SlideShare a Scribd company logo
Issues and Challenges of Power
Projects
K Biswal
Director (Finance)
NTPC Limited
An Analytical Perspective
PROJECT MEET 2015
NTPC’s Plan Perfect – 128 GW by 2032
Power Mix STANDALONE SUBS./JV Total
Coal 34425 4229 38654
Gas 4017 1967 5984
Hydro 800 0 800
RE 110 0 110
TOTAL 39352 6196 45548
45548 MW
23,004 MW
48,338 MW
11,110 MW 82,452 MW
45,548 MW
68552 MW
76,662 MW
128000 MW 1,28,000 MW
Sept2015 Capacity Under Construction Invited Bids from Vendor FR approved or being prepared Total by FY : 2032
Vision to Maintain
Leadership Position in
India, Current
Development Pipeline of
82.5 GW
Problems faced duging Project Execution
PPA Land
Environment
Clearance
Water Coal Linkage
Basic elements for investment approval of Power Projects
 All our investment decisions and due-dilligence covers all the above aspects
 All Problems are somewhat lies with above five factors either directly or indirectly
Without PPAs,
setting up of
Project is
suicidal
 Physical possession
and LA is taking
long time
 Expectations of
PAPs growing day
by day
 Acceptability of
R&R Policies
 NGO/Green Lobby
 Environment
clearance of
Power plant is
linked to
environmental
clearance of its
fuel linkage
 Water scarcity
for industrial
use
 Delays in CWC
clearance
 State Govt.
insistence on
Pondage/canal
lining
 Delays in
getting
environment/fo
rest clearance
 Coal Demand &
Supply
Mismatch
Timely Execution is key for Project Bankability
Sr.No. Project/Unit
**
Inv App.
Date
COD -
Inv App.
COD -
Revised
Delay (in
Months)
1 Barh-1 Feb'2005 Nov'2014 Mar'2018 41
2 Bongaigaon Jan'2008 Oct'2011 Mar'2017 66
3 BRBCL Feb'2007 Jun'2014 Jun'2017 37
4 KBUNL Mar'2010 Feb'2013 Mar'2016 38
ROE and
RONW can
be
improved
by
improving
the ratio of
CWIP to
Gross Fixed
Assets
(Out of Fixed
Asset**s of
Rs.1,35,000
cr., CWIP is
around
Rs.56,000 cr.
which is not
giving any
return)
** List is just indicative only
CWIP to Gross Block
(%) (Actual)
2014-15 42%
2013-14 38%
2012-13 36%
Therefore, in order to achieve our target of
128 GW by 2032, we have only one option, i.e.
to expedite conversion of CWIP into generating
assets so as maintain our profits & cash flows.
As on date the ratio of CWIP to Gross Block is at
ALARMING level of 42% - This needs to be
managed at around 35%.
CWIP to FIXED ASSETS TO BE CAPPED
Pace of Conversion of CWIP into Operating asset need to be matched with the pace of
Award of new projects otherwise NTPC Balance Sheet would come under stress.
Impact of Delay
In case, project is delayed beyond
the time period stipulated in the
Tariff Regulations.
Loss of ROE by 0.5% for the entire
life of the project.
Capital cost incurred up to Cut off
Date only will be admitted.
Capital cost beyond Cut off Date is
subject to prudence check by CERC.
For Example, in the recent tariff order
issued by CERC for Farakka-III, the
disallowed capital cost on account of cost
overrun is
IEDC 7.60 Crs
IDC 79.21 Crs
Price escalation 21.33 Crs
TOTAL 108.14 Crs
Because of above, there is a gap of about
5% between gross block as per books of
accounts (Rs 2222.49 Crs) and allowed gross
block by CERC.
Impact of delay in projects over DCO and IEDC & EDC
NTPC
versus IPP
Capital cost of NTPC
plants on an average
34% higher than IPPs.
Avg. Timelines for
completion of super
critical pants is 49 months
by IPPs whereas NTPC’s
Sipat I – 86 Months & Barh
II – 62 Months.
75
Months
78
Months
50
Months
34
Months
72
Months
3,229
6,946
3,746
6,444
2,256
4,161
10,413
4,843
7,313
2,861
1,264 1,566
530
1,754
694
3,007
4,314
1,780
2,237
958
Koldam Barh-I Bongaigaon Sipat-I Tapovan
Original DCO RCE
Original (IEDC+IDC) Revised (IEDC+EDC)
Risk and Cost of Packages
 Risk and Cost Provision should act as
deterrent for the errant contractor
 Cost and Risk provision exist only on
paper
 Cost and Risk leads
Litigation/arbitration
 Hence Cost and Risk is a misnomer in
NTPC
 Contract closing become nightmare
Remedy Proposed
 Sub-contracting to the right Vendor
can be ensured
 Assessment of Vendor should be on
360 degree basis
 Foreign Vendor should be
scrutinized thoroughly
 Policy advocacy to check this menace
 Alternate Dispute Resolution
Vendor Assessment
INDURE
BGR
TECPRO McNally
TPE
Energo
Non-Performance
Poor Financial Conditions
Lack of Quality Manpower
 QR need to be Package-wise
 Vendor Rating – To be part of QR
 Objective Assessment of Capability
& manpower deployed
Key Take-aways
1. We should strive hard to generate Affordable Power.
2. We should shed the notion that every money spent can be passed on to the
consumer. All round efforts should launched to contain cost by bringing in
Prudence on Capex and Opex Spending to earn Rank on the Merit Order.
3. Pit-head and port linked stations should be preferred for expansion.
4. We should excel on all operational parameters and contain fuel cost by
maximum.
5. High Fixed Cost may pose PPA denial.
Thanking you all

More Related Content

Similar to Issues and Challenges of Power Projects.pptx

Contract Availability for LRET Development
Contract Availability for LRET DevelopmentContract Availability for LRET Development
Contract Availability for LRET Development
Simon Mathis
 
Project management in thermal power plants
Project management in thermal power plantsProject management in thermal power plants
Project management in thermal power plants
Prashant Alekar
 
Repowering Indian Discoms - Academic Research
Repowering Indian Discoms - Academic ResearchRepowering Indian Discoms - Academic Research
Repowering Indian Discoms - Academic Research
Aditya Parchure
 
Birendra Behuria ppt.pptx
Birendra Behuria ppt.pptxBirendra Behuria ppt.pptx
Birendra Behuria ppt.pptx
BanaDurga
 
Q3 2014 AES Corporation Earnings Conference Call
Q3 2014 AES Corporation Earnings Conference CallQ3 2014 AES Corporation Earnings Conference Call
Q3 2014 AES Corporation Earnings Conference Call
AES_BigSky
 
2018 - 2021 Eni Strategic Plan
2018 - 2021 Eni Strategic Plan2018 - 2021 Eni Strategic Plan
2018 - 2021 Eni Strategic Plan
Eni
 
TGP Q3 2020 Earnings Presentation
TGP Q3  2020 Earnings PresentationTGP Q3  2020 Earnings Presentation
TGP Q3 2020 Earnings Presentation
Teekay Corporation
 
Eni: trasformata in società forte e solida, punta all’espansione. L'Italia è ...
Eni: trasformata in società forte e solida, punta all’espansione. L'Italia è ...Eni: trasformata in società forte e solida, punta all’espansione. L'Italia è ...
Eni: trasformata in società forte e solida, punta all’espansione. L'Italia è ...
Eni
 
2018-21 eni presentation NY inv day
2018-21 eni presentation NY inv day2018-21 eni presentation NY inv day
2018-21 eni presentation NY inv day
Eni
 
L&T Outthink Challenge - National Finalist & Campus Winners
L&T Outthink Challenge - National Finalist & Campus WinnersL&T Outthink Challenge - National Finalist & Campus Winners
L&T Outthink Challenge - National Finalist & Campus Winners
Naveen Kumar
 
TPWODL- Q1 FY24 _Board Meeting Presentation.pptx
TPWODL- Q1 FY24 _Board Meeting Presentation.pptxTPWODL- Q1 FY24 _Board Meeting Presentation.pptx
TPWODL- Q1 FY24 _Board Meeting Presentation.pptx
SantoshkumarGupta67
 
2019 2022 Strategy
2019 2022 Strategy2019 2022 Strategy
2019 2022 Strategy
Eni
 
Financing Energy Optimization Projects
Financing Energy Optimization Projects Financing Energy Optimization Projects
Financing Energy Optimization Projects
Avanceon
 
Decc discussion slides investor simulation workshop breakout_biomass conversi...
Decc discussion slides investor simulation workshop breakout_biomass conversi...Decc discussion slides investor simulation workshop breakout_biomass conversi...
Decc discussion slides investor simulation workshop breakout_biomass conversi...
Department of Energy and Climate Change
 
Far eastenergyapr2012corporatepresentation
Far eastenergyapr2012corporatepresentationFar eastenergyapr2012corporatepresentation
Far eastenergyapr2012corporatepresentation
nabarnes
 
Earnings release 2Q14
Earnings release 2Q14Earnings release 2Q14
Earnings release 2Q14
ersa_ri
 
DAYANG – Fundamental Analysis FY15
DAYANG – Fundamental Analysis FY15DAYANG – Fundamental Analysis FY15
DAYANG – Fundamental Analysis FY15
lcchong76
 
Mc dermott pareto_final
Mc dermott pareto_finalMc dermott pareto_final
Mc dermott pareto_final
investorcbi
 
Larsen & Toubro - Outthink 2017 (Strategy Case Competition) - Grand Finale
Larsen & Toubro - Outthink 2017 (Strategy Case Competition) - Grand FinaleLarsen & Toubro - Outthink 2017 (Strategy Case Competition) - Grand Finale
Larsen & Toubro - Outthink 2017 (Strategy Case Competition) - Grand Finale
Anupreet Choudhary
 
The Contracts for Difference – Strike Back (with a cameo appearance by...Ener...
The Contracts for Difference – Strike Back (with a cameo appearance by...Ener...The Contracts for Difference – Strike Back (with a cameo appearance by...Ener...
The Contracts for Difference – Strike Back (with a cameo appearance by...Ener...
Bhalindra Bath - projects & M&A law
 

Similar to Issues and Challenges of Power Projects.pptx (20)

Contract Availability for LRET Development
Contract Availability for LRET DevelopmentContract Availability for LRET Development
Contract Availability for LRET Development
 
Project management in thermal power plants
Project management in thermal power plantsProject management in thermal power plants
Project management in thermal power plants
 
Repowering Indian Discoms - Academic Research
Repowering Indian Discoms - Academic ResearchRepowering Indian Discoms - Academic Research
Repowering Indian Discoms - Academic Research
 
Birendra Behuria ppt.pptx
Birendra Behuria ppt.pptxBirendra Behuria ppt.pptx
Birendra Behuria ppt.pptx
 
Q3 2014 AES Corporation Earnings Conference Call
Q3 2014 AES Corporation Earnings Conference CallQ3 2014 AES Corporation Earnings Conference Call
Q3 2014 AES Corporation Earnings Conference Call
 
2018 - 2021 Eni Strategic Plan
2018 - 2021 Eni Strategic Plan2018 - 2021 Eni Strategic Plan
2018 - 2021 Eni Strategic Plan
 
TGP Q3 2020 Earnings Presentation
TGP Q3  2020 Earnings PresentationTGP Q3  2020 Earnings Presentation
TGP Q3 2020 Earnings Presentation
 
Eni: trasformata in società forte e solida, punta all’espansione. L'Italia è ...
Eni: trasformata in società forte e solida, punta all’espansione. L'Italia è ...Eni: trasformata in società forte e solida, punta all’espansione. L'Italia è ...
Eni: trasformata in società forte e solida, punta all’espansione. L'Italia è ...
 
2018-21 eni presentation NY inv day
2018-21 eni presentation NY inv day2018-21 eni presentation NY inv day
2018-21 eni presentation NY inv day
 
L&T Outthink Challenge - National Finalist & Campus Winners
L&T Outthink Challenge - National Finalist & Campus WinnersL&T Outthink Challenge - National Finalist & Campus Winners
L&T Outthink Challenge - National Finalist & Campus Winners
 
TPWODL- Q1 FY24 _Board Meeting Presentation.pptx
TPWODL- Q1 FY24 _Board Meeting Presentation.pptxTPWODL- Q1 FY24 _Board Meeting Presentation.pptx
TPWODL- Q1 FY24 _Board Meeting Presentation.pptx
 
2019 2022 Strategy
2019 2022 Strategy2019 2022 Strategy
2019 2022 Strategy
 
Financing Energy Optimization Projects
Financing Energy Optimization Projects Financing Energy Optimization Projects
Financing Energy Optimization Projects
 
Decc discussion slides investor simulation workshop breakout_biomass conversi...
Decc discussion slides investor simulation workshop breakout_biomass conversi...Decc discussion slides investor simulation workshop breakout_biomass conversi...
Decc discussion slides investor simulation workshop breakout_biomass conversi...
 
Far eastenergyapr2012corporatepresentation
Far eastenergyapr2012corporatepresentationFar eastenergyapr2012corporatepresentation
Far eastenergyapr2012corporatepresentation
 
Earnings release 2Q14
Earnings release 2Q14Earnings release 2Q14
Earnings release 2Q14
 
DAYANG – Fundamental Analysis FY15
DAYANG – Fundamental Analysis FY15DAYANG – Fundamental Analysis FY15
DAYANG – Fundamental Analysis FY15
 
Mc dermott pareto_final
Mc dermott pareto_finalMc dermott pareto_final
Mc dermott pareto_final
 
Larsen & Toubro - Outthink 2017 (Strategy Case Competition) - Grand Finale
Larsen & Toubro - Outthink 2017 (Strategy Case Competition) - Grand FinaleLarsen & Toubro - Outthink 2017 (Strategy Case Competition) - Grand Finale
Larsen & Toubro - Outthink 2017 (Strategy Case Competition) - Grand Finale
 
The Contracts for Difference – Strike Back (with a cameo appearance by...Ener...
The Contracts for Difference – Strike Back (with a cameo appearance by...Ener...The Contracts for Difference – Strike Back (with a cameo appearance by...Ener...
The Contracts for Difference – Strike Back (with a cameo appearance by...Ener...
 

Recently uploaded

Stainless Steel Conveyor Manufacturers Chennai
Stainless Steel Conveyor Manufacturers ChennaiStainless Steel Conveyor Manufacturers Chennai
Stainless Steel Conveyor Manufacturers Chennai
ConveyorSystem
 
欧洲杯投注-欧洲杯投注外围盘口-欧洲杯投注盘口app|【​网址​🎉ac22.net🎉​】
欧洲杯投注-欧洲杯投注外围盘口-欧洲杯投注盘口app|【​网址​🎉ac22.net🎉​】欧洲杯投注-欧洲杯投注外围盘口-欧洲杯投注盘口app|【​网址​🎉ac22.net🎉​】
欧洲杯投注-欧洲杯投注外围盘口-欧洲杯投注盘口app|【​网址​🎉ac22.net🎉​】
concepsionchomo153
 
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan ChartSatta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results
 
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan ChartSatta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results
 
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan ChartSatta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results
 
Truck Loading Conveyor Manufacturers Chennai
Truck Loading Conveyor Manufacturers ChennaiTruck Loading Conveyor Manufacturers Chennai
Truck Loading Conveyor Manufacturers Chennai
ConveyorSystem
 
➒➌➎➏➑➐➋➑➐➐ Satta Matka Dpboss Matka Guessing Indian Matka
➒➌➎➏➑➐➋➑➐➐ Satta Matka Dpboss Matka Guessing Indian Matka➒➌➎➏➑➐➋➑➐➐ Satta Matka Dpboss Matka Guessing Indian Matka
➒➌➎➏➑➐➋➑➐➐ Satta Matka Dpboss Matka Guessing Indian Matka
➒➌➎➏➑➐➋➑➐➐Dpboss Matka Guessing Satta Matka Kalyan Chart Indian Matka
 
➒➌➎➏➑➐➋➑➐➐ Satta Matka Dpboss Matka Guessing Indian Matka
➒➌➎➏➑➐➋➑➐➐ Satta Matka Dpboss Matka Guessing Indian Matka➒➌➎➏➑➐➋➑➐➐ Satta Matka Dpboss Matka Guessing Indian Matka
➒➌➎➏➑➐➋➑➐➐ Satta Matka Dpboss Matka Guessing Indian Matka
➒➌➎➏➑➐➋➑➐➐Dpboss Matka Guessing Satta Matka Kalyan Chart Indian Matka
 
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan ChartSatta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results
 
➒➌➎➏➑➐➋➑➐➐ Satta Matta Matka Dpboss Matka Guessing Kalyan panel Chart
➒➌➎➏➑➐➋➑➐➐ Satta Matta Matka Dpboss Matka Guessing Kalyan panel Chart➒➌➎➏➑➐➋➑➐➐ Satta Matta Matka Dpboss Matka Guessing Kalyan panel Chart
➒➌➎➏➑➐➋➑➐➐ Satta Matta Matka Dpboss Matka Guessing Kalyan panel Chart
➒➌➎➏➑➐➋➑➐➐Dpboss Matka Guessing Satta Matka Kalyan Chart Indian Matka
 
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan ChartSatta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results
 
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan ChartSatta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results
 
➒➌➎➏➑➐➋➑➐➐ Satta Matka Dpboss Matka Guessing Indian Matka
➒➌➎➏➑➐➋➑➐➐ Satta Matka Dpboss Matka Guessing Indian Matka➒➌➎➏➑➐➋➑➐➐ Satta Matka Dpboss Matka Guessing Indian Matka
➒➌➎➏➑➐➋➑➐➐ Satta Matka Dpboss Matka Guessing Indian Matka
➒➌➎➏➑➐➋➑➐➐Dpboss Matka Guessing Satta Matka Kalyan Chart Indian Matka
 
Kanban Coaching Exchange with Dave White - Example SDR Report
Kanban Coaching Exchange with Dave White - Example SDR ReportKanban Coaching Exchange with Dave White - Example SDR Report
Kanban Coaching Exchange with Dave White - Example SDR Report
Helen Meek
 
Pro Tips for Effortless Contract Management
Pro Tips for Effortless Contract ManagementPro Tips for Effortless Contract Management
Pro Tips for Effortless Contract Management
Eternity Paralegal Services
 
L'indice de performance des ports à conteneurs de l'année 2023
L'indice de performance des ports à conteneurs de l'année 2023L'indice de performance des ports à conteneurs de l'année 2023
L'indice de performance des ports à conteneurs de l'année 2023
SPATPortToamasina
 
Adani Group's Active Interest In Increasing Its Presence in the Cement Manufa...
Adani Group's Active Interest In Increasing Its Presence in the Cement Manufa...Adani Group's Active Interest In Increasing Its Presence in the Cement Manufa...
Adani Group's Active Interest In Increasing Its Presence in the Cement Manufa...
Adani case
 
AI Transformation Playbook: Thinking AI-First for Your Business
AI Transformation Playbook: Thinking AI-First for Your BusinessAI Transformation Playbook: Thinking AI-First for Your Business
AI Transformation Playbook: Thinking AI-First for Your Business
Arijit Dutta
 
CULR Spring 2024 Journal.pdf testing for duke
CULR Spring 2024 Journal.pdf testing for dukeCULR Spring 2024 Journal.pdf testing for duke
CULR Spring 2024 Journal.pdf testing for duke
ZevinAttisha
 
Adani Group Requests For Additional Land For Its Dharavi Redevelopment Projec...
Adani Group Requests For Additional Land For Its Dharavi Redevelopment Projec...Adani Group Requests For Additional Land For Its Dharavi Redevelopment Projec...
Adani Group Requests For Additional Land For Its Dharavi Redevelopment Projec...
Adani case
 

Recently uploaded (20)

Stainless Steel Conveyor Manufacturers Chennai
Stainless Steel Conveyor Manufacturers ChennaiStainless Steel Conveyor Manufacturers Chennai
Stainless Steel Conveyor Manufacturers Chennai
 
欧洲杯投注-欧洲杯投注外围盘口-欧洲杯投注盘口app|【​网址​🎉ac22.net🎉​】
欧洲杯投注-欧洲杯投注外围盘口-欧洲杯投注盘口app|【​网址​🎉ac22.net🎉​】欧洲杯投注-欧洲杯投注外围盘口-欧洲杯投注盘口app|【​网址​🎉ac22.net🎉​】
欧洲杯投注-欧洲杯投注外围盘口-欧洲杯投注盘口app|【​网址​🎉ac22.net🎉​】
 
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan ChartSatta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
 
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan ChartSatta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
 
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan ChartSatta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
 
Truck Loading Conveyor Manufacturers Chennai
Truck Loading Conveyor Manufacturers ChennaiTruck Loading Conveyor Manufacturers Chennai
Truck Loading Conveyor Manufacturers Chennai
 
➒➌➎➏➑➐➋➑➐➐ Satta Matka Dpboss Matka Guessing Indian Matka
➒➌➎➏➑➐➋➑➐➐ Satta Matka Dpboss Matka Guessing Indian Matka➒➌➎➏➑➐➋➑➐➐ Satta Matka Dpboss Matka Guessing Indian Matka
➒➌➎➏➑➐➋➑➐➐ Satta Matka Dpboss Matka Guessing Indian Matka
 
➒➌➎➏➑➐➋➑➐➐ Satta Matka Dpboss Matka Guessing Indian Matka
➒➌➎➏➑➐➋➑➐➐ Satta Matka Dpboss Matka Guessing Indian Matka➒➌➎➏➑➐➋➑➐➐ Satta Matka Dpboss Matka Guessing Indian Matka
➒➌➎➏➑➐➋➑➐➐ Satta Matka Dpboss Matka Guessing Indian Matka
 
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan ChartSatta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
 
➒➌➎➏➑➐➋➑➐➐ Satta Matta Matka Dpboss Matka Guessing Kalyan panel Chart
➒➌➎➏➑➐➋➑➐➐ Satta Matta Matka Dpboss Matka Guessing Kalyan panel Chart➒➌➎➏➑➐➋➑➐➐ Satta Matta Matka Dpboss Matka Guessing Kalyan panel Chart
➒➌➎➏➑➐➋➑➐➐ Satta Matta Matka Dpboss Matka Guessing Kalyan panel Chart
 
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan ChartSatta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
 
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan ChartSatta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
 
➒➌➎➏➑➐➋➑➐➐ Satta Matka Dpboss Matka Guessing Indian Matka
➒➌➎➏➑➐➋➑➐➐ Satta Matka Dpboss Matka Guessing Indian Matka➒➌➎➏➑➐➋➑➐➐ Satta Matka Dpboss Matka Guessing Indian Matka
➒➌➎➏➑➐➋➑➐➐ Satta Matka Dpboss Matka Guessing Indian Matka
 
Kanban Coaching Exchange with Dave White - Example SDR Report
Kanban Coaching Exchange with Dave White - Example SDR ReportKanban Coaching Exchange with Dave White - Example SDR Report
Kanban Coaching Exchange with Dave White - Example SDR Report
 
Pro Tips for Effortless Contract Management
Pro Tips for Effortless Contract ManagementPro Tips for Effortless Contract Management
Pro Tips for Effortless Contract Management
 
L'indice de performance des ports à conteneurs de l'année 2023
L'indice de performance des ports à conteneurs de l'année 2023L'indice de performance des ports à conteneurs de l'année 2023
L'indice de performance des ports à conteneurs de l'année 2023
 
Adani Group's Active Interest In Increasing Its Presence in the Cement Manufa...
Adani Group's Active Interest In Increasing Its Presence in the Cement Manufa...Adani Group's Active Interest In Increasing Its Presence in the Cement Manufa...
Adani Group's Active Interest In Increasing Its Presence in the Cement Manufa...
 
AI Transformation Playbook: Thinking AI-First for Your Business
AI Transformation Playbook: Thinking AI-First for Your BusinessAI Transformation Playbook: Thinking AI-First for Your Business
AI Transformation Playbook: Thinking AI-First for Your Business
 
CULR Spring 2024 Journal.pdf testing for duke
CULR Spring 2024 Journal.pdf testing for dukeCULR Spring 2024 Journal.pdf testing for duke
CULR Spring 2024 Journal.pdf testing for duke
 
Adani Group Requests For Additional Land For Its Dharavi Redevelopment Projec...
Adani Group Requests For Additional Land For Its Dharavi Redevelopment Projec...Adani Group Requests For Additional Land For Its Dharavi Redevelopment Projec...
Adani Group Requests For Additional Land For Its Dharavi Redevelopment Projec...
 

Issues and Challenges of Power Projects.pptx

  • 1. Issues and Challenges of Power Projects K Biswal Director (Finance) NTPC Limited An Analytical Perspective PROJECT MEET 2015
  • 2. NTPC’s Plan Perfect – 128 GW by 2032 Power Mix STANDALONE SUBS./JV Total Coal 34425 4229 38654 Gas 4017 1967 5984 Hydro 800 0 800 RE 110 0 110 TOTAL 39352 6196 45548 45548 MW 23,004 MW 48,338 MW 11,110 MW 82,452 MW 45,548 MW 68552 MW 76,662 MW 128000 MW 1,28,000 MW Sept2015 Capacity Under Construction Invited Bids from Vendor FR approved or being prepared Total by FY : 2032 Vision to Maintain Leadership Position in India, Current Development Pipeline of 82.5 GW
  • 3. Problems faced duging Project Execution PPA Land Environment Clearance Water Coal Linkage Basic elements for investment approval of Power Projects  All our investment decisions and due-dilligence covers all the above aspects  All Problems are somewhat lies with above five factors either directly or indirectly Without PPAs, setting up of Project is suicidal  Physical possession and LA is taking long time  Expectations of PAPs growing day by day  Acceptability of R&R Policies  NGO/Green Lobby  Environment clearance of Power plant is linked to environmental clearance of its fuel linkage  Water scarcity for industrial use  Delays in CWC clearance  State Govt. insistence on Pondage/canal lining  Delays in getting environment/fo rest clearance  Coal Demand & Supply Mismatch
  • 4. Timely Execution is key for Project Bankability Sr.No. Project/Unit ** Inv App. Date COD - Inv App. COD - Revised Delay (in Months) 1 Barh-1 Feb'2005 Nov'2014 Mar'2018 41 2 Bongaigaon Jan'2008 Oct'2011 Mar'2017 66 3 BRBCL Feb'2007 Jun'2014 Jun'2017 37 4 KBUNL Mar'2010 Feb'2013 Mar'2016 38 ROE and RONW can be improved by improving the ratio of CWIP to Gross Fixed Assets (Out of Fixed Asset**s of Rs.1,35,000 cr., CWIP is around Rs.56,000 cr. which is not giving any return) ** List is just indicative only
  • 5. CWIP to Gross Block (%) (Actual) 2014-15 42% 2013-14 38% 2012-13 36% Therefore, in order to achieve our target of 128 GW by 2032, we have only one option, i.e. to expedite conversion of CWIP into generating assets so as maintain our profits & cash flows. As on date the ratio of CWIP to Gross Block is at ALARMING level of 42% - This needs to be managed at around 35%. CWIP to FIXED ASSETS TO BE CAPPED Pace of Conversion of CWIP into Operating asset need to be matched with the pace of Award of new projects otherwise NTPC Balance Sheet would come under stress.
  • 6. Impact of Delay In case, project is delayed beyond the time period stipulated in the Tariff Regulations. Loss of ROE by 0.5% for the entire life of the project. Capital cost incurred up to Cut off Date only will be admitted. Capital cost beyond Cut off Date is subject to prudence check by CERC. For Example, in the recent tariff order issued by CERC for Farakka-III, the disallowed capital cost on account of cost overrun is IEDC 7.60 Crs IDC 79.21 Crs Price escalation 21.33 Crs TOTAL 108.14 Crs Because of above, there is a gap of about 5% between gross block as per books of accounts (Rs 2222.49 Crs) and allowed gross block by CERC.
  • 7. Impact of delay in projects over DCO and IEDC & EDC NTPC versus IPP Capital cost of NTPC plants on an average 34% higher than IPPs. Avg. Timelines for completion of super critical pants is 49 months by IPPs whereas NTPC’s Sipat I – 86 Months & Barh II – 62 Months. 75 Months 78 Months 50 Months 34 Months 72 Months 3,229 6,946 3,746 6,444 2,256 4,161 10,413 4,843 7,313 2,861 1,264 1,566 530 1,754 694 3,007 4,314 1,780 2,237 958 Koldam Barh-I Bongaigaon Sipat-I Tapovan Original DCO RCE Original (IEDC+IDC) Revised (IEDC+EDC)
  • 8. Risk and Cost of Packages  Risk and Cost Provision should act as deterrent for the errant contractor  Cost and Risk provision exist only on paper  Cost and Risk leads Litigation/arbitration  Hence Cost and Risk is a misnomer in NTPC  Contract closing become nightmare Remedy Proposed  Sub-contracting to the right Vendor can be ensured  Assessment of Vendor should be on 360 degree basis  Foreign Vendor should be scrutinized thoroughly  Policy advocacy to check this menace  Alternate Dispute Resolution
  • 9. Vendor Assessment INDURE BGR TECPRO McNally TPE Energo Non-Performance Poor Financial Conditions Lack of Quality Manpower  QR need to be Package-wise  Vendor Rating – To be part of QR  Objective Assessment of Capability & manpower deployed
  • 10. Key Take-aways 1. We should strive hard to generate Affordable Power. 2. We should shed the notion that every money spent can be passed on to the consumer. All round efforts should launched to contain cost by bringing in Prudence on Capex and Opex Spending to earn Rank on the Merit Order. 3. Pit-head and port linked stations should be preferred for expansion. 4. We should excel on all operational parameters and contain fuel cost by maximum. 5. High Fixed Cost may pose PPA denial.