DEMO PROJECT
                                                                                   OFFICE CONSTRUCTION PROJECT DETAILS ‐ 1

Project Start: January 10, 2011                              % Complete Type:       Physical
Data Date:    January 10, 2011                               Calendar:              Standard 5 Day Workweek

                                                                                    Duration
Activity ID                   Activity Name                     Activity Type                Predecessors + Relationship
                                                                                     (days )
   A1000      Project Start                                    Start Milestone           0
   A1010      Determination of the need of facility            Task Dependent           14                A1000
   A1020      Cost / Benefit Analysis                          Task Dependent           21                A1010
   A1030      Envoirment Inpact Analysis                       Task Dependent           14                A1020
   A1040      Feasibility Report Prepation                     Task Dependent           21                A1030
   A1050      Analysis of feasibility Report                   Task Dependent            7                A1040
   A1060      Yes / No Decision                                Finish Milestone          0                A1050
   A1070      Architecture Layout                              Task Dependent           14                A1060
   A1080      Structural Layout                                Task Dependent           14             A1070 SS+7
   A1090      Architecture Design                              Task Dependent           21                A1070
   A1100      Structural Design                                Task Dependent           21                A1080
   A1110      MEP Design                                       Task Dependent           21            A1090, A1100
   A1120      Interial Design                                  Task Dependent           21         A1090 FS+7, A1100
                                                                                               A1080, A1090, A1100, A1110, 
   A1130      Submission of Drawings                            Task Dependent           7
                                                                                                          A1120
   A1140      Pre‐Qualification of Contractors                  Task Dependent          14                A1130
   A1150      Selection of Pre‐Qualified Contractors            Task Dependent           7                A1140
   A1160      Tender Floating                                   Task Dependent          14                A1150
   A1170      Tender Negotiation                                Task Dependent          14                A1160
   A1180      Award of Contract                                 Start Milestone          0                A1170
   A1190      Construction Supervision                           Level of Effort        347             A1180 SS
   A1200      Mobilization                                      Task Dependent          14                A1180
   A1210      Site Clearance                                    Task Dependent           7                A1200
   A1220      Site Layout and Preparation                       Task Dependent           7                A1210
   A1230      Bulk Excavation                                   Task Dependent          14                A1220
   A1240      Structural Excavation                             Task Dependent          14                A1230
   A1250      Foundation                                        Task Dependent          14                A1240
   A1260      Columns ‐ GF                                      Task Dependent           7       A1250 SS+7, A1250 FF+3
   A1270      Beams / Slabs ‐ GF                                Task Dependent          21                A1260
   A1280      Block Masonry                                     Task Dependent          21             A1270 FS+15
   A1290      Plumbering and Electrical Rough ‐ in ‐ GF         Task Dependent          14       A1270 SS+3, A1270 FF‐3
   A1300      Plaster ‐ GF                                      Task Dependent          28       A1280 FS+7, A1310 FF+7
   A1310      Doors / Windows ‐ GF                              Task Dependent          21             A1280 FS+7
   A1320      Floor Finishing ‐ GF                              Task Dependent          35      A1300, A1310, A1330 FF+7
   A1330      Plumbering Fixtures ‐ GF                          Task Dependent          21        A1290, A1300, A1310
   A1340      Electrical Finishes ‐ GF                          Task Dependent          21       A1330 SS+7, A1330 FF+7
                                                                                               A1300, A1310, A1320, A1330, 
   A1350      Painting ‐ GF                                     Task Dependent          28
                                                                                                          A1340
   A1360      Columns ‐ FF                                      Task Dependent          14             A1270 FS+7
   A1370      Beams / Slabs ‐ FF                                Task Dependent          28                A1360
   A1380      Block Masonry ‐ FF                                Task Dependent          28             A1370 FS+15
   A1390      Plumbering & Electrical Rough ‐ in‐ FF            Task Dependent          21       A1370 SS+3, A1370 FF‐3
   A1400      Plaster ‐ FF                                      Task Dependent          35       A1380 FS+7, A1410 FF+7
   A1410      Doors / Windows ‐ FF                              Task Dependent          28             A1380 FS+7
   A1420      Floor Finishing ‐ FF                              Task Dependent          42      A1400, A1410, A1430 FF+7
   A1430      Plumbering Fixture ‐ FF                           Task Dependent          28        A1390, A1400, A1410
   A1440      Electrical Finishes ‐ FF                          Task Dependent          28       A1430 SS+7, A1430 FF+7
                                                                                               A1350, A1400, A1410, A1420, 
   A1450      Painting ‐ FF                                     Task Dependent          35
                                                                                                      A1430, A1440
   A1460      Underground Water Tank                           Task Dependent           14         A1350, A1260 SS+4
   A1470      External Plaster                                 Task Dependent           21                A1400
   A1480      External Paint                                   Task Dependent           28            A1450, A1470
   A1490      Punch List                                       Task Dependent           14        A1350, A1450, A1480
   A1500      Project Handover                                 Finish Milestone          0          A1490, A1190 FF
                                                       www.NovelOPS.com
DEMO PROJECT
                                                                                     OFFICE CONSTRUCTION PROJECT DETAILS ‐ 2

Project Start: January 10, 2011                   % Complete Type: Physical
Data Date:    January 10, 2011                    Calendar:        Standard 5 Day Workweek


      DEFINE PROJECT LEVEL ACTIVITY CODES                      DEFINE WORK BREAKDOWN STRUCTURE (WBS)

                    CODE 1 : PHAS
   VALUES                        DESCRIPTION
    FEAS        Feasibility
    DESG        Design & Architecture
    PROC        Procurement
    CONS        Construction
    FNSH        Project Hand Over

                    CODE 2 : DEPT
   VALUES                        DESCRIPTION
    MNG         Management
    DESG        Design
    STRC        Contractor Structure Work
    MEP         Mech., Electrical, Plumbering 
    FNSH        Contractor Finishing Works

                    CODE 3 : FLRS
   VALUES                        DESCRIPTION
     PL         Preliminary Works
     GF         Ground Floor
     FF         First Floor
     EX         External Works




                                                 www.NovelOPS.com
DEMO PROJECT
                                                                            OFFICE CONSTRUCTION PROJECT DETAILS ‐ 3

Project Start DJanuary 10, 2011                            % Complete Type:     Physical
Data Date:    January 10, 2011                             Calendar:            Standard 5 Day Workweek

                                                                                        ACTIVITY  CODES
Activity ID                  Activity Name                     WBS Code
                                                                                   PHAS      DEPT       FLRS
   A1000      Project Start                                       OC               FEAS        MNG          PL
   A1010      Determination of the need of facility             OC.01              FEAS        MNG          PL
   A1020      Cost / Benefit Analysis                           OC.01              FEAS        MNG          PL
   A1030      Envoirment Inpact Analysis                        OC.01              FEAS        DESG         PL
   A1040      Feasibility Report Prepation                      OC.01              FEAS        DESG         PL
   A1050      Analysis of feasibility Report                    OC.01              FEAS        MNG          PL
   A1060      Yes / No Decision                                 OC.02              FEAS        MNG          PL
   A1070      Architecture Layout                               OC.02              DESG        DESG         PL
   A1080      Structural Layout                                 OC.02              DESG        DESG         PL
   A1090      Architecture Design                               OC.02              DESG        DESG         PL
   A1100      Structural Design                                 OC.02              DESG        DESG         PL
   A1110      MEP Design                                        OC.02              DESG        DESG         PL
   A1120      Interial Design                                   OC.02              DESG        DESG         PL
   A1130      Submission of Drawings                            OC.02              DESG        DESG         PL
   A1140      Pre‐Qualification of Contractors                  OC.03              PROC        MNG          PL
   A1150      Selection of Pre‐Qualified Contractors            OC.03              PROC        MNG          PL
   A1160      Tender Floating                                   OC.03              PROC        MNG          PL
   A1170      Tender Negotiation                                OC.03              PROC        MNG          PL
   A1180      Award of Contract                                 OC.03              CONS        MNG          PL
   A1190      Construction Supervision                          OC.04              FNSH        MNG          EX
   A1200      Mobilization                                     OC.04.01            CONS        STRC         PL
   A1210      Site Clearance                                   OC.04.01            CONS        STRC         PL
   A1220      Site Layout and Preparation                      OC.04.01            CONS        STRC         PL
   A1230      Bulk Excavation                                  OC.04.02            CONS        STRC         EX
   A1240      Structural Excavation                            OC.04.02            CONS        STRC         EX
   A1250      Foundation                                      OC.04.03.01          CONS        STRC         EX
   A1260      Columns ‐ GF                                    OC.04.03.02          CONS        STRC         GF
   A1270      Beams / Slabs ‐ GF                              OC.04.03.02          CONS        STRC         GF
   A1280      Block Masonry                                   OC.04.05.01          CONS        FNSH         GF
   A1290      Plumbering and Electrical Rough ‐ in ‐ GF       OC.04.04.01          CONS        MEP          GF
   A1300      Plaster ‐ GF                                    OC.04.05.01          CONS        FNSH         GF
   A1310      Doors / Windows ‐ GF                            OC.04.05.01          CONS        FNSH         GF
   A1320      Floor Finishing ‐ GF                            OC.04.05.01          CONS        FNSH         GF
   A1330      Plumbering Fixtures ‐ GF                        OC.04.05.01          CONS        MEP          GF
   A1340      Electrical Finishes ‐ GF                        OC.04.04.01          CONS        MEP          GF
   A1350      Painting ‐ GF                                   OC.04.05.01          CONS        FNSH         GF
   A1360      Columns ‐ FF                                    OC.04.03.03          CONS        STRC         FF
   A1370      Beams / Slabs ‐ FF                              OC.04.03.03          CONS        STRC         FF
   A1380      Block Masonry ‐ FF                              OC.04.05.02          CONS        FNSH         FF
   A1390      Plumbering & Electrical Rough ‐ in‐ FF          OC.04.04.02          CONS        MEP          FF
   A1400      Plaster ‐ FF                                    OC.04.05.02          CONS        FNSH         FF
   A1410      Doors / Windows ‐ FF                            OC.04.05.02          CONS        FNSH         FF
   A1420      Floor Finishing ‐ FF                            OC.04.05.02          CONS        FNSH         FF
   A1430      Plumbering Fixture ‐ FF                         OC.04.04.02          CONS        MEP          FF
   A1440      Electrical Finishes ‐ FF                        OC.04.04.02          CONS        MEP          FF
   A1450      Painting ‐ FF                                   OC.04.05.02          CONS        FNSH         FF
   A1460      Underground Water Tank                          OC.04.03.04          CONS        STRC         EX
   A1470      External Plaster                                OC.04.05.03          CONS        FNSH         EX
   A1480      External Paint                                  OC.04.05.03          CONS        FNSH         EX
   A1490      Punch List                                       OC.04.06            FNSH        MNG          EX
   A1500      Project Handover                                 OC.04.06            FNSH        MNG          EX

                                                   www.NovelOPS.com

Office Construction - Practice project

  • 1.
    DEMO PROJECT OFFICE CONSTRUCTION PROJECT DETAILS ‐ 1 Project Start: January 10, 2011 % Complete Type: Physical Data Date: January 10, 2011 Calendar: Standard 5 Day Workweek Duration Activity ID Activity Name Activity Type Predecessors + Relationship (days ) A1000 Project Start Start Milestone 0 A1010 Determination of the need of facility Task Dependent 14 A1000 A1020 Cost / Benefit Analysis Task Dependent 21 A1010 A1030 Envoirment Inpact Analysis Task Dependent 14 A1020 A1040 Feasibility Report Prepation Task Dependent 21 A1030 A1050 Analysis of feasibility Report Task Dependent 7 A1040 A1060 Yes / No Decision Finish Milestone 0 A1050 A1070 Architecture Layout Task Dependent 14 A1060 A1080 Structural Layout Task Dependent 14 A1070 SS+7 A1090 Architecture Design Task Dependent 21 A1070 A1100 Structural Design Task Dependent 21 A1080 A1110 MEP Design Task Dependent 21 A1090, A1100 A1120 Interial Design Task Dependent 21 A1090 FS+7, A1100 A1080, A1090, A1100, A1110,  A1130 Submission of Drawings Task Dependent 7 A1120 A1140 Pre‐Qualification of Contractors Task Dependent 14 A1130 A1150 Selection of Pre‐Qualified Contractors Task Dependent 7 A1140 A1160 Tender Floating Task Dependent 14 A1150 A1170 Tender Negotiation Task Dependent 14 A1160 A1180 Award of Contract Start Milestone 0 A1170 A1190 Construction Supervision Level of Effort 347 A1180 SS A1200 Mobilization Task Dependent 14 A1180 A1210 Site Clearance Task Dependent 7 A1200 A1220 Site Layout and Preparation Task Dependent 7 A1210 A1230 Bulk Excavation Task Dependent 14 A1220 A1240 Structural Excavation Task Dependent 14 A1230 A1250 Foundation Task Dependent 14 A1240 A1260 Columns ‐ GF Task Dependent 7 A1250 SS+7, A1250 FF+3 A1270 Beams / Slabs ‐ GF Task Dependent 21 A1260 A1280 Block Masonry Task Dependent 21 A1270 FS+15 A1290 Plumbering and Electrical Rough ‐ in ‐ GF Task Dependent 14 A1270 SS+3, A1270 FF‐3 A1300 Plaster ‐ GF Task Dependent 28 A1280 FS+7, A1310 FF+7 A1310 Doors / Windows ‐ GF Task Dependent 21 A1280 FS+7 A1320 Floor Finishing ‐ GF Task Dependent 35 A1300, A1310, A1330 FF+7 A1330 Plumbering Fixtures ‐ GF Task Dependent 21 A1290, A1300, A1310 A1340 Electrical Finishes ‐ GF Task Dependent 21 A1330 SS+7, A1330 FF+7 A1300, A1310, A1320, A1330,  A1350 Painting ‐ GF Task Dependent 28 A1340 A1360 Columns ‐ FF Task Dependent 14 A1270 FS+7 A1370 Beams / Slabs ‐ FF Task Dependent 28 A1360 A1380 Block Masonry ‐ FF Task Dependent 28 A1370 FS+15 A1390 Plumbering & Electrical Rough ‐ in‐ FF Task Dependent 21 A1370 SS+3, A1370 FF‐3 A1400 Plaster ‐ FF Task Dependent 35 A1380 FS+7, A1410 FF+7 A1410 Doors / Windows ‐ FF Task Dependent 28 A1380 FS+7 A1420 Floor Finishing ‐ FF Task Dependent 42 A1400, A1410, A1430 FF+7 A1430 Plumbering Fixture ‐ FF Task Dependent 28 A1390, A1400, A1410 A1440 Electrical Finishes ‐ FF Task Dependent 28 A1430 SS+7, A1430 FF+7 A1350, A1400, A1410, A1420,  A1450 Painting ‐ FF Task Dependent 35 A1430, A1440 A1460 Underground Water Tank Task Dependent 14 A1350, A1260 SS+4 A1470 External Plaster Task Dependent 21 A1400 A1480 External Paint Task Dependent 28 A1450, A1470 A1490 Punch List Task Dependent 14 A1350, A1450, A1480 A1500 Project Handover Finish Milestone 0 A1490, A1190 FF www.NovelOPS.com
  • 2.
    DEMO PROJECT OFFICE CONSTRUCTION PROJECT DETAILS ‐ 2 Project Start: January 10, 2011 % Complete Type: Physical Data Date: January 10, 2011 Calendar: Standard 5 Day Workweek DEFINE PROJECT LEVEL ACTIVITY CODES DEFINE WORK BREAKDOWN STRUCTURE (WBS) CODE 1 : PHAS VALUES DESCRIPTION FEAS Feasibility DESG Design & Architecture PROC Procurement CONS Construction FNSH Project Hand Over CODE 2 : DEPT VALUES DESCRIPTION MNG Management DESG Design STRC Contractor Structure Work MEP Mech., Electrical, Plumbering  FNSH Contractor Finishing Works CODE 3 : FLRS VALUES DESCRIPTION PL Preliminary Works GF Ground Floor FF First Floor EX External Works www.NovelOPS.com
  • 3.
    DEMO PROJECT OFFICE CONSTRUCTION PROJECT DETAILS ‐ 3 Project Start DJanuary 10, 2011 % Complete Type: Physical Data Date: January 10, 2011 Calendar: Standard 5 Day Workweek ACTIVITY  CODES Activity ID Activity Name WBS Code PHAS DEPT FLRS A1000 Project Start OC FEAS MNG PL A1010 Determination of the need of facility OC.01 FEAS MNG PL A1020 Cost / Benefit Analysis OC.01 FEAS MNG PL A1030 Envoirment Inpact Analysis OC.01 FEAS DESG PL A1040 Feasibility Report Prepation OC.01 FEAS DESG PL A1050 Analysis of feasibility Report OC.01 FEAS MNG PL A1060 Yes / No Decision OC.02 FEAS MNG PL A1070 Architecture Layout OC.02 DESG DESG PL A1080 Structural Layout OC.02 DESG DESG PL A1090 Architecture Design OC.02 DESG DESG PL A1100 Structural Design OC.02 DESG DESG PL A1110 MEP Design OC.02 DESG DESG PL A1120 Interial Design OC.02 DESG DESG PL A1130 Submission of Drawings OC.02 DESG DESG PL A1140 Pre‐Qualification of Contractors OC.03 PROC MNG PL A1150 Selection of Pre‐Qualified Contractors OC.03 PROC MNG PL A1160 Tender Floating OC.03 PROC MNG PL A1170 Tender Negotiation OC.03 PROC MNG PL A1180 Award of Contract OC.03 CONS MNG PL A1190 Construction Supervision OC.04 FNSH MNG EX A1200 Mobilization OC.04.01 CONS STRC PL A1210 Site Clearance OC.04.01 CONS STRC PL A1220 Site Layout and Preparation OC.04.01 CONS STRC PL A1230 Bulk Excavation OC.04.02 CONS STRC EX A1240 Structural Excavation OC.04.02 CONS STRC EX A1250 Foundation OC.04.03.01 CONS STRC EX A1260 Columns ‐ GF OC.04.03.02 CONS STRC GF A1270 Beams / Slabs ‐ GF OC.04.03.02 CONS STRC GF A1280 Block Masonry OC.04.05.01 CONS FNSH GF A1290 Plumbering and Electrical Rough ‐ in ‐ GF OC.04.04.01 CONS MEP GF A1300 Plaster ‐ GF OC.04.05.01 CONS FNSH GF A1310 Doors / Windows ‐ GF OC.04.05.01 CONS FNSH GF A1320 Floor Finishing ‐ GF OC.04.05.01 CONS FNSH GF A1330 Plumbering Fixtures ‐ GF OC.04.05.01 CONS MEP GF A1340 Electrical Finishes ‐ GF OC.04.04.01 CONS MEP GF A1350 Painting ‐ GF OC.04.05.01 CONS FNSH GF A1360 Columns ‐ FF OC.04.03.03 CONS STRC FF A1370 Beams / Slabs ‐ FF OC.04.03.03 CONS STRC FF A1380 Block Masonry ‐ FF OC.04.05.02 CONS FNSH FF A1390 Plumbering & Electrical Rough ‐ in‐ FF OC.04.04.02 CONS MEP FF A1400 Plaster ‐ FF OC.04.05.02 CONS FNSH FF A1410 Doors / Windows ‐ FF OC.04.05.02 CONS FNSH FF A1420 Floor Finishing ‐ FF OC.04.05.02 CONS FNSH FF A1430 Plumbering Fixture ‐ FF OC.04.04.02 CONS MEP FF A1440 Electrical Finishes ‐ FF OC.04.04.02 CONS MEP FF A1450 Painting ‐ FF OC.04.05.02 CONS FNSH FF A1460 Underground Water Tank OC.04.03.04 CONS STRC EX A1470 External Plaster OC.04.05.03 CONS FNSH EX A1480 External Paint OC.04.05.03 CONS FNSH EX A1490 Punch List OC.04.06 FNSH MNG EX A1500 Project Handover OC.04.06 FNSH MNG EX www.NovelOPS.com