Timetable-Key dates 
September 2014 Second Year 1 payment released, subject to revised 
project and financial plans. 
January 2015 Inform your Account Manager if you are predicting an 
under spend for Year 1 
February 2015 Grants Hub will issue Monitoring Packs for 
completion and letter confirming funding for 2014-15 
30th April 2015 Deadline for return of Monitoring Packs 
May 2015 Grants Hub will review your report and take advise 
from Policy colleagues. If satisfactory, the first Year 2 
payment will be released. 
October 2015 Second Year 2 payment released, subject to 
accounts
3 
How to complete 
• Please refer back to your application and report 
progress on the outcomes you identified there 
• Keep your answers clear and concise; provide facts 
and figures where possible. 
• Be honest, even when a project does not proceed as 
expected, there are lessons to be learned
4 
What we are looking for: 
• Achievement of outcomes 
• Keeping on track with project plan and budget 
• Does your project still meet DH priorities? 
• Is there still an appetite for it with your service users?
5 
Things to consider 
• We expect you to be working towards long-term 
sustainability throughout the project. 
• In the final year of your project, we will need two 
reports. 
• Consider risk management throughout the project
6 
Things to consider cont… 
• Monitoring is a continual process 
• We may call to review progress outside of the reporting 
period 
• Please let us know about any large meetings or 
conferences you are having. 
• Copy your Account Manager in to any key documents, 
for example; booklets, project updates to your board, 
reports of findings
7 
Finally 
• If you have any concerns or questions at any time, 
contact your Account Manager or Senior Account 
Manager and we will be happy to help. 
• Any Questions?

Monitoring slides claire mc cay - voluntary sector grants hub (slideshare)

  • 1.
    1 Monitoring IESDNew Awards Event
  • 2.
    2 Timetable-Key dates September 2014 Second Year 1 payment released, subject to revised project and financial plans. January 2015 Inform your Account Manager if you are predicting an under spend for Year 1 February 2015 Grants Hub will issue Monitoring Packs for completion and letter confirming funding for 2014-15 30th April 2015 Deadline for return of Monitoring Packs May 2015 Grants Hub will review your report and take advise from Policy colleagues. If satisfactory, the first Year 2 payment will be released. October 2015 Second Year 2 payment released, subject to accounts
  • 3.
    3 How tocomplete • Please refer back to your application and report progress on the outcomes you identified there • Keep your answers clear and concise; provide facts and figures where possible. • Be honest, even when a project does not proceed as expected, there are lessons to be learned
  • 4.
    4 What weare looking for: • Achievement of outcomes • Keeping on track with project plan and budget • Does your project still meet DH priorities? • Is there still an appetite for it with your service users?
  • 5.
    5 Things toconsider • We expect you to be working towards long-term sustainability throughout the project. • In the final year of your project, we will need two reports. • Consider risk management throughout the project
  • 6.
    6 Things toconsider cont… • Monitoring is a continual process • We may call to review progress outside of the reporting period • Please let us know about any large meetings or conferences you are having. • Copy your Account Manager in to any key documents, for example; booklets, project updates to your board, reports of findings
  • 7.
    7 Finally •If you have any concerns or questions at any time, contact your Account Manager or Senior Account Manager and we will be happy to help. • Any Questions?