Merck presented on their efforts to rapidly develop vaccines through platform technologies and process optimizations. They discussed leveraging existing vaccine platforms and manufacturing processes to speed development timelines. For Ebola, they were able to produce over 750,000 doses within 9 months. For their COVID vaccine, they advanced from clone selection to phase 1 ready in 6 months. They also summarized their rapid development of a Sudan vaccine within 6 weeks through partnerships and applying lessons from other vaccine programs. Merck highlighted the importance of regulatory alignment, analytical capabilities, manufacturing flexibility and cross-functional partnerships to enable emergency response timelines.