Humphreys & Associates, Inc.
                         3111 N. Tustin Avenue, Suite 250
                                Orange, CA 92865
                              (714) 685-1730 (Phone)
                               (714) 685-1734 (Fax)
                          Email: humphreys@humphreys-assoc.com
                             http://www.humphreys-assoc.com

   No portion of this material covered by the copyrights hereon may be
   duplicated, reproduced, distributed, or copied in any form, or by any means
   - graphic, electronic, or mechanical, including photocopying, recording,
   taping, printing, or information and retrieval systems without written
   permission of Humphreys & Associates, Inc.


        The following material is copyrighted by Humphreys & Associates, Inc. 1979 – 2008.
   Portions of the following material are also copyrighted by Arthur Andersen & Co. 1980 - 1981.
©Humphreys & Associates, Inc. 1979-2009  All rights reserved.
Establishing A
      Performance Measurement Baseline
                   (PMB)

                          Presented by
                        Gary Humphreys
                               of
                  HUMPHREYS & ASSOCIATES, INC.

                                     Daytona Beach, FL
                                    February 24-25, 2009
©Humphreys & Associates, Inc. 1979-2009
The Earned Value Process

             • Identify short tasks
             • Schedule each task
             • Assign a budget to each task
             • Measure progress of the tasks
©Humphreys & Associates, Inc. 1979-2009        0046
Work Definition
                                             WBS Index
                  Work Breakdown Structure

                                             WBS DICTIONARY




©Humphreys & Associates, Inc. 1979-2009                       0091
Statement Of Work                                                                           Electronics
                                                                                              system

       (SOW)/                                                Prime mission                                                              Program

    WBS Matrix                                                 equipment                               Training                        management


                                                  Hardware     Software        System      Equipment              Facilities    System          Project .
                                                                             integration                                       engineering    management

                                      Paragraph
                                        2.1.1
                          Paragraph
                             2.1
                                      Paragraph
              Paragraph                 2.1.2
                 2.0
                          Paragraph
                             2.2

                                      Paragraph
                                        3.1.1
                          Paragraph
                            3.1
                                      Paragraph
  Statement   Paragraph                 3.1.2
   of work       3.0
                                      Paragraph
                                        3.2.1
                          Paragraph
                             3.2
                                      Paragraph
                                        3.2.2

                                      Paragraph
                                        4.1.1
                          Paragraph
                             4.1
                                      Paragraph
                                        4.1.2
              Paragraph
                 4.0
                                      Paragraph
                          Paragraph     4.2.1
                             4.2
                                      Paragraph
                                        4.2.2



©Humphreys & Associates, Inc. 1979-2009                                                                                                             5452
Work Breakdown Structure
                         Dictionary

             Documents the scope of each element
             Is a valuable communication tool
             Identifies closely related items that are
             not included
             Serves as a framework for understanding
             changes in scope
©Humphreys & Associates, Inc. 1979-2009                  0093
Responsibility Assignment Matrix and Control Account Structure
                                                                        Contract Work Breakdown Structure
                                                                                                 Contract



                                                                                     Engine                 Training



                                                                            Fan               Compressor               Turbine



                                                                    Fan             Full Scale               Minor          Dual Spool
                                                                 Assembly           Fan Rig                 Fan Rig       Compressor Rig
              Test




                                                        Case       Rotor             Stator
                                                      Assembly   Assembly           Assembly
              Engineering
    Company




                                                                                                                                 Control
                              Design




                                       Mechanical     Control
                                        Design        Account                                                                    Account


                                        Analytical               Control
                                         Design                  Account          Account                                             Work
              Manufacturing




                                                                                                                                     Packages
                                       Drafting and    Control    Control         Control
                                        Checking       Account    Account         Account                                            Planning
                                                                                                                                     Packages


©Humphreys & Associates, Inc. 1979-2009                                                                                                         0106
Organization Structure Considerations

                     Workload
                     Expertise
                     Availability of contractors
                     Scope of work
                     Economic environment
©Humphreys & Associates, Inc. 1979-2009            0101
Control Account
               A tool established by or for
               the owner to monitor the cost
               and schedule performance of
               a managerially significant
               element of the work.
©Humphreys & Associates, Inc. 1979-2009        0104
Why Have A Schedule Baseline?

               Assure development of an achievable
               initial project plan
               Document assumptions, original scope,
               and plan
               Provide basis for meaningful analysis
               and trending

                                                       1336
©Humphreys & Associates, Inc. 1979-2009
Schedule Integration “Schedules Must Tier”

                                                                                     Contract/
   Total Program Level
                                                                                     Program
   •   Customer
   •   Senior management                                                             Schedule
   •   Program Office

                                     Item                   1     2 3 4    5 6 7
  Intermediate Level                 Control Account 14                             Major event
  •    Customer                                                                    or Functional
                                     Control Account 15
  •    Program Office
                                     Control Account 16                            Organization
  •    Functional management
                                     Control Account 17                              Milestone
  •    Control Account Managers
                                     Control Account 18                              Schedule

  Detail Program Level               Control              Start           Stop
                                     Account 16
  •    Program Office                WP No. 1                                        Control
  •    Functional management         WP No. 2                                      Account and
  •    Control account Managers      WP No. 3                                      Work Package
                                     WP No. 4                                       Schedules
                                     WP No. 5

©Humphreys & Associates, Inc. 1979-2009                                                            0151
Target
                                             Price


                              Target                 Budget
                              Profit                  Base


    For                       Performance                         Withheld
   Known                      Measurement            Management
                                                       Reserve      For
   Effort                       Baseline
                                                                  Unknowns

                                  Control              Summary
     Undistributed                Account                Level
       Budget                     Budgets              Planning
                                                       Packages
                                                                         0622
©Humphreys & Associates, Inc. 1979-2009
Planning And Budgeting:
          Establishing The Performance
              Measurement Baseline

                Identify management reserves
                Allocate resources to scheduled tasks
                Identify performance measurement
                methods
                Time-phase the resources (budget plan)
                                                         0621
©Humphreys & Associates, Inc. 1979-2009
Provide A Time-Phased Budget
                                          $




                                $




                $                         $     $



                         For each WBS element
©Humphreys & Associates, Inc. 1979-2009             0146
By Providing A Time-Phased
           Budget for Each Control Account
   Control Account
      Task                                Schedule           Resources

         1                                    $                 $

         2                                           $          $

         3                                               $      $

      Total                                          $          $

©Humphreys & Associates, Inc. 1979-2009                             0147
Elements Of The Base And Baseline


                                          Distributed Budget
                                          Distributed Budget
                                          (Control Account)
                                           (Control Account)



         Discrete
          Discrete                        Apportioned
                                          Apportioned          Level of
                                                               Level of   Planning
                                                                           Planning
       Work Packages
       Work Packages                        Effort
                                             Effort             Effort
                                                                Effort    Packages
                                                                          Packages




©Humphreys & Associates, Inc. 1979-2009                                               0157
Three Classifications Of
           Work Measurement
           1   . Discrete effort
           2   . Apportioned effort
           3   . Level Of Effort (LOE)
©Humphreys & Associates, Inc. 1979-2009   0165
Work Packages
      It represents units of work at levels where work is
      performed
      It is clearly distinguished from all other Work Packages
      It is assignable to a single organizational element and
      Control Account
      It has scheduled start and completion dates and, as
      applicable, interim milestones all of which are
      representative of physical accomplishment

©Humphreys & Associates, Inc. 1979-2009                          0168
Work Packages
      It has a budget or assigned value expressed in
      terms of dollars, hours or other measurable units
      It’s duration is limited to a relatively short span of
      time or it is subdivided by discrete milestones to
      facilitate the objective measurement of work
      performed
      It is integrated with detailed engineering,
      manufacturing, or other schedules
©Humphreys & Associates, Inc. 1979-2009                    0169
Discrete Work
              Measurement Techniques
                            Incremental milestones
                            50/50 method
                            0/100 method
                            Equivalent units
                            Units complete
                            Percent complete
©Humphreys & Associates, Inc. 1979-2009              0174
Incremental Milestone---Planning

               1                          2            3   4

       Milestone                              Budget

               1                                 300
               2                               1,200
               3                               1,200
               4                                 600
         Totals                               3,300

©Humphreys & Associates, Inc. 1979-2009                        0175
Incremental Milestone---Status
                                                   3           4

        Milestone                         Budget       Earned Value

               1                             300                300
               2                           1,200              1,200
               3                           1,200                  0
               4                             600                  0
          Totals                          3,300              1,500


©Humphreys & Associates, Inc. 1979-2009                               0176
Units Complete---Planning

           Month            January       February   March     April     Total

           Budget
                              1,500        2,000     2,200     1,000     6,700
            Feet
          Budget
          @ $100          $150,000        $200,000   $220,000 $100,000 $670,000
          per foot




©Humphreys & Associates, Inc. 1979-2009                                           0184
Units Complete---Status
              Month        January        February   March       April     Total
              Budget         1,500         2,000      2,200      1,000     6,700
               Feet
             Budget
             @ $100        $150,000       $200,000   $220,000   $100,000   $670,000
             per foot
             Quantity
                             1,000         2,000      2,000      1,700     6,700
             Installed

              Earned
              @ $100       $100,000       $200,000   $200,000   $170,000   $670,000
              per foot


©Humphreys & Associates, Inc. 1979-2009                                               0185
Percent Complete
       Month                January       February   March   April        BAC
       Budget                150          185        250     200          785

       Date             3                                            25




      Status of work depends upon individual evaluation
                                 of work accomplished
©Humphreys & Associates, Inc. 1979-2009                                         0186
Typical Work Activities For Planning Classification

                           DISCRETE EFFORT
                           Design drawings
                           Test specifications
                           Material parts list
                           Component test
                           Fabrication operation
                           Printed circuit card design
©Humphreys & Associates, Inc. 1979-2009                  0170
Example Of Apportioned Effort
         Inspection estimated as 10% of related
              production Control Account
                            Budget                              Earned
              Production                  Inspection   Production    Inspection
               Control                     Control      Control       Control
               Account                     Account      Account       Account

     June           200                      20           150            15
     July           500                      50           450            45
     Aug            100                      10           150            15

    Total           800                      80           750            75
©Humphreys & Associates, Inc. 1979-2009                                           0193
The Major Resource Questions

         Is the project achievable within the
         time and resource constraints?

         Is the project being planned to use
         resources efficiently?
                                                1309
©Humphreys & Associates, Inc. 1979-2009
Funds vs. Budget                      CONTRACT
                                                                TARGET
                REQUIRED FUNDING                               PRICE (CTP)
    D               PROFILE                               *
    O
    L                                                      CONTRACT
    L                                                     TARGET COST
    A                                                        (CTC)
                                                 BUDGET
    R
    S



                                          TIME
©Humphreys & Associates, Inc. 1979-2009                                 0119
Funds vs. ACWP + ETC
                                                     REVISED FUNDING
                                                        FORECAST       EAC
                                          TIME NOW
                       CURRENT
          D           AUTHORIZED
          O             FUNDING

          L                                                  ETC
          L
          A
          R                                              BUDGET
                                              EARNED
          S                                    VALUE
                               ACTUALS


©Humphreys & Associates, Inc. 1979-2009    TIME                              0154
Funding Profiles vs. Performance Trend Lines
                                                                      EAC
                                            TIME NOW
                         FUNDING
           D             PROFILE
           O                                                    ETC
           L            ACTUALS
           L
           A
           R                                           BUDGET
           S
                                          EARNED
                                           VALUE



©Humphreys & Associates, Inc. 1979-2009
                                              TIME                          8126
Rolling Wave Planning
     A M J J A S O N D J F M A M J J A S O N D J F M A M J

              9 Months                               All Future Periods

                  Control Account Time Phased                             Plan

      WP No. 1

             WP No. 2

                     WP No. 3
                                             Planning Package(s)          & Work
  Time Now                                Remaining Budget, Schedule      Scope




©Humphreys & Associates, Inc. 1979-2009                                            0200
Rolling Wave Planning
     A M J       J A S O N D J F M A M J                 J A S O N D J F M A M J
       3                6               3                 All Future Periods
     Months           Months          Months

                  Control Account Time Phased                               Plan
      WP No. 1
              WP No. 2
                     WP No. 3
                                                  Planning Package(s)       & Work
                                               Remaining Budget, Schedule   Scope
         Time Now

                                      WP No. 4



©Humphreys & Associates, Inc. 1979-2009                                              0201
Detailed Planning Becomes Budget
            When Formally Authorized

                Control Account           Contract
                 Authorization




©Humphreys & Associates, Inc. 1979-2009              0159
Work Authorization And Release
                                WBS orientation
                                Traceability/hierarchy
                                Responsibility assignment
                                Scope of work
                                Schedule
                                Budget
                                Charge number
©Humphreys & Associates, Inc. 1979-2009                     0160
CONTROL ACCOUNT WORK AUTHORIZATION                                    Revision Number: Original
                                                                                                    Issue Date: 2/1/year 1
                             Control account number: 1.4.2 Title: System test plan/procedures Responsible organization: 4000

                                          Program name: Mor Ded                                      Contract. number 1234-5678

                       Work statement (including applicable reference                   Schedule (baseline):      Start           Completion
                       documents)                                                                    Original: 02/09/Year 1       09/04/Year 1
                       (Indicate schedule dates for each item, unless
                                                                                                       Revised: __________        __________
                       noted above)

                                                                                               Amount authorized
                               Elements Of Cost                        Prior authorization     Current authorization          Total Budget
                       Direct labor hours..............……                     -0-                       864                         864
                       Contract help hours...........…...
                            Total hours...............                       -0-                         864                        864
                       Direct labor $..........................              -0-                       10627                      10627
                       Contract help $........................
                       Material $.................................
                       Subcontract $...........................
                       Other direct costs $................
                            Total $......................               $    -0-                 $     10627              $       10627
                        Update test plans & procedures to reflect changes in test equipment, simulation equipment. System
                        design and testing methods.
                        (In accordance with Contract Data Requirements List items ADOB & ADOC).




                                                                            SAMPLE
                                                                                                                    (continue on reverse side)

                                              Release authority                                      Performance commitment
                      Name                                           Date              Name.                                   Date



©Humphreys & Associates, Inc. 1979-2009                                                                                         Page 1 of ___
                                                                                                                                                 0161
Subsystem Integration
                                                                      Technical
                       Organization                                  Description/   Performance
      WBS Level                           Scheduling    Budgeting
                          Level                                        Work         Measurement
                                                                    Authorization
                                           Contract                                   Contract
        Program           Division                      Contract      Contract      Performance
                                          (milestone)                               Report (CPR)
                                           Program      WAD &                         Contract
                         Program                                       Sales
       Reporting                            Master      Budget                      Performance
                         Manager                                       Order        Report (CPR)
                                           Schedule      Data
                        Responsible/ Intermediate       WAD &           Work         Functional
        Control                                                     Authorization
                        Performing Schedule &           Budget
                                                                     Document       Performance
        Account          Manager         CAP             Data                       Report (FPR)
                                                                       (WAD)
                                           Control      Control       Control          CAM
         Work           Performing         Account      Account       Account
                                             Plan                                   Performance
        Package          Employee                         Plan          Plan
                                            (CAP)        (CAP)         (CAP)          Report


©Humphreys & Associates, Inc. 1979-2009                                                            0120
WBS


     Summarize Costs


                                              $     $
    ORGANIZATION
                                          $   $         $
                                          $         $
                                              $         $
©Humphreys & Associates, Inc. 1979-2009                     0217
Plan Ahead For Orderly Data Collection

                    Identify needed data
                    Determine level of detail
                    Determine source of each data item
                    Define data identification codes
                    Design forms
                    Design and write procedures
                    Train personnel
©Humphreys & Associates, Inc. 1979-2009                  0218
Change control and
      the Performance
    Measurement Baseline

©Humphreys & Associates, Inc. 1979-2009   0329
Effect Of Changes
                                                                 New Budget
                                                                     At
                                                                 Completion
                                  New Baseline

     $                                                 Changes
                                                                 Original Budget
                                                                       At
                                                                  Completion
                                   Original Baseline


                                          Time
©Humphreys & Associates, Inc. 1979-2009                                            0330
Budget Baseline Log
                                             Contract   Authorized
                                              Target     Unpriced          Management         Undistributed Distributed
        Date            Description           Cost         Work      CBB    Reserve
                                                                                        PMB     Budget        Budget
                                              (CTC)       (AUW)


         1/14   ABC Contract                  120          -         120      10        110       10          100
         1/31   January Summary               120          -         120      10        110       10          100
         2/5    Contract Change No. 001         -         45         45       5         40          -          40
                P.O. Letter-Additional
         2/15   Management Reports              -         30         30        -        30          -          30
         2/23   P.O. Letter-Motor Redesign      -         30         30        -        30          -          30
         2/28   February Summary              120        105         225      15        210       10          200




©Humphreys & Associates, Inc. 1979-2009                                                                                   0338
Avoid
       Changes to budgets of completed work

       Transfer of work without budget or
       budget without work

       Reopening completed tasks
©Humphreys & Associates, Inc. 1979-2009           0335
Implementation Schedule
                                          Q 1   Q 2   Q 3   Q 4
   1.     Organization & Start up
   2.     Assessment
   3.     Design
   4.     Documentation
   5.     Training
   6.     Implementation
   7.     Review & Validation
©Humphreys & Associates, Inc. 1979-2009                           0351
The End of Instruction
                                                 Reporting   EAC
                                                  Cutoff
               CONTRACT TARGET COST                Date
                                                             BAC

                            ACWP
       $                                                     $
                                                     BCWS
                                   BCWP
                                          TIME
       Thank you for your participation
©Humphreys & Associates, Inc. 1979-2009                            0567

Humphreys.gary

  • 1.
    Humphreys & Associates,Inc. 3111 N. Tustin Avenue, Suite 250 Orange, CA 92865 (714) 685-1730 (Phone) (714) 685-1734 (Fax) Email: humphreys@humphreys-assoc.com http://www.humphreys-assoc.com No portion of this material covered by the copyrights hereon may be duplicated, reproduced, distributed, or copied in any form, or by any means - graphic, electronic, or mechanical, including photocopying, recording, taping, printing, or information and retrieval systems without written permission of Humphreys & Associates, Inc. The following material is copyrighted by Humphreys & Associates, Inc. 1979 – 2008. Portions of the following material are also copyrighted by Arthur Andersen & Co. 1980 - 1981. ©Humphreys & Associates, Inc. 1979-2009 All rights reserved.
  • 2.
    Establishing A Performance Measurement Baseline (PMB) Presented by Gary Humphreys of HUMPHREYS & ASSOCIATES, INC. Daytona Beach, FL February 24-25, 2009 ©Humphreys & Associates, Inc. 1979-2009
  • 3.
    The Earned ValueProcess • Identify short tasks • Schedule each task • Assign a budget to each task • Measure progress of the tasks ©Humphreys & Associates, Inc. 1979-2009 0046
  • 4.
    Work Definition WBS Index Work Breakdown Structure WBS DICTIONARY ©Humphreys & Associates, Inc. 1979-2009 0091
  • 5.
    Statement Of Work Electronics system (SOW)/ Prime mission Program WBS Matrix equipment Training management Hardware Software System Equipment Facilities System Project . integration engineering management Paragraph 2.1.1 Paragraph 2.1 Paragraph Paragraph 2.1.2 2.0 Paragraph 2.2 Paragraph 3.1.1 Paragraph 3.1 Paragraph Statement Paragraph 3.1.2 of work 3.0 Paragraph 3.2.1 Paragraph 3.2 Paragraph 3.2.2 Paragraph 4.1.1 Paragraph 4.1 Paragraph 4.1.2 Paragraph 4.0 Paragraph Paragraph 4.2.1 4.2 Paragraph 4.2.2 ©Humphreys & Associates, Inc. 1979-2009 5452
  • 6.
    Work Breakdown Structure Dictionary Documents the scope of each element Is a valuable communication tool Identifies closely related items that are not included Serves as a framework for understanding changes in scope ©Humphreys & Associates, Inc. 1979-2009 0093
  • 7.
    Responsibility Assignment Matrixand Control Account Structure Contract Work Breakdown Structure Contract Engine Training Fan Compressor Turbine Fan Full Scale Minor Dual Spool Assembly Fan Rig Fan Rig Compressor Rig Test Case Rotor Stator Assembly Assembly Assembly Engineering Company Control Design Mechanical Control Design Account Account Analytical Control Design Account Account Work Manufacturing Packages Drafting and Control Control Control Checking Account Account Account Planning Packages ©Humphreys & Associates, Inc. 1979-2009 0106
  • 8.
    Organization Structure Considerations Workload Expertise Availability of contractors Scope of work Economic environment ©Humphreys & Associates, Inc. 1979-2009 0101
  • 9.
    Control Account A tool established by or for the owner to monitor the cost and schedule performance of a managerially significant element of the work. ©Humphreys & Associates, Inc. 1979-2009 0104
  • 10.
    Why Have ASchedule Baseline? Assure development of an achievable initial project plan Document assumptions, original scope, and plan Provide basis for meaningful analysis and trending 1336 ©Humphreys & Associates, Inc. 1979-2009
  • 11.
    Schedule Integration “SchedulesMust Tier” Contract/ Total Program Level Program • Customer • Senior management Schedule • Program Office Item 1 2 3 4 5 6 7 Intermediate Level Control Account 14 Major event • Customer or Functional Control Account 15 • Program Office Control Account 16 Organization • Functional management Control Account 17 Milestone • Control Account Managers Control Account 18 Schedule Detail Program Level Control Start Stop Account 16 • Program Office WP No. 1 Control • Functional management WP No. 2 Account and • Control account Managers WP No. 3 Work Package WP No. 4 Schedules WP No. 5 ©Humphreys & Associates, Inc. 1979-2009 0151
  • 12.
    Target Price Target Budget Profit Base For Performance Withheld Known Measurement Management Reserve For Effort Baseline Unknowns Control Summary Undistributed Account Level Budget Budgets Planning Packages 0622 ©Humphreys & Associates, Inc. 1979-2009
  • 13.
    Planning And Budgeting: Establishing The Performance Measurement Baseline Identify management reserves Allocate resources to scheduled tasks Identify performance measurement methods Time-phase the resources (budget plan) 0621 ©Humphreys & Associates, Inc. 1979-2009
  • 14.
    Provide A Time-PhasedBudget $ $ $ $ $ For each WBS element ©Humphreys & Associates, Inc. 1979-2009 0146
  • 15.
    By Providing ATime-Phased Budget for Each Control Account Control Account Task Schedule Resources 1 $ $ 2 $ $ 3 $ $ Total $ $ ©Humphreys & Associates, Inc. 1979-2009 0147
  • 16.
    Elements Of TheBase And Baseline Distributed Budget Distributed Budget (Control Account) (Control Account) Discrete Discrete Apportioned Apportioned Level of Level of Planning Planning Work Packages Work Packages Effort Effort Effort Effort Packages Packages ©Humphreys & Associates, Inc. 1979-2009 0157
  • 17.
    Three Classifications Of Work Measurement 1 . Discrete effort 2 . Apportioned effort 3 . Level Of Effort (LOE) ©Humphreys & Associates, Inc. 1979-2009 0165
  • 18.
    Work Packages It represents units of work at levels where work is performed It is clearly distinguished from all other Work Packages It is assignable to a single organizational element and Control Account It has scheduled start and completion dates and, as applicable, interim milestones all of which are representative of physical accomplishment ©Humphreys & Associates, Inc. 1979-2009 0168
  • 19.
    Work Packages It has a budget or assigned value expressed in terms of dollars, hours or other measurable units It’s duration is limited to a relatively short span of time or it is subdivided by discrete milestones to facilitate the objective measurement of work performed It is integrated with detailed engineering, manufacturing, or other schedules ©Humphreys & Associates, Inc. 1979-2009 0169
  • 20.
    Discrete Work Measurement Techniques Incremental milestones 50/50 method 0/100 method Equivalent units Units complete Percent complete ©Humphreys & Associates, Inc. 1979-2009 0174
  • 21.
    Incremental Milestone---Planning 1 2 3 4 Milestone Budget 1 300 2 1,200 3 1,200 4 600 Totals 3,300 ©Humphreys & Associates, Inc. 1979-2009 0175
  • 22.
    Incremental Milestone---Status 3 4 Milestone Budget Earned Value 1 300 300 2 1,200 1,200 3 1,200 0 4 600 0 Totals 3,300 1,500 ©Humphreys & Associates, Inc. 1979-2009 0176
  • 23.
    Units Complete---Planning Month January February March April Total Budget 1,500 2,000 2,200 1,000 6,700 Feet Budget @ $100 $150,000 $200,000 $220,000 $100,000 $670,000 per foot ©Humphreys & Associates, Inc. 1979-2009 0184
  • 24.
    Units Complete---Status Month January February March April Total Budget 1,500 2,000 2,200 1,000 6,700 Feet Budget @ $100 $150,000 $200,000 $220,000 $100,000 $670,000 per foot Quantity 1,000 2,000 2,000 1,700 6,700 Installed Earned @ $100 $100,000 $200,000 $200,000 $170,000 $670,000 per foot ©Humphreys & Associates, Inc. 1979-2009 0185
  • 25.
    Percent Complete Month January February March April BAC Budget 150 185 250 200 785 Date 3 25 Status of work depends upon individual evaluation of work accomplished ©Humphreys & Associates, Inc. 1979-2009 0186
  • 26.
    Typical Work ActivitiesFor Planning Classification DISCRETE EFFORT Design drawings Test specifications Material parts list Component test Fabrication operation Printed circuit card design ©Humphreys & Associates, Inc. 1979-2009 0170
  • 27.
    Example Of ApportionedEffort Inspection estimated as 10% of related production Control Account Budget Earned Production Inspection Production Inspection Control Control Control Control Account Account Account Account June 200 20 150 15 July 500 50 450 45 Aug 100 10 150 15 Total 800 80 750 75 ©Humphreys & Associates, Inc. 1979-2009 0193
  • 28.
    The Major ResourceQuestions Is the project achievable within the time and resource constraints? Is the project being planned to use resources efficiently? 1309 ©Humphreys & Associates, Inc. 1979-2009
  • 29.
    Funds vs. Budget CONTRACT TARGET REQUIRED FUNDING PRICE (CTP) D PROFILE * O L CONTRACT L TARGET COST A (CTC) BUDGET R S TIME ©Humphreys & Associates, Inc. 1979-2009 0119
  • 30.
    Funds vs. ACWP+ ETC REVISED FUNDING FORECAST EAC TIME NOW CURRENT D AUTHORIZED O FUNDING L ETC L A R BUDGET EARNED S VALUE ACTUALS ©Humphreys & Associates, Inc. 1979-2009 TIME 0154
  • 31.
    Funding Profiles vs.Performance Trend Lines EAC TIME NOW FUNDING D PROFILE O ETC L ACTUALS L A R BUDGET S EARNED VALUE ©Humphreys & Associates, Inc. 1979-2009 TIME 8126
  • 32.
    Rolling Wave Planning A M J J A S O N D J F M A M J J A S O N D J F M A M J 9 Months All Future Periods Control Account Time Phased Plan WP No. 1 WP No. 2 WP No. 3 Planning Package(s) & Work Time Now Remaining Budget, Schedule Scope ©Humphreys & Associates, Inc. 1979-2009 0200
  • 33.
    Rolling Wave Planning A M J J A S O N D J F M A M J J A S O N D J F M A M J 3 6 3 All Future Periods Months Months Months Control Account Time Phased Plan WP No. 1 WP No. 2 WP No. 3 Planning Package(s) & Work Remaining Budget, Schedule Scope Time Now WP No. 4 ©Humphreys & Associates, Inc. 1979-2009 0201
  • 34.
    Detailed Planning BecomesBudget When Formally Authorized Control Account Contract Authorization ©Humphreys & Associates, Inc. 1979-2009 0159
  • 35.
    Work Authorization AndRelease WBS orientation Traceability/hierarchy Responsibility assignment Scope of work Schedule Budget Charge number ©Humphreys & Associates, Inc. 1979-2009 0160
  • 36.
    CONTROL ACCOUNT WORKAUTHORIZATION Revision Number: Original Issue Date: 2/1/year 1 Control account number: 1.4.2 Title: System test plan/procedures Responsible organization: 4000 Program name: Mor Ded Contract. number 1234-5678 Work statement (including applicable reference Schedule (baseline): Start Completion documents) Original: 02/09/Year 1 09/04/Year 1 (Indicate schedule dates for each item, unless Revised: __________ __________ noted above) Amount authorized Elements Of Cost Prior authorization Current authorization Total Budget Direct labor hours..............…… -0- 864 864 Contract help hours...........…... Total hours............... -0- 864 864 Direct labor $.......................... -0- 10627 10627 Contract help $........................ Material $................................. Subcontract $........................... Other direct costs $................ Total $...................... $ -0- $ 10627 $ 10627 Update test plans & procedures to reflect changes in test equipment, simulation equipment. System design and testing methods. (In accordance with Contract Data Requirements List items ADOB & ADOC). SAMPLE (continue on reverse side) Release authority Performance commitment Name Date Name. Date ©Humphreys & Associates, Inc. 1979-2009 Page 1 of ___ 0161
  • 37.
    Subsystem Integration Technical Organization Description/ Performance WBS Level Scheduling Budgeting Level Work Measurement Authorization Contract Contract Program Division Contract Contract Performance (milestone) Report (CPR) Program WAD & Contract Program Sales Reporting Master Budget Performance Manager Order Report (CPR) Schedule Data Responsible/ Intermediate WAD & Work Functional Control Authorization Performing Schedule & Budget Document Performance Account Manager CAP Data Report (FPR) (WAD) Control Control Control CAM Work Performing Account Account Account Plan Performance Package Employee Plan Plan (CAP) (CAP) (CAP) Report ©Humphreys & Associates, Inc. 1979-2009 0120
  • 38.
    WBS Summarize Costs $ $ ORGANIZATION $ $ $ $ $ $ $ ©Humphreys & Associates, Inc. 1979-2009 0217
  • 39.
    Plan Ahead ForOrderly Data Collection Identify needed data Determine level of detail Determine source of each data item Define data identification codes Design forms Design and write procedures Train personnel ©Humphreys & Associates, Inc. 1979-2009 0218
  • 40.
    Change control and the Performance Measurement Baseline ©Humphreys & Associates, Inc. 1979-2009 0329
  • 41.
    Effect Of Changes New Budget At Completion New Baseline $ Changes Original Budget At Completion Original Baseline Time ©Humphreys & Associates, Inc. 1979-2009 0330
  • 42.
    Budget Baseline Log Contract Authorized Target Unpriced Management Undistributed Distributed Date Description Cost Work CBB Reserve PMB Budget Budget (CTC) (AUW) 1/14 ABC Contract 120 - 120 10 110 10 100 1/31 January Summary 120 - 120 10 110 10 100 2/5 Contract Change No. 001 - 45 45 5 40 - 40 P.O. Letter-Additional 2/15 Management Reports - 30 30 - 30 - 30 2/23 P.O. Letter-Motor Redesign - 30 30 - 30 - 30 2/28 February Summary 120 105 225 15 210 10 200 ©Humphreys & Associates, Inc. 1979-2009 0338
  • 43.
    Avoid Changes to budgets of completed work Transfer of work without budget or budget without work Reopening completed tasks ©Humphreys & Associates, Inc. 1979-2009 0335
  • 44.
    Implementation Schedule Q 1 Q 2 Q 3 Q 4 1. Organization & Start up 2. Assessment 3. Design 4. Documentation 5. Training 6. Implementation 7. Review & Validation ©Humphreys & Associates, Inc. 1979-2009 0351
  • 45.
    The End ofInstruction Reporting EAC Cutoff CONTRACT TARGET COST Date BAC ACWP $ $ BCWS BCWP TIME Thank you for your participation ©Humphreys & Associates, Inc. 1979-2009 0567