1. The document provides installation instructions for Orion retention sockets used for installing illuminated sign poles and lighting columns. It describes excavating a hole and pouring concrete to fully surround the socket below ground level. 2. Ducts are connected to the socket and cables are run through before the surface is leveled. The socket is checked for verticality and the concrete is allowed to harden. 3. To install a pole, the dirt cover is removed and bolts are loosened from the clamp ring. The ring and o-ring are placed over the pole which is inserted vertically into the socket. Bolts are tightened to secure the pole in place.