D. Anagnostakis, J.M. Ritchie and T. Lim explore how Lanner predictive simulation software WITNESS can help improve the environmental impact of a manufacturing system.
Presenting at the Lanner predictive simulation conference, 2016, D. Anagnostakis, J.M. Ritchie and T. Lim explore how Lanner predictive simulation software WITNESS can help improve the environmental impact of a manufacturing system.
Similar to D. Anagnostakis, J.M. Ritchie and T. Lim explore how Lanner predictive simulation software WITNESS can help improve the environmental impact of a manufacturing system.
Proposed Design Models of Axial-Flux Permanent Magnet Synchronous Generator ...abdoyakob
Similar to D. Anagnostakis, J.M. Ritchie and T. Lim explore how Lanner predictive simulation software WITNESS can help improve the environmental impact of a manufacturing system. (20)
Adobe Marketo Engage Deep Dives: Using Webhooks to Transfer Data
D. Anagnostakis, J.M. Ritchie and T. Lim explore how Lanner predictive simulation software WITNESS can help improve the environmental impact of a manufacturing system.
1. Predictive Simulation Conference
April 28, 2016
MTC, Coventry, UK
Modelling and Improving the Environmental
Impact of a Manufacturing System
D. Anagnostakis, J. M. Ritchie, T. Lim
2. Outline
1. Introduction
2. Case study
3. Manufacturing system
4. Modelling
5. Simulation
6. Results and discussion
7. Conclusion
3. Introduction
The company
Progress Rail Services (UK) Ltd.
• Design and manufacture railway switches and
crossings.
• Crossing manufacture at South Queensferry plant.
• Material: austenitic manganese steel.
• Energy and carbon reduction pressures.
1. Introduction
2. Case study
3. Manufacturing system
4. Modelling
5. Simulation
6. Results and discussion
7. Conclusion
4. Case Study
Aim
Environmental impact assessment of a production
system within a manufacturing company.
• Environmental performance indicators regarding
energy consumption & carbon emissions.
• Discrete event simulation models using WITNESS
predictive simulation software (Lanner Ltd., UK).
1. Introduction
2. Case study
3. Manufacturing system
4. Modelling
5. Simulation
6. Results and discussion
7. Conclusion
5. Manufacturing system
Casting
Heat Treatment
Machine Shop
Finishing department
Production of 10 crossing variants
Similar geometry
Different length and width
Manufacturing System 1. Introduction
2. Case study
3. Manufacturing system
4. Modelling
5. Simulation
6. Results and discussion
7. Conclusion
9. Modelling
• Product demand
• Power required
• Resources
Input
• Machines
• Setup time
• Process time
System
• Energy
consumption
• Carbon emissions
Output
1. Introduction
2. Case study
3. Manufacturing system
4. Modelling
5. Simulation
6. Results and discussion
7. Conclusion
Production
launch
Peak
demand End of
production
10. Power consumption modelling
1. Cranes and Charger
Main hoisting and lowering power:
𝑃ℎ = 𝑊𝑙𝑖𝑓𝑡 + 𝑊𝑝𝑎𝑟𝑡 ∗ 𝑔 ∗
𝑣ℎ
60∗𝑒𝑓𝑓
𝑃𝑙 = −(𝑊𝑙𝑖𝑓𝑡 + 𝑊𝑝𝑎𝑟𝑡) ∗ 𝑔 ∗
𝑣 𝑙
60
∗ 𝑒𝑓𝑓
Main travelling power:
𝑃𝑡𝑟 = 𝑊𝑙𝑖𝑓𝑡 + 𝑊𝑝𝑎𝑟𝑡 ∗ 𝑐 ∗ 𝑔 ∗
𝑣 𝑡𝑟
60∗𝑒𝑓𝑓
Power for acceleration and deceleration in hoisting motion:
𝑃ℎ,𝑎𝑐𝑐 = (𝑊𝑙𝑖𝑓𝑡 + 𝑊𝑝𝑎𝑟𝑡) ∗
(𝑣ℎ 60
2
𝑡 𝑎𝑐𝑐∗𝑒𝑓𝑓
𝑃ℎ,𝑑𝑒𝑐 = − 𝑊𝑙𝑖𝑓𝑡 + 𝑊𝑝𝑎𝑟𝑡 ∗
(𝑣ℎ 60
2
𝑡 𝑑𝑒𝑐
∗ 𝑒𝑓𝑓
Power for acceleration and deceleration in lowering motion
𝑃𝑙,𝑎𝑐𝑐 = 𝑊𝑙𝑖𝑓𝑡 + 𝑊𝑝𝑎𝑟𝑡 ∗
(𝑣 𝑙 60
2
𝑡 𝑎𝑐𝑐
∗ 𝑒𝑓𝑓 𝑃𝑙,𝑑𝑒𝑐 = − 𝑊𝑙𝑖𝑓𝑡 + 𝑊𝑝𝑎𝑟𝑡 ∗
(𝑣 𝑙 60
2
𝑡 𝑑𝑒𝑐∗𝑒𝑓𝑓
Power for motor acceleration and deceleration in hoisting
𝑃ℎ,𝑚,𝑎𝑐𝑐 = 𝑊𝐾𝑟
2
∗
(2∗𝜋∗𝑛 𝑚 60
2
1000∗𝑡 𝑎𝑐𝑐
𝑃ℎ,𝑚,𝑑𝑒𝑐 = −𝑊𝐾𝑟
2
∗
(2∗𝜋∗𝑛 𝑚 60
2
1000∗𝑡 𝑑𝑒𝑐
Power for motor acceleration and deceleration in lowering
𝑃𝑙,𝑚,𝑎𝑐𝑐 = 𝑊𝐾𝑟
2
∗
2∗𝜋∗
𝑣 𝑙
𝑣ℎ
∗𝑛 𝑚 60
2
1000∗𝑡 𝑎𝑐𝑐
𝑃𝑙,𝑚,𝑑𝑒𝑐 = −𝑊𝐾𝑟
2
∗
2∗𝜋∗
𝑣 𝑙
𝑣ℎ
∗𝑛 𝑚 60
2
1000∗𝑡 𝑑𝑒𝑐
Power for acceleration and deceleration in travelling.
𝑃𝑡𝑟,𝑎𝑐𝑐 = 𝑊𝑙𝑖𝑓𝑡 + 𝑊𝑝𝑎𝑟𝑡 ∗
𝑣 𝑡𝑟
60
2
𝑡 𝑎𝑐𝑐∗𝑒𝑓𝑓
𝑃𝑡𝑟,𝑑𝑒𝑐 = − 𝑊𝑙𝑖𝑓𝑡 + 𝑊𝑝𝑎𝑟𝑡 ∗
(
𝑣 𝑡𝑟
60
)2∗𝑒𝑓𝑓
𝑡 𝑑𝑒𝑐
Power for motor acceleration and deceleration in travelling
𝑃𝑡𝑟,𝑚,𝑎𝑐𝑐 = 𝑊𝐾𝑟
2
∗
(2∗𝜋∗𝑛 𝑚 60
2
1000∗𝑡 𝑎𝑐𝑐
𝑃𝑡𝑟,𝑚,𝑑𝑒𝑐 = −𝑊𝐾𝑟
2
∗
(2∗𝜋∗𝑛 𝑚 60
2
1000∗𝑡 𝑑𝑒𝑐
13. 1 2 3
Heat Treatment Machine shop Finishing
Final WITNESS Model
Modelling components in WITNESS
WITNESS - Part route Summary
WITNESS - Part file and Input structure
WITNESS - Usage details report
WITNESS - Built-in graphs
WITNESS - Output variables
14. Simulation Scenario
• 240 working days
• 3 shifts x 7.5 working hours/shift
• Annual production volume: 800 crossings
• Products demand and variants:
1. Introduction
2. Case study
3. Manufacturing system
4. Modelling
5. Simulation
6. Results and discussion
7. Conclusion
16. Results and discussion
Current plant:
Total energy consumption: 722.5 MWh
Natural Gas provides 60% of total consumed energy
Total carbon emissions: 206 Tones CO2
Electricity causes 50% of total CO2 emissions
0
200
400
600
800
EnergyUsage(MWh)
Electricity Natural Gas
Diesel fuel Total Energy Usage
0
50
100
150
200
250
TotalEmissions(Ton.CO2)
Electricity Natural Gas
Diesel fuel Total Emissions
1. Introduction
2. Case study
3. Manufacturing system
4. Modelling
5. Simulation
6. Results and discussion
7. Conclusion
17. Real plant vs. Ideal plant
Real plant:
115% more energy consumption
98% more carbon emissions
All previous values based on real efficiency
recalculated based on 100% efficiency for the
components involved in each work station.
0
250
500
750
EnergyUsage(MWh)
Real plant Ideal plant
0
50
100
150
200
250
TotalEmissions(Ton.CO2)
Real plant Ideal plant
18. Optimisation Scenario
Benefits after
replacement of furnace:
18% less energy consumption
14% less carbon emissions
28% cost reduction in natural gas
0
250
500
750
EnergyUsage(MWh)
Real plant New plant
0
50
100
150
200
250
TotalEmissions(Ton.CO2)
Real plant New plant
0
2500
5000
7500
10000
NatralGasCost(£)
Real plant New plant
19. Conclusions
Modelling and simulation tools can contribute to:
Identification of high energy consuming components
Reduction of energy consumption and CO2 emissions
Increase in money savings
Enhanced decision making in environmental and production
performance issues
Potential to be embedded in new product development process.
1. Introduction
2. Case study
3. Manufacturing system
4. Modelling
5. Simulation
6. Results and discussion
7. Conclusion
21. References
1. Kalla D., Twomey J., Overcash M., Methodology for systematic analysis and
improvement of manufacturing unit process life cycle inventory, 2010, Wichita
State University
2. Rajemi M. F., Energy Analysis in Turning and Milling, 2010, University of
Manchester, School of Mechanical, Aerospace and Civil Engineering
3. Tran K., Study of Electrical Usage and Demand at the Container Terminal, PhD
Thesis, 2012, Deakin University
4. M.E. Eltantawie, Design, Manufacture and Simulate a Hydraulic Bending Press,
2013, Int. Journal of Mechanical Engineering and Robotics Research
5. W. Trinks, M. H. Mawhinney, R. A. Shannon, R. J. Reedand J. R. Garvey,
Industrial Furnaces, 2004, John Wiley & Sons, Inc
6. Rooda J. E., Vervoot J., Analysis of Manufacturing systems, 2005, Technische
Universiteit Eindhoven, Department of Mechanical Engineering
The objective of this study is the environmental impact assessment of a production system. Using appropriate indicators related to energy consumption and carbon emissions and discrete event simulation such as WITNESS, we can estimate the impacts from production processes on the environment.
The objective of this study is the environmental impact assessment of a production system. Using appropriate indicators related to energy consumption and carbon emissions and discrete event simulation such as WITNESS, we can estimate the impacts from production processes on the environment.
The case study is based on a manufacturing company which produces equipment such as rails and railroad parts. The under investigation production system consists of three departments: heat treatment, machine shop and finishing focusing on the production of 10 different variants of casting crossings, which have similar geometry but different total length and width.
The first section is the heat treatment department. In the figure the process flow of the crossings through this department appears. The crossings are loaded by an overhead crane on a charger which first loads the crossings in a furnace for heating at 1060 C. After this the crossings are quenched in a water tank, again using the charger. Finally the charger comes back to the initial position where the crossings are unloaded by the crane to a storage area.
The other two parts of the production are the machine shop and the finishing department. The crossings are loaded in each work station by overhead cranes and unloaded from the machine shop to the finishing department using forklifts. The machine shop consists of a hydraulic press machine, two manual milling machines and 3 CNC milling machines. The finishing department includes three working stations where operators using hand held grinders remove any imperfections from the crossings surfaces.
The other two parts of the production are the machine shop and the finishing department. The crossings are loaded in each work station by overhead cranes and unloaded from the machine shop to the finishing department using forklifts. The machine shop consists of a hydraulic press machine, two manual milling machines and 3 CNC milling machines. The finishing department includes three working stations where operators using hand held grinders remove any imperfections from the crossings surfaces.
To analyze and model the system at a detailed enough level, an input-output approach was used, taking into account parameters such as product demand, setup and process times.
Three distinct areas are included in the Witness model, Heat treatment, machine shop and finishing.
For each component and machine the energy consumption of the greatest consumers has been modeled, such as fans, pumps and motors.
The simulation period assumed to be 240 working days, 3 shifts with 7.5 h per shift. The total annual production volume is 800 crossings following this production mix for each one of the ten different variants of crossings.
The final results from the simulation have indicated a total energy consumption of 722500 kwh and 206000 kg of CO2 emissions. We can observe that 60% of the total energy is provided by natural gas and half of the emissions are caused by the consumption of electricity.
However to understand if these results are good or bad relative to the overall environmental performance of the system, the current system was compared to the ideal equivalent system which would have 100% of efficiency.
The results of the comparison indicated that the real system consumes 115 % more total energy than the ideal and emits 98% more CO2 during the production period.
Thus it is obvious that there is a need for improvements from an energy consumption point of view.
Another way to use this methodology is for assessing the performance of production systems when a component of the system (e.g. a milling machine or CNC) changes.
In this case it was assumed that the furnace is replaced by another one 10 % more efficient than the old.
The results show that the total energy consumption have been reduced by 18% while the total emissions have been reduced by 14 %.
Moreover considering the average cost unit for natural gas, the purchase cost is calculated to be 28% less.
As a conclusion it can be said that by applying the proposed methodology combined with the discrete event simulation combined, high energy consuming areas or components within a production system can be identified leading to reduction of the energy consumption and carbon emissions and increase of money saving due to proper changes throughout the manufacturing system. Moreover this methodology can be extended to include further parameters and conditions relative to environmental or production performance issues, enhancing the process of decision making on these issues.