Shoaib Mohd Tantray
Those Housing Units which are
AFFORDABLE
By LOW – INCOME & MIDDLE INCOME FAMILY
REDUCE
CONVENTIONAL BUILDING MATERIALS
REVIEW
ALTERNATE BUILDING MATERIAL
USE
LOCAL MATERIALS
REUSE
WASTE MATERIALS
 Cost Effective
 Environment Friendly
 Locally Available
Without Compromising
 Strength
 Performance
 Life
 Autoclaved Aerated Concrete Blocks
 FLY ASH – Key Ingredient in the Manufacture
of AAC Blocks
 Replaces the use of Red Clay Bricks
 SIZE: 600 mm x 250 mm x 150 mm
(2’ x 9” x 6”)
 WEIGHT: 14 kg
PARAMETER RED CLAY BRICKS AAC BLOCKS
No. Of Bricks 585 bricks 50 blocks
JOINTS 1656 162
Bonding Cement: 2 bags Cement: 1 bag
Material Sand: 20 ft3
Labour 6 men 3 men
TIME 6 hours 30 minutes 3 hours
PARAMETER RED CLAY BRICKS AAC BLOCKS
Water Usage Requires more water Requires Less Water
Plastering Always Required Not Necessarily
Wastage 10 – 30 % Minimal Wastage
COST of Rs. 1350 Rs. 650
Bonding
Material
COST of Rs. 1500 Rs. 400
Labour
SAVINGS
CEMENT 40 – 50 %
MORTAR 70 – 80 %
PLASTER 60 – 70 %
LABOUR 50 – 60 %
CONSTT. TIME 40 – 50 %
Compressive Strength:
Clay Brick: 2.5 – 3.5 N/mm2
AAC Blocks: 3 – 4.5 N/mm2
MOISTURE RESISTANCE:
Clay Bricks: Average
AAC Block: Better than the Red Brick
THERMAL CONDUCTIVITY:
Clay Bricks: High
AAC Block: Less
Fire Resistance:
Clay Bricks: 2 hours (100 mm thick wall)
AAC Block: 4 hours (100 mm thick wall)
 Prefabricated Gypsum Boards Reinforced With Glass
Fibres
 Suitable For Rapid Erection Of Walls In Buildings
 Manufactured By Using Phosphogypsum As A Core
Material
SIZE Of Panel: 12 m x 3 m x 124 mm
COST: Rs. 1000/m2
15 mm thickness
 As Light Weight Load Bearing Wall
 As Partition Wall
 As Compound Wall
 Horizontal Roofs/Slabs
 In Floors
 In Staircases
 FOUNDATION: As per Conventional Building Methods
 FITTING: Panels Are Lifted With Cranes And Special
Hooks And Are Placed In The Proper Position.
 CUTTING of Doors, Windows, Sanitary Fittings, etc.
 REINFORCEMENT Bars are inserted
 CONCRETE POURING:
Poured in Different Levels of 1m each at the interval of 1hr
SLAB:
 Panels are placed
 Reinforcement
 Concrete Pouring
 Fire resistance up to 1000° C.
 Earthquake resistant (up to Ritcher
Scale 8)
 Water resistant
 Acts as insulating material
 Eco friendly (waste product of
fertilizer industry, Gypsum, is used
to make the panels)
 Usage of cement is reduced.
 Does not need conventional
plastering
 Reduce the construction time
 Reduce the labour cost
 Economical
 Requirement of Free Space
 Extensive planning during design phase
 Lack of experience in the existing contractors
 Clear span shall be limited to 5m.
ITEMS
Conventional
Building
GFRG Building
Savings
%
Cement 32.55 tons 16 tons 50.8 %
Steel 2779 kg 1800 kg 35.2 %
Sand 83.37 cum 20 cum 76 %
Water 20,00,000 L 50,000 L 75 %
ITEMS
Conventional
Building
GFRG Building
Savings
%
Labour 1200 man days 389 man days 67.59 %
Built Area 154.45 sqm 143 sqm 8 %
TIME 4 months 21 days 82 %
COST Rs. 18.27 lakhs Rs. 13.25 lakhs 27.47 %
- END -

Low Cost Housing

  • 1.
  • 2.
    Those Housing Unitswhich are AFFORDABLE By LOW – INCOME & MIDDLE INCOME FAMILY
  • 4.
    REDUCE CONVENTIONAL BUILDING MATERIALS REVIEW ALTERNATEBUILDING MATERIAL USE LOCAL MATERIALS REUSE WASTE MATERIALS
  • 5.
     Cost Effective Environment Friendly  Locally Available Without Compromising  Strength  Performance  Life
  • 6.
     Autoclaved AeratedConcrete Blocks  FLY ASH – Key Ingredient in the Manufacture of AAC Blocks  Replaces the use of Red Clay Bricks
  • 7.
     SIZE: 600mm x 250 mm x 150 mm (2’ x 9” x 6”)  WEIGHT: 14 kg
  • 9.
    PARAMETER RED CLAYBRICKS AAC BLOCKS No. Of Bricks 585 bricks 50 blocks JOINTS 1656 162 Bonding Cement: 2 bags Cement: 1 bag Material Sand: 20 ft3 Labour 6 men 3 men TIME 6 hours 30 minutes 3 hours
  • 10.
    PARAMETER RED CLAYBRICKS AAC BLOCKS Water Usage Requires more water Requires Less Water Plastering Always Required Not Necessarily Wastage 10 – 30 % Minimal Wastage COST of Rs. 1350 Rs. 650 Bonding Material COST of Rs. 1500 Rs. 400 Labour
  • 11.
    SAVINGS CEMENT 40 –50 % MORTAR 70 – 80 % PLASTER 60 – 70 % LABOUR 50 – 60 % CONSTT. TIME 40 – 50 %
  • 12.
    Compressive Strength: Clay Brick:2.5 – 3.5 N/mm2 AAC Blocks: 3 – 4.5 N/mm2 MOISTURE RESISTANCE: Clay Bricks: Average AAC Block: Better than the Red Brick THERMAL CONDUCTIVITY: Clay Bricks: High AAC Block: Less Fire Resistance: Clay Bricks: 2 hours (100 mm thick wall) AAC Block: 4 hours (100 mm thick wall)
  • 13.
     Prefabricated GypsumBoards Reinforced With Glass Fibres  Suitable For Rapid Erection Of Walls In Buildings  Manufactured By Using Phosphogypsum As A Core Material
  • 14.
    SIZE Of Panel:12 m x 3 m x 124 mm COST: Rs. 1000/m2 15 mm thickness
  • 15.
     As LightWeight Load Bearing Wall  As Partition Wall  As Compound Wall  Horizontal Roofs/Slabs  In Floors  In Staircases
  • 16.
     FOUNDATION: Asper Conventional Building Methods
  • 17.
     FITTING: PanelsAre Lifted With Cranes And Special Hooks And Are Placed In The Proper Position.
  • 18.
     CUTTING ofDoors, Windows, Sanitary Fittings, etc.
  • 19.
  • 20.
     CONCRETE POURING: Pouredin Different Levels of 1m each at the interval of 1hr
  • 21.
    SLAB:  Panels areplaced  Reinforcement  Concrete Pouring
  • 22.
     Fire resistanceup to 1000° C.  Earthquake resistant (up to Ritcher Scale 8)  Water resistant  Acts as insulating material  Eco friendly (waste product of fertilizer industry, Gypsum, is used to make the panels)  Usage of cement is reduced.  Does not need conventional plastering  Reduce the construction time  Reduce the labour cost  Economical
  • 23.
     Requirement ofFree Space  Extensive planning during design phase  Lack of experience in the existing contractors  Clear span shall be limited to 5m.
  • 24.
    ITEMS Conventional Building GFRG Building Savings % Cement 32.55tons 16 tons 50.8 % Steel 2779 kg 1800 kg 35.2 % Sand 83.37 cum 20 cum 76 % Water 20,00,000 L 50,000 L 75 %
  • 25.
    ITEMS Conventional Building GFRG Building Savings % Labour 1200man days 389 man days 67.59 % Built Area 154.45 sqm 143 sqm 8 % TIME 4 months 21 days 82 % COST Rs. 18.27 lakhs Rs. 13.25 lakhs 27.47 %
  • 26.