JAMES AH CAMPBELL
CEO, ROCKWELL DIAMONDS INC“uncovering the facets of our potential”
SAMREC/SAMVAL COMPANION VOLUME CONFERENCE
17-18 MAY 2016
217-18 May 2016 |
OUTLINE
• PUBLIC REPORTING
• MINERAL REPORTING STANDARDS AND CODES
• REGULATORY REQUIREMENTS
• DIAMOND MINING
• ASSESSING DIAMOND POTENTIAL
• JUNIOR MINERS
• CASE STUDIES
• KIMBERLITE MINING
• ALLUVIAL MINING
• IMPLICATIONS FOR INVESTORS
• IMPLICATIONS FOR PUBLIC REPORTING
• CONCLUDING REMARKS
James Campbell is President and CEO of
Rockwell Diamonds Inc. Previous roles
include Non Executive Director of Stellar
Diamonds plc, Vice President - New Business
for Lucara Diamond Corp, Managing Director
of African Diamonds plc, Executive Deputy
Chairman of West African Diamonds plc.
James worked at De Beers for over twenty
years; his roles included General Manager for
Advanced Exploration & Resource Delivery
and Nicky Oppenheimer's Personal Assistant.
James holds a degree in Mining & Exploration
Geology from the Royal School of Mines
(Imperial College, London University) and an
MBA with distinction from Durham University.
He is a Fellow of the Institute of Mining,
Metallurgy & Materials, South African Institute
of Mining & Metallurgy and Institute of
Directors of South Africa. He is also a
Chartered Engineer (UK), Chartered Scientist
(UK) and a Professional Natural Scientist
(RSA).
James also chairs two NPO’s and is
deeply committed to South Africa.
317-18 May 2016 |
REGULATORY & REPORTING REQUIREMENTS
417-18 May 2016 |
PUBLIC REPORTING
Public reporting refers to all disclosure, such as press
releases, website postings, presentations, technical reports
and technical disclosure accompanying financial reports
(statements of Mineral Resources and Reserves)
Public reporting must be
♦ Material. i.e. present all reasonably expected information
♦ Transparent, i.e. presented in a clear and unambiguous
manner
♦ Prepared by Competent Persons (CP)
Competent Persons must
♦ Be a Member or Fellow of a Recognised Professional
Organisation (RPO).
♦ Have a minimum of five years’ relevant experience in the
style of mineralisation or type of deposit under consideration
and in the activity which that person is undertaking.
♦ Be satisfied that they could face their peers and
demonstrate competence in the commodity, type of deposit
and situation under consideration.
Professional codes of practice
set minimum standards for public
reporting.
Public reports must be prepared
by a Competent Person (CP)
Codes differ slightly on the
requirements for CP’s relevant
experience
Membership in the RPO should
be primarily on the basis of
academic qualifications and
experience
RPOs should have enforceable
disciplinary processes including
the powers to suspend or expel
a member
Source: CRIRSCO
517-18 May 2016 |
MINERAL REPORTING STANDARDS & CODES
National reporting standards for selected countries
International initiative launched
in South Africa in 1994
Working group established to
develop a set of standard
definitions for reporting of
mineral resources and mineral
reserves
Today most national reporting
standards share a common set
of codes and guidelines
The Canadian mining sector’s
credibility improved greatly
after the NI 43-101 was
introduced in 2001
19971994 1999 2000
International
initiative to
standardise
definitions for
market-related
reporting
(CRIRSCO)
Agreement on
definitions for
Mineral
Resources and
Mineral
Reserves
(Denver Accord)
Alignment with
United Nations
Framework
Classification
Updated JORC
Code published
(first release 1989)
Other national
reporting
standards/codes
published, e.g.
SAMREC, CIM
Country Reporting Standard/Code
Australia JORC Code (2012)
Canada CIM Definition Standards for Mineral Resources and
Reserves – NI 43-101 (2014)
Europe/UK PERC Reporting Standard (2013)
Russia NAEN Code (2011)
South Africa SAMREC Code (2007)
SAMVAL Code (2008)
USA SME Guide (2014)
Source: CRIRSCO, PWC
617-18 May 2016 |
REGULATORY REQUIREMENTS
Mining reporting requirements applicable in selected jurisdictions
Stock
Exchange
Mining-specific Reporting
Requirements (post-listing)
Mineral Reporting
Standard
ASX Annual and half-year financial report
Quarterly report by CP on production
and development activities (incl.
expenditure); exploration activities;
mineral results & ore results
JORC
JSE Annual and quarterly financial report
Description of exploration and mining
activities by CP; mineral resource and
reserve statement
SAMREC
TSX/TSXV Annual and quarterly financial report CIM (NI 43-101)
LSE/AIM Annual and half-year financial report
Interim management statement
Resource updates by CP (AIM)
JORC, SAMREC, CIM,
other selected codes
HKEx/GEM Annual and quarterly financial report
Half-yearly updates on mining
JORC, SAMREC, CIM
The world’s largest diversified
mining groups are listed on LSE
In 2013, TSX and TSX-V
combined were home to 57% of
the world’s publicly listed mining
companies
Cross border international
listings and dual/triple listings of
miners on AIM, TSX and ASX
continue to increase
HKEx is becoming a destination
of choice for mining companies.
However, companies with only
inferred resources are not
eligible for listing
Source: PWC, Mining Association of Canada
717-18 May 2016 |
DIAMOND MINING
817-18 May 2016 |
DIAMOND MINING – TWO SCENARIOS
KIMBERLITES
• High establishment costs
• Open pit and underground
operations (with progression
in some cases)
• Grade, diamond distribution
can be constrained with
sampling and modelling
• Higher resource confidence
can mitigate uncertainty
ALLUVIALS
• Lower start-up costs
• Low grade, high variability
• High uncertainty
• High volume, low cost approach
• Scarcity of larger (high-value)
diamonds
• Volumes are key to repeatability
Alluvial operations perceived
as being better suited to
smaller operators (juniors)
than kimberlites
Most juniors and mid-tiers own
kimberlite projects
Majors such as De Beers have
been running large-scale
alluvial operations
Diamonds from alluvial
operations are on average
larger (cts/stone) and more
valuable ($/ct)
Attracting equity and debt
funding is challenging in
current markets
917-18 May 2016 |
LISTED DIAMOND MINING IN SOUTH AFRICA
Company Size Listing SA operations
(K = kimberlite;
A = alluvial)
Annual
Production
(cts)
Annual
Revenue
(US$)
Blue Rock
Diamonds
Junior AIM Kareevlei (K) Ramp-up N/A
De Beers Major N/A Venetia,
Voorspoed (K)
4.5M No SA
reports
Diamcor
Mining
Junior TSX-V,
OTC
Krone-Endora (A) +/- 20,000
(incidental)
+/- 3M
DiamondCorp Junior AIM Lace (K) +/- 7,000
(ramp-up)
N/A
Petra
Diamonds
Mid-
tier
LSE Cullinan, Finsch,
Kimberley,
Koffiefontein (K)
3M 360M
Rockwell
Diamonds
Junior TSX,
JSE
Middle Orange
River (A)
36,000 51M
Trans Hex Junior JSE Lower Orange
River,
Namaqualand (A)
62,000 83M
South Africa currently produces
8% of world diamonds by
volume
In 2014 SA produced 8.1 million
carats of diamonds (nearly half
as pre-GFC levels)
The bulk of SA diamond
production is from primary
sources (kimberlites)
Operators are chiefly junior /
mid-tier companies
No new discoveries, nor
significant projects in the
pipeline
Source: company websites, SA Chamber of Mines
Many private diamond mining companies too
1017-18 May 2016 |
A PERSPECTIVE ON JUNIOR MINERS
Source: Investopedia; mineralsnorth.ca; undervaluedequity
Some common traits of juniors Some common traits of majors
• Discoverers and developers of
new economic deposits
• Typically small-cap companies
• Exploration spend is their
lifeblood
• No/little production cashflow to
fund exploration activities
• Funding derived from share
issues & management
• No dividends paid - shareholders
rewarded by share price increase
• Results attract high degree of
public scrutiny and assurance
• Subject to full extent of regulatory
and reporting obligations
• Technical management teams
with deep practical experience
• Innovative, agile and fast
• Owners of mining operations
• Typically more than one mine
• Publicly traded, well capitalised
companies
• Exploration activities internally
funded by production cashflow
• Exploration spend viewed as
discretionary
• Steady, predictable cashflow
• Large corporate structures
• Complex decision processes
• Internal assurance processes
• Able to adjust production to
changing market conditions
• Large technical and non-
technical management
departments.
What defines a junior miner?
♦ No single definition
♦ Prospectors and developers
♦ “The exploration division of
the mining industry”
♦ No marked separation
between junior and mid-tier
1117-18 May 2016 |
ASSESSING DIAMOND POTENTIAL FOR MINING
(GENERALISED PROCESS)
Confidence in the
deposit/resource improves as
new information is analysed and
assumptions are re-visited
As confidence increases, so do
costs and timeframes
Technology plays a critical role in
resource assessment process,
as do risk modelling simulations
Accurate and reliable resource
models are essential inputs to a
sound economic assessment
Expert operators are able to
shorten timeframes, without
compromising on quality of
resource assessment
Deep knowledge, expertise are
key differentiators
Mapping,
sampling,
geophysics
Core drilling or
trenching
(100’s kg)
Initial bulk
sampling
(10-100’s t)
Infill drilling,
bulk sampling
(1000’s t)
Inferred
Resource
Indicated
Resource
Diamond potential,
surface size
estimate
Preliminary grade
estimate, prelim.
geological model
Global grade,
preliminary value
estimate
Geological,
density, volume,
grade, value
models
Preliminary
Economic
Assessment
Pre-Feasibility
Study
Bankable
Feasibility Study
Deposit
Target /
Anomaly
ActivityOutcomes
Mineral
Resource
Economic
Studies
INCREASING COSTS & TIMEFRAMES
DECREASING UNCERTAINTY & RISK
Duration: months
Cost: R millions
Duration: years
Cost: R tens of millions
1217-18 May 2016 |
ASSESSING DIAMOND VALUE
Unlike other mineral commodities, diamonds don’t have set prices
Equity funders require that a rough diamond pricing model be
decided upfront in a deal
Two models in diamond valuation: fixed price book or open tender
Open tenders have the following advantages:
♦ Market related price
♦ Competitive bidding
♦ Pricing transparency
♦ Clients get the goods they want
♦ Premium paid for valued goods
Disadvantages of open tenders include:
♦ Less predictable cash flows
♦ Higher risk of price volatility
♦ Speculative buying
Open tenders are on the increase
♦ Initiated by juniors seeking transparent pricing models
♦ Majors have been integrating tenders into their sales
Five Models underpin a diamond
resource: Geological, Density,
Volume, Grade, Value
Modelling of value is unique to
diamond resource estimation
Value estimates require a
substantial investment in order
for a representative sample to be
obtained
Understanding the size
distribution of diamonds in a
deposit is critical in designing an
effective treatment plant
The value of diamonds
recovered can be optimised
through the selection of a
suitable bottom cut-off size
(BCOS)
Source: GIA, Rockwell
1317-18 May 2016 |
DIAMOND MINING CASE STUDIES
1417-18 May 2016 |
A KIMBERLITE CASE STUDY: AK6 (KAROWE MINE)
AK6 is a diamondiferous
kimberlite pipe located in the
Orapa kimberlite field in north-
eastern Botswana
Discovered by De Beers in 1969,
but deemed low priority
Evaluated in 2003-2007 by
De Beers – African Diamonds JV
Now called Karowe Mine and is
owned and mined by Lucara
Diamond Corp
Mining began in 2012
Anticipated LoM is 15 years
Source: Lucara, JAH Campbell
1517-18 May 2016 |
AK6 - THE JOURNEY
Initial
evaluation by
De Beers
Preliminary
size, grade,
value
encouraging
Boteti JV:
African
Diamonds, De
Beers (49/51)
Evaluation
Phase 1
Inferred
Mineral
Resource
Positive
sampling
results
released
Decision to
fast-track
evaluation
Evaluation
Phase 2
Indicated
Mineral
Resource
Conceptual
Study (DB):
marginal
economics;
capital
USD380M
Pre-Feasibility
Study (AFD):
robust
economics
Feasibility
Study (DB):
marginal
economics
Mining
Licence (2008)
Value
Engineering
Study (AFD):
robust
economics;
capital
USD88M
Lucara
acquires DB’s
share in Boteti
Feasibility
Study (Lucara):
robust
economics;
capital
USD156M
Lucara
acquires AFD’s
share in Boteti
Construction &
Commissioning
Cost:
USD110M
Mining begins
in Q2 2012
2003-5 2010-122005-6 2006-7 AK6 initially downgraded due
to small size (3.3ha), low
grade (3cpht) and poor mineral
chemistry
Re-assessed by De Beers
(Debot) in 2003
Boteti JV (AFD-DB) formed in
2004, prior to initial evaluation
results being released
Facilitated by AFD, Debot sold
its share to Lucara in 2009, in
the wake of the GFC and due
to apparent marginal
economics
AFD exited in 2010 following
significant share premium
buyout from Lucara
2008-9
1617-18 May 2016 |
AK6 EVALUATION PROGRAMME (2003-2007)
Extensive evaluation:
♦ +/-23,000m core drilling
♦ +/- 12,500m LDD
♦ +25,000t samples collected
(not all processed)
Total cost of evaluation
programme USD26.8M
High levels of diamond
damage observed
High abundance of high value
Type II diamonds
Phase Technique Objective Results
Initial
evaluation
LDD
5x12¼”
Macro potential, preliminary
grade
97t (in situ)
25cpht (+1mm)
138USD/ct
High-resolution
geophysics
Surface area, geological
model
9.5ha
EvaluationPhase1
Percussion drilling
44x6.5”
Delineation, geological model,
mineral chemistry, macro
4,575m
28t (in situ)
29.6cpht (+1mm)
Core drilling
17xinclined
12xvertical
Internal geology, LDD pilots,
micro
9,883m
South Lobe
increased
LDD
13x23” @70m
Grade and revenue – inferred
resource 500ct for valuation
2,747t (in situ)
689cts
25.1cpht (+1mm)
EvaluationPhase2
Core drilling
11xvertical
29xinclined
Delineation, internal geology,
LDD pilots
12,860m
Kimberlite at
884m
LDD
12x23” @50m
Grade and revenue –
indicated resource 3000ct for
valuation
3,298t (in situ)
483cts
17.8 cpht (+1mm)
Trenching (S Lobe)
Grade and revenue 7.393t (in situ)
Trenching (C Lobe)
Grade and revenue 12,074t (in situ)
Source: Lucara, JAH Campbell
1717-18 May 2016 |
AK6 / KAROWE RESOURCE STATEMENTS
Karowe Mineral
Resource / Reserve
(2013)
Tonnes
(000,000’s)
Grade
(cpht)
M Carats
(+1.25mm)
Value
(USD/ct)
Probable Reserve
(to 324m)
33.1 15.5 5.1 394
Indicated Resource
(to 400m)
48.07 16 7.61 393
Inferred Resource
(400-750m)
21 14 3.04 412
Source: JAH Campbell, Lucara
2003-7 evaluation programme led
to first mineral resource estimate
for AK6 (2009)
Grades regarded as conservative;
improvement anticipated with
further work
Considerable upside expected in
diamond values (revised upwards
by +25% in 2010)
Latest Karowe resource statement
(2013) reflects a drop in grades
and increase in values
Higher BCOS (1.25mm) accounts
for grade decrease
Value increase chiefly due to
incorporation of production and
sales data into estimates
2013 value estimation qualified
as conservative
AK6 Mineral
Resource (2009)
Tonnes
(000,000’s)
Grade
(cpht)
M Carats
(+1 mm)
Value
(USD/ct)
Indicated Resource
(to 372m)
40 22 8.9 153
Inferred Resource
(372-758m)
31 19 6 139
1817-18 May 2016 |
KAROWE PRODUCTION PERFORMANCE
A proven large stone producer
2015 large stone recoveries:
20 greater than 200cts
7 greater than 300cts
Three exceptional stones
recovered from South Lobe in
November 2015, including
world’s second largest
diamond: 1,111cts Type IIa
Lesedi La Rona
Year
Tonnes
mined
(000,000’s)
Tonnes
treated
(000,000’s)
Carats
recovered
Grade
(cpht)
Ave
$/ct
sold
Stones
>10.8ct
s
2015 3.18 2.24 365,690 16.3 593 727
2014 3.32 2.42 430,292 17.7 644 815
2013 3.94 2.35 440,751 18.8 411 732
Source: Lucara
Operating costs are USD33-35 per tonne treated
Lobes
1917-18 May 2016 |
REFLECTIONS ON AK6
Quality and abundance of large
diamonds initially
underestimated
Type IIa diamonds typically
colourless and extremely
transparent (notable examples
are the Cullinan and Koh-i-Noor)
Valuation models: market tender
vs. price book
Joint Venture dynamics: different
perspectives; funding structure
Fit-for-purpose approach to plant
design
Risk modelling / simulations
Impact of global events:
timing is crucial
Diamond value
♦ Type IIa diamonds recovered during bulk sampling
♦ Abundance of Type II and larger diamonds inadequately
considered in initial valuations
♦ Diamond value underestimated in financial modelling
♦ Karowe consistently delivering large and exceptional stones
Joint Venture
♦ Agreement signed ahead of first bulk sampling results
♦ JV operated by a major
♦ Substantial variance in
› Risk appetite
› Plant design philosophy
› Capital estimates
› Project economics
Economic context
♦ Global Financial Crisis
♦ Change in De Beers’ strategy
♦ Investors’ reluctance to fund a project deemed marginal
2017-18 May 2016 |
AN ALLUVIAL CASE STUDY: SAXENDRIFT MINE
Alluvial diamond operation on
the south bank of the Orange
River, 160 km from Kimberley
Mined by TransHex in 2000-6
Purchased by Rockwell
Diamonds (RDI) in 2008
LoM extended by acquisition of
Saxendrift Extension in 2012
First full SA implementation of
Bourevestnik bulk X-Ray
technology in operational
environment
Saxendrift Mine has produced
numerous +100ct stones,
including the Alana (169cts)
and the Rockwell (287cts)
2117-18 May 2016 |
SAXENDRIFT MINE
Three terrace complexes with
associated palaeochannel
depositional packages identified
on Saxendrift Mine:
Brakfontein Hill (“BHC”)
Saxendrift Hill (“SHC”)
Saxendrift River (“SRC”)
Saxendrift project properties
extend over 5,120.55ha,
comprising both Mining Rights
and Prospecting Rights
Saxendrift Mine also includes
Kwartelspan Complex (KPC),
contiguous to the east
Saxendrift River
Complex (SRC)
Saxendrift Hill Complex
(SHC)
Brakfontein Hill Complex
(BHC)
2217-18 May 2016 |
SAXENDRIFT HISTORY
Early
artisanal
diggings in
mid 1920’s
98,000cts
recovered
Hard
calcrete
cover, poor
returns
Diggings end
by 1950
Mapping and
bulk
sampling by
Broadacres,
Moonstone
NCDM&E
operating
Saxendrift,
Brakfontein
Gem buys
NCDM&E
(1998)
TransHex,
Gem merge
(1999)
TransHex
acquires
permit (2000)
Saxendrift
Mine
commissioned
MOR
exploration
2001: 216ct
stone found
2003:
45,000$/ct for
blue diamond
Saxendrift
put on C&M
76,803cts
produced
RDI buys
Saxendrift
(2008)
New plant
installed
BHC bulk
sampling
(2008-9) and
trial mining
(2009-10)
BHC mining
(2011-2015)
SRC bulk
sampling
(2012-14)
SHC bulk
sampling
(2013-14)
KPC bulk
sampling
(2014)
RC drilling
for volume
estimations
(2015)
1920-50’s 2006-101980-90’s
Early digging activities dating
back to 1920’s-1950’s
Bulk sampling in 1980’s-90’s
Formal mining in late 1990’s
Blasting and earthmoving
equipment used to rip and
remove hard calcrete
Mined by TransHex since
2000, Rockwell since 2008
Concurrent bulk-sampling and
mining since late-2000’s
Drillhole material from volume
estimation not sampled for
diamonds (low grade)
2000-5 2011-16
Source: Rockwell, Explorations Unlimited
2317-18 May 2016 |
SAXENDRIFT BULK SAMPLING / TRIAL MINING (2008-2014)
Due to the low grades and large
stone sizes in alluvial diamond
deposits, bulk samples are
collected and processed to
determine in-situ grades
Recovered diamonds are sold
on the open market to determine
realisable value
Mining in one area of an alluvial
diamond mine can occur
concurrently with trial-mining
and/or bulk-sampling operations
in other areas
The transition to trial mining and
onto production mining can be
seamless
Area Volume (m3) Carats
Grade
(ct/100m3)
Stones
Size
(ct/st)
Average
value
(USD/ct)
BHC
194,287
2,398,009
2,436.73
14,073.49
1.25
0.62
1,414 (2009)
1,956 (2010)
SRC
2,218,210 13,523.10 0.61 3,089 4.38 1,726 (2014)
SHC
1,007,781 4,209.27 0.42 761 5.53 1,904 (2014)
KPC
80,590 450.62 0.57 187 2.41 1,072 (2014)
Source: Rockwell, Explorations Unlimited
2417-18 May 2016 |
SAXENDRIFT MINERAL RESOURCE
0
500
1000
1500
2000
2500
3000
0
2,000,000
4,000,000
6,000,000
8,000,000
10,000,000
12,000,000
14,000,000
2007 2009 2010 2012 2014 2015
USD/ct
Volume(m3)
MINERAL RESOURCE ESTIMATES
Inferred Indicated Value
2007 third party Mineral
Resource estimate re-modelled
in 2009 to Rockwell’s group
standards: drop in volumes,
increase in grades
Change in mining method in
2010 (entire sequence mined)
explains increase in volumes
and drop in grade
Bottom cut-off size increased
from 2mm to 5mm in 2011
(fewer carats recovered)
Upgrade of Inferred to Indicated
Resource in 2012 due to
proximity to mining face
Two-year moving average
of value from 2013
GFC
BCOS 5mm
Inf Res upgrade
0.68
0.41 1.01
0.72
0.66
0.56
0.47
0.47
0.45
0.53
0.42
0.5
RDI
model
Mining
method
Grade
2517-18 May 2016 |
SAXENDRIFT PRODUCTION PERFORMANCE
Recovered grades in line with
modelled grades
Rigour applied to resource
modelling (and NI 43-101
reporting) leads to consistent
production performance
Mining feedback validates
resource assessment
Optimised EMV fleet is
paramount to operational
performance
Notable recoveries in 2014-15
included 6 stones over 100cts
Year
Volume treated
(m3)
Carats
recovered
Grade
(cts/100m3)
Ave $/ct
sold
2015 2,559,000 10,442 0.41 2,363
2014 2,296,000 12,701 0.55 2,338
2013 1,775,130 8,373 0.47 1,918
2012 1,469,215 6,944 0.47 2,444
2011 1,449,875 6,705 0.46 2,003
2010 1,216,503 8834 0.73 1968
2009 194,287 2,437 1.18 1,767
0
500
1000
1500
2000
2500
3000
3500
0
100000
200000
300000
400000
500000
600000
700000
800000
Q1-F14 Q2-F14 Q3-F14 Q4-F14 Q1-F15 Q2-F15 Q3-F15 Q4-F15
USD/ct
Volume(m3)
Saxendrift production 2014-15
Volume processed Value
Source: Rockwelll AR’s
0.39
Grade
0.54 0.76 0.50 0.64 0.34 0.39 0.32
2617-18 May 2016 |
IMPLICATIONS FOR INVESTORS AND REPORTING
2717-18 May 2016 |
JUNIOR FUNDING
Equity financing is the juniors’
dominant source of funding,
while the majority of mining
debt financings are undertaken
by large market cap companies
In 2013, 62% of global mining
equity financing was raised on
TSX and TSX-V
ASX, TSX and AIM are funding
junior exploration and
development companies
Juniors are responsible for the
majority of further issues,
reflecting their need for cash to
fund exploration and feasibility
studies
Source: PDAC, PWC
2817-18 May 2016 |
IMPLICATIONS FOR INVESTORS
Mining investors view favourably:
♦ Companies with experienced management teams, exploring
in prospective areas and with reasonable project timelines
♦ The use of new technology, as it demonstrates an ability to
work faster and cost-effectively
♦ Clarity on a company’s position with respect to key drivers
of future value (the investors’ reward lies in the increase in
share price)
♦ Companies who “graduate” from the venture to the main
board of a stock exchange, as this implies additional
corporate governance and due diligence effort
Mining investors view less favourably:
♦ New discoveries without a demonstrable way to mine the
mineral resource economically
♦ Junior miners with little or no track record, especially so
during cyclical mining downturns
Typically, juniors have to raise
equity to fund their
exploration/evaluation
activities all the way to
feasibility stage (whereas
majors are able to self-fund
this process)
Attracting and retaining
investors’ interest requires an
ongoing effort
Information of relevance to
investors is disclosed through
public reporting
Caution must be exercised not
to overstate the potential of a
project in an effort to keep
investors’ interest alive
Source: Canadian Mining Journal. PWC, Pinnacle Digest
2917-18 May 2016 |
IMPLICATIONS FOR PUBLIC REPORTING
Public reporting is expected to:
♦ Provide high levels of assurance to accompany disclosure
of information of a financial or operational nature
♦ Provide clearly defined and highly reliable measures that
have the potential to influence markets
♦ Include non-GAAP performance measures - such as
production volumes, resources/reserves and cash costs –
which investors use in their analyses
♦ Report accurately on responsible operational activities in an
unambiguous, timely fashion
Accurate and transparent reports are critical in securing
subscriptions to further share issues, as IPOs generally raise
funds to cover only the first 2-3 years of exploration
Juniors are subject to a high
degree of public scrutiny and
assurance (majors tend to
conduct these internally)
Mineral resource estimates
and other non-GAAP
measures are increasingly
scrutinised by investors
Shortened project timeframes
are appealing, as long as
accuracy of information is not
compromised
Relevant and accurate
reporting helps to sustain
interest throughout the
lifecycle of a project
3017-18 May 2016 |
CONCLUDING REMARKS
Mineral resource development is a complex and costly process
with a high degree of risk
Technology has a key role to play in the risk reduction process
Plant design philosophy can make or break a project
Experienced technical management is probably the most
important critical success factor
In order to comply with regulatory requirements, project results
must be reported within accepted frameworks
Stringent reporting parameters don’t always allow for the full
characterisation of future potential of a mining project
(commentary is just as important)
Accepted reporting standards are primarily designed to protect
investors from misrepresentation of resource value
There is a fine line between compliance and excessive caution,
which may result in conservative understatements of future
potential
Reporting and regulatory
requirements place a
significant burden of
compliance on juniors
However, relevance and
transparency of reporting is
increasingly important in
attracting junior funding
Rigour and diligence applied to
resource development pays off
in resource performance and
repeatability of results
Accelerated project timeframes
are appealing, but there is no
room for compromise on
resource assessment

More Related Content

What's hot

Rd preso feb
Rd preso febRd preso feb
Rd preso feb
Patrick Balit
 
Rd preso jan
Rd preso janRd preso jan
Rd preso jan
Patrick Balit
 
Jan 2022 riley gold final
Jan 2022 riley gold finalJan 2022 riley gold final
Jan 2022 riley gold final
ZhalaRahim1
 
Riley Gold (TSXV: RLYG) Corporate Presentation | February 2022
Riley Gold (TSXV: RLYG) Corporate Presentation | February 2022Riley Gold (TSXV: RLYG) Corporate Presentation | February 2022
Riley Gold (TSXV: RLYG) Corporate Presentation | February 2022
AnnaSokolova11
 
Gold 2013 Sydney - Middle Island Resources ASX:MDI
Gold 2013 Sydney - Middle Island Resources ASX:MDIGold 2013 Sydney - Middle Island Resources ASX:MDI
Gold 2013 Sydney - Middle Island Resources ASX:MDI
Symposium
 
Sage june 2013__investor_presentation
Sage june 2013__investor_presentationSage june 2013__investor_presentation
Sage june 2013__investor_presentationSagegold
 
CRIRSCO Botswana 26 March Presentation
CRIRSCO Botswana 26 March PresentationCRIRSCO Botswana 26 March Presentation
CRIRSCO Botswana 26 March Presentation
roger_dixon
 
Rd preso jan
Rd preso janRd preso jan
Rd preso jan
Patrick Balit
 
Hawthorne Gold Corp Corporate Presentation
Hawthorne Gold Corp Corporate PresentationHawthorne Gold Corp Corporate Presentation
Hawthorne Gold Corp Corporate PresentationAdnet Communications
 
Investor Presentation - September 2014
Investor Presentation - September 2014Investor Presentation - September 2014
Investor Presentation - September 2014
Sagegold
 
Cxb corp pres_nov2016_new
Cxb corp pres_nov2016_newCxb corp pres_nov2016_new
Cxb corp pres_nov2016_new
Adnet Communications
 
Rd preso dec
Rd preso decRd preso dec
Rd preso dec
Patrick Balit
 
Tri star apr 2021 ppt-original
Tri star   apr 2021 ppt-originalTri star   apr 2021 ppt-original
Tri star apr 2021 ppt-original
AdnetNew
 
Cascada updated corporate presentation september 2021
Cascada updated corporate presentation september 2021Cascada updated corporate presentation september 2021
Cascada updated corporate presentation september 2021
ZhalaRahim
 
International Reporting Standards for Exploration Results, Mineral Resources ...
International Reporting Standards for Exploration Results, Mineral Resources ...International Reporting Standards for Exploration Results, Mineral Resources ...
International Reporting Standards for Exploration Results, Mineral Resources ...
roger_dixon
 
Esperanza Resources Corp. Presentation - A Clear Path To Gold
Esperanza Resources Corp. Presentation - A Clear Path To GoldEsperanza Resources Corp. Presentation - A Clear Path To Gold
Esperanza Resources Corp. Presentation - A Clear Path To GoldEsperanzaResources
 
Fm corp presentation update september
Fm corp presentation update septemberFm corp presentation update september
Fm corp presentation update september
ForbesandManhattan
 
Rd preso jan
Rd preso janRd preso jan
Rd preso jan
Patrick Balit
 
The role of Geoscientists in a Junior Exploration Company
The role of Geoscientists in a Junior Exploration CompanyThe role of Geoscientists in a Junior Exploration Company
The role of Geoscientists in a Junior Exploration Company
James AH Campbell
 
Glen Eagle Resources Fact sheet + Presentation
Glen Eagle Resources Fact sheet + PresentationGlen Eagle Resources Fact sheet + Presentation
Glen Eagle Resources Fact sheet + Presentation
MomentumPR
 

What's hot (20)

Rd preso feb
Rd preso febRd preso feb
Rd preso feb
 
Rd preso jan
Rd preso janRd preso jan
Rd preso jan
 
Jan 2022 riley gold final
Jan 2022 riley gold finalJan 2022 riley gold final
Jan 2022 riley gold final
 
Riley Gold (TSXV: RLYG) Corporate Presentation | February 2022
Riley Gold (TSXV: RLYG) Corporate Presentation | February 2022Riley Gold (TSXV: RLYG) Corporate Presentation | February 2022
Riley Gold (TSXV: RLYG) Corporate Presentation | February 2022
 
Gold 2013 Sydney - Middle Island Resources ASX:MDI
Gold 2013 Sydney - Middle Island Resources ASX:MDIGold 2013 Sydney - Middle Island Resources ASX:MDI
Gold 2013 Sydney - Middle Island Resources ASX:MDI
 
Sage june 2013__investor_presentation
Sage june 2013__investor_presentationSage june 2013__investor_presentation
Sage june 2013__investor_presentation
 
CRIRSCO Botswana 26 March Presentation
CRIRSCO Botswana 26 March PresentationCRIRSCO Botswana 26 March Presentation
CRIRSCO Botswana 26 March Presentation
 
Rd preso jan
Rd preso janRd preso jan
Rd preso jan
 
Hawthorne Gold Corp Corporate Presentation
Hawthorne Gold Corp Corporate PresentationHawthorne Gold Corp Corporate Presentation
Hawthorne Gold Corp Corporate Presentation
 
Investor Presentation - September 2014
Investor Presentation - September 2014Investor Presentation - September 2014
Investor Presentation - September 2014
 
Cxb corp pres_nov2016_new
Cxb corp pres_nov2016_newCxb corp pres_nov2016_new
Cxb corp pres_nov2016_new
 
Rd preso dec
Rd preso decRd preso dec
Rd preso dec
 
Tri star apr 2021 ppt-original
Tri star   apr 2021 ppt-originalTri star   apr 2021 ppt-original
Tri star apr 2021 ppt-original
 
Cascada updated corporate presentation september 2021
Cascada updated corporate presentation september 2021Cascada updated corporate presentation september 2021
Cascada updated corporate presentation september 2021
 
International Reporting Standards for Exploration Results, Mineral Resources ...
International Reporting Standards for Exploration Results, Mineral Resources ...International Reporting Standards for Exploration Results, Mineral Resources ...
International Reporting Standards for Exploration Results, Mineral Resources ...
 
Esperanza Resources Corp. Presentation - A Clear Path To Gold
Esperanza Resources Corp. Presentation - A Clear Path To GoldEsperanza Resources Corp. Presentation - A Clear Path To Gold
Esperanza Resources Corp. Presentation - A Clear Path To Gold
 
Fm corp presentation update september
Fm corp presentation update septemberFm corp presentation update september
Fm corp presentation update september
 
Rd preso jan
Rd preso janRd preso jan
Rd preso jan
 
The role of Geoscientists in a Junior Exploration Company
The role of Geoscientists in a Junior Exploration CompanyThe role of Geoscientists in a Junior Exploration Company
The role of Geoscientists in a Junior Exploration Company
 
Glen Eagle Resources Fact sheet + Presentation
Glen Eagle Resources Fact sheet + PresentationGlen Eagle Resources Fact sheet + Presentation
Glen Eagle Resources Fact sheet + Presentation
 

Viewers also liked

Livro redes e_manutencao
Livro redes e_manutencaoLivro redes e_manutencao
Livro redes e_manutencao
flaviobtmg
 
BettyHahnPhotographyorMaybeNotYatesEditorEssay
BettyHahnPhotographyorMaybeNotYatesEditorEssayBettyHahnPhotographyorMaybeNotYatesEditorEssay
BettyHahnPhotographyorMaybeNotYatesEditorEssaySteve Yates
 
159343618 sales-case-digests-set1-1
159343618 sales-case-digests-set1-1159343618 sales-case-digests-set1-1
159343618 sales-case-digests-set1-1
homeworkping7
 
60371653 crim-cases
60371653 crim-cases60371653 crim-cases
60371653 crim-cases
homeworkping4
 
Tableaux de conversion des tailles
Tableaux de conversion des taillesTableaux de conversion des tailles
Tableaux de conversion des tailles
WebInterpret SAS
 
A perspective on The South African diamond mining industry
A perspective on The South African diamond mining industryA perspective on The South African diamond mining industry
A perspective on The South African diamond mining industry
James AH Campbell
 
Rockwell Diamonds Mining Indaba 2012 Presentation
Rockwell Diamonds Mining Indaba 2012 PresentationRockwell Diamonds Mining Indaba 2012 Presentation
Rockwell Diamonds Mining Indaba 2012 Presentation
James AH Campbell
 
Referencial de educacao_para_o_desenvolvimento
Referencial de educacao_para_o_desenvolvimentoReferencial de educacao_para_o_desenvolvimento
Referencial de educacao_para_o_desenvolvimento
psicologiaestoi
 

Viewers also liked (10)

Livro redes e_manutencao
Livro redes e_manutencaoLivro redes e_manutencao
Livro redes e_manutencao
 
BettyHahnPhotographyorMaybeNotYatesEditorEssay
BettyHahnPhotographyorMaybeNotYatesEditorEssayBettyHahnPhotographyorMaybeNotYatesEditorEssay
BettyHahnPhotographyorMaybeNotYatesEditorEssay
 
159343618 sales-case-digests-set1-1
159343618 sales-case-digests-set1-1159343618 sales-case-digests-set1-1
159343618 sales-case-digests-set1-1
 
8. Education 2.5me - RTHK CM Lui
8. Education 2.5me - RTHK CM Lui8. Education 2.5me - RTHK CM Lui
8. Education 2.5me - RTHK CM Lui
 
60371653 crim-cases
60371653 crim-cases60371653 crim-cases
60371653 crim-cases
 
Tableaux de conversion des tailles
Tableaux de conversion des taillesTableaux de conversion des tailles
Tableaux de conversion des tailles
 
A perspective on The South African diamond mining industry
A perspective on The South African diamond mining industryA perspective on The South African diamond mining industry
A perspective on The South African diamond mining industry
 
El método iii
El método iiiEl método iii
El método iii
 
Rockwell Diamonds Mining Indaba 2012 Presentation
Rockwell Diamonds Mining Indaba 2012 PresentationRockwell Diamonds Mining Indaba 2012 Presentation
Rockwell Diamonds Mining Indaba 2012 Presentation
 
Referencial de educacao_para_o_desenvolvimento
Referencial de educacao_para_o_desenvolvimentoReferencial de educacao_para_o_desenvolvimento
Referencial de educacao_para_o_desenvolvimento
 

Similar to Samcode/Samval Keynote Presentation 2016

CRIRSCO EGRC UNFC Workshop April 23 2013, Geneva Switzerland
CRIRSCO EGRC UNFC Workshop April 23 2013, Geneva SwitzerlandCRIRSCO EGRC UNFC Workshop April 23 2013, Geneva Switzerland
CRIRSCO EGRC UNFC Workshop April 23 2013, Geneva Switzerland
roger_dixon
 
North Arrow Corporate Presentation (december 2021) final
North Arrow Corporate Presentation (december 2021) finalNorth Arrow Corporate Presentation (december 2021) final
North Arrow Corporate Presentation (december 2021) final
narminerals
 
Dgc 16 04_07 - laurentian 1x1 presentation
Dgc 16 04_07 - laurentian 1x1 presentationDgc 16 04_07 - laurentian 1x1 presentation
Dgc 16 04_07 - laurentian 1x1 presentation
detour-gold
 
Nar pdac investor presentation 2019 (final)
Nar pdac investor presentation 2019 (final)Nar pdac investor presentation 2019 (final)
Nar pdac investor presentation 2019 (final)
narminerals
 
North Arrow Minerals Corporate Overview - May24, 2017
North Arrow Minerals Corporate Overview - May24, 2017North Arrow Minerals Corporate Overview - May24, 2017
North Arrow Minerals Corporate Overview - May24, 2017
narminerals
 
Nap investor presentation april 2014 updated
Nap investor presentation april 2014 updatedNap investor presentation april 2014 updated
Nap investor presentation april 2014 updatedNorth American Palladium
 
Vancouver Resource Investment Conference
Vancouver Resource Investment ConferenceVancouver Resource Investment Conference
Vancouver Resource Investment Conference
Lake Shore Gold
 
SkyHarbour Investor Presentation
SkyHarbour Investor PresentationSkyHarbour Investor Presentation
SkyHarbour Investor Presentation
Company Spotlight
 
Corporate Presentation
Corporate PresentationCorporate Presentation
Corporate Presentation
Company Spotlight
 
Exeter presentation nov_web
Exeter presentation nov_webExeter presentation nov_web
Exeter presentation nov_web
Exeter Resource Corporation
 
CEIP Definitive Feasibility Study Community Information Sessions April 2014
CEIP Definitive Feasibility Study Community Information Sessions April 2014CEIP Definitive Feasibility Study Community Information Sessions April 2014
CEIP Definitive Feasibility Study Community Information Sessions April 2014
Iron_Road_Limited
 
Nap investor presentation march 2015
Nap investor presentation march 2015Nap investor presentation march 2015
Nap investor presentation march 2015
North American Palladium
 
Iron Road - Australia Business Week in India Presentation
Iron Road - Australia Business Week in India PresentationIron Road - Australia Business Week in India Presentation
Iron Road - Australia Business Week in India Presentation
Iron_Road_Limited
 
December Presentation
December PresentationDecember Presentation
December Presentation
Exeter Resource Corporation
 
Precious Metals Summit, Zurich Switzerland
Precious Metals Summit, Zurich SwitzerlandPrecious Metals Summit, Zurich Switzerland
Precious Metals Summit, Zurich Switzerland
Lake Shore Gold
 
NAP Investor Presentation August 2014
NAP Investor Presentation August 2014NAP Investor Presentation August 2014
NAP Investor Presentation August 2014
North American Palladium
 
Forsys Investor Presentation October 2013
Forsys Investor Presentation   October 2013Forsys Investor Presentation   October 2013
Forsys Investor Presentation October 2013
TMX Equicom
 
Denver Gold Forum 2014
Denver Gold Forum 2014Denver Gold Forum 2014
Denver Gold Forum 2014
NewmontMining
 

Similar to Samcode/Samval Keynote Presentation 2016 (20)

CRIRSCO EGRC UNFC Workshop April 23 2013, Geneva Switzerland
CRIRSCO EGRC UNFC Workshop April 23 2013, Geneva SwitzerlandCRIRSCO EGRC UNFC Workshop April 23 2013, Geneva Switzerland
CRIRSCO EGRC UNFC Workshop April 23 2013, Geneva Switzerland
 
North Arrow Corporate Presentation (december 2021) final
North Arrow Corporate Presentation (december 2021) finalNorth Arrow Corporate Presentation (december 2021) final
North Arrow Corporate Presentation (december 2021) final
 
Dgc 16 04_07 - laurentian 1x1 presentation
Dgc 16 04_07 - laurentian 1x1 presentationDgc 16 04_07 - laurentian 1x1 presentation
Dgc 16 04_07 - laurentian 1x1 presentation
 
Nar pdac investor presentation 2019 (final)
Nar pdac investor presentation 2019 (final)Nar pdac investor presentation 2019 (final)
Nar pdac investor presentation 2019 (final)
 
North Arrow Minerals Corporate Overview - May24, 2017
North Arrow Minerals Corporate Overview - May24, 2017North Arrow Minerals Corporate Overview - May24, 2017
North Arrow Minerals Corporate Overview - May24, 2017
 
Nap investor presentation april 2014 updated
Nap investor presentation april 2014 updatedNap investor presentation april 2014 updated
Nap investor presentation april 2014 updated
 
Vancouver Resource Investment Conference
Vancouver Resource Investment ConferenceVancouver Resource Investment Conference
Vancouver Resource Investment Conference
 
SkyHarbour Investor Presentation
SkyHarbour Investor PresentationSkyHarbour Investor Presentation
SkyHarbour Investor Presentation
 
Corporate Presentation
Corporate PresentationCorporate Presentation
Corporate Presentation
 
Investor Presentation
Investor PresentationInvestor Presentation
Investor Presentation
 
Exeter presentation nov_web
Exeter presentation nov_webExeter presentation nov_web
Exeter presentation nov_web
 
CEIP Definitive Feasibility Study Community Information Sessions April 2014
CEIP Definitive Feasibility Study Community Information Sessions April 2014CEIP Definitive Feasibility Study Community Information Sessions April 2014
CEIP Definitive Feasibility Study Community Information Sessions April 2014
 
Nap investor presentation march 2015
Nap investor presentation march 2015Nap investor presentation march 2015
Nap investor presentation march 2015
 
Iron Road - Australia Business Week in India Presentation
Iron Road - Australia Business Week in India PresentationIron Road - Australia Business Week in India Presentation
Iron Road - Australia Business Week in India Presentation
 
December Presentation
December PresentationDecember Presentation
December Presentation
 
Precious Metals Summit, Zurich Switzerland
Precious Metals Summit, Zurich SwitzerlandPrecious Metals Summit, Zurich Switzerland
Precious Metals Summit, Zurich Switzerland
 
CLF November 2010 Investor Presentation
CLF November 2010 Investor PresentationCLF November 2010 Investor Presentation
CLF November 2010 Investor Presentation
 
NAP Investor Presentation August 2014
NAP Investor Presentation August 2014NAP Investor Presentation August 2014
NAP Investor Presentation August 2014
 
Forsys Investor Presentation October 2013
Forsys Investor Presentation   October 2013Forsys Investor Presentation   October 2013
Forsys Investor Presentation October 2013
 
Denver Gold Forum 2014
Denver Gold Forum 2014Denver Gold Forum 2014
Denver Gold Forum 2014
 

More from James AH Campbell

Diamond exploration, mining, financing and driving entrepreneurial behaviour.
Diamond exploration, mining, financing and driving entrepreneurial behaviour.Diamond exploration, mining, financing and driving entrepreneurial behaviour.
Diamond exploration, mining, financing and driving entrepreneurial behaviour.
James AH Campbell
 
The Economic Diamond Potential of the Kalahari of Botswana
The Economic Diamond Potential of the Kalahari of BotswanaThe Economic Diamond Potential of the Kalahari of Botswana
The Economic Diamond Potential of the Kalahari of Botswana
James AH Campbell
 
Corporate Governance for South African Mining Companies (a practitioner's view)
Corporate Governance for South African Mining Companies (a practitioner's view)Corporate Governance for South African Mining Companies (a practitioner's view)
Corporate Governance for South African Mining Companies (a practitioner's view)
James AH Campbell
 
Attracting Funds to Develop the Diamond Potential of Southern Africa
Attracting Funds to Develop the Diamond Potential of Southern AfricaAttracting Funds to Develop the Diamond Potential of Southern Africa
Attracting Funds to Develop the Diamond Potential of Southern Africa
James AH Campbell
 
Junior Indaba June 2023 Myth Busting Green Metals
Junior Indaba June 2023 Myth Busting Green MetalsJunior Indaba June 2023 Myth Busting Green Metals
Junior Indaba June 2023 Myth Busting Green Metals
James AH Campbell
 
Prospecting for Solutions: Challenges facing the South African Mining Industry
Prospecting for Solutions: Challenges facing the South African Mining IndustryProspecting for Solutions: Challenges facing the South African Mining Industry
Prospecting for Solutions: Challenges facing the South African Mining Industry
James AH Campbell
 
Tirisano 43-101_2010
Tirisano 43-101_2010Tirisano 43-101_2010
Tirisano 43-101_2010
James AH Campbell
 
Botswana Diamonds - 5 Oct 22 - FEQ Buy Note TP 6.8p.pdf
Botswana Diamonds - 5 Oct 22 - FEQ Buy Note TP 6.8p.pdfBotswana Diamonds - 5 Oct 22 - FEQ Buy Note TP 6.8p.pdf
Botswana Diamonds - 5 Oct 22 - FEQ Buy Note TP 6.8p.pdf
James AH Campbell
 
Is there any overlap between Corporate Governance & Public Reporting?
Is there any overlap between Corporate Governance & Public Reporting?Is there any overlap between Corporate Governance & Public Reporting?
Is there any overlap between Corporate Governance & Public Reporting?
James AH Campbell
 
Prospecting for Solutions: Challenges facing the South African Mining Industry
Prospecting for Solutions: Challenges facing the South African Mining IndustryProspecting for Solutions: Challenges facing the South African Mining Industry
Prospecting for Solutions: Challenges facing the South African Mining Industry
James AH Campbell
 
Prospecting for Solutions: Challenges facing the South African Mining Industry
Prospecting for Solutions: Challenges facing the South African Mining IndustryProspecting for Solutions: Challenges facing the South African Mining Industry
Prospecting for Solutions: Challenges facing the South African Mining Industry
James AH Campbell
 
Corporate Governance for South African Mining Companies (a practitioner's view)
Corporate Governance for South African Mining Companies (a practitioner's view)Corporate Governance for South African Mining Companies (a practitioner's view)
Corporate Governance for South African Mining Companies (a practitioner's view)
James AH Campbell
 
Africa Report BOD 6 Sept 2022.pdf
Africa Report BOD 6 Sept 2022.pdfAfrica Report BOD 6 Sept 2022.pdf
Africa Report BOD 6 Sept 2022.pdf
James AH Campbell
 
The discovery and evaluation of AK6
The discovery and evaluation of AK6The discovery and evaluation of AK6
The discovery and evaluation of AK6
James AH Campbell
 
Southern Africa deemed highly prospective for diamonds – Nadine Ramdass – Bos...
Southern Africa deemed highly prospective for diamonds – Nadine Ramdass – Bos...Southern Africa deemed highly prospective for diamonds – Nadine Ramdass – Bos...
Southern Africa deemed highly prospective for diamonds – Nadine Ramdass – Bos...
James AH Campbell
 
The Future of Botswana's Diamond Resources
The Future of Botswana's Diamond ResourcesThe Future of Botswana's Diamond Resources
The Future of Botswana's Diamond Resources
James AH Campbell
 
Botswana Diamonds starting to shine.
Botswana Diamonds starting to shine.Botswana Diamonds starting to shine.
Botswana Diamonds starting to shine.
James AH Campbell
 
Father of the Bride speech
Father of the Bride speechFather of the Bride speech
Father of the Bride speech
James AH Campbell
 
CPR Bat Shelomo
CPR Bat ShelomoCPR Bat Shelomo
CPR Bat Shelomo
James AH Campbell
 
Volcanoes Presentation
Volcanoes Presentation Volcanoes Presentation
Volcanoes Presentation
James AH Campbell
 

More from James AH Campbell (20)

Diamond exploration, mining, financing and driving entrepreneurial behaviour.
Diamond exploration, mining, financing and driving entrepreneurial behaviour.Diamond exploration, mining, financing and driving entrepreneurial behaviour.
Diamond exploration, mining, financing and driving entrepreneurial behaviour.
 
The Economic Diamond Potential of the Kalahari of Botswana
The Economic Diamond Potential of the Kalahari of BotswanaThe Economic Diamond Potential of the Kalahari of Botswana
The Economic Diamond Potential of the Kalahari of Botswana
 
Corporate Governance for South African Mining Companies (a practitioner's view)
Corporate Governance for South African Mining Companies (a practitioner's view)Corporate Governance for South African Mining Companies (a practitioner's view)
Corporate Governance for South African Mining Companies (a practitioner's view)
 
Attracting Funds to Develop the Diamond Potential of Southern Africa
Attracting Funds to Develop the Diamond Potential of Southern AfricaAttracting Funds to Develop the Diamond Potential of Southern Africa
Attracting Funds to Develop the Diamond Potential of Southern Africa
 
Junior Indaba June 2023 Myth Busting Green Metals
Junior Indaba June 2023 Myth Busting Green MetalsJunior Indaba June 2023 Myth Busting Green Metals
Junior Indaba June 2023 Myth Busting Green Metals
 
Prospecting for Solutions: Challenges facing the South African Mining Industry
Prospecting for Solutions: Challenges facing the South African Mining IndustryProspecting for Solutions: Challenges facing the South African Mining Industry
Prospecting for Solutions: Challenges facing the South African Mining Industry
 
Tirisano 43-101_2010
Tirisano 43-101_2010Tirisano 43-101_2010
Tirisano 43-101_2010
 
Botswana Diamonds - 5 Oct 22 - FEQ Buy Note TP 6.8p.pdf
Botswana Diamonds - 5 Oct 22 - FEQ Buy Note TP 6.8p.pdfBotswana Diamonds - 5 Oct 22 - FEQ Buy Note TP 6.8p.pdf
Botswana Diamonds - 5 Oct 22 - FEQ Buy Note TP 6.8p.pdf
 
Is there any overlap between Corporate Governance & Public Reporting?
Is there any overlap between Corporate Governance & Public Reporting?Is there any overlap between Corporate Governance & Public Reporting?
Is there any overlap between Corporate Governance & Public Reporting?
 
Prospecting for Solutions: Challenges facing the South African Mining Industry
Prospecting for Solutions: Challenges facing the South African Mining IndustryProspecting for Solutions: Challenges facing the South African Mining Industry
Prospecting for Solutions: Challenges facing the South African Mining Industry
 
Prospecting for Solutions: Challenges facing the South African Mining Industry
Prospecting for Solutions: Challenges facing the South African Mining IndustryProspecting for Solutions: Challenges facing the South African Mining Industry
Prospecting for Solutions: Challenges facing the South African Mining Industry
 
Corporate Governance for South African Mining Companies (a practitioner's view)
Corporate Governance for South African Mining Companies (a practitioner's view)Corporate Governance for South African Mining Companies (a practitioner's view)
Corporate Governance for South African Mining Companies (a practitioner's view)
 
Africa Report BOD 6 Sept 2022.pdf
Africa Report BOD 6 Sept 2022.pdfAfrica Report BOD 6 Sept 2022.pdf
Africa Report BOD 6 Sept 2022.pdf
 
The discovery and evaluation of AK6
The discovery and evaluation of AK6The discovery and evaluation of AK6
The discovery and evaluation of AK6
 
Southern Africa deemed highly prospective for diamonds – Nadine Ramdass – Bos...
Southern Africa deemed highly prospective for diamonds – Nadine Ramdass – Bos...Southern Africa deemed highly prospective for diamonds – Nadine Ramdass – Bos...
Southern Africa deemed highly prospective for diamonds – Nadine Ramdass – Bos...
 
The Future of Botswana's Diamond Resources
The Future of Botswana's Diamond ResourcesThe Future of Botswana's Diamond Resources
The Future of Botswana's Diamond Resources
 
Botswana Diamonds starting to shine.
Botswana Diamonds starting to shine.Botswana Diamonds starting to shine.
Botswana Diamonds starting to shine.
 
Father of the Bride speech
Father of the Bride speechFather of the Bride speech
Father of the Bride speech
 
CPR Bat Shelomo
CPR Bat ShelomoCPR Bat Shelomo
CPR Bat Shelomo
 
Volcanoes Presentation
Volcanoes Presentation Volcanoes Presentation
Volcanoes Presentation
 

Recently uploaded

Enterprise Excellence is Inclusive Excellence.pdf
Enterprise Excellence is Inclusive Excellence.pdfEnterprise Excellence is Inclusive Excellence.pdf
Enterprise Excellence is Inclusive Excellence.pdf
KaiNexus
 
Exploring Patterns of Connection with Social Dreaming
Exploring Patterns of Connection with Social DreamingExploring Patterns of Connection with Social Dreaming
Exploring Patterns of Connection with Social Dreaming
Nicola Wreford-Howard
 
Role of Remote Sensing and Monitoring in Mining
Role of Remote Sensing and Monitoring in MiningRole of Remote Sensing and Monitoring in Mining
Role of Remote Sensing and Monitoring in Mining
Naaraayani Minerals Pvt.Ltd
 
Filing Your Delaware Franchise Tax A Detailed Guide
Filing Your Delaware Franchise Tax A Detailed GuideFiling Your Delaware Franchise Tax A Detailed Guide
Filing Your Delaware Franchise Tax A Detailed Guide
YourLegal Accounting
 
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdfMeas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
dylandmeas
 
Putting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptxPutting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptx
Cynthia Clay
 
Attending a job Interview for B1 and B2 Englsih learners
Attending a job Interview for B1 and B2 Englsih learnersAttending a job Interview for B1 and B2 Englsih learners
Attending a job Interview for B1 and B2 Englsih learners
Erika906060
 
April 2024 Nostalgia Products Newsletter
April 2024 Nostalgia Products NewsletterApril 2024 Nostalgia Products Newsletter
April 2024 Nostalgia Products Newsletter
NathanBaughman3
 
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
taqyed
 
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
BBPMedia1
 
Maksym Vyshnivetskyi: PMO Quality Management (UA)
Maksym Vyshnivetskyi: PMO Quality Management (UA)Maksym Vyshnivetskyi: PMO Quality Management (UA)
Maksym Vyshnivetskyi: PMO Quality Management (UA)
Lviv Startup Club
 
20240425_ TJ Communications Credentials_compressed.pdf
20240425_ TJ Communications Credentials_compressed.pdf20240425_ TJ Communications Credentials_compressed.pdf
20240425_ TJ Communications Credentials_compressed.pdf
tjcomstrang
 
Digital Transformation in PLM - WHAT and HOW - for distribution.pdf
Digital Transformation in PLM - WHAT and HOW - for distribution.pdfDigital Transformation in PLM - WHAT and HOW - for distribution.pdf
Digital Transformation in PLM - WHAT and HOW - for distribution.pdf
Jos Voskuil
 
Buy Verified PayPal Account | Buy Google 5 Star Reviews
Buy Verified PayPal Account | Buy Google 5 Star ReviewsBuy Verified PayPal Account | Buy Google 5 Star Reviews
Buy Verified PayPal Account | Buy Google 5 Star Reviews
usawebmarket
 
Taurus Zodiac Sign_ Personality Traits and Sign Dates.pptx
Taurus Zodiac Sign_ Personality Traits and Sign Dates.pptxTaurus Zodiac Sign_ Personality Traits and Sign Dates.pptx
Taurus Zodiac Sign_ Personality Traits and Sign Dates.pptx
my Pandit
 
BeMetals Presentation_May_22_2024 .pdf
BeMetals Presentation_May_22_2024   .pdfBeMetals Presentation_May_22_2024   .pdf
BeMetals Presentation_May_22_2024 .pdf
DerekIwanaka1
 
falcon-invoice-discounting-a-premier-platform-for-investors-in-india
falcon-invoice-discounting-a-premier-platform-for-investors-in-indiafalcon-invoice-discounting-a-premier-platform-for-investors-in-india
falcon-invoice-discounting-a-premier-platform-for-investors-in-india
Falcon Invoice Discounting
 
chapter 10 - excise tax of transfer and business taxation
chapter 10 - excise tax of transfer and business taxationchapter 10 - excise tax of transfer and business taxation
chapter 10 - excise tax of transfer and business taxation
AUDIJEAngelo
 
Accpac to QuickBooks Conversion Navigating the Transition with Online Account...
Accpac to QuickBooks Conversion Navigating the Transition with Online Account...Accpac to QuickBooks Conversion Navigating the Transition with Online Account...
Accpac to QuickBooks Conversion Navigating the Transition with Online Account...
PaulBryant58
 
anas about venice for grade 6f about venice
anas about venice for grade 6f about veniceanas about venice for grade 6f about venice
anas about venice for grade 6f about venice
anasabutalha2013
 

Recently uploaded (20)

Enterprise Excellence is Inclusive Excellence.pdf
Enterprise Excellence is Inclusive Excellence.pdfEnterprise Excellence is Inclusive Excellence.pdf
Enterprise Excellence is Inclusive Excellence.pdf
 
Exploring Patterns of Connection with Social Dreaming
Exploring Patterns of Connection with Social DreamingExploring Patterns of Connection with Social Dreaming
Exploring Patterns of Connection with Social Dreaming
 
Role of Remote Sensing and Monitoring in Mining
Role of Remote Sensing and Monitoring in MiningRole of Remote Sensing and Monitoring in Mining
Role of Remote Sensing and Monitoring in Mining
 
Filing Your Delaware Franchise Tax A Detailed Guide
Filing Your Delaware Franchise Tax A Detailed GuideFiling Your Delaware Franchise Tax A Detailed Guide
Filing Your Delaware Franchise Tax A Detailed Guide
 
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdfMeas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
 
Putting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptxPutting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptx
 
Attending a job Interview for B1 and B2 Englsih learners
Attending a job Interview for B1 and B2 Englsih learnersAttending a job Interview for B1 and B2 Englsih learners
Attending a job Interview for B1 and B2 Englsih learners
 
April 2024 Nostalgia Products Newsletter
April 2024 Nostalgia Products NewsletterApril 2024 Nostalgia Products Newsletter
April 2024 Nostalgia Products Newsletter
 
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
 
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
 
Maksym Vyshnivetskyi: PMO Quality Management (UA)
Maksym Vyshnivetskyi: PMO Quality Management (UA)Maksym Vyshnivetskyi: PMO Quality Management (UA)
Maksym Vyshnivetskyi: PMO Quality Management (UA)
 
20240425_ TJ Communications Credentials_compressed.pdf
20240425_ TJ Communications Credentials_compressed.pdf20240425_ TJ Communications Credentials_compressed.pdf
20240425_ TJ Communications Credentials_compressed.pdf
 
Digital Transformation in PLM - WHAT and HOW - for distribution.pdf
Digital Transformation in PLM - WHAT and HOW - for distribution.pdfDigital Transformation in PLM - WHAT and HOW - for distribution.pdf
Digital Transformation in PLM - WHAT and HOW - for distribution.pdf
 
Buy Verified PayPal Account | Buy Google 5 Star Reviews
Buy Verified PayPal Account | Buy Google 5 Star ReviewsBuy Verified PayPal Account | Buy Google 5 Star Reviews
Buy Verified PayPal Account | Buy Google 5 Star Reviews
 
Taurus Zodiac Sign_ Personality Traits and Sign Dates.pptx
Taurus Zodiac Sign_ Personality Traits and Sign Dates.pptxTaurus Zodiac Sign_ Personality Traits and Sign Dates.pptx
Taurus Zodiac Sign_ Personality Traits and Sign Dates.pptx
 
BeMetals Presentation_May_22_2024 .pdf
BeMetals Presentation_May_22_2024   .pdfBeMetals Presentation_May_22_2024   .pdf
BeMetals Presentation_May_22_2024 .pdf
 
falcon-invoice-discounting-a-premier-platform-for-investors-in-india
falcon-invoice-discounting-a-premier-platform-for-investors-in-indiafalcon-invoice-discounting-a-premier-platform-for-investors-in-india
falcon-invoice-discounting-a-premier-platform-for-investors-in-india
 
chapter 10 - excise tax of transfer and business taxation
chapter 10 - excise tax of transfer and business taxationchapter 10 - excise tax of transfer and business taxation
chapter 10 - excise tax of transfer and business taxation
 
Accpac to QuickBooks Conversion Navigating the Transition with Online Account...
Accpac to QuickBooks Conversion Navigating the Transition with Online Account...Accpac to QuickBooks Conversion Navigating the Transition with Online Account...
Accpac to QuickBooks Conversion Navigating the Transition with Online Account...
 
anas about venice for grade 6f about venice
anas about venice for grade 6f about veniceanas about venice for grade 6f about venice
anas about venice for grade 6f about venice
 

Samcode/Samval Keynote Presentation 2016

  • 1. 117-18 May 2016 | PERSPECTIVES ON DIAMOND RESOURCE DEVELOPMENT AND REGULATORY COMPLIANCE JAMES AH CAMPBELL CEO, ROCKWELL DIAMONDS INC“uncovering the facets of our potential” SAMREC/SAMVAL COMPANION VOLUME CONFERENCE 17-18 MAY 2016
  • 2. 217-18 May 2016 | OUTLINE • PUBLIC REPORTING • MINERAL REPORTING STANDARDS AND CODES • REGULATORY REQUIREMENTS • DIAMOND MINING • ASSESSING DIAMOND POTENTIAL • JUNIOR MINERS • CASE STUDIES • KIMBERLITE MINING • ALLUVIAL MINING • IMPLICATIONS FOR INVESTORS • IMPLICATIONS FOR PUBLIC REPORTING • CONCLUDING REMARKS James Campbell is President and CEO of Rockwell Diamonds Inc. Previous roles include Non Executive Director of Stellar Diamonds plc, Vice President - New Business for Lucara Diamond Corp, Managing Director of African Diamonds plc, Executive Deputy Chairman of West African Diamonds plc. James worked at De Beers for over twenty years; his roles included General Manager for Advanced Exploration & Resource Delivery and Nicky Oppenheimer's Personal Assistant. James holds a degree in Mining & Exploration Geology from the Royal School of Mines (Imperial College, London University) and an MBA with distinction from Durham University. He is a Fellow of the Institute of Mining, Metallurgy & Materials, South African Institute of Mining & Metallurgy and Institute of Directors of South Africa. He is also a Chartered Engineer (UK), Chartered Scientist (UK) and a Professional Natural Scientist (RSA). James also chairs two NPO’s and is deeply committed to South Africa.
  • 3. 317-18 May 2016 | REGULATORY & REPORTING REQUIREMENTS
  • 4. 417-18 May 2016 | PUBLIC REPORTING Public reporting refers to all disclosure, such as press releases, website postings, presentations, technical reports and technical disclosure accompanying financial reports (statements of Mineral Resources and Reserves) Public reporting must be ♦ Material. i.e. present all reasonably expected information ♦ Transparent, i.e. presented in a clear and unambiguous manner ♦ Prepared by Competent Persons (CP) Competent Persons must ♦ Be a Member or Fellow of a Recognised Professional Organisation (RPO). ♦ Have a minimum of five years’ relevant experience in the style of mineralisation or type of deposit under consideration and in the activity which that person is undertaking. ♦ Be satisfied that they could face their peers and demonstrate competence in the commodity, type of deposit and situation under consideration. Professional codes of practice set minimum standards for public reporting. Public reports must be prepared by a Competent Person (CP) Codes differ slightly on the requirements for CP’s relevant experience Membership in the RPO should be primarily on the basis of academic qualifications and experience RPOs should have enforceable disciplinary processes including the powers to suspend or expel a member Source: CRIRSCO
  • 5. 517-18 May 2016 | MINERAL REPORTING STANDARDS & CODES National reporting standards for selected countries International initiative launched in South Africa in 1994 Working group established to develop a set of standard definitions for reporting of mineral resources and mineral reserves Today most national reporting standards share a common set of codes and guidelines The Canadian mining sector’s credibility improved greatly after the NI 43-101 was introduced in 2001 19971994 1999 2000 International initiative to standardise definitions for market-related reporting (CRIRSCO) Agreement on definitions for Mineral Resources and Mineral Reserves (Denver Accord) Alignment with United Nations Framework Classification Updated JORC Code published (first release 1989) Other national reporting standards/codes published, e.g. SAMREC, CIM Country Reporting Standard/Code Australia JORC Code (2012) Canada CIM Definition Standards for Mineral Resources and Reserves – NI 43-101 (2014) Europe/UK PERC Reporting Standard (2013) Russia NAEN Code (2011) South Africa SAMREC Code (2007) SAMVAL Code (2008) USA SME Guide (2014) Source: CRIRSCO, PWC
  • 6. 617-18 May 2016 | REGULATORY REQUIREMENTS Mining reporting requirements applicable in selected jurisdictions Stock Exchange Mining-specific Reporting Requirements (post-listing) Mineral Reporting Standard ASX Annual and half-year financial report Quarterly report by CP on production and development activities (incl. expenditure); exploration activities; mineral results & ore results JORC JSE Annual and quarterly financial report Description of exploration and mining activities by CP; mineral resource and reserve statement SAMREC TSX/TSXV Annual and quarterly financial report CIM (NI 43-101) LSE/AIM Annual and half-year financial report Interim management statement Resource updates by CP (AIM) JORC, SAMREC, CIM, other selected codes HKEx/GEM Annual and quarterly financial report Half-yearly updates on mining JORC, SAMREC, CIM The world’s largest diversified mining groups are listed on LSE In 2013, TSX and TSX-V combined were home to 57% of the world’s publicly listed mining companies Cross border international listings and dual/triple listings of miners on AIM, TSX and ASX continue to increase HKEx is becoming a destination of choice for mining companies. However, companies with only inferred resources are not eligible for listing Source: PWC, Mining Association of Canada
  • 7. 717-18 May 2016 | DIAMOND MINING
  • 8. 817-18 May 2016 | DIAMOND MINING – TWO SCENARIOS KIMBERLITES • High establishment costs • Open pit and underground operations (with progression in some cases) • Grade, diamond distribution can be constrained with sampling and modelling • Higher resource confidence can mitigate uncertainty ALLUVIALS • Lower start-up costs • Low grade, high variability • High uncertainty • High volume, low cost approach • Scarcity of larger (high-value) diamonds • Volumes are key to repeatability Alluvial operations perceived as being better suited to smaller operators (juniors) than kimberlites Most juniors and mid-tiers own kimberlite projects Majors such as De Beers have been running large-scale alluvial operations Diamonds from alluvial operations are on average larger (cts/stone) and more valuable ($/ct) Attracting equity and debt funding is challenging in current markets
  • 9. 917-18 May 2016 | LISTED DIAMOND MINING IN SOUTH AFRICA Company Size Listing SA operations (K = kimberlite; A = alluvial) Annual Production (cts) Annual Revenue (US$) Blue Rock Diamonds Junior AIM Kareevlei (K) Ramp-up N/A De Beers Major N/A Venetia, Voorspoed (K) 4.5M No SA reports Diamcor Mining Junior TSX-V, OTC Krone-Endora (A) +/- 20,000 (incidental) +/- 3M DiamondCorp Junior AIM Lace (K) +/- 7,000 (ramp-up) N/A Petra Diamonds Mid- tier LSE Cullinan, Finsch, Kimberley, Koffiefontein (K) 3M 360M Rockwell Diamonds Junior TSX, JSE Middle Orange River (A) 36,000 51M Trans Hex Junior JSE Lower Orange River, Namaqualand (A) 62,000 83M South Africa currently produces 8% of world diamonds by volume In 2014 SA produced 8.1 million carats of diamonds (nearly half as pre-GFC levels) The bulk of SA diamond production is from primary sources (kimberlites) Operators are chiefly junior / mid-tier companies No new discoveries, nor significant projects in the pipeline Source: company websites, SA Chamber of Mines Many private diamond mining companies too
  • 10. 1017-18 May 2016 | A PERSPECTIVE ON JUNIOR MINERS Source: Investopedia; mineralsnorth.ca; undervaluedequity Some common traits of juniors Some common traits of majors • Discoverers and developers of new economic deposits • Typically small-cap companies • Exploration spend is their lifeblood • No/little production cashflow to fund exploration activities • Funding derived from share issues & management • No dividends paid - shareholders rewarded by share price increase • Results attract high degree of public scrutiny and assurance • Subject to full extent of regulatory and reporting obligations • Technical management teams with deep practical experience • Innovative, agile and fast • Owners of mining operations • Typically more than one mine • Publicly traded, well capitalised companies • Exploration activities internally funded by production cashflow • Exploration spend viewed as discretionary • Steady, predictable cashflow • Large corporate structures • Complex decision processes • Internal assurance processes • Able to adjust production to changing market conditions • Large technical and non- technical management departments. What defines a junior miner? ♦ No single definition ♦ Prospectors and developers ♦ “The exploration division of the mining industry” ♦ No marked separation between junior and mid-tier
  • 11. 1117-18 May 2016 | ASSESSING DIAMOND POTENTIAL FOR MINING (GENERALISED PROCESS) Confidence in the deposit/resource improves as new information is analysed and assumptions are re-visited As confidence increases, so do costs and timeframes Technology plays a critical role in resource assessment process, as do risk modelling simulations Accurate and reliable resource models are essential inputs to a sound economic assessment Expert operators are able to shorten timeframes, without compromising on quality of resource assessment Deep knowledge, expertise are key differentiators Mapping, sampling, geophysics Core drilling or trenching (100’s kg) Initial bulk sampling (10-100’s t) Infill drilling, bulk sampling (1000’s t) Inferred Resource Indicated Resource Diamond potential, surface size estimate Preliminary grade estimate, prelim. geological model Global grade, preliminary value estimate Geological, density, volume, grade, value models Preliminary Economic Assessment Pre-Feasibility Study Bankable Feasibility Study Deposit Target / Anomaly ActivityOutcomes Mineral Resource Economic Studies INCREASING COSTS & TIMEFRAMES DECREASING UNCERTAINTY & RISK Duration: months Cost: R millions Duration: years Cost: R tens of millions
  • 12. 1217-18 May 2016 | ASSESSING DIAMOND VALUE Unlike other mineral commodities, diamonds don’t have set prices Equity funders require that a rough diamond pricing model be decided upfront in a deal Two models in diamond valuation: fixed price book or open tender Open tenders have the following advantages: ♦ Market related price ♦ Competitive bidding ♦ Pricing transparency ♦ Clients get the goods they want ♦ Premium paid for valued goods Disadvantages of open tenders include: ♦ Less predictable cash flows ♦ Higher risk of price volatility ♦ Speculative buying Open tenders are on the increase ♦ Initiated by juniors seeking transparent pricing models ♦ Majors have been integrating tenders into their sales Five Models underpin a diamond resource: Geological, Density, Volume, Grade, Value Modelling of value is unique to diamond resource estimation Value estimates require a substantial investment in order for a representative sample to be obtained Understanding the size distribution of diamonds in a deposit is critical in designing an effective treatment plant The value of diamonds recovered can be optimised through the selection of a suitable bottom cut-off size (BCOS) Source: GIA, Rockwell
  • 13. 1317-18 May 2016 | DIAMOND MINING CASE STUDIES
  • 14. 1417-18 May 2016 | A KIMBERLITE CASE STUDY: AK6 (KAROWE MINE) AK6 is a diamondiferous kimberlite pipe located in the Orapa kimberlite field in north- eastern Botswana Discovered by De Beers in 1969, but deemed low priority Evaluated in 2003-2007 by De Beers – African Diamonds JV Now called Karowe Mine and is owned and mined by Lucara Diamond Corp Mining began in 2012 Anticipated LoM is 15 years Source: Lucara, JAH Campbell
  • 15. 1517-18 May 2016 | AK6 - THE JOURNEY Initial evaluation by De Beers Preliminary size, grade, value encouraging Boteti JV: African Diamonds, De Beers (49/51) Evaluation Phase 1 Inferred Mineral Resource Positive sampling results released Decision to fast-track evaluation Evaluation Phase 2 Indicated Mineral Resource Conceptual Study (DB): marginal economics; capital USD380M Pre-Feasibility Study (AFD): robust economics Feasibility Study (DB): marginal economics Mining Licence (2008) Value Engineering Study (AFD): robust economics; capital USD88M Lucara acquires DB’s share in Boteti Feasibility Study (Lucara): robust economics; capital USD156M Lucara acquires AFD’s share in Boteti Construction & Commissioning Cost: USD110M Mining begins in Q2 2012 2003-5 2010-122005-6 2006-7 AK6 initially downgraded due to small size (3.3ha), low grade (3cpht) and poor mineral chemistry Re-assessed by De Beers (Debot) in 2003 Boteti JV (AFD-DB) formed in 2004, prior to initial evaluation results being released Facilitated by AFD, Debot sold its share to Lucara in 2009, in the wake of the GFC and due to apparent marginal economics AFD exited in 2010 following significant share premium buyout from Lucara 2008-9
  • 16. 1617-18 May 2016 | AK6 EVALUATION PROGRAMME (2003-2007) Extensive evaluation: ♦ +/-23,000m core drilling ♦ +/- 12,500m LDD ♦ +25,000t samples collected (not all processed) Total cost of evaluation programme USD26.8M High levels of diamond damage observed High abundance of high value Type II diamonds Phase Technique Objective Results Initial evaluation LDD 5x12¼” Macro potential, preliminary grade 97t (in situ) 25cpht (+1mm) 138USD/ct High-resolution geophysics Surface area, geological model 9.5ha EvaluationPhase1 Percussion drilling 44x6.5” Delineation, geological model, mineral chemistry, macro 4,575m 28t (in situ) 29.6cpht (+1mm) Core drilling 17xinclined 12xvertical Internal geology, LDD pilots, micro 9,883m South Lobe increased LDD 13x23” @70m Grade and revenue – inferred resource 500ct for valuation 2,747t (in situ) 689cts 25.1cpht (+1mm) EvaluationPhase2 Core drilling 11xvertical 29xinclined Delineation, internal geology, LDD pilots 12,860m Kimberlite at 884m LDD 12x23” @50m Grade and revenue – indicated resource 3000ct for valuation 3,298t (in situ) 483cts 17.8 cpht (+1mm) Trenching (S Lobe) Grade and revenue 7.393t (in situ) Trenching (C Lobe) Grade and revenue 12,074t (in situ) Source: Lucara, JAH Campbell
  • 17. 1717-18 May 2016 | AK6 / KAROWE RESOURCE STATEMENTS Karowe Mineral Resource / Reserve (2013) Tonnes (000,000’s) Grade (cpht) M Carats (+1.25mm) Value (USD/ct) Probable Reserve (to 324m) 33.1 15.5 5.1 394 Indicated Resource (to 400m) 48.07 16 7.61 393 Inferred Resource (400-750m) 21 14 3.04 412 Source: JAH Campbell, Lucara 2003-7 evaluation programme led to first mineral resource estimate for AK6 (2009) Grades regarded as conservative; improvement anticipated with further work Considerable upside expected in diamond values (revised upwards by +25% in 2010) Latest Karowe resource statement (2013) reflects a drop in grades and increase in values Higher BCOS (1.25mm) accounts for grade decrease Value increase chiefly due to incorporation of production and sales data into estimates 2013 value estimation qualified as conservative AK6 Mineral Resource (2009) Tonnes (000,000’s) Grade (cpht) M Carats (+1 mm) Value (USD/ct) Indicated Resource (to 372m) 40 22 8.9 153 Inferred Resource (372-758m) 31 19 6 139
  • 18. 1817-18 May 2016 | KAROWE PRODUCTION PERFORMANCE A proven large stone producer 2015 large stone recoveries: 20 greater than 200cts 7 greater than 300cts Three exceptional stones recovered from South Lobe in November 2015, including world’s second largest diamond: 1,111cts Type IIa Lesedi La Rona Year Tonnes mined (000,000’s) Tonnes treated (000,000’s) Carats recovered Grade (cpht) Ave $/ct sold Stones >10.8ct s 2015 3.18 2.24 365,690 16.3 593 727 2014 3.32 2.42 430,292 17.7 644 815 2013 3.94 2.35 440,751 18.8 411 732 Source: Lucara Operating costs are USD33-35 per tonne treated Lobes
  • 19. 1917-18 May 2016 | REFLECTIONS ON AK6 Quality and abundance of large diamonds initially underestimated Type IIa diamonds typically colourless and extremely transparent (notable examples are the Cullinan and Koh-i-Noor) Valuation models: market tender vs. price book Joint Venture dynamics: different perspectives; funding structure Fit-for-purpose approach to plant design Risk modelling / simulations Impact of global events: timing is crucial Diamond value ♦ Type IIa diamonds recovered during bulk sampling ♦ Abundance of Type II and larger diamonds inadequately considered in initial valuations ♦ Diamond value underestimated in financial modelling ♦ Karowe consistently delivering large and exceptional stones Joint Venture ♦ Agreement signed ahead of first bulk sampling results ♦ JV operated by a major ♦ Substantial variance in › Risk appetite › Plant design philosophy › Capital estimates › Project economics Economic context ♦ Global Financial Crisis ♦ Change in De Beers’ strategy ♦ Investors’ reluctance to fund a project deemed marginal
  • 20. 2017-18 May 2016 | AN ALLUVIAL CASE STUDY: SAXENDRIFT MINE Alluvial diamond operation on the south bank of the Orange River, 160 km from Kimberley Mined by TransHex in 2000-6 Purchased by Rockwell Diamonds (RDI) in 2008 LoM extended by acquisition of Saxendrift Extension in 2012 First full SA implementation of Bourevestnik bulk X-Ray technology in operational environment Saxendrift Mine has produced numerous +100ct stones, including the Alana (169cts) and the Rockwell (287cts)
  • 21. 2117-18 May 2016 | SAXENDRIFT MINE Three terrace complexes with associated palaeochannel depositional packages identified on Saxendrift Mine: Brakfontein Hill (“BHC”) Saxendrift Hill (“SHC”) Saxendrift River (“SRC”) Saxendrift project properties extend over 5,120.55ha, comprising both Mining Rights and Prospecting Rights Saxendrift Mine also includes Kwartelspan Complex (KPC), contiguous to the east Saxendrift River Complex (SRC) Saxendrift Hill Complex (SHC) Brakfontein Hill Complex (BHC)
  • 22. 2217-18 May 2016 | SAXENDRIFT HISTORY Early artisanal diggings in mid 1920’s 98,000cts recovered Hard calcrete cover, poor returns Diggings end by 1950 Mapping and bulk sampling by Broadacres, Moonstone NCDM&E operating Saxendrift, Brakfontein Gem buys NCDM&E (1998) TransHex, Gem merge (1999) TransHex acquires permit (2000) Saxendrift Mine commissioned MOR exploration 2001: 216ct stone found 2003: 45,000$/ct for blue diamond Saxendrift put on C&M 76,803cts produced RDI buys Saxendrift (2008) New plant installed BHC bulk sampling (2008-9) and trial mining (2009-10) BHC mining (2011-2015) SRC bulk sampling (2012-14) SHC bulk sampling (2013-14) KPC bulk sampling (2014) RC drilling for volume estimations (2015) 1920-50’s 2006-101980-90’s Early digging activities dating back to 1920’s-1950’s Bulk sampling in 1980’s-90’s Formal mining in late 1990’s Blasting and earthmoving equipment used to rip and remove hard calcrete Mined by TransHex since 2000, Rockwell since 2008 Concurrent bulk-sampling and mining since late-2000’s Drillhole material from volume estimation not sampled for diamonds (low grade) 2000-5 2011-16 Source: Rockwell, Explorations Unlimited
  • 23. 2317-18 May 2016 | SAXENDRIFT BULK SAMPLING / TRIAL MINING (2008-2014) Due to the low grades and large stone sizes in alluvial diamond deposits, bulk samples are collected and processed to determine in-situ grades Recovered diamonds are sold on the open market to determine realisable value Mining in one area of an alluvial diamond mine can occur concurrently with trial-mining and/or bulk-sampling operations in other areas The transition to trial mining and onto production mining can be seamless Area Volume (m3) Carats Grade (ct/100m3) Stones Size (ct/st) Average value (USD/ct) BHC 194,287 2,398,009 2,436.73 14,073.49 1.25 0.62 1,414 (2009) 1,956 (2010) SRC 2,218,210 13,523.10 0.61 3,089 4.38 1,726 (2014) SHC 1,007,781 4,209.27 0.42 761 5.53 1,904 (2014) KPC 80,590 450.62 0.57 187 2.41 1,072 (2014) Source: Rockwell, Explorations Unlimited
  • 24. 2417-18 May 2016 | SAXENDRIFT MINERAL RESOURCE 0 500 1000 1500 2000 2500 3000 0 2,000,000 4,000,000 6,000,000 8,000,000 10,000,000 12,000,000 14,000,000 2007 2009 2010 2012 2014 2015 USD/ct Volume(m3) MINERAL RESOURCE ESTIMATES Inferred Indicated Value 2007 third party Mineral Resource estimate re-modelled in 2009 to Rockwell’s group standards: drop in volumes, increase in grades Change in mining method in 2010 (entire sequence mined) explains increase in volumes and drop in grade Bottom cut-off size increased from 2mm to 5mm in 2011 (fewer carats recovered) Upgrade of Inferred to Indicated Resource in 2012 due to proximity to mining face Two-year moving average of value from 2013 GFC BCOS 5mm Inf Res upgrade 0.68 0.41 1.01 0.72 0.66 0.56 0.47 0.47 0.45 0.53 0.42 0.5 RDI model Mining method Grade
  • 25. 2517-18 May 2016 | SAXENDRIFT PRODUCTION PERFORMANCE Recovered grades in line with modelled grades Rigour applied to resource modelling (and NI 43-101 reporting) leads to consistent production performance Mining feedback validates resource assessment Optimised EMV fleet is paramount to operational performance Notable recoveries in 2014-15 included 6 stones over 100cts Year Volume treated (m3) Carats recovered Grade (cts/100m3) Ave $/ct sold 2015 2,559,000 10,442 0.41 2,363 2014 2,296,000 12,701 0.55 2,338 2013 1,775,130 8,373 0.47 1,918 2012 1,469,215 6,944 0.47 2,444 2011 1,449,875 6,705 0.46 2,003 2010 1,216,503 8834 0.73 1968 2009 194,287 2,437 1.18 1,767 0 500 1000 1500 2000 2500 3000 3500 0 100000 200000 300000 400000 500000 600000 700000 800000 Q1-F14 Q2-F14 Q3-F14 Q4-F14 Q1-F15 Q2-F15 Q3-F15 Q4-F15 USD/ct Volume(m3) Saxendrift production 2014-15 Volume processed Value Source: Rockwelll AR’s 0.39 Grade 0.54 0.76 0.50 0.64 0.34 0.39 0.32
  • 26. 2617-18 May 2016 | IMPLICATIONS FOR INVESTORS AND REPORTING
  • 27. 2717-18 May 2016 | JUNIOR FUNDING Equity financing is the juniors’ dominant source of funding, while the majority of mining debt financings are undertaken by large market cap companies In 2013, 62% of global mining equity financing was raised on TSX and TSX-V ASX, TSX and AIM are funding junior exploration and development companies Juniors are responsible for the majority of further issues, reflecting their need for cash to fund exploration and feasibility studies Source: PDAC, PWC
  • 28. 2817-18 May 2016 | IMPLICATIONS FOR INVESTORS Mining investors view favourably: ♦ Companies with experienced management teams, exploring in prospective areas and with reasonable project timelines ♦ The use of new technology, as it demonstrates an ability to work faster and cost-effectively ♦ Clarity on a company’s position with respect to key drivers of future value (the investors’ reward lies in the increase in share price) ♦ Companies who “graduate” from the venture to the main board of a stock exchange, as this implies additional corporate governance and due diligence effort Mining investors view less favourably: ♦ New discoveries without a demonstrable way to mine the mineral resource economically ♦ Junior miners with little or no track record, especially so during cyclical mining downturns Typically, juniors have to raise equity to fund their exploration/evaluation activities all the way to feasibility stage (whereas majors are able to self-fund this process) Attracting and retaining investors’ interest requires an ongoing effort Information of relevance to investors is disclosed through public reporting Caution must be exercised not to overstate the potential of a project in an effort to keep investors’ interest alive Source: Canadian Mining Journal. PWC, Pinnacle Digest
  • 29. 2917-18 May 2016 | IMPLICATIONS FOR PUBLIC REPORTING Public reporting is expected to: ♦ Provide high levels of assurance to accompany disclosure of information of a financial or operational nature ♦ Provide clearly defined and highly reliable measures that have the potential to influence markets ♦ Include non-GAAP performance measures - such as production volumes, resources/reserves and cash costs – which investors use in their analyses ♦ Report accurately on responsible operational activities in an unambiguous, timely fashion Accurate and transparent reports are critical in securing subscriptions to further share issues, as IPOs generally raise funds to cover only the first 2-3 years of exploration Juniors are subject to a high degree of public scrutiny and assurance (majors tend to conduct these internally) Mineral resource estimates and other non-GAAP measures are increasingly scrutinised by investors Shortened project timeframes are appealing, as long as accuracy of information is not compromised Relevant and accurate reporting helps to sustain interest throughout the lifecycle of a project
  • 30. 3017-18 May 2016 | CONCLUDING REMARKS Mineral resource development is a complex and costly process with a high degree of risk Technology has a key role to play in the risk reduction process Plant design philosophy can make or break a project Experienced technical management is probably the most important critical success factor In order to comply with regulatory requirements, project results must be reported within accepted frameworks Stringent reporting parameters don’t always allow for the full characterisation of future potential of a mining project (commentary is just as important) Accepted reporting standards are primarily designed to protect investors from misrepresentation of resource value There is a fine line between compliance and excessive caution, which may result in conservative understatements of future potential Reporting and regulatory requirements place a significant burden of compliance on juniors However, relevance and transparency of reporting is increasingly important in attracting junior funding Rigour and diligence applied to resource development pays off in resource performance and repeatability of results Accelerated project timeframes are appealing, but there is no room for compromise on resource assessment