The Pluto LNG project in Western Australia has experienced significant delays and cost overruns. The project was initially expected to cost £8 billion and start production in 2012, but costs have risen to almost £10 billion and the start date is now 15 months delayed. Reasons for the delays include bad weather, mechanical faults during installation, design flaws, and onshore commissioning errors. The project aims to provide a reliable energy source for Asia-Pacific customers and boost the Western Australian economy by £19 billion over 25 years of operation.