The document discusses the Nam Theun 2 hydroelectric project in Laos and its environmental and social impacts. It provides details on the project such as its size of 4000 square km, power generation capacity of 1080 MW, number of households relocated at 1300, and total cost of $1.25 billion. It also mentions the project allocates $110 million for environmental and social programs. The document then discusses approaches to addressing risks of impoverishment for resettled communities and restoring livelihoods in a culturally sensitive manner through understanding socioeconomic situations, communication, consultation, compensation, adaptation, and long-term monitoring.