●Bin accuracy is 89.5%
●Inventory accuracy is 96%
●Excessive “No Location Summary” units
●Stockouts during sales was 2.5% per 1k
orders
CURRENT STATE
●Meet inventory accuracy requirements
●Maintain .01% stockout levels
FUTURE STATE
1. Consistent cycle counting program
2.Monitor inventory adjustments
3.Effective space management
4.Thorough training of IC associates
IMPLEMENTATION PLAN
CYCLE COUNTING PROGRAM
CURRENT STATE
Inconsistent counts
Three and under
counts
Variances are not
confirmed
FUTURE STATE
Dedicated cycle
counters
10 and under counts
Confirm variances
before accepting
adjustments
MONITORING ADJUSTMENTS
CURRENT STATE
“CC” adjustment code
used for all
transactions
Daily adjustments are
not monitored
FUTURE STATE
Utilize Adjustment
Reason codes
Obtain and review
adjustment report
SPACE MANAGEMENT
CURRENT STATE
SKUs are spread
across multiple
locations
Excess distance
between additional
locations
FUTURE STATE
SKU consolidation
based on cube
utilization
System directed
putaway for
identical SKUs
TRAINING PROGRAM
CURRENT STATE
Minimal training on
new associates
Inconsistent training
across the board
FUTURE STATE
Comprehensive
training and
satisfactory test
completion
Analytical aptitude
test for core
associates
IC CPU AND HITTING COSTS
MEETING CPU GOALS IN PRODUCTION
Receiving 2 million units Shipping 2 million units

More Related Content

What's hot

JIT & Lean Manufacturing - ADDVALUE - Nilesh Arora
JIT & Lean Manufacturing - ADDVALUE - Nilesh AroraJIT & Lean Manufacturing - ADDVALUE - Nilesh Arora
JIT & Lean Manufacturing - ADDVALUE - Nilesh Arora
ADD VALUE CONSULTING Inc
 
Warehouse Management
Warehouse Management Warehouse Management
Cycle counting final
Cycle counting finalCycle counting final
Cycle counting final
srihari S
 
SBS - SMED Training (Set Up Reduction)
SBS - SMED Training (Set Up Reduction)SBS - SMED Training (Set Up Reduction)
SBS - SMED Training (Set Up Reduction)Chris Cummins
 
Basics of logistics and inventory management
Basics of logistics and inventory managementBasics of logistics and inventory management
Basics of logistics and inventory management
Vignesh Loganathan
 
INVENTORY MANAGEMENT
INVENTORY MANAGEMENT INVENTORY MANAGEMENT
INVENTORY MANAGEMENT
Zamri Yahya
 
Inventory management
Inventory managementInventory management
Inventory management
kahogan62
 
MPCP What and How DWM.pptx
MPCP What and How DWM.pptxMPCP What and How DWM.pptx
MPCP What and How DWM.pptx
ukavathekar
 
Lean Warehouse
Lean WarehouseLean Warehouse
Lean Warehouse
Zensar Technologies Ltd.
 
Lean manufacturing basics
Lean manufacturing basicsLean manufacturing basics
Lean manufacturing basics
sarah bridge
 
How to improve order picking efficiency
How to improve order picking efficiencyHow to improve order picking efficiency
How to improve order picking efficiency
SILVER LINING STORAGE SOLUTIONS
 
Material management presentation
Material management presentationMaterial management presentation
Material management presentation
AshaEk
 
Inventory Management - a ppt for PGDM/MBA
Inventory Management - a ppt for PGDM/MBAInventory Management - a ppt for PGDM/MBA
Inventory Management - a ppt for PGDM/MBA
AJ Raina
 
Warehouse Management System
Warehouse Management SystemWarehouse Management System
Warehouse Management System
WebXpress.IN
 
Continual Improvement Process-Basic Idea
Continual Improvement Process-Basic IdeaContinual Improvement Process-Basic Idea
Continual Improvement Process-Basic Idea
Sheikh Khawar Qayyum
 
Multi echelon-inventory-optimization
Multi echelon-inventory-optimizationMulti echelon-inventory-optimization
Multi echelon-inventory-optimizationPuneet Mishra
 
Warehouse Management System
Warehouse Management SystemWarehouse Management System
Warehouse Management System
Vishal Kaushik
 

What's hot (20)

JIT & Lean Manufacturing - ADDVALUE - Nilesh Arora
JIT & Lean Manufacturing - ADDVALUE - Nilesh AroraJIT & Lean Manufacturing - ADDVALUE - Nilesh Arora
JIT & Lean Manufacturing - ADDVALUE - Nilesh Arora
 
Warehouse Management
Warehouse Management Warehouse Management
Warehouse Management
 
Cycle counting final
Cycle counting finalCycle counting final
Cycle counting final
 
Lean Warehousing
Lean WarehousingLean Warehousing
Lean Warehousing
 
SBS - SMED Training (Set Up Reduction)
SBS - SMED Training (Set Up Reduction)SBS - SMED Training (Set Up Reduction)
SBS - SMED Training (Set Up Reduction)
 
Basics of logistics and inventory management
Basics of logistics and inventory managementBasics of logistics and inventory management
Basics of logistics and inventory management
 
INVENTORY MANAGEMENT
INVENTORY MANAGEMENT INVENTORY MANAGEMENT
INVENTORY MANAGEMENT
 
Inventory management
Inventory managementInventory management
Inventory management
 
MPCP What and How DWM.pptx
MPCP What and How DWM.pptxMPCP What and How DWM.pptx
MPCP What and How DWM.pptx
 
Lean Warehouse
Lean WarehouseLean Warehouse
Lean Warehouse
 
Lean manufacturing basics
Lean manufacturing basicsLean manufacturing basics
Lean manufacturing basics
 
How to improve order picking efficiency
How to improve order picking efficiencyHow to improve order picking efficiency
How to improve order picking efficiency
 
Material management presentation
Material management presentationMaterial management presentation
Material management presentation
 
Inventory
InventoryInventory
Inventory
 
Inventory Management - a ppt for PGDM/MBA
Inventory Management - a ppt for PGDM/MBAInventory Management - a ppt for PGDM/MBA
Inventory Management - a ppt for PGDM/MBA
 
Warehouse Management System
Warehouse Management SystemWarehouse Management System
Warehouse Management System
 
Continual Improvement Process-Basic Idea
Continual Improvement Process-Basic IdeaContinual Improvement Process-Basic Idea
Continual Improvement Process-Basic Idea
 
Just In Time - JIT
Just In Time - JITJust In Time - JIT
Just In Time - JIT
 
Multi echelon-inventory-optimization
Multi echelon-inventory-optimizationMulti echelon-inventory-optimization
Multi echelon-inventory-optimization
 
Warehouse Management System
Warehouse Management SystemWarehouse Management System
Warehouse Management System
 

Similar to Inventory Accuracy Improvement Plan

Evm power point 25 august 2015 prams co (2)
Evm power point 25 august 2015 prams co (2)Evm power point 25 august 2015 prams co (2)
Evm power point 25 august 2015 prams co (2)
Roger H. Mandel
 
Evm power point 25 august 2015 prams co (2)
Evm power point 25 august 2015 prams co (2)Evm power point 25 august 2015 prams co (2)
Evm power point 25 august 2015 prams co (2)
Roger H. Mandel
 
calibrationintervalspresentation.pdf
calibrationintervalspresentation.pdfcalibrationintervalspresentation.pdf
calibrationintervalspresentation.pdf
AbdulSalamSagir1
 
Smart Pharmaceutical Consulting - Lean Manufacturing of Pharmaceuticals
Smart Pharmaceutical Consulting - Lean Manufacturing of PharmaceuticalsSmart Pharmaceutical Consulting - Lean Manufacturing of Pharmaceuticals
Smart Pharmaceutical Consulting - Lean Manufacturing of Pharmaceuticals
Christopher Macklin
 
Key steps in transforming a calibration program slideshare
Key steps in transforming a calibration program slideshareKey steps in transforming a calibration program slideshare
Key steps in transforming a calibration program slideshare
John Cummins, CPIP
 
New Maturity Model Can Fire Up Restaurant Operations
New Maturity Model Can Fire Up Restaurant OperationsNew Maturity Model Can Fire Up Restaurant Operations
New Maturity Model Can Fire Up Restaurant Operations
Beth Miller
 
New maturity-model-can-fire-up-restaurant-operations
New maturity-model-can-fire-up-restaurant-operationsNew maturity-model-can-fire-up-restaurant-operations
New maturity-model-can-fire-up-restaurant-operations
malini87
 
New Maturity Model Can Fire Up Restaurant Operations
New Maturity Model Can Fire Up Restaurant OperationsNew Maturity Model Can Fire Up Restaurant Operations
New Maturity Model Can Fire Up Restaurant Operations
aayamkhatri
 
New Maturity Model Can Fire Up Restaurant Operations
New Maturity Model Can Fire Up Restaurant OperationsNew Maturity Model Can Fire Up Restaurant Operations
New Maturity Model Can Fire Up Restaurant Operations
Nidhi Vora
 
New maturity-model-can-fire-up-restaurant-operations
New maturity-model-can-fire-up-restaurant-operationsNew maturity-model-can-fire-up-restaurant-operations
New maturity-model-can-fire-up-restaurant-operations
siya4
 
New Maturity Model by Wipro Ecoenergy Can Fire Up Restaurant Operations
New Maturity Model by Wipro Ecoenergy Can Fire Up Restaurant OperationsNew Maturity Model by Wipro Ecoenergy Can Fire Up Restaurant Operations
New Maturity Model by Wipro Ecoenergy Can Fire Up Restaurant Operations
Shreeja Sahadevan
 
Modernizing complex MRO processes
Modernizing complex MRO processesModernizing complex MRO processes
Modernizing complex MRO processes
TIP Technologies
 
CAPP, MRP, CRP, CAQC (model 2)
CAPP, MRP, CRP, CAQC (model 2) CAPP, MRP, CRP, CAQC (model 2)
CAPP, MRP, CRP, CAQC (model 2)
Deepika V S
 
Lubrication Maturity Matrix
Lubrication Maturity MatrixLubrication Maturity Matrix
Lubrication Maturity Matrix
Ricky Smith CMRP, CMRT
 
Evm intro. slide deck 13 may 2018
Evm intro. slide deck 13 may 2018Evm intro. slide deck 13 may 2018
Evm intro. slide deck 13 may 2018
Roger H. Mandel
 
PRODUCTION PLANNING AND CONTROL
PRODUCTION PLANNING AND CONTROL PRODUCTION PLANNING AND CONTROL
PRODUCTION PLANNING AND CONTROL
AttiMurugan
 
Machine Maintenance Management Predictive Analytics Use Case - Smarten
Machine Maintenance Management Predictive Analytics Use Case - SmartenMachine Maintenance Management Predictive Analytics Use Case - Smarten
Machine Maintenance Management Predictive Analytics Use Case - Smarten
Smarten Augmented Analytics
 
Internal Quality Control Lecture MD General 2014 Course, Clin Path Ain Shams ...
Internal Quality Control Lecture MD General 2014 Course, Clin Path Ain Shams ...Internal Quality Control Lecture MD General 2014 Course, Clin Path Ain Shams ...
Internal Quality Control Lecture MD General 2014 Course, Clin Path Ain Shams ...Adel Elazab Elged
 
Joel Marusiak, Neovia Logistics presenatation at Spare Parts 2013
Joel Marusiak, Neovia Logistics presenatation at Spare Parts 2013Joel Marusiak, Neovia Logistics presenatation at Spare Parts 2013
Joel Marusiak, Neovia Logistics presenatation at Spare Parts 2013
Copperberg
 
KITARON Finite Capacity Production Planning system
KITARON Finite Capacity Production Planning systemKITARON Finite Capacity Production Planning system
KITARON Finite Capacity Production Planning system
Geosoft Systems
 

Similar to Inventory Accuracy Improvement Plan (20)

Evm power point 25 august 2015 prams co (2)
Evm power point 25 august 2015 prams co (2)Evm power point 25 august 2015 prams co (2)
Evm power point 25 august 2015 prams co (2)
 
Evm power point 25 august 2015 prams co (2)
Evm power point 25 august 2015 prams co (2)Evm power point 25 august 2015 prams co (2)
Evm power point 25 august 2015 prams co (2)
 
calibrationintervalspresentation.pdf
calibrationintervalspresentation.pdfcalibrationintervalspresentation.pdf
calibrationintervalspresentation.pdf
 
Smart Pharmaceutical Consulting - Lean Manufacturing of Pharmaceuticals
Smart Pharmaceutical Consulting - Lean Manufacturing of PharmaceuticalsSmart Pharmaceutical Consulting - Lean Manufacturing of Pharmaceuticals
Smart Pharmaceutical Consulting - Lean Manufacturing of Pharmaceuticals
 
Key steps in transforming a calibration program slideshare
Key steps in transforming a calibration program slideshareKey steps in transforming a calibration program slideshare
Key steps in transforming a calibration program slideshare
 
New Maturity Model Can Fire Up Restaurant Operations
New Maturity Model Can Fire Up Restaurant OperationsNew Maturity Model Can Fire Up Restaurant Operations
New Maturity Model Can Fire Up Restaurant Operations
 
New maturity-model-can-fire-up-restaurant-operations
New maturity-model-can-fire-up-restaurant-operationsNew maturity-model-can-fire-up-restaurant-operations
New maturity-model-can-fire-up-restaurant-operations
 
New Maturity Model Can Fire Up Restaurant Operations
New Maturity Model Can Fire Up Restaurant OperationsNew Maturity Model Can Fire Up Restaurant Operations
New Maturity Model Can Fire Up Restaurant Operations
 
New Maturity Model Can Fire Up Restaurant Operations
New Maturity Model Can Fire Up Restaurant OperationsNew Maturity Model Can Fire Up Restaurant Operations
New Maturity Model Can Fire Up Restaurant Operations
 
New maturity-model-can-fire-up-restaurant-operations
New maturity-model-can-fire-up-restaurant-operationsNew maturity-model-can-fire-up-restaurant-operations
New maturity-model-can-fire-up-restaurant-operations
 
New Maturity Model by Wipro Ecoenergy Can Fire Up Restaurant Operations
New Maturity Model by Wipro Ecoenergy Can Fire Up Restaurant OperationsNew Maturity Model by Wipro Ecoenergy Can Fire Up Restaurant Operations
New Maturity Model by Wipro Ecoenergy Can Fire Up Restaurant Operations
 
Modernizing complex MRO processes
Modernizing complex MRO processesModernizing complex MRO processes
Modernizing complex MRO processes
 
CAPP, MRP, CRP, CAQC (model 2)
CAPP, MRP, CRP, CAQC (model 2) CAPP, MRP, CRP, CAQC (model 2)
CAPP, MRP, CRP, CAQC (model 2)
 
Lubrication Maturity Matrix
Lubrication Maturity MatrixLubrication Maturity Matrix
Lubrication Maturity Matrix
 
Evm intro. slide deck 13 may 2018
Evm intro. slide deck 13 may 2018Evm intro. slide deck 13 may 2018
Evm intro. slide deck 13 may 2018
 
PRODUCTION PLANNING AND CONTROL
PRODUCTION PLANNING AND CONTROL PRODUCTION PLANNING AND CONTROL
PRODUCTION PLANNING AND CONTROL
 
Machine Maintenance Management Predictive Analytics Use Case - Smarten
Machine Maintenance Management Predictive Analytics Use Case - SmartenMachine Maintenance Management Predictive Analytics Use Case - Smarten
Machine Maintenance Management Predictive Analytics Use Case - Smarten
 
Internal Quality Control Lecture MD General 2014 Course, Clin Path Ain Shams ...
Internal Quality Control Lecture MD General 2014 Course, Clin Path Ain Shams ...Internal Quality Control Lecture MD General 2014 Course, Clin Path Ain Shams ...
Internal Quality Control Lecture MD General 2014 Course, Clin Path Ain Shams ...
 
Joel Marusiak, Neovia Logistics presenatation at Spare Parts 2013
Joel Marusiak, Neovia Logistics presenatation at Spare Parts 2013Joel Marusiak, Neovia Logistics presenatation at Spare Parts 2013
Joel Marusiak, Neovia Logistics presenatation at Spare Parts 2013
 
KITARON Finite Capacity Production Planning system
KITARON Finite Capacity Production Planning systemKITARON Finite Capacity Production Planning system
KITARON Finite Capacity Production Planning system
 

Inventory Accuracy Improvement Plan

  • 2. ●Bin accuracy is 89.5% ●Inventory accuracy is 96% ●Excessive “No Location Summary” units ●Stockouts during sales was 2.5% per 1k orders CURRENT STATE
  • 3. ●Meet inventory accuracy requirements ●Maintain .01% stockout levels FUTURE STATE
  • 4. 1. Consistent cycle counting program 2.Monitor inventory adjustments 3.Effective space management 4.Thorough training of IC associates IMPLEMENTATION PLAN
  • 5. CYCLE COUNTING PROGRAM CURRENT STATE Inconsistent counts Three and under counts Variances are not confirmed FUTURE STATE Dedicated cycle counters 10 and under counts Confirm variances before accepting adjustments
  • 6. MONITORING ADJUSTMENTS CURRENT STATE “CC” adjustment code used for all transactions Daily adjustments are not monitored FUTURE STATE Utilize Adjustment Reason codes Obtain and review adjustment report
  • 7. SPACE MANAGEMENT CURRENT STATE SKUs are spread across multiple locations Excess distance between additional locations FUTURE STATE SKU consolidation based on cube utilization System directed putaway for identical SKUs
  • 8. TRAINING PROGRAM CURRENT STATE Minimal training on new associates Inconsistent training across the board FUTURE STATE Comprehensive training and satisfactory test completion Analytical aptitude test for core associates
  • 9. IC CPU AND HITTING COSTS
  • 10. MEETING CPU GOALS IN PRODUCTION Receiving 2 million units Shipping 2 million units