                   Improved Local Search for Job Shop
                   Scheduling with Uncertain Durations

                    Inés González-Rodríguez1 Camino R. Vela2
                   Jorge Puente2 Alejandro Hernández-Arauzo2

                             1 Dept.    of Mathematics, Statistics and Computing,
                                          University of Cantabria (Spain)
                               2 Dept.   of Computer Science and A.I. Centre,
                                          University of Oviedo (Spain)


                                                 ICAPS 2009.
The Fuzzy Job Shop Scheduling Problem   Improved Local Search   Experimental Results   Conclusions   References



Starting Point



      Previous work on job shop scheduling with uncertain durations:
              using local search
              very competitive makespan values :)
              but with a high computational load :(

      We would like to. . .
      keep makespan quality while improving efficiency.
The Fuzzy Job Shop Scheduling Problem   Improved Local Search   Experimental Results   Conclusions   References



Outline


      1    The Fuzzy Job Shop Scheduling Problem

      2    Improved Local Search
             Existing Approach
             Makespan Calculation for Neighbours
             Makespan Lower Bound
             Reduced Neighbourhood

      3    Experimental Results

      4    Conclusions
The Fuzzy Job Shop Scheduling Problem   Improved Local Search   Experimental Results   Conclusions   References



Job Shop Scheduling Problem



                                                                                        J1




                                                                                        J2




                                                                                        J3
The Fuzzy Job Shop Scheduling Problem   Improved Local Search   Experimental Results   Conclusions   References



Job Shop Scheduling Problem



                                                                                         J1




                                                                                         J2




                                                                                         J3
The Fuzzy Job Shop Scheduling Problem   Improved Local Search   Experimental Results   Conclusions   References



Job Shop Scheduling Problem



                                                                                         J1




                                                                                         J2




                                                                                         J3
The Fuzzy Job Shop Scheduling Problem   Improved Local Search   Experimental Results   Conclusions   References



Job Shop Scheduling Problem



                                                                                          J1




                                                                                          J2




                                                                                          J3
The Fuzzy Job Shop Scheduling Problem   Improved Local Search   Experimental Results   Conclusions   References



Motivation For Uncertainty




             Classical JSP assumes complete knowledge! about
             processing times. But. . .
             what can we do if we only have incomplete knowledge?
              (Un)fortunately, THE REAL WORLD IS FULL OF
              UNCERTAINTY !!!
The Fuzzy Job Shop Scheduling Problem        Improved Local Search   Experimental Results   Conclusions   References



Triangular Fuzzy Numbers




      Assume we only know:
              an interval of possible values for the duration [a1 , a3 ],

                                        a1                                   a3
The Fuzzy Job Shop Scheduling Problem        Improved Local Search   Experimental Results   Conclusions   References



Triangular Fuzzy Numbers




      Assume we only know:
              an interval of possible values for the duration [a1 , a3 ],
              the most likely duration a2 in this interval.




                                        a1                  a2               a3
The Fuzzy Job Shop Scheduling Problem        Improved Local Search   Experimental Results   Conclusions   References



Triangular Fuzzy Numbers




      This knowledge is represented by a triangular fuzzy number,
      TFN, A = (a1 , a2 , a3 ):




                                        a1                  a2               a3
The Fuzzy Job Shop Scheduling Problem   Improved Local Search   Experimental Results   Conclusions   References



Working With Triangular Fuzzy Numbers


              addition:

                                 A + B = (a1 + b1 , a2 + b2 , a3 + b3 )

              maximum:

                  max(A, B) ≈ (max{a1 , b1 }, max{a2 , b2 }, max{a3 , b3 })

              expected value:

                                                     1 1
                                        E[A] =         (a + 2a2 + a3 )
                                                     4
The Fuzzy Job Shop Scheduling Problem       Improved Local Search   Experimental Results   Conclusions   References



Solution Graph With TFNs

      A solution is represented by an acyclic graph:
                                                   (3, 4, 7)
                                        1                           2
                                             (3, 4, 7)                                (1, 2, 3)

                                            (4, 5, 6)                          (2, 3, 4)
          0                             3                           4                             7

                           (4, 5, 6)                (1, 2, 6)           (2, 3, 4)
                                                                                      (1, 2, 4)

                                        5                           6
                                                   (1, 2, 6)
      or by a task processing order: π =(1 3 5 4 2 6).
The Fuzzy Job Shop Scheduling Problem   Improved Local Search   Experimental Results   Conclusions   References



Fuzzy? Schedule




      What is fuzzy in this schedule?
              Task starting and completion times and the makespan are
              fuzzy.
              But, the task processing order is precise.
The Fuzzy Job Shop Scheduling Problem   Improved Local Search   Experimental Results   Conclusions   References



Optimal Makespan


      We want to minimise a fuzzy makespan. But. . .
            Problem It is not clear when a TFN is less than another:
The Fuzzy Job Shop Scheduling Problem   Improved Local Search   Experimental Results   Conclusions   References



Optimal Makespan


      We want to minimise a fuzzy makespan. But. . .
            Problem It is not clear when a TFN is less than another:




            Solution The expected value defines a total ordering;
                     A ≤E B iff E[A] ≤ E[B]:
The Fuzzy Job Shop Scheduling Problem   Improved Local Search   Experimental Results   Conclusions   References



Optimal Makespan


      We want to minimise a fuzzy makespan. But. . .
            Problem It is not clear when a TFN is less than another:




            Solution The expected value defines a total ordering;
                     A ≤E B iff E[A] ≤ E[B]:

      Objective for FJSP
      Minimise the expected makespan E[Cmax ]
The Fuzzy Job Shop Scheduling Problem           Improved Local Search   Experimental Results    Conclusions   References



Criticality With Exact Durations

                                                              3
                                            1                           2
                                                      3                                     1

                                                          4                             2
          0                                 3                           4                            7

                                        4               1                   2
                                                                                            1

                                            5                           6
                                                              1
      Critical path: (3, 4, 6); critical arcs: (4, 6); critical blocks:
      (3), (4, 6).
The Fuzzy Job Shop Scheduling Problem       Improved Local Search   Experimental Results   Conclusions   References



Criticality With TFNs: Parallel Graphs


                                             Solution Graph G:
                                                   (3, 4, 7)
                                        1                           2
                                             (3, 4, 7)                                (1, 2, 3)

                                            (4, 5, 6)                          (2, 3, 4)
          0                             3                           4                             7

                           (4, 5, 6)                (1, 2, 6)           (2, 3, 4)
                                                                                      (1, 2, 4)

                                        5                           6
                                                   (1, 2, 6)
The Fuzzy Job Shop Scheduling Problem       Improved Local Search   Experimental Results   Conclusions   References



Criticality With TFNs: Parallel Graphs

                                    Parallel Solution Graph G1 :
                                                    (3,4,7)
                                        1                           2
                                              (3,4,7)                                 (1,2,3)

                                             (4,5,6)                           (2,3,4)
          0                             3                           4                           7

                             (4,5,6)                (1,2,6)             (2,3,4)
                                                                                      (1,2,4)

                                        5                           6
                                                    (1,2,6)
                                                         1
                                  Critical path: 3,4,6; Cmax = 7
The Fuzzy Job Shop Scheduling Problem       Improved Local Search   Experimental Results   Conclusions   References



Criticality With TFNs: Parallel Graphs

                                             Solution Graph G:
                                                   (3, 4, 7)
                                        1                           2
                                             (3, 4, 7)                                (1, 2, 3)

                                            (4, 5, 6)                          (2, 3, 4)
          0                             3                           4                             7

                           (4, 5, 6)                (1, 2, 6)           (2, 3, 4)
                                                                                      (1, 2, 4)

                                        5                           6
                                                   (1, 2, 6)
                   Critical paths: [3,4,6], [3,5,6]; Cmax = (7, 10, 16)
The Fuzzy Job Shop Scheduling Problem   Improved Local Search   Experimental Results   Conclusions   References



Previous Neighbourhood


      Idea: obtain neighbours by reversing every resource critical arc.
      Definition
      Take
              a task processing order π
              a resource arc v = (x, y ) in the associated solution graph
              π(v ) , the order obtained from π after reversing arc v .
      The neighbourhood structure obtained from π is:

                             H(π) = {π(v ) : v ∈ R(π) is critical}.
The Fuzzy Job Shop Scheduling Problem       Improved Local Search   Experimental Results   Conclusions   References



Previous Neighbourhood

                            Solution Graph G(π), π=(1 3 5 4 2 6)
                                                   (3, 4, 7)
                                        1                           2
                                             (3, 4, 7)                                (1, 2, 3)

                                            (4, 5, 6)                          (2, 3, 4)
          0                             3                           4                             7

                           (4, 5, 6)                (1, 2, 6)           (2, 3, 4)
                                                                                      (1, 2, 4)

                                        5                           6
                                                   (1, 2, 6)
                   Critical paths: [3,4,6], [3,5,6]; Cmax = (7, 10, 16)
The Fuzzy Job Shop Scheduling Problem       Improved Local Search   Experimental Results   Conclusions   References



Previous Neighbourhood


                   Neighbour Solution Graph G(σ), σ=(1 5 3 4 2 6)
                                                   (3, 4, 7)
                                        1                           2
                                             (3, 4, 7)                                (1, 2, 3)
                                            (4, 5, 6)
                                            (4, 5, 6)                          (2, 3, 4)
          0                             3                           4                             7

                                                                        (2, 3, 4)
                                                                                      (1, 2, 4)
                                            (1, 2, 6)
                                        5                           6
                                                   (1, 2, 6)
The Fuzzy Job Shop Scheduling Problem   Improved Local Search   Experimental Results   Conclusions   References



Previous Neighbourhood: Properties



      Good News :)
              All neighbours in H are feasible solutions.
              The reversal of a non-critical arc can never reduce
              makespan.
The Fuzzy Job Shop Scheduling Problem   Improved Local Search   Experimental Results   Conclusions   References



Previous Neighbourhood: Properties



      Good News :)
              All neighbours in H are feasible solutions.
              The reversal of a non-critical arc can never reduce
              makespan.

      Bad News :(
      In the fuzzy case, the neighbourhood has a considerable size,
      with the consequent increase in computational cost.
The Fuzzy Job Shop Scheduling Problem   Improved Local Search   Experimental Results   Conclusions   References



Proposed Improvements




      How can we improve the neighbourhood structure? Ideas:
         1    More efficient makespan calculation for neighbours.
         2    Use inexpensive makespan lower bound to discard
              neighbours.
         3    Reduce neighbourhood.
The Fuzzy Job Shop Scheduling Problem   Improved Local Search   Experimental Results   Conclusions   References



Neighbour’s Makespan Calculation




      Idea: avoid unnecesary calculations using available information
              Makespan (and more) known for initial solution π;
              Neighbour σ = πv differs from π “only” in the reversal of an
              arc.
The Fuzzy Job Shop Scheduling Problem   Improved Local Search   Experimental Results   Conclusions   References



Heads and Tails



      Definition
      For a solution graph G(π) and a task x with processing time px :
              The head of x is the starting time of x, denoted rx :

                                  rx = max{rPJx + pPJx , rPνx + pPνx }

              The tail of x is the time lag between x’s completion time
              and the completion time of the last task, denoted qx :

                                 qx = max{qSJx + pSJx , qSνx + pSνx }
The Fuzzy Job Shop Scheduling Problem   Improved Local Search   Experimental Results   Conclusions   References



Heads and Tails in the Neighbour


            Pνx                  π                        Pνx            σ = π(x,y )


            PJx         x      SJx                        PJx        x       SJx


                      PJy        y      SJy                        PJy         y       SJy


                                        Sνy                                            Sνy


      To calculate heads (tails) in σ, we need only re-calculate the
      heads (tails) of tasks from x onwards (backwards) in G(σ).
The Fuzzy Job Shop Scheduling Problem   Improved Local Search   Experimental Results   Conclusions   References



Neighbour’s Makespan Lower Bound




      Idea:
              We are only interested in neighbours with improving
              makespan.
              Use makespan lower bound to discard non-improving
              neighbours.
      How can we calculate an inexpensive lower bound?
The Fuzzy Job Shop Scheduling Problem   Improved Local Search   Experimental Results   Conclusions   References



Makespan After a Move

      Notation for a processing order π and tasks x and y :
              D[P] a TFN where D i [P] is the length of the longest path in
              a set of paths P of Gi , i = 1, 2, 3.
              Pπ (x ∨ y ): set of all paths in the solution graph G(π)
              containing x or y ;
              Pπ (x ∧ y ): set of all paths in G(π) containing both x and y ;
              Pπ (¬x): set of all paths in G(π) not containing x.

      Proposition
      For σ = π(v ) , where v = (x, y ) is an arc in G(π)

                        Cmax (σ) = max{D[Pπ (¬x)], D[Pσ (x ∨ y )]}
The Fuzzy Job Shop Scheduling Problem   Improved Local Search   Experimental Results   Conclusions   References



Lower Bound for Makespan After a Move


      Consequence: D[Pσ (x ∨ y )] ≤E Cmax (σ). Using heads and
      tails:
      Corollary
      Let rx (qx ) be the head (tail) of x in σ = π(x,y ) . The TFN

                          LBσ = max{rx + px + qx , ry + py + qy }

      provides a lower bound for Cmax (σ).

      If Cmax (π) ≤E LBσ , we already know the neighbour is not
      improving.
The Fuzzy Job Shop Scheduling Problem   Improved Local Search   Experimental Results   Conclusions   References



Idea to Reduce Neighbourhood




              In the crisp case, reversing arcs inside a critical block does
              not improve the makespan.
              Can we prove the same for the fuzzy job shop?
The Fuzzy Job Shop Scheduling Problem   Improved Local Search   Experimental Results   Conclusions   References



Reduced Neighbourhood



      Definition
      If V(π) is the set of all arcs in the extreme of a critical block, the
      reduced neighbourhood structure for π is:

                                    HR (π) = {π(v ) : v ∈ V(π)}.

      Properties
              HR (π) ⊂ H(π)
              HR (π) contains only feasible schedules
The Fuzzy Job Shop Scheduling Problem   Improved Local Search   Experimental Results   Conclusions   References



Reduced Neighbourhood




      The discarded neighbours from H(π) − HR (π) never improve
      the makespan.
      Theorem
      For a feasible processing order π,

                     ∀σ ∈ H(π) − HR (π), E[Cmax (π)] ≤ E[Cmax (σ)]
The Fuzzy Job Shop Scheduling Problem   Improved Local Search   Experimental Results   Conclusions   References



Reduced Neighbourhood




      Sufficient condition for optimality:
      Proposition
      If the neighbourhood HR (π) = ∅, then π is an optimal
      processing order.

      If the local search procedure stops because the neighbourhood
      is empty, it has found a global optimum.
The Fuzzy Job Shop Scheduling Problem   Improved Local Search   Experimental Results   Conclusions   References



Experiment Setup



      Goal
      Evaluate empirically the contribution of our proposals to
      improving local search efficiency.

      Problem Instances
         1    Take 12 crisp hard job shop benchmark problems;
         2    Generate 10 fuzzy versions of each instance (durations:
              TFNs with a2 = original value).
      Total of 120 fuzzy job shop instances.
The Fuzzy Job Shop Scheduling Problem   Improved Local Search   Experimental Results   Conclusions   References



Experiment Setup




      Solving Method
      Based on memetic algorithm GVPV08 proposed in ICAPS
      2008 [2] combining:
              GA: Genetic algorithm
              LS: Hill-climbing with H.
      We plug 3 new proposals in the local search.
The Fuzzy Job Shop Scheduling Problem   Improved Local Search   Experimental Results   Conclusions   References



Experiment Setup




              GVPV08 compared favourably with state-of-the-art
              methods (SA [1] and GA [3]) in terms of makespan.
              New improvements do not affect makespan, only
              computational load of LS.
      We know results will be “good” re. makespan; our aim is to
      evaluate efficiency improvement.
The Fuzzy Job Shop Scheduling Problem   Improved Local Search   Experimental Results   Conclusions   References



Scheduling Neighbours With Heads and Tails

              Problem      Size   GVPV08 (s) MA (s) Red%
               FT10      10 × 10     801.2       588.2 26.59%
               FT20       20 × 5    1693.9        682.1 59.73%
                La21     15 × 10    1769.4       1072.8 39.37%
                La24     15 × 10    1562.4        950.1 39.19%
                La25     15 × 10    1722.8        993.7 42.32%
                La27     20 × 10    4137.8       2242.8 45.80%
                La29     20 × 10    3936.0       2071.7 47.37%
                La38     15 × 15    3037,6       2556.7 15.83%
                La40     15 × 15    3220.4       2652.2 17.64%
               ABZ7      20 × 15    7396.1       5294.7 28.41%
               ABZ8      20 × 15    8098.5       5780.9 28.62%
               ABZ9      20 × 15    7308.0       5652.1 22.66%
                 Average CPU time reduction of 34.5% using MA
The Fuzzy Job Shop Scheduling Problem   Improved Local Search   Experimental Results   Conclusions   References



Makespan Estimate And Reduced Neighbourhood


      Incorporate proposed improvements to MA (using heads and
      tails):
         1    MA(R)= MA using HR instead of H.
         2    MA(LB) = MA using LB to estimate makespan.
         3    MA(LB+R) = MA using both HR and LB.
      We compare:
              number of evaluated neighbours,
              CPU time in seconds
      (averaged across 30 executions and 10 fuzzy instances of each
      problem).
The Fuzzy Job Shop Scheduling Problem   Improved Local Search   Experimental Results    Conclusions   References



Number Of Evaluated Neighbours

          Problem              MA                MA(R)            MA(LB)               MA(R+LB)
          FT10              2.83E+07           1.44E+07          6.25E+06              3.61E+06
          FT20              6.78E+07           1.14E+07          2.25E+07              5.16E+06
          La21              4.46E+07           1.93E+07          1.07E+07              5.76E+06
          La24              3.87E+07           2.04E+07          9.00E+06              5.59E+06
          La25              4.28E+07           1.78E+07          1.03E+07              5.75E+06
          La27              8.37E+07           2.77E+07          2.53E+07              9.79E+06
          La29              7.85E+07           2.44E+07          2.40E+07              8.90E+06
          La38              5.16E+07           3.10E+07          1.11E+07              8.02E+06
          La40              5.42E+07           3.03E+07          1.16E+07              8.42E+06
          ABZ7              9.74E+07           4.07E+07          2.57E+07              1.30E+07
          ABZ8              1.08E+08           4.60E+07          2.87E+07              1.48E+07
          ABZ9              9.65E+07           4.43E+07          2.42E+07              1.33E+07
          Av. Red.              –                 57%               75%                   87%
The Fuzzy Job Shop Scheduling Problem   Improved Local Search   Experimental Results   Conclusions   References



CPU Time In Seconds

                 Problem             MA         MA(R)           MA(LB)         MA(R+LB)
                 FT10               588.2       372.90           179.3          166.5
                 FT20               682.1        283.1           295.4          211.0
                 La21              1072.8        610.9           327.8          292.2
                 La24               950.1        636.4           304.5          284.0
                 La25               993.7        555.3           322.4          289.5
                 La27              2242.8       1072.5           641.9          511.6
                 La29              2071.7        962.8           609.8          485.8
                 La38              2556.7       1732.8           546.7          514.0
                 La40              2652.2       1643.2           565.1          531.5
                 ABZ7              5294.7       2671.0          1073.8          898.4
                 ABZ8              5780.9       2936.5          1168.0          975.2
                 ABZ9              5652.1       3107.7          1078.5          925.8
                 Av. Red.             –          45%             73%             76%
The Fuzzy Job Shop Scheduling Problem   Improved Local Search   Experimental Results   Conclusions   References



Conclusions



      Previous work: good makespan but high computational cost.
      Proposed improvements:
         1    Simple but effective neighbour scheduling algorithm.
         2    Makespan estimate: evaluate only 25% of neighbours.
         3    Reduced neighbourhood structure: < 1/2 of original
              neighbourhood.

      Combined Use
      Evaluate 13% of original neighbours in 23% of CPU time!!!
The Fuzzy Job Shop Scheduling Problem   Improved Local Search   Experimental Results   Conclusions   References



Future Work




              Better neighbourhood structures to improve makespan.
              Alternative meta-heuristics (taboo search, PSO,. . . ).
              Alternative uncertainty models.
The Fuzzy Job Shop Scheduling Problem   Improved Local Search   Experimental Results   Conclusions   References



References I


             Fortemps, P. (1997) Jobshop scheduling with imprecise
             durations: a fuzzy approach.
             IEEE Transactions of Fuzzy Systems 7:557–569.
             González Rodríguez, I.; Vela, C. R.; Puente, J.; and Varela,
             R. (2008) A new local search for the job shop problem with
             uncertain durations.
             In Proc. of ICAPS08, 124–131. Sidney: AAAI Press
             Sakawa, M., and Kubota, R. (2000) Fuzzy programming for
             multiobjective job shop scheduling with fuzzy processing
             time and fuzzy duedate through genetic algorithms.
             European Journal of Operational Research 120:393–407.
The Fuzzy Job Shop Scheduling Problem   Improved Local Search   Experimental Results   Conclusions   References



References II




             Taillard, E. D. (1994) Parallel taboo search techniques for
             the job shop scheduling problem.
             ORSA Journal on Computing 6(2):108–117.
             Van Laarhoven, P.; Aarts, E.; and Lenstra, K. (1992) Job
             shop scheduling by simulated annealing.
             Operations Research 40:113–125.

More Related Content

Recently uploaded

Spellings Wk 4 and Wk 5 for Grade 4 at CAPS
Spellings Wk 4 and Wk 5 for Grade 4 at CAPSSpellings Wk 4 and Wk 5 for Grade 4 at CAPS
Spellings Wk 4 and Wk 5 for Grade 4 at CAPS
AnaAcapella
 
Transparency, Recognition and the role of eSealing - Ildiko Mazar and Koen No...
Transparency, Recognition and the role of eSealing - Ildiko Mazar and Koen No...Transparency, Recognition and the role of eSealing - Ildiko Mazar and Koen No...
Transparency, Recognition and the role of eSealing - Ildiko Mazar and Koen No...
EADTU
 

Recently uploaded (20)

21st_Century_Skills_Framework_Final_Presentation_2.pptx
21st_Century_Skills_Framework_Final_Presentation_2.pptx21st_Century_Skills_Framework_Final_Presentation_2.pptx
21st_Century_Skills_Framework_Final_Presentation_2.pptx
 
How to Manage Call for Tendor in Odoo 17
How to Manage Call for Tendor in Odoo 17How to Manage Call for Tendor in Odoo 17
How to Manage Call for Tendor in Odoo 17
 
FSB Advising Checklist - Orientation 2024
FSB Advising Checklist - Orientation 2024FSB Advising Checklist - Orientation 2024
FSB Advising Checklist - Orientation 2024
 
NO1 Top Black Magic Specialist In Lahore Black magic In Pakistan Kala Ilam Ex...
NO1 Top Black Magic Specialist In Lahore Black magic In Pakistan Kala Ilam Ex...NO1 Top Black Magic Specialist In Lahore Black magic In Pakistan Kala Ilam Ex...
NO1 Top Black Magic Specialist In Lahore Black magic In Pakistan Kala Ilam Ex...
 
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptxHMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
 
Spellings Wk 4 and Wk 5 for Grade 4 at CAPS
Spellings Wk 4 and Wk 5 for Grade 4 at CAPSSpellings Wk 4 and Wk 5 for Grade 4 at CAPS
Spellings Wk 4 and Wk 5 for Grade 4 at CAPS
 
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptxHMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
 
What is 3 Way Matching Process in Odoo 17.pptx
What is 3 Way Matching Process in Odoo 17.pptxWhat is 3 Way Matching Process in Odoo 17.pptx
What is 3 Way Matching Process in Odoo 17.pptx
 
Jamworks pilot and AI at Jisc (20/03/2024)
Jamworks pilot and AI at Jisc (20/03/2024)Jamworks pilot and AI at Jisc (20/03/2024)
Jamworks pilot and AI at Jisc (20/03/2024)
 
COMMUNICATING NEGATIVE NEWS - APPROACHES .pptx
COMMUNICATING NEGATIVE NEWS - APPROACHES .pptxCOMMUNICATING NEGATIVE NEWS - APPROACHES .pptx
COMMUNICATING NEGATIVE NEWS - APPROACHES .pptx
 
How to setup Pycharm environment for Odoo 17.pptx
How to setup Pycharm environment for Odoo 17.pptxHow to setup Pycharm environment for Odoo 17.pptx
How to setup Pycharm environment for Odoo 17.pptx
 
dusjagr & nano talk on open tools for agriculture research and learning
dusjagr & nano talk on open tools for agriculture research and learningdusjagr & nano talk on open tools for agriculture research and learning
dusjagr & nano talk on open tools for agriculture research and learning
 
AIM of Education-Teachers Training-2024.ppt
AIM of Education-Teachers Training-2024.pptAIM of Education-Teachers Training-2024.ppt
AIM of Education-Teachers Training-2024.ppt
 
Transparency, Recognition and the role of eSealing - Ildiko Mazar and Koen No...
Transparency, Recognition and the role of eSealing - Ildiko Mazar and Koen No...Transparency, Recognition and the role of eSealing - Ildiko Mazar and Koen No...
Transparency, Recognition and the role of eSealing - Ildiko Mazar and Koen No...
 
How to Add New Custom Addons Path in Odoo 17
How to Add New Custom Addons Path in Odoo 17How to Add New Custom Addons Path in Odoo 17
How to Add New Custom Addons Path in Odoo 17
 
Diuretic, Hypoglycemic and Limit test of Heavy metals and Arsenic.-1.pdf
Diuretic, Hypoglycemic and Limit test of Heavy metals and Arsenic.-1.pdfDiuretic, Hypoglycemic and Limit test of Heavy metals and Arsenic.-1.pdf
Diuretic, Hypoglycemic and Limit test of Heavy metals and Arsenic.-1.pdf
 
Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)
 
OS-operating systems- ch05 (CPU Scheduling) ...
OS-operating systems- ch05 (CPU Scheduling) ...OS-operating systems- ch05 (CPU Scheduling) ...
OS-operating systems- ch05 (CPU Scheduling) ...
 
80 ĐỀ THI THỬ TUYỂN SINH TIẾNG ANH VÀO 10 SỞ GD – ĐT THÀNH PHỐ HỒ CHÍ MINH NĂ...
80 ĐỀ THI THỬ TUYỂN SINH TIẾNG ANH VÀO 10 SỞ GD – ĐT THÀNH PHỐ HỒ CHÍ MINH NĂ...80 ĐỀ THI THỬ TUYỂN SINH TIẾNG ANH VÀO 10 SỞ GD – ĐT THÀNH PHỐ HỒ CHÍ MINH NĂ...
80 ĐỀ THI THỬ TUYỂN SINH TIẾNG ANH VÀO 10 SỞ GD – ĐT THÀNH PHỐ HỒ CHÍ MINH NĂ...
 
Michaelis Menten Equation and Estimation Of Vmax and Tmax.pptx
Michaelis Menten Equation and Estimation Of Vmax and Tmax.pptxMichaelis Menten Equation and Estimation Of Vmax and Tmax.pptx
Michaelis Menten Equation and Estimation Of Vmax and Tmax.pptx
 

Featured

How Race, Age and Gender Shape Attitudes Towards Mental Health
How Race, Age and Gender Shape Attitudes Towards Mental HealthHow Race, Age and Gender Shape Attitudes Towards Mental Health
How Race, Age and Gender Shape Attitudes Towards Mental Health
ThinkNow
 
Social Media Marketing Trends 2024 // The Global Indie Insights
Social Media Marketing Trends 2024 // The Global Indie InsightsSocial Media Marketing Trends 2024 // The Global Indie Insights
Social Media Marketing Trends 2024 // The Global Indie Insights
Kurio // The Social Media Age(ncy)
 

Featured (20)

2024 State of Marketing Report – by Hubspot
2024 State of Marketing Report – by Hubspot2024 State of Marketing Report – by Hubspot
2024 State of Marketing Report – by Hubspot
 
Everything You Need To Know About ChatGPT
Everything You Need To Know About ChatGPTEverything You Need To Know About ChatGPT
Everything You Need To Know About ChatGPT
 
Product Design Trends in 2024 | Teenage Engineerings
Product Design Trends in 2024 | Teenage EngineeringsProduct Design Trends in 2024 | Teenage Engineerings
Product Design Trends in 2024 | Teenage Engineerings
 
How Race, Age and Gender Shape Attitudes Towards Mental Health
How Race, Age and Gender Shape Attitudes Towards Mental HealthHow Race, Age and Gender Shape Attitudes Towards Mental Health
How Race, Age and Gender Shape Attitudes Towards Mental Health
 
AI Trends in Creative Operations 2024 by Artwork Flow.pdf
AI Trends in Creative Operations 2024 by Artwork Flow.pdfAI Trends in Creative Operations 2024 by Artwork Flow.pdf
AI Trends in Creative Operations 2024 by Artwork Flow.pdf
 
Skeleton Culture Code
Skeleton Culture CodeSkeleton Culture Code
Skeleton Culture Code
 
PEPSICO Presentation to CAGNY Conference Feb 2024
PEPSICO Presentation to CAGNY Conference Feb 2024PEPSICO Presentation to CAGNY Conference Feb 2024
PEPSICO Presentation to CAGNY Conference Feb 2024
 
Content Methodology: A Best Practices Report (Webinar)
Content Methodology: A Best Practices Report (Webinar)Content Methodology: A Best Practices Report (Webinar)
Content Methodology: A Best Practices Report (Webinar)
 
How to Prepare For a Successful Job Search for 2024
How to Prepare For a Successful Job Search for 2024How to Prepare For a Successful Job Search for 2024
How to Prepare For a Successful Job Search for 2024
 
Social Media Marketing Trends 2024 // The Global Indie Insights
Social Media Marketing Trends 2024 // The Global Indie InsightsSocial Media Marketing Trends 2024 // The Global Indie Insights
Social Media Marketing Trends 2024 // The Global Indie Insights
 
Trends In Paid Search: Navigating The Digital Landscape In 2024
Trends In Paid Search: Navigating The Digital Landscape In 2024Trends In Paid Search: Navigating The Digital Landscape In 2024
Trends In Paid Search: Navigating The Digital Landscape In 2024
 
5 Public speaking tips from TED - Visualized summary
5 Public speaking tips from TED - Visualized summary5 Public speaking tips from TED - Visualized summary
5 Public speaking tips from TED - Visualized summary
 
ChatGPT and the Future of Work - Clark Boyd
ChatGPT and the Future of Work - Clark Boyd ChatGPT and the Future of Work - Clark Boyd
ChatGPT and the Future of Work - Clark Boyd
 
Getting into the tech field. what next
Getting into the tech field. what next Getting into the tech field. what next
Getting into the tech field. what next
 
Google's Just Not That Into You: Understanding Core Updates & Search Intent
Google's Just Not That Into You: Understanding Core Updates & Search IntentGoogle's Just Not That Into You: Understanding Core Updates & Search Intent
Google's Just Not That Into You: Understanding Core Updates & Search Intent
 
How to have difficult conversations
How to have difficult conversations How to have difficult conversations
How to have difficult conversations
 
Introduction to Data Science
Introduction to Data ScienceIntroduction to Data Science
Introduction to Data Science
 
Time Management & Productivity - Best Practices
Time Management & Productivity -  Best PracticesTime Management & Productivity -  Best Practices
Time Management & Productivity - Best Practices
 
The six step guide to practical project management
The six step guide to practical project managementThe six step guide to practical project management
The six step guide to practical project management
 
Beginners Guide to TikTok for Search - Rachel Pearson - We are Tilt __ Bright...
Beginners Guide to TikTok for Search - Rachel Pearson - We are Tilt __ Bright...Beginners Guide to TikTok for Search - Rachel Pearson - We are Tilt __ Bright...
Beginners Guide to TikTok for Search - Rachel Pearson - We are Tilt __ Bright...
 

icaps 2009 Talk

  • 1. The Fuzzy Job Shop Scheduling Problem Improved Local Search Experimental Results Conclusions References Improved Local Search for Job Shop Scheduling with Uncertain Durations Inés González-Rodríguez1 Camino R. Vela2 Jorge Puente2 Alejandro Hernández-Arauzo2 1 Dept. of Mathematics, Statistics and Computing, University of Cantabria (Spain) 2 Dept. of Computer Science and A.I. Centre, University of Oviedo (Spain) ICAPS 2009.
  • 2. The Fuzzy Job Shop Scheduling Problem Improved Local Search Experimental Results Conclusions References Starting Point Previous work on job shop scheduling with uncertain durations: using local search very competitive makespan values :) but with a high computational load :( We would like to. . . keep makespan quality while improving efficiency.
  • 3. The Fuzzy Job Shop Scheduling Problem Improved Local Search Experimental Results Conclusions References Outline 1 The Fuzzy Job Shop Scheduling Problem 2 Improved Local Search Existing Approach Makespan Calculation for Neighbours Makespan Lower Bound Reduced Neighbourhood 3 Experimental Results 4 Conclusions
  • 4. The Fuzzy Job Shop Scheduling Problem Improved Local Search Experimental Results Conclusions References Job Shop Scheduling Problem J1 J2 J3
  • 5. The Fuzzy Job Shop Scheduling Problem Improved Local Search Experimental Results Conclusions References Job Shop Scheduling Problem J1 J2 J3
  • 6. The Fuzzy Job Shop Scheduling Problem Improved Local Search Experimental Results Conclusions References Job Shop Scheduling Problem J1 J2 J3
  • 7. The Fuzzy Job Shop Scheduling Problem Improved Local Search Experimental Results Conclusions References Job Shop Scheduling Problem J1 J2 J3
  • 8. The Fuzzy Job Shop Scheduling Problem Improved Local Search Experimental Results Conclusions References Motivation For Uncertainty Classical JSP assumes complete knowledge! about processing times. But. . . what can we do if we only have incomplete knowledge? (Un)fortunately, THE REAL WORLD IS FULL OF UNCERTAINTY !!!
  • 9. The Fuzzy Job Shop Scheduling Problem Improved Local Search Experimental Results Conclusions References Triangular Fuzzy Numbers Assume we only know: an interval of possible values for the duration [a1 , a3 ], a1 a3
  • 10. The Fuzzy Job Shop Scheduling Problem Improved Local Search Experimental Results Conclusions References Triangular Fuzzy Numbers Assume we only know: an interval of possible values for the duration [a1 , a3 ], the most likely duration a2 in this interval. a1 a2 a3
  • 11. The Fuzzy Job Shop Scheduling Problem Improved Local Search Experimental Results Conclusions References Triangular Fuzzy Numbers This knowledge is represented by a triangular fuzzy number, TFN, A = (a1 , a2 , a3 ): a1 a2 a3
  • 12. The Fuzzy Job Shop Scheduling Problem Improved Local Search Experimental Results Conclusions References Working With Triangular Fuzzy Numbers addition: A + B = (a1 + b1 , a2 + b2 , a3 + b3 ) maximum: max(A, B) ≈ (max{a1 , b1 }, max{a2 , b2 }, max{a3 , b3 }) expected value: 1 1 E[A] = (a + 2a2 + a3 ) 4
  • 13. The Fuzzy Job Shop Scheduling Problem Improved Local Search Experimental Results Conclusions References Solution Graph With TFNs A solution is represented by an acyclic graph: (3, 4, 7) 1 2 (3, 4, 7) (1, 2, 3) (4, 5, 6) (2, 3, 4) 0 3 4 7 (4, 5, 6) (1, 2, 6) (2, 3, 4) (1, 2, 4) 5 6 (1, 2, 6) or by a task processing order: π =(1 3 5 4 2 6).
  • 14. The Fuzzy Job Shop Scheduling Problem Improved Local Search Experimental Results Conclusions References Fuzzy? Schedule What is fuzzy in this schedule? Task starting and completion times and the makespan are fuzzy. But, the task processing order is precise.
  • 15. The Fuzzy Job Shop Scheduling Problem Improved Local Search Experimental Results Conclusions References Optimal Makespan We want to minimise a fuzzy makespan. But. . . Problem It is not clear when a TFN is less than another:
  • 16. The Fuzzy Job Shop Scheduling Problem Improved Local Search Experimental Results Conclusions References Optimal Makespan We want to minimise a fuzzy makespan. But. . . Problem It is not clear when a TFN is less than another: Solution The expected value defines a total ordering; A ≤E B iff E[A] ≤ E[B]:
  • 17. The Fuzzy Job Shop Scheduling Problem Improved Local Search Experimental Results Conclusions References Optimal Makespan We want to minimise a fuzzy makespan. But. . . Problem It is not clear when a TFN is less than another: Solution The expected value defines a total ordering; A ≤E B iff E[A] ≤ E[B]: Objective for FJSP Minimise the expected makespan E[Cmax ]
  • 18. The Fuzzy Job Shop Scheduling Problem Improved Local Search Experimental Results Conclusions References Criticality With Exact Durations 3 1 2 3 1 4 2 0 3 4 7 4 1 2 1 5 6 1 Critical path: (3, 4, 6); critical arcs: (4, 6); critical blocks: (3), (4, 6).
  • 19. The Fuzzy Job Shop Scheduling Problem Improved Local Search Experimental Results Conclusions References Criticality With TFNs: Parallel Graphs Solution Graph G: (3, 4, 7) 1 2 (3, 4, 7) (1, 2, 3) (4, 5, 6) (2, 3, 4) 0 3 4 7 (4, 5, 6) (1, 2, 6) (2, 3, 4) (1, 2, 4) 5 6 (1, 2, 6)
  • 20. The Fuzzy Job Shop Scheduling Problem Improved Local Search Experimental Results Conclusions References Criticality With TFNs: Parallel Graphs Parallel Solution Graph G1 : (3,4,7) 1 2 (3,4,7) (1,2,3) (4,5,6) (2,3,4) 0 3 4 7 (4,5,6) (1,2,6) (2,3,4) (1,2,4) 5 6 (1,2,6) 1 Critical path: 3,4,6; Cmax = 7
  • 21. The Fuzzy Job Shop Scheduling Problem Improved Local Search Experimental Results Conclusions References Criticality With TFNs: Parallel Graphs Solution Graph G: (3, 4, 7) 1 2 (3, 4, 7) (1, 2, 3) (4, 5, 6) (2, 3, 4) 0 3 4 7 (4, 5, 6) (1, 2, 6) (2, 3, 4) (1, 2, 4) 5 6 (1, 2, 6) Critical paths: [3,4,6], [3,5,6]; Cmax = (7, 10, 16)
  • 22. The Fuzzy Job Shop Scheduling Problem Improved Local Search Experimental Results Conclusions References Previous Neighbourhood Idea: obtain neighbours by reversing every resource critical arc. Definition Take a task processing order π a resource arc v = (x, y ) in the associated solution graph π(v ) , the order obtained from π after reversing arc v . The neighbourhood structure obtained from π is: H(π) = {π(v ) : v ∈ R(π) is critical}.
  • 23. The Fuzzy Job Shop Scheduling Problem Improved Local Search Experimental Results Conclusions References Previous Neighbourhood Solution Graph G(π), π=(1 3 5 4 2 6) (3, 4, 7) 1 2 (3, 4, 7) (1, 2, 3) (4, 5, 6) (2, 3, 4) 0 3 4 7 (4, 5, 6) (1, 2, 6) (2, 3, 4) (1, 2, 4) 5 6 (1, 2, 6) Critical paths: [3,4,6], [3,5,6]; Cmax = (7, 10, 16)
  • 24. The Fuzzy Job Shop Scheduling Problem Improved Local Search Experimental Results Conclusions References Previous Neighbourhood Neighbour Solution Graph G(σ), σ=(1 5 3 4 2 6) (3, 4, 7) 1 2 (3, 4, 7) (1, 2, 3) (4, 5, 6) (4, 5, 6) (2, 3, 4) 0 3 4 7 (2, 3, 4) (1, 2, 4) (1, 2, 6) 5 6 (1, 2, 6)
  • 25. The Fuzzy Job Shop Scheduling Problem Improved Local Search Experimental Results Conclusions References Previous Neighbourhood: Properties Good News :) All neighbours in H are feasible solutions. The reversal of a non-critical arc can never reduce makespan.
  • 26. The Fuzzy Job Shop Scheduling Problem Improved Local Search Experimental Results Conclusions References Previous Neighbourhood: Properties Good News :) All neighbours in H are feasible solutions. The reversal of a non-critical arc can never reduce makespan. Bad News :( In the fuzzy case, the neighbourhood has a considerable size, with the consequent increase in computational cost.
  • 27. The Fuzzy Job Shop Scheduling Problem Improved Local Search Experimental Results Conclusions References Proposed Improvements How can we improve the neighbourhood structure? Ideas: 1 More efficient makespan calculation for neighbours. 2 Use inexpensive makespan lower bound to discard neighbours. 3 Reduce neighbourhood.
  • 28. The Fuzzy Job Shop Scheduling Problem Improved Local Search Experimental Results Conclusions References Neighbour’s Makespan Calculation Idea: avoid unnecesary calculations using available information Makespan (and more) known for initial solution π; Neighbour σ = πv differs from π “only” in the reversal of an arc.
  • 29. The Fuzzy Job Shop Scheduling Problem Improved Local Search Experimental Results Conclusions References Heads and Tails Definition For a solution graph G(π) and a task x with processing time px : The head of x is the starting time of x, denoted rx : rx = max{rPJx + pPJx , rPνx + pPνx } The tail of x is the time lag between x’s completion time and the completion time of the last task, denoted qx : qx = max{qSJx + pSJx , qSνx + pSνx }
  • 30. The Fuzzy Job Shop Scheduling Problem Improved Local Search Experimental Results Conclusions References Heads and Tails in the Neighbour Pνx π Pνx σ = π(x,y ) PJx x SJx PJx x SJx PJy y SJy PJy y SJy Sνy Sνy To calculate heads (tails) in σ, we need only re-calculate the heads (tails) of tasks from x onwards (backwards) in G(σ).
  • 31. The Fuzzy Job Shop Scheduling Problem Improved Local Search Experimental Results Conclusions References Neighbour’s Makespan Lower Bound Idea: We are only interested in neighbours with improving makespan. Use makespan lower bound to discard non-improving neighbours. How can we calculate an inexpensive lower bound?
  • 32. The Fuzzy Job Shop Scheduling Problem Improved Local Search Experimental Results Conclusions References Makespan After a Move Notation for a processing order π and tasks x and y : D[P] a TFN where D i [P] is the length of the longest path in a set of paths P of Gi , i = 1, 2, 3. Pπ (x ∨ y ): set of all paths in the solution graph G(π) containing x or y ; Pπ (x ∧ y ): set of all paths in G(π) containing both x and y ; Pπ (¬x): set of all paths in G(π) not containing x. Proposition For σ = π(v ) , where v = (x, y ) is an arc in G(π) Cmax (σ) = max{D[Pπ (¬x)], D[Pσ (x ∨ y )]}
  • 33. The Fuzzy Job Shop Scheduling Problem Improved Local Search Experimental Results Conclusions References Lower Bound for Makespan After a Move Consequence: D[Pσ (x ∨ y )] ≤E Cmax (σ). Using heads and tails: Corollary Let rx (qx ) be the head (tail) of x in σ = π(x,y ) . The TFN LBσ = max{rx + px + qx , ry + py + qy } provides a lower bound for Cmax (σ). If Cmax (π) ≤E LBσ , we already know the neighbour is not improving.
  • 34. The Fuzzy Job Shop Scheduling Problem Improved Local Search Experimental Results Conclusions References Idea to Reduce Neighbourhood In the crisp case, reversing arcs inside a critical block does not improve the makespan. Can we prove the same for the fuzzy job shop?
  • 35. The Fuzzy Job Shop Scheduling Problem Improved Local Search Experimental Results Conclusions References Reduced Neighbourhood Definition If V(π) is the set of all arcs in the extreme of a critical block, the reduced neighbourhood structure for π is: HR (π) = {π(v ) : v ∈ V(π)}. Properties HR (π) ⊂ H(π) HR (π) contains only feasible schedules
  • 36. The Fuzzy Job Shop Scheduling Problem Improved Local Search Experimental Results Conclusions References Reduced Neighbourhood The discarded neighbours from H(π) − HR (π) never improve the makespan. Theorem For a feasible processing order π, ∀σ ∈ H(π) − HR (π), E[Cmax (π)] ≤ E[Cmax (σ)]
  • 37. The Fuzzy Job Shop Scheduling Problem Improved Local Search Experimental Results Conclusions References Reduced Neighbourhood Sufficient condition for optimality: Proposition If the neighbourhood HR (π) = ∅, then π is an optimal processing order. If the local search procedure stops because the neighbourhood is empty, it has found a global optimum.
  • 38. The Fuzzy Job Shop Scheduling Problem Improved Local Search Experimental Results Conclusions References Experiment Setup Goal Evaluate empirically the contribution of our proposals to improving local search efficiency. Problem Instances 1 Take 12 crisp hard job shop benchmark problems; 2 Generate 10 fuzzy versions of each instance (durations: TFNs with a2 = original value). Total of 120 fuzzy job shop instances.
  • 39. The Fuzzy Job Shop Scheduling Problem Improved Local Search Experimental Results Conclusions References Experiment Setup Solving Method Based on memetic algorithm GVPV08 proposed in ICAPS 2008 [2] combining: GA: Genetic algorithm LS: Hill-climbing with H. We plug 3 new proposals in the local search.
  • 40. The Fuzzy Job Shop Scheduling Problem Improved Local Search Experimental Results Conclusions References Experiment Setup GVPV08 compared favourably with state-of-the-art methods (SA [1] and GA [3]) in terms of makespan. New improvements do not affect makespan, only computational load of LS. We know results will be “good” re. makespan; our aim is to evaluate efficiency improvement.
  • 41. The Fuzzy Job Shop Scheduling Problem Improved Local Search Experimental Results Conclusions References Scheduling Neighbours With Heads and Tails Problem Size GVPV08 (s) MA (s) Red% FT10 10 × 10 801.2 588.2 26.59% FT20 20 × 5 1693.9 682.1 59.73% La21 15 × 10 1769.4 1072.8 39.37% La24 15 × 10 1562.4 950.1 39.19% La25 15 × 10 1722.8 993.7 42.32% La27 20 × 10 4137.8 2242.8 45.80% La29 20 × 10 3936.0 2071.7 47.37% La38 15 × 15 3037,6 2556.7 15.83% La40 15 × 15 3220.4 2652.2 17.64% ABZ7 20 × 15 7396.1 5294.7 28.41% ABZ8 20 × 15 8098.5 5780.9 28.62% ABZ9 20 × 15 7308.0 5652.1 22.66% Average CPU time reduction of 34.5% using MA
  • 42. The Fuzzy Job Shop Scheduling Problem Improved Local Search Experimental Results Conclusions References Makespan Estimate And Reduced Neighbourhood Incorporate proposed improvements to MA (using heads and tails): 1 MA(R)= MA using HR instead of H. 2 MA(LB) = MA using LB to estimate makespan. 3 MA(LB+R) = MA using both HR and LB. We compare: number of evaluated neighbours, CPU time in seconds (averaged across 30 executions and 10 fuzzy instances of each problem).
  • 43. The Fuzzy Job Shop Scheduling Problem Improved Local Search Experimental Results Conclusions References Number Of Evaluated Neighbours Problem MA MA(R) MA(LB) MA(R+LB) FT10 2.83E+07 1.44E+07 6.25E+06 3.61E+06 FT20 6.78E+07 1.14E+07 2.25E+07 5.16E+06 La21 4.46E+07 1.93E+07 1.07E+07 5.76E+06 La24 3.87E+07 2.04E+07 9.00E+06 5.59E+06 La25 4.28E+07 1.78E+07 1.03E+07 5.75E+06 La27 8.37E+07 2.77E+07 2.53E+07 9.79E+06 La29 7.85E+07 2.44E+07 2.40E+07 8.90E+06 La38 5.16E+07 3.10E+07 1.11E+07 8.02E+06 La40 5.42E+07 3.03E+07 1.16E+07 8.42E+06 ABZ7 9.74E+07 4.07E+07 2.57E+07 1.30E+07 ABZ8 1.08E+08 4.60E+07 2.87E+07 1.48E+07 ABZ9 9.65E+07 4.43E+07 2.42E+07 1.33E+07 Av. Red. – 57% 75% 87%
  • 44. The Fuzzy Job Shop Scheduling Problem Improved Local Search Experimental Results Conclusions References CPU Time In Seconds Problem MA MA(R) MA(LB) MA(R+LB) FT10 588.2 372.90 179.3 166.5 FT20 682.1 283.1 295.4 211.0 La21 1072.8 610.9 327.8 292.2 La24 950.1 636.4 304.5 284.0 La25 993.7 555.3 322.4 289.5 La27 2242.8 1072.5 641.9 511.6 La29 2071.7 962.8 609.8 485.8 La38 2556.7 1732.8 546.7 514.0 La40 2652.2 1643.2 565.1 531.5 ABZ7 5294.7 2671.0 1073.8 898.4 ABZ8 5780.9 2936.5 1168.0 975.2 ABZ9 5652.1 3107.7 1078.5 925.8 Av. Red. – 45% 73% 76%
  • 45. The Fuzzy Job Shop Scheduling Problem Improved Local Search Experimental Results Conclusions References Conclusions Previous work: good makespan but high computational cost. Proposed improvements: 1 Simple but effective neighbour scheduling algorithm. 2 Makespan estimate: evaluate only 25% of neighbours. 3 Reduced neighbourhood structure: < 1/2 of original neighbourhood. Combined Use Evaluate 13% of original neighbours in 23% of CPU time!!!
  • 46. The Fuzzy Job Shop Scheduling Problem Improved Local Search Experimental Results Conclusions References Future Work Better neighbourhood structures to improve makespan. Alternative meta-heuristics (taboo search, PSO,. . . ). Alternative uncertainty models.
  • 47. The Fuzzy Job Shop Scheduling Problem Improved Local Search Experimental Results Conclusions References References I Fortemps, P. (1997) Jobshop scheduling with imprecise durations: a fuzzy approach. IEEE Transactions of Fuzzy Systems 7:557–569. González Rodríguez, I.; Vela, C. R.; Puente, J.; and Varela, R. (2008) A new local search for the job shop problem with uncertain durations. In Proc. of ICAPS08, 124–131. Sidney: AAAI Press Sakawa, M., and Kubota, R. (2000) Fuzzy programming for multiobjective job shop scheduling with fuzzy processing time and fuzzy duedate through genetic algorithms. European Journal of Operational Research 120:393–407.
  • 48. The Fuzzy Job Shop Scheduling Problem Improved Local Search Experimental Results Conclusions References References II Taillard, E. D. (1994) Parallel taboo search techniques for the job shop scheduling problem. ORSA Journal on Computing 6(2):108–117. Van Laarhoven, P.; Aarts, E.; and Lenstra, K. (1992) Job shop scheduling by simulated annealing. Operations Research 40:113–125.