SAFETY IN PIPE LINE
1
HSE Department SPPL – Project Management Consultancy
Site Survey &,ROW Preparation (Leveling) Crossings ( Road,River & Nala Etc…)
Pipes Transportation & Stringing Hydrostatic test (Pre & Post)
Welding & Joint Coating Pre Commissioning and Commissioning
Trenching, Lowering & Backfilling
PIPELINE KEY ACTIVITIES
2
HSE Department SPPL – Project Management Consultancy
HIGH RISK AREAS
3
HSE Department SPPL – Project Management Consultancy
PIPELINE KEY ACTIVITIES
HAZARDS AND SAFETY PRECAUTIONS
SPPL – Project Management Consultancy
HSE Department 4
Site Survey & ROW Preparation
HAZARDS :-
1. Overhead power lines
2. Snake/ Insect bite
3. Vehicle incidents
PRECAUTIONS :-
1. Use wooden / FRP survey pole
2. First aid box & emergency vehicle
3. Defensive driving
4. Regular inspection
SPPL – Project Management Consultancy
HSE Department 5
Pipe Transportation & Handling
HAZARDS :-
1. Falling object
2. Rollover
3. Pinching
4. Vehicle incident
5. Failure of lifting equipment /gadgets
PRECAUTIONS :-
1. Secure pipes - with min. 3 No’s
lashes &adequate ballast
2. Head board
3. Ensure SWL of trailer
4. Rigging methodology
5. Journey Management
SPPL – Project Management Consultancy
HSE Department 6
Pipe Stringing
HAZARDS :-
1. Failure of lifting equipment / tools
And tackles
2. Failure of rigging
3. Overhead power lines
PRECAUTIONS:-
1. Rigging plan
2. Safe distance from OHPL
3. Provide Bunting Pole
4. Equipment fitness &
5. inspection
SPPL – Project Management Consultancy
HSE Department 7
HAZARDS :-
1. Failure of Lifting equipment's /
gadgets
2. Electric shock
3. Fire Hazard
PRECAUTIONS :-
1. Ensure SWL and physical condition
2. Electrical line through RCCB
3. Proper earthing
4. House keeping
5. Availability of Fire extinguisher & Sand
Mainline Fit-up & welding
SPPL – Project Management Consultancy
HSE Department 8
HAZARDS:-
1. Underground Utilities
2. Fall of Person / Material
3. Collapse of Soil
PRECAUTIONS
1. Refer line diagram and use
detectors
2. Hard barricade & caution
board
Excavation & Trenching
SPPL – Project Management Consultancy
HSE Department 9
HAZARDS:-
1. Hit by rock during blasting
2. Property damage
3. Failure of detonators
4. Contact with explosive items
PRECAUTIONS:-
1. Refer line diagram for UG utilities
2. Blasting Precautions
3. Work permit system
Rock Blasting
SPPL – Project Management Consultancy
HSE Department 10
HAZARDS :-
1. Failure of lifting equipment /
gadgets
2. Over Head power lines
3. it by object
PRECAUTIONS :-
1. Equipment Fitness
2. Shut down / Bunting pole
3. Stay away from lowering area
4. Flag man
Lowering
BUNTING POLE
SPPL – Project Management Consultancy
HSE Department 11
PRECAUTIONS :-
1. Refer line diagram and use detectors
2. Trial Pit
3. Only Manual excavation - distance
4. Protect & support exposed utility
5. Hard barricade & caution board
HAZARDS :-
1. UG/AG pipelines & cables
2. Damage of Existing lines
3. Soil collapse
4. Fall of person / Material
Crossing – Existing Pipeline
SPPL – Project Management Consultancy
HSE Department 12
HAZARDS :-
1. Underground Utilities
2. Equipment rotating parts
PRECAUTIONS :-
1. Refer line diagram and use detectors
2. Provide guard
3. Avoid heavy equipment movement
Crossing – HDD Boring
SPPL – Project Management Consultancy
HSE Department 13
HAZARDS :-
1. Underground Utilities
2. Equipment rotating parts
3. Fall of Person / Material
4. Collapse of Soil
PRECAUTIONS :-
1. Excavation Safety
2. Refer line diagram and use detectors
3. Proper guard
4. Hard barricade
5. Road signage & signal lights
Crossing – Thrust Boring
SPPL – Project Management Consultancy
HSE Department 14
HAZARDS :-
1. Underground Utilities
2. Fall of Person / Material
3. Collapse of Soil
4. Vehicle incident
PRECAUTIONS :-
1. Refer line diagram and use detectors
2. Hard barricade & caution board
3. Road diversion & trial run
4. Road signage's with traffic light
Crossing – Open Cut Crossings
SPPL – Project Management Consultancy
HSE Department 15
HAZARDS :-
1. Pressure Release
2. Explosion
PRECAUTIONS :-
1. Pressure Testing Safety
2. Follow work permit
3. Provide barricade & signboards
Pre- Commissioning & Commissioning
Pigging
SPPL – Project Management Consultancy
HSE Department 16
Hydro test
Journey Management
HAZARDS :-
1. Vehicle crash
2. Topple of vehicle
3. Vehicle Breakdown
PRECAUTIONS :-
1. Journey Management
2. Experienced driver & defensive driving
3. IVMS( In-Vehicle Monitoring System )
4. Regular Inspection and Maintenance
IVMS Device
SPPL – Project Management Consultancy
HSE Department 17
HSE Department
SPPL – Project Management Consultancy
18
Thank You

HSE Orientation for Pipeline Project -SPPL.pptx

  • 1.
    SAFETY IN PIPELINE 1 HSE Department SPPL – Project Management Consultancy
  • 2.
    Site Survey &,ROWPreparation (Leveling) Crossings ( Road,River & Nala Etc…) Pipes Transportation & Stringing Hydrostatic test (Pre & Post) Welding & Joint Coating Pre Commissioning and Commissioning Trenching, Lowering & Backfilling PIPELINE KEY ACTIVITIES 2 HSE Department SPPL – Project Management Consultancy
  • 3.
    HIGH RISK AREAS 3 HSEDepartment SPPL – Project Management Consultancy
  • 4.
    PIPELINE KEY ACTIVITIES HAZARDSAND SAFETY PRECAUTIONS SPPL – Project Management Consultancy HSE Department 4
  • 5.
    Site Survey &ROW Preparation HAZARDS :- 1. Overhead power lines 2. Snake/ Insect bite 3. Vehicle incidents PRECAUTIONS :- 1. Use wooden / FRP survey pole 2. First aid box & emergency vehicle 3. Defensive driving 4. Regular inspection SPPL – Project Management Consultancy HSE Department 5
  • 6.
    Pipe Transportation &Handling HAZARDS :- 1. Falling object 2. Rollover 3. Pinching 4. Vehicle incident 5. Failure of lifting equipment /gadgets PRECAUTIONS :- 1. Secure pipes - with min. 3 No’s lashes &adequate ballast 2. Head board 3. Ensure SWL of trailer 4. Rigging methodology 5. Journey Management SPPL – Project Management Consultancy HSE Department 6
  • 7.
    Pipe Stringing HAZARDS :- 1.Failure of lifting equipment / tools And tackles 2. Failure of rigging 3. Overhead power lines PRECAUTIONS:- 1. Rigging plan 2. Safe distance from OHPL 3. Provide Bunting Pole 4. Equipment fitness & 5. inspection SPPL – Project Management Consultancy HSE Department 7
  • 8.
    HAZARDS :- 1. Failureof Lifting equipment's / gadgets 2. Electric shock 3. Fire Hazard PRECAUTIONS :- 1. Ensure SWL and physical condition 2. Electrical line through RCCB 3. Proper earthing 4. House keeping 5. Availability of Fire extinguisher & Sand Mainline Fit-up & welding SPPL – Project Management Consultancy HSE Department 8
  • 9.
    HAZARDS:- 1. Underground Utilities 2.Fall of Person / Material 3. Collapse of Soil PRECAUTIONS 1. Refer line diagram and use detectors 2. Hard barricade & caution board Excavation & Trenching SPPL – Project Management Consultancy HSE Department 9
  • 10.
    HAZARDS:- 1. Hit byrock during blasting 2. Property damage 3. Failure of detonators 4. Contact with explosive items PRECAUTIONS:- 1. Refer line diagram for UG utilities 2. Blasting Precautions 3. Work permit system Rock Blasting SPPL – Project Management Consultancy HSE Department 10
  • 11.
    HAZARDS :- 1. Failureof lifting equipment / gadgets 2. Over Head power lines 3. it by object PRECAUTIONS :- 1. Equipment Fitness 2. Shut down / Bunting pole 3. Stay away from lowering area 4. Flag man Lowering BUNTING POLE SPPL – Project Management Consultancy HSE Department 11
  • 12.
    PRECAUTIONS :- 1. Referline diagram and use detectors 2. Trial Pit 3. Only Manual excavation - distance 4. Protect & support exposed utility 5. Hard barricade & caution board HAZARDS :- 1. UG/AG pipelines & cables 2. Damage of Existing lines 3. Soil collapse 4. Fall of person / Material Crossing – Existing Pipeline SPPL – Project Management Consultancy HSE Department 12
  • 13.
    HAZARDS :- 1. UndergroundUtilities 2. Equipment rotating parts PRECAUTIONS :- 1. Refer line diagram and use detectors 2. Provide guard 3. Avoid heavy equipment movement Crossing – HDD Boring SPPL – Project Management Consultancy HSE Department 13
  • 14.
    HAZARDS :- 1. UndergroundUtilities 2. Equipment rotating parts 3. Fall of Person / Material 4. Collapse of Soil PRECAUTIONS :- 1. Excavation Safety 2. Refer line diagram and use detectors 3. Proper guard 4. Hard barricade 5. Road signage & signal lights Crossing – Thrust Boring SPPL – Project Management Consultancy HSE Department 14
  • 15.
    HAZARDS :- 1. UndergroundUtilities 2. Fall of Person / Material 3. Collapse of Soil 4. Vehicle incident PRECAUTIONS :- 1. Refer line diagram and use detectors 2. Hard barricade & caution board 3. Road diversion & trial run 4. Road signage's with traffic light Crossing – Open Cut Crossings SPPL – Project Management Consultancy HSE Department 15
  • 16.
    HAZARDS :- 1. PressureRelease 2. Explosion PRECAUTIONS :- 1. Pressure Testing Safety 2. Follow work permit 3. Provide barricade & signboards Pre- Commissioning & Commissioning Pigging SPPL – Project Management Consultancy HSE Department 16 Hydro test
  • 17.
    Journey Management HAZARDS :- 1.Vehicle crash 2. Topple of vehicle 3. Vehicle Breakdown PRECAUTIONS :- 1. Journey Management 2. Experienced driver & defensive driving 3. IVMS( In-Vehicle Monitoring System ) 4. Regular Inspection and Maintenance IVMS Device SPPL – Project Management Consultancy HSE Department 17
  • 18.
    HSE Department SPPL –Project Management Consultancy 18 Thank You