2024 02 15 AZ GOP LD4 Gen Meeting Minutes_FINAL_20240228.docx
Lick Creek Greenway Trail Design Study
1. Lick Creek Greenway Trail
Preliminary Design Study
City Council Meeting
August 9, 2012
2. Background
• 2002 – Proposed in the Bikeway and Pedestrian
Master Plan
• 2004 – Prioritized by the Hike and Bike Task Force
and adopted by City Council as a High Priority
• 2008 – Funding included in bond referendum
approved by voters ($4.4 million)
• 2011 – Awarded contract to Halff Associates, Inc.
to conduct a preliminary design study
• May 2012 – Route alternatives presented to Council
3. Preliminary Design Study
Project Scope
Research and evaluate existing and future
conditions
Identify and evaluate three (3) alternative
routes
Gather public input
Develop construction cost estimate
Identify preferred route
4. Public Participation Schedule
December 3, 2011
Stakeholder meeting with SpringBrook and Pebble Creek
HOAs to hear specific concerns and desires
January 23rd and 25th
Present, discuss, and gather input on the three alternative
alignments
49 attendees at the meeting on the 23rd
96 attendees at the meeting on the 25th
March 19th
Present and discuss the proposed preferred alignment
59 attendees at the meeting
11. Land Dedication
In April the SpringBrook HOA voted on a
proposition to allow the HOA Board to negotiate
with the City to dedicate 18 acres of common area
170 votes were cast from a total of 196 Lot owners
100 votes for the dedication
70 votes against the dedication
Some homeowners in the neighborhood
strongly oppose the land dedication and the
trail in the common area
12. Council Update
May 24, 2012 staff update to Council
Allow neighborhood and HOA several months to
make progress toward addressing the issues
related to the land dedication
Staff does not feel the neighborhood and
HOA are close to reaching a consensus on the
alignment for Segment A
13. Recommended Route – Segment A
Segment A (Eagle/Longmire/Barron)
Reconstruct sidewalks less than 5-feet wide
Address ADA issues
Wayfinding signage
Stripe bike lanes
Provide benches or other trail related amenities
when sufficient ROW is available
Minimize impacts to landscaping, fences, and
neighborhood signs inside the ROW
Keep all improvements inside the existing ROW
or existing public access easements
19. Cost Estimate
Segment A Segment B Segment C Total
Recommended Approx.
Route $650,000 $1,593,000 $773,000 $3,016,000
20. Staff Recommendation
Staff recommends proceeding with the
complete design of the project
Segment A (Eagle/Longmire/Barron) –
Upgrade existing infrastructure
Segments B and C - Follow consultant’s
preferred alignment for the multi-use path
24. March 19th Meeting
Approximately 59 people in attendance
Of the questionnaires returned regarding the
preferred route:
Segment A – 57.9% in favor
Segment B – 80% in favor
Segment C – 72.7% in favor