Carson City Center
Citizen’s Advisory Committee




         Copyright P3 Development Inc 2010
Overview of P3’s Tasks Under the DCA


  Desired Elements
  Program Analysis
  Present Final Development Program for
  Acceptance by Board of Supervisors




          Copyright P3 Development Inc 2010
Desired Elements



Knowledge & Discovery Center                    Office Space

Business & Technology Incubator                 Retail Space
                                                Evening Entertainment Venue
Central Outdoor Plaza
                                                Residential Space
Public Transit Hub
                                                Public Improvements &
Digital Media Lab
                                                  Infrastructure
Parking Structure                               Hotel and/or Event Center

                         Copyright P3 Development Inc 2010
Program Analysis



Master Plan
Infrastructure Analysis
Parking Analysis
Real Estate Issues
Financing Analysis
Development Plan
Public Outreach
                  Copyright P3 Development Inc 2010
Next Step




Present Final Development Program for
  Acceptance by Board of Supervisors




            Copyright P3 Development Inc 2010
Answer Questions We Posed to the Citizen’s
              Committee


 What would our clients like to build?

 What can be built?

 What is feasible?




        Copyright P3 Development Inc 2010
What Would Clients Like?



Desired Elements in Different Combinations
Base Option
Additional Elements when Feasible




                 Copyright P3 Development Inc 2010
What Can Be Built?



Site is Large Enough
No Substantial Physical or Environmental
 Impediments




                 Copyright P3 Development Inc 2010
What is Feasible?


  Summary
  Scope
  Development Budget/Timeline
  Financing Plan
  Closing the Gap



           Copyright P3 Development Inc 2010
What is Feasible?




Feasible: Capable of being accomplished or
 brought about; possible




                 Copyright P3 Development Inc 2010
Summary



The project is feasible
Public-Private Partnership
The financing structure will not impact the City’s
 debt limit
The financing can be tax exempt
The City will not issue bonds
Long term lease subject to annual appropriation
Commence Summer 2011
First lease payment 2015
                   Copyright P3 Development Inc 2010
Scope



Project Assumptions
  ›   Parking Requirement: 2 spaces per 1,000 sf
  ›   Retail Forecast: 7,500 to 10,000 sf
Master Plan
Parking Plan



                   Copyright P3 Development Inc 2010
Scope: Existing Site




  Copyright P3 Development Inc 2010
Scope: Roads




Copyright P3 Development Inc 2010
Scope: Public Improvements




      Copyright P3 Development Inc 2010
Scope: Master Plan




  Copyright P3 Development Inc 2010
Scope: Parking




Copyright P3 Development Inc 2010
Scope: Parking




Copyright P3 Development Inc 2010
Development Budget/Timeline



Assumptions
  ›   Public Investment
  ›   Private Investment




                   Copyright P3 Development Inc 2010
Development Budget/Timeline




      Copyright P3 Development Inc 2010
Development Budget/Timeline




      Copyright P3 Development Inc 2010
Development Budget/Timeline




      Copyright P3 Development Inc 2010
Financing Plan



Assumptions
   ›   No Impact on City’s Debt Limit
   ›   Lease/Lease Purchase
   ›   Taxable or Tax Exempt
   ›   Down Payment




                 Copyright P3 Development Inc 2010
Financing Plan



Financing Structure: Lease Based Financing
Viable & Flexible Method
   ›   Tax Exempt or Taxable Borrowing Rates
   ›   Amount Financed is the Guaranteed Maximum Price

Numerous Structural Options Available

Lease/Leaseback Basic Outline
   ›   Developer/Project Leases Land from Hop & Mae Adams Foundation
   ›   Development Team Builds Project for Guaranteed Maximum Price
   ›   Project is Leased to City
   ›   City Makes Lease Payments
   ›   City Acquires Project at end of Lease Term
                           Copyright P3 Development Inc 2010
Financing Plan
Closing the Gap



Reduce the Amount to be Financed
  ›   Cost of Improvements
  ›   Increase the Amount of Cash Contribution
  ›   Obtain Federal Grants
  ›   Library Fundraising Program
Increase Annual Revenues



                    Copyright P3 Development Inc 2010
Copyright P3 Development Inc 2010

Nugget Project Presentation, Sept. 27, 2010

  • 1.
    Carson City Center Citizen’sAdvisory Committee Copyright P3 Development Inc 2010
  • 2.
    Overview of P3’sTasks Under the DCA Desired Elements Program Analysis Present Final Development Program for Acceptance by Board of Supervisors Copyright P3 Development Inc 2010
  • 3.
    Desired Elements Knowledge &Discovery Center Office Space Business & Technology Incubator Retail Space Evening Entertainment Venue Central Outdoor Plaza Residential Space Public Transit Hub Public Improvements & Digital Media Lab Infrastructure Parking Structure Hotel and/or Event Center Copyright P3 Development Inc 2010
  • 4.
    Program Analysis Master Plan InfrastructureAnalysis Parking Analysis Real Estate Issues Financing Analysis Development Plan Public Outreach Copyright P3 Development Inc 2010
  • 5.
    Next Step Present FinalDevelopment Program for Acceptance by Board of Supervisors Copyright P3 Development Inc 2010
  • 6.
    Answer Questions WePosed to the Citizen’s Committee What would our clients like to build? What can be built? What is feasible? Copyright P3 Development Inc 2010
  • 7.
    What Would ClientsLike? Desired Elements in Different Combinations Base Option Additional Elements when Feasible Copyright P3 Development Inc 2010
  • 8.
    What Can BeBuilt? Site is Large Enough No Substantial Physical or Environmental Impediments Copyright P3 Development Inc 2010
  • 9.
    What is Feasible? Summary Scope Development Budget/Timeline Financing Plan Closing the Gap Copyright P3 Development Inc 2010
  • 10.
    What is Feasible? Feasible:Capable of being accomplished or brought about; possible Copyright P3 Development Inc 2010
  • 11.
    Summary The project isfeasible Public-Private Partnership The financing structure will not impact the City’s debt limit The financing can be tax exempt The City will not issue bonds Long term lease subject to annual appropriation Commence Summer 2011 First lease payment 2015 Copyright P3 Development Inc 2010
  • 12.
    Scope Project Assumptions › Parking Requirement: 2 spaces per 1,000 sf › Retail Forecast: 7,500 to 10,000 sf Master Plan Parking Plan Copyright P3 Development Inc 2010
  • 13.
    Scope: Existing Site Copyright P3 Development Inc 2010
  • 14.
    Scope: Roads Copyright P3Development Inc 2010
  • 15.
    Scope: Public Improvements Copyright P3 Development Inc 2010
  • 16.
    Scope: Master Plan Copyright P3 Development Inc 2010
  • 17.
    Scope: Parking Copyright P3Development Inc 2010
  • 18.
    Scope: Parking Copyright P3Development Inc 2010
  • 19.
    Development Budget/Timeline Assumptions › Public Investment › Private Investment Copyright P3 Development Inc 2010
  • 20.
    Development Budget/Timeline Copyright P3 Development Inc 2010
  • 21.
    Development Budget/Timeline Copyright P3 Development Inc 2010
  • 22.
    Development Budget/Timeline Copyright P3 Development Inc 2010
  • 23.
    Financing Plan Assumptions › No Impact on City’s Debt Limit › Lease/Lease Purchase › Taxable or Tax Exempt › Down Payment Copyright P3 Development Inc 2010
  • 24.
    Financing Plan Financing Structure:Lease Based Financing Viable & Flexible Method › Tax Exempt or Taxable Borrowing Rates › Amount Financed is the Guaranteed Maximum Price Numerous Structural Options Available Lease/Leaseback Basic Outline › Developer/Project Leases Land from Hop & Mae Adams Foundation › Development Team Builds Project for Guaranteed Maximum Price › Project is Leased to City › City Makes Lease Payments › City Acquires Project at end of Lease Term Copyright P3 Development Inc 2010
  • 25.
  • 26.
    Closing the Gap Reducethe Amount to be Financed › Cost of Improvements › Increase the Amount of Cash Contribution › Obtain Federal Grants › Library Fundraising Program Increase Annual Revenues Copyright P3 Development Inc 2010
  • 27.