SlideShare a Scribd company logo
908 770 4955
www.theoutageexpert.com
__________
________________________
Outage Fundamentals
How to use the tools
908 770 4955
www.theoutageexpert.com
__________
________________________
Zone Outage Control™
Will reduce cost and schedule by 10% for three
outage cycles.
908 770 4955
www.theoutageexpert.com
__________
________________________
For example:
An outage cost of
$3,000,000
An outage duration of
21 Days
An down day cost of
$50,000
908 770 4955
www.theoutageexpert.com
__________
________________________
Zone Outage Control™ will save you
10% on cost or
$300,000
10% on schedule or
2.1 days at $50,000 a day
or $105,000
For a total savings of
$405,000
908 770 4955
www.theoutageexpert.com
__________
________________________
Zone Outage
Control™ will give
you cost to date
and cost to finish
4 hours after the
end of each shift
with minimal
effort.
908 770 4955
www.theoutageexpert.com
__________
________________________
Zone Outage Control™ will reduce and eventually
eliminate downtime due to poor outage close out.
(100% availability for 18 months post outage)
908 770 4955
www.theoutageexpert.com
__________
________________________
Boiler Book
Organization of
information
(remember the
waltz)
All the
information in
one place
Inspection
documents
creation
Material and
spares ordering
908 770 4955
www.theoutageexpert.com
__________
________________________
Working Schedule
First schedule the
shutdown/open and ready
for work hour by hour
• Get ops / maintenance /
engineering to give you
their schedules
Then schedule the zones
• Get the contractors and
lead man to develop a
shift by shift task list and
manpower loading then
review
Then schedule unit testing
• Get ops to give you their
timing
Then the start up
• Get ops to give you their
timing
908 770 4955
www.theoutageexpert.com
__________
________________________
Get everyone to buy in after the schedule is roughed in.
908 770 4955
www.theoutageexpert.com
__________
________________________
Get commitment from everyone.
Upper
Management
Management Operations Maintenance
Engineering Safety All
Contractors
All Lead Men
908 770 4955
www.theoutageexpert.com
__________
________________________
Cost Control Dashboard
Take the working schedule and monazite it shift by shift and contractor by
contractor in excel
908 770 4955
www.theoutageexpert.com
__________
________________________
Follow the outage calendar.
908 770 4955
www.theoutageexpert.com
__________
________________________
Get all the
mental soak time
you can
Constantly
mentally
rehearse
everyone’s part.
908 770 4955
www.theoutageexpert.com
__________
________________________
Build a team out of different departments and companies.
908 770 4955
www.theoutageexpert.com
__________
________________________
Have as many lead men and contractor meetings and lunches
before the outage.
908 770 4955
www.theoutageexpert.com
__________
________________________
Everyone needs to know their part.
908 770 4955
www.theoutageexpert.com
__________
________________________
Choose an Outage Manager.
The Outage Manager chooses a night manager.
908 770 4955
www.theoutageexpert.com
__________
________________________
Once the bell rings
In shutdown / LOTO / open
and ready for work, the
outage manager needs to be
there for each hand off of
work.
908 770 4955
www.theoutageexpert.com
__________
________________________
Daily outage meetings.
Twice a day (morning and night)
With leadmen and contractor foreman.
908 770 4955
www.theoutageexpert.com
__________
________________________
SAFETY FIRST
Near misses
written
Near misses
closed
General
concerns
Site
conditions
Upcoming
dangerous
tasks
Contractor
coordination
908 770 4955
www.theoutageexpert.com
__________
________________________
Have a zone chart.
Only talk about what will be done in next 12 hours
Never accept “That should be done by shift change”
908 770 4955
www.theoutageexpert.com
__________
________________________
Make everyone aware
that they need to
answer the question
you asked or else
908 770 4955
www.theoutageexpert.com
__________
________________________
Collect
timesheets
at every
meeting.
908 770 4955
www.theoutageexpert.com
__________
________________________
Buy donuts
and coffee.
908 770 4955
www.theoutageexpert.com
__________
________________________
Outage
meeting should
only be 15
minutes to half
an hour.
908 770 4955
www.theoutageexpert.com
__________
________________________
Create a
team of all
involved.
908 770 4955
www.theoutageexpert.com
__________
________________________
Call the ball
when it’s
time to shift
between
assess and
elbows and
close outs.
908 770 4955
www.theoutageexpert.com
__________
________________________
PRINT OUT ENDING
MILESTONES IN LARGE
PRINT AND HANG
THEM EVERYWHERE.
908 770 4955
www.theoutageexpert.com
__________
________________________
Inspections and
Outage Report
Review all as found
sheets
Create work scopes
from as found
inspection
documents
Get all close out/as
left documents
Keep all the
originals in a three
ring binder and
that’s your outage
report
908 770 4955
www.theoutageexpert.com
__________
________________________
As outage manager,
keep these basic
principles in mind:
Keep everyone focused
on what’s next and the
end of the outage
Declare when the
outage is over (date and
time) loudly as possible
days before your
appointed date and time
If a job site looks like a
mess it is, stop and get
it right or you will fight
it all outage

More Related Content

Similar to How to Use the Tools

Vendor Networks
Vendor NetworksVendor Networks
Vendor Networks
jacevedo84
 
Outage Schedule Timeline
Outage Schedule TimelineOutage Schedule Timeline
Outage Schedule Timeline
jacevedo84
 
Outage Optimization Opportunities
Outage Optimization Opportunities Outage Optimization Opportunities
Outage Optimization Opportunities
jacevedo84
 
Emergency Power Planner
Emergency Power PlannerEmergency Power Planner
Emergency Power PlannerLyndon Schultz
 
CADAdminTemplate_2015
CADAdminTemplate_2015CADAdminTemplate_2015
CADAdminTemplate_2015Michael Roark
 
AlgoPlanner_CompleteSolution
AlgoPlanner_CompleteSolutionAlgoPlanner_CompleteSolution
AlgoPlanner_CompleteSolutionKenn Hersted
 
P3 Productivity Consulting & Training - 10’ work-area rule & lost time (sampl...
P3 Productivity Consulting & Training - 10’ work-area rule & lost time (sampl...P3 Productivity Consulting & Training - 10’ work-area rule & lost time (sampl...
P3 Productivity Consulting & Training - 10’ work-area rule & lost time (sampl...
Stu Jardine
 
Amalfi core coop-emsac_5-nov10_9a
Amalfi core coop-emsac_5-nov10_9aAmalfi core coop-emsac_5-nov10_9a
Amalfi core coop-emsac_5-nov10_9a
AmalfiCORE, LLC
 
03 Job Pro Atwork
03 Job Pro Atwork03 Job Pro Atwork
03 Job Pro Atwork
fraserg
 
New Holland 9040M Grape Harvester Service Repair Manual.pdf
New Holland 9040M Grape Harvester Service Repair Manual.pdfNew Holland 9040M Grape Harvester Service Repair Manual.pdf
New Holland 9040M Grape Harvester Service Repair Manual.pdf
sijixia28250
 
New Holland 9080L Grape Harvester Service Repair Manual.pdf
New Holland 9080L Grape Harvester Service Repair Manual.pdfNew Holland 9080L Grape Harvester Service Repair Manual.pdf
New Holland 9080L Grape Harvester Service Repair Manual.pdf
lianghuanpiaosi
 
New Holland 9090L GE Grape Harvester Service Repair Manual.pdf
New Holland 9090L GE Grape Harvester Service Repair Manual.pdfNew Holland 9090L GE Grape Harvester Service Repair Manual.pdf
New Holland 9090L GE Grape Harvester Service Repair Manual.pdf
lianghuanpiaosi
 
New Holland 9080L H Grape Harvester Service Repair Manual.pdf
New Holland 9080L H Grape Harvester Service Repair Manual.pdfNew Holland 9080L H Grape Harvester Service Repair Manual.pdf
New Holland 9080L H Grape Harvester Service Repair Manual.pdf
l5bfy3r1n
 
New Holland 9090L Grape Harvester Service Repair Manual.pdf
New Holland 9090L Grape Harvester Service Repair Manual.pdfNew Holland 9090L Grape Harvester Service Repair Manual.pdf
New Holland 9090L Grape Harvester Service Repair Manual.pdf
lianghuanpiaosi
 
New Holland 9090L H Grape Harvester Service Repair Manual.pdf
New Holland 9090L H Grape Harvester Service Repair Manual.pdfNew Holland 9090L H Grape Harvester Service Repair Manual.pdf
New Holland 9090L H Grape Harvester Service Repair Manual.pdf
lianghuanpiaosi
 
New Holland 9060L Grape Harvester Service Repair Manual.pdf
New Holland 9060L Grape Harvester Service Repair Manual.pdfNew Holland 9060L Grape Harvester Service Repair Manual.pdf
New Holland 9060L Grape Harvester Service Repair Manual.pdf
lianghuanpiaosi
 
New Holland 9040L Grape Harvester Service Repair Manual.pdf
New Holland 9040L Grape Harvester Service Repair Manual.pdfNew Holland 9040L Grape Harvester Service Repair Manual.pdf
New Holland 9040L Grape Harvester Service Repair Manual.pdf
lianghuanpiaosi
 
New Holland 9060L Grape Harvester Service Repair Manual.pdf
New Holland 9060L Grape Harvester Service Repair Manual.pdfNew Holland 9060L Grape Harvester Service Repair Manual.pdf
New Holland 9060L Grape Harvester Service Repair Manual.pdf
sijixia28250
 
New Holland 9090L GE Grape Harvester Service Repair Manual.pdf
New Holland 9090L GE Grape Harvester Service Repair Manual.pdfNew Holland 9090L GE Grape Harvester Service Repair Manual.pdf
New Holland 9090L GE Grape Harvester Service Repair Manual.pdf
l5bfy3r1n
 

Similar to How to Use the Tools (20)

Vendor Networks
Vendor NetworksVendor Networks
Vendor Networks
 
Outage Schedule Timeline
Outage Schedule TimelineOutage Schedule Timeline
Outage Schedule Timeline
 
Outage Optimization Opportunities
Outage Optimization Opportunities Outage Optimization Opportunities
Outage Optimization Opportunities
 
Emergency Power Planner
Emergency Power PlannerEmergency Power Planner
Emergency Power Planner
 
CADAdminTemplate_2015
CADAdminTemplate_2015CADAdminTemplate_2015
CADAdminTemplate_2015
 
AlgoPlanner_CompleteSolution
AlgoPlanner_CompleteSolutionAlgoPlanner_CompleteSolution
AlgoPlanner_CompleteSolution
 
P3 Productivity Consulting & Training - 10’ work-area rule & lost time (sampl...
P3 Productivity Consulting & Training - 10’ work-area rule & lost time (sampl...P3 Productivity Consulting & Training - 10’ work-area rule & lost time (sampl...
P3 Productivity Consulting & Training - 10’ work-area rule & lost time (sampl...
 
FORM_ORÇ_ASTEMG
FORM_ORÇ_ASTEMGFORM_ORÇ_ASTEMG
FORM_ORÇ_ASTEMG
 
Amalfi core coop-emsac_5-nov10_9a
Amalfi core coop-emsac_5-nov10_9aAmalfi core coop-emsac_5-nov10_9a
Amalfi core coop-emsac_5-nov10_9a
 
03 Job Pro Atwork
03 Job Pro Atwork03 Job Pro Atwork
03 Job Pro Atwork
 
New Holland 9040M Grape Harvester Service Repair Manual.pdf
New Holland 9040M Grape Harvester Service Repair Manual.pdfNew Holland 9040M Grape Harvester Service Repair Manual.pdf
New Holland 9040M Grape Harvester Service Repair Manual.pdf
 
New Holland 9080L Grape Harvester Service Repair Manual.pdf
New Holland 9080L Grape Harvester Service Repair Manual.pdfNew Holland 9080L Grape Harvester Service Repair Manual.pdf
New Holland 9080L Grape Harvester Service Repair Manual.pdf
 
New Holland 9090L GE Grape Harvester Service Repair Manual.pdf
New Holland 9090L GE Grape Harvester Service Repair Manual.pdfNew Holland 9090L GE Grape Harvester Service Repair Manual.pdf
New Holland 9090L GE Grape Harvester Service Repair Manual.pdf
 
New Holland 9080L H Grape Harvester Service Repair Manual.pdf
New Holland 9080L H Grape Harvester Service Repair Manual.pdfNew Holland 9080L H Grape Harvester Service Repair Manual.pdf
New Holland 9080L H Grape Harvester Service Repair Manual.pdf
 
New Holland 9090L Grape Harvester Service Repair Manual.pdf
New Holland 9090L Grape Harvester Service Repair Manual.pdfNew Holland 9090L Grape Harvester Service Repair Manual.pdf
New Holland 9090L Grape Harvester Service Repair Manual.pdf
 
New Holland 9090L H Grape Harvester Service Repair Manual.pdf
New Holland 9090L H Grape Harvester Service Repair Manual.pdfNew Holland 9090L H Grape Harvester Service Repair Manual.pdf
New Holland 9090L H Grape Harvester Service Repair Manual.pdf
 
New Holland 9060L Grape Harvester Service Repair Manual.pdf
New Holland 9060L Grape Harvester Service Repair Manual.pdfNew Holland 9060L Grape Harvester Service Repair Manual.pdf
New Holland 9060L Grape Harvester Service Repair Manual.pdf
 
New Holland 9040L Grape Harvester Service Repair Manual.pdf
New Holland 9040L Grape Harvester Service Repair Manual.pdfNew Holland 9040L Grape Harvester Service Repair Manual.pdf
New Holland 9040L Grape Harvester Service Repair Manual.pdf
 
New Holland 9060L Grape Harvester Service Repair Manual.pdf
New Holland 9060L Grape Harvester Service Repair Manual.pdfNew Holland 9060L Grape Harvester Service Repair Manual.pdf
New Holland 9060L Grape Harvester Service Repair Manual.pdf
 
New Holland 9090L GE Grape Harvester Service Repair Manual.pdf
New Holland 9090L GE Grape Harvester Service Repair Manual.pdfNew Holland 9090L GE Grape Harvester Service Repair Manual.pdf
New Holland 9090L GE Grape Harvester Service Repair Manual.pdf
 

More from jacevedo84

Core Competency Presentations
Core Competency PresentationsCore Competency Presentations
Core Competency Presentationsjacevedo84
 
Core Competency Email Marketing
Core Competency Email MarketingCore Competency Email Marketing
Core Competency Email Marketingjacevedo84
 
Jamie Acevedo Visual Resume
Jamie Acevedo Visual ResumeJamie Acevedo Visual Resume
Jamie Acevedo Visual Resume
jacevedo84
 
Motivation
MotivationMotivation
Motivation
jacevedo84
 
Heating Plant Overall for CEOs
Heating Plant Overall for CEOsHeating Plant Overall for CEOs
Heating Plant Overall for CEOs
jacevedo84
 
Steam CEO Training
Steam CEO TrainingSteam CEO Training
Steam CEO Training
jacevedo84
 
You Don't Know What You Don't Know
You Don't Know What You Don't KnowYou Don't Know What You Don't Know
You Don't Know What You Don't Know
jacevedo84
 
Parkchester April 2014 Management Report
Parkchester April 2014 Management ReportParkchester April 2014 Management Report
Parkchester April 2014 Management Report
jacevedo84
 
ENGR 426
ENGR 426ENGR 426
ENGR 426
jacevedo84
 
Coil Trol Energy Star Wars 2015
Coil Trol Energy Star Wars 2015Coil Trol Energy Star Wars 2015
Coil Trol Energy Star Wars 2015
jacevedo84
 

More from jacevedo84 (10)

Core Competency Presentations
Core Competency PresentationsCore Competency Presentations
Core Competency Presentations
 
Core Competency Email Marketing
Core Competency Email MarketingCore Competency Email Marketing
Core Competency Email Marketing
 
Jamie Acevedo Visual Resume
Jamie Acevedo Visual ResumeJamie Acevedo Visual Resume
Jamie Acevedo Visual Resume
 
Motivation
MotivationMotivation
Motivation
 
Heating Plant Overall for CEOs
Heating Plant Overall for CEOsHeating Plant Overall for CEOs
Heating Plant Overall for CEOs
 
Steam CEO Training
Steam CEO TrainingSteam CEO Training
Steam CEO Training
 
You Don't Know What You Don't Know
You Don't Know What You Don't KnowYou Don't Know What You Don't Know
You Don't Know What You Don't Know
 
Parkchester April 2014 Management Report
Parkchester April 2014 Management ReportParkchester April 2014 Management Report
Parkchester April 2014 Management Report
 
ENGR 426
ENGR 426ENGR 426
ENGR 426
 
Coil Trol Energy Star Wars 2015
Coil Trol Energy Star Wars 2015Coil Trol Energy Star Wars 2015
Coil Trol Energy Star Wars 2015
 

Recently uploaded

Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming PipelinesHarnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Christina Lin
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
Kerry Sado
 
Technical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prismsTechnical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prisms
heavyhaig
 
Unbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptxUnbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptx
ChristineTorrepenida1
 
Building Electrical System Design & Installation
Building Electrical System Design & InstallationBuilding Electrical System Design & Installation
Building Electrical System Design & Installation
symbo111
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
Aditya Rajan Patra
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
AJAYKUMARPUND1
 
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTSHeap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Soumen Santra
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
ydteq
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
bakpo1
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
Kamal Acharya
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
fxintegritypublishin
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
manasideore6
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Dr.Costas Sachpazis
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Teleport Manpower Consultant
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
gdsczhcet
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
DESIGN AND ANALYSIS OF A CAR SHOWROOM USING E TABS
DESIGN AND ANALYSIS OF A CAR SHOWROOM USING E TABSDESIGN AND ANALYSIS OF A CAR SHOWROOM USING E TABS
DESIGN AND ANALYSIS OF A CAR SHOWROOM USING E TABS
itech2017
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 

Recently uploaded (20)

Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming PipelinesHarnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
 
Technical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prismsTechnical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prisms
 
Unbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptxUnbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptx
 
Building Electrical System Design & Installation
Building Electrical System Design & InstallationBuilding Electrical System Design & Installation
Building Electrical System Design & Installation
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
 
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTSHeap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
DESIGN AND ANALYSIS OF A CAR SHOWROOM USING E TABS
DESIGN AND ANALYSIS OF A CAR SHOWROOM USING E TABSDESIGN AND ANALYSIS OF A CAR SHOWROOM USING E TABS
DESIGN AND ANALYSIS OF A CAR SHOWROOM USING E TABS
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 

How to Use the Tools

Editor's Notes

  1. Zone Outage Control Will reduce cost and schedule by 10% for three outage cycles
  2. Slide 2 Zone Outage Control Will reduce cost and schedule by 10% for three outage cycles Phase in the following
  3. Slide 2 Zone Outage Control Will reduce cost and schedule by 10% for three outage cycles Phase in the following
  4. Zone outage control will give you cost to date and cost to finish 4 hours after the end of every shift with minimal effort
  5. Zone outage control will reduce and eventually eliminate downtime due to poor outage close out (100% availability for 18 months post outage)
  6. Boiler book                 Organization of information (remember the waltz) All the information in one place                 Inspection documents creation                 Material and spares ordering
  7. Working schedule                 First schedule the shutdown/open and ready for work hour by hour                                 Get ops/maintenance/engineering to give you their schedules                 Then schedule the zones                                 Get the contractors and leadman to develop a shift by shift task list and manpower loading then review                 Then schedule unit testing                                 Get ops to give you their timing                 Then the start up                                 Get ops to give you their timing
  8. Working schedule                 Once you have the schedule roughed in then get buy in and commitment from everyone                                 Upper Management       (The Money)                                 Management                     (The Boss)                                 All departments                                                 Ops                                                 Maintenance                                                 Engineering                                                 Safety                                 All contractors                                 All leadman
  9. Upper Management       (The Money)                                 Management                     (The Boss)                                 All departments                                                 Ops                                                 Maintenance                                                 Engineering                                                 Safety                                 All contractors                                 All leadman
  10. Cost control dashboard                 Take the working schedule and monazite it shift by shift and contractor by contractor in excel
  11. Cost control dashboard                 Take the working schedule and monazite it shift by shift and contractor by contractor in excel
  12.                 Get all the mental soak time you can                 You want to constantly mentally rehearse everyone part in the play with them
  13.                 You need to build a team out of different departments and company’s
  14.                 It helps to have as many leadman and contractor meetings and lunches before the outage
  15.                 Everyone need to know their part (Money and schedule that their part contributes to the outage)
  16. Pick and Outage manager who is responsible for the whole thing The outage manager needs to pick a night manager
  17. Once the bell rings                 In shutown/loto/open and ready for work the outage manager needs to be there for each hand off of work (it’s a relay race and people don’t like to give up the batton)
  18. Daily outage meetings                 2 a day (morning and night)                 With Leadmen and contractor forman
  19. Safety first                                 Near misses written                                 Near misses closed                                 General concerns                                 Site conditions                                 Upcoming dangerous tasks                                 Contractor interferences
  20.                 Have a zone chart and then go through the zones with whats expected on the next shift and when you expect them to be done                                 Only talk about whats done and going to be done in the next 12 hours                                 Never accept “That should be done by shift change”
  21.                                                Make everyone aware that they need to answer the question you asked or else (skull and cross bones)
  22.                 Timesheets (have someone get all the time sheets)
  23.                 Buy dougnuts and coffee
  24.                 Should only be 15 minute to a half hour no matter how large the outage
  25. Create a team of all involved
  26.                 Call the ball when its time to shift between asses and elbows and close out (It’s been lovely having you no get the F**K out!!)
  27.                         Put up in large print ending milestone (Boilers hydro, turbines is full speed no load etc etc)
  28. Inspections and outage report                 Review all as found sheets                 Create work scopes from as found inspection documents                 Get all close out/as left documents                 Keep all the originals in a three ring binder and that’s your outage report
  29. Basic principles to always keep in mind as the outage manager                 Keep everyone focused on whats next and the end of the outage                 Declare when the outage in over (date and time) loudly as possible days before your appointed date and time                 If a job site looks like a mess it is, stop and get it right or you will fight it all outage