 1. Scope of Works: • Comprehensive planned preventive maintenance (PPM) 3-years contract of the 3-compartment 16-men hyperbaric & recompression chamber system • Includes the planned preventive maintenance of the ETC Baramed XD monoplace hyperbaric chamber system • Condition survey: visual inspection, non-destructive test & hydrostatic test • Viewports & gaskets replacement & leak testing • Doors re-alignment & seal replacement • Air compressor system maintenance, including air dryer, air banks & CO2 scrubber • Gauges & analyzers calibration • BIBS replacements • Replacements of hyperbaric safe patients’ seat • Supply of new hyperbaric automated chamber control system • Communication system repair & testing • Environmental Control Unit (ECU) refurbishment •Documentation: Refurbishment Report (MDR) & Operator’s Manual • Training: Hyperbaric System Assurance Training, Diving & Hyperbaric Medicine Refresher & Operator’s Training For more information, kindly contact: HEALING CHAMBERS OF ASIA SDN BHD (Co. Reg. No.: 642186-T) No. 3, Persiaran Titiwangsa 3, Taman Tasik Titiwangsa, Setapak 53200 Kuala Lumpur, MALAYSIA. Tel: +603.4023.3333 Fax: +603.4023.3030 Web: www.healingchambers.com.my INSTITUTE OF UNDERWATER & HYPERBARIC MEDICINE - HYPERBARIC & RECOMPRESSION CHAMBER SYSTEM COMPREHENSIVE PLANNED PREVENTIVE MAINTENANCE CONTRACT Job ID: #0120 - Malaysia Ministry of Defense, Jan. 2010 - Dec. 2013