SlideShare a Scribd company logo
The short version with some examples
Stephen Sikorski 2015
1
It has occurred to me that most of the times in my career that I have
been given the added responsibility of another department to run, a
pattern existed between those departments I would be given :
β€’ The demand on the area far exceeded the current
processes capabilities.
β€’ The effectiveness & efficiency of the area were seriously in
question.
β€’ There were no measurement metrics in place.
β€’ Very few people understood the process despite the
process being well documented.
β€’ Change needed to come very very quickly. (Usually a
matter of weeks)
Stephen Sikorski 2015
The following lays out the steps that I have taken a few times over
in order to quickly succeed in managing a new department.
2
Stephen Sikorski 2015
Step 1: Create a current state value stream map (If you
are not sure how, I suggest reading the book Learning to See by Mike Rother and John Shook the book is
very short yet very informative)
Example not actual
3
Stephen Sikorski 2015
Step 2: Identify the area bottleneck(s) (constraint)
β€’ If it is not apparent from the current state map use the following:
Service or Product A B C D
#1 0.5 0.6 2.0 1.5
#2 2.0 0.0 3.0 4.0
#3 0.0 3.0 4.0 2.0
Demand for week 1
#1 20 10 12 40 30
#2 15 30 0 45 60
#3 25 0 75 100 50
Total Hours Reqd: 40 87 185 140
Capacity Hours Available/Wk 40 80 160 160
Demand for week 2
#1 30 15 18 60 45
#2 30 60 0 90 120
#3 0 0 0 0 0
Total Hours Reqd: 75 18 150 165
Capacity Hours Available/Wk 40 80 160 160
(Requirements are hours per unit)
Resources:
Calculated resources required (week)
Calculated resources required (week)
Create a constraint map in excel using the cycle time data collected from the
value stream map.
Example not actual
4
Stephen Sikorski 2015
Step 3: Address the constraints (For repeat
bottlenecks Implement OEE and perform SMED)
To implement OEE
I. Brainstorm with equipment operator and
maintenance personnel all of the reasons the
equipment may stop.
II. Create the excel sheets on the following pages.
5
Stephen Sikorski 2015
OEE Entry Sheet Machine: # Operator:
DatePart/Item Number
Run/Batch/
Lot
Number
Start
Time
End
Time
Run
Quantity
Rejects
Total Run
Time
(min)
Stop
Time
End Stop
Time
Stopagge
Reason
Total
Stop
Time
(min)
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
Operating Down
III. Have equipment operator begin filling in the form you
made. (Make sure this excel sheet auto fills to and from the
excel sheets on the following pages). Watch the left side of
this page for variation in run times and the right side for
variation in and types of stoppages.
6
Stephen Sikorski 2015
Number Reason Date
Sum of
Operating
Time (min)
Planned
Production
Time (min)
Down
Time
Actual
Down
Time
A 0 0 0
B
C
D
E
F
G
H
I Categories Time(mins) Percentage
J Total Operational Time 0 #DIV/0!
K Total Stoppage 0 #DIV/0!
L 0 #DIV/0!
M 0 #DIV/0!
N 0 #DIV/0!
O 0 #DIV/0!
P 0 #DIV/0!
Q 0 #DIV/0!
IV. This excel sheet should feed into and from the
excel sheet and chart on the following pages.
7
Stephen Sikorski 2015
Shift Length Hours = 0 Minutes
Short Breaks Breaks @ 10 Minutes Each = 0 Minutes Total
Lunch Break Breaks @ 30 Minutes Each = 0 Minutes Total
Down Time Minutes
Ideal Run Rate PPM(Parts Per Minute)
Total Parts 0 Parts
Reject Parts 0 Parts
Variables Calculation Result
Planned
Production Time Shift Length - Breaks 10 Minutes
Operating Time Planned Production Time - Down Time 0 Minutes
Good Parts Total Parts - Reject Parts 0 Parts
Factors Calculation My OEE%
Availability Operating Time / Planned Production Time
Performance (Total Parts / Operation Time) / Ideal Run Rate
Quality Good Parts / Total Parts
Overall OEE Availability x Performance x Quality
SHIFT REPORT
V. This is the third OEE excel sheet (which tells
your actual OEE)
8
Stephen Sikorski 2015
VI. Address the top 80% of your stoppage drain. (This
auto fills from your second excel sheet)
100.00%
27.21%
8.55% 2.56%
11.11%10.26%
0.00%0.00%
67.52%
0.00%0.00%0.00%0.00% 0.00%0.00%
0.00%0.00%0.00%
0.00% 0.00%
0.00%0.00%
20.00%
40.00%
60.00%
80.00%
100.00%
120.00%
0
50
100
150
200
250
300
350
400
450
500
mins
Categories
Total Planned Production Time, Total Stoppage Time, and Subcategories
of Stoppage Time
Time(mins)
Percentage
Example not actual
9
Stephen Sikorski 2015
SMED SETUP REDUCTION OBSERVATION FORM Stephen Sikorski
Dept. Required Setup Tools: Standard Setup Time :
Machine
Operrator
Actual Time Target Time
No Task (P) (R) (L) (A) Internal External Improvement Internal External
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
( P)- Preperation- Actions performed to support the change over.
( R)- Replacment -This includes mounting, replacing, securing, attaching tools or parts.
( L)- Locating- Calibrations, measurments, setting, aligning.
( A)- Adjusting- Actions repeted in order to attain correct machine setting.
VII. You will most likely have to perform a SMED (single minute
exchange of dies) in order to get your changeovers under control
10
Stephen Sikorski 2015
VIII. Use the daily pareto chart as an operator level
metric. (Teach the constraint operator to identify
variations in the data as he/she fills in the form
and report them immediately).
IX. Congratulate and reward the operator we he/she
has very low stoppage time and when he/she
stops and points out variations.
11
Stephen Sikorski 2015
Step 4: Create department level metrics
I prefer the following formulas when creating my metrics:
𝑻 𝑻 βˆ’ π‘ͺ 𝑻
𝑻 𝑻
[%]
Where:
T/T – takt time of the value
stream
C/T – cycle time of the
process
Passive Waste (Muri) metric
shows the potential overload
and underutilization of
employees and equipment.
𝑡𝑽𝑨
π‘ͺ 𝑻
[%]
Where:
NVA – non-value added
activity time
C/T – cycle time of a
process
Shows (Muda) the
percentage of non-value
added activities being
performed.
12
Stephen Sikorski 2015
𝑨 𝑻 βˆ’ 𝑺 𝑻
𝑨 𝑻
[%]
Where:
A/T - daily available time
S/T - standard available time
Shows (Muri) actual over
and underutilization of
employees or equipment.
I generally use this as a
check of the OEE data.
𝜎 π‘€π‘œπ‘Ÿπ‘˜π‘™π‘œπ‘Žπ‘‘
π‘₯ π‘€π‘œπ‘Ÿπ‘™π‘œπ‘Žπ‘‘ [%]
Where:
𝜎 π‘€π‘œπ‘Ÿπ‘˜π‘™π‘œπ‘Žπ‘‘ βˆ’ π‘ π‘‘π‘Žπ‘›π‘‘π‘Žπ‘Ÿπ‘‘
deviation in operators cycle
times within the value stream
π‘₯ workload βˆ’ average
operators cycle time within the
value stream
Passive Waste (Mura) metric
shows the variation in
workload between operators in
a single process or a value
stream.
department level metrics
13
Stephen Sikorski 2015
𝑨 𝑻 βˆ’π‘«π‘³
𝑨 𝑻
[%]
Where:
A/T – available time
DL – direct labor time
Shows the percent of
time wasted on non-
production activities.
𝑫𝑳 βˆ’ 𝑺 𝑻
𝑫𝑳
[%]
Where:
S/T – standard time
DL – direct labor time
Shows the percentage
of time wasted due to
poor efficiency of either
man or machine.
department level metrics
14
Stephen Sikorski 2015
π‘Ίπ‘Ύπ‘°π‘·βˆ’π‘Ύπ‘°π‘·
𝑺𝑾𝑰𝑷
[%]
Where:
SWIP – standard
inventory in a process
WIP – actual inventory in
a process
Shows how efficiently
materials flow
through a process.
𝑹 𝑻
𝑨 𝑻
[%]
Where:
R/T – time spent on rework
A/T – available time
Shows the
percentage of time
wasted on rework.
department level metrics
15
Stephen Sikorski 2015
16
Step 5: Implement an Appropriate
Response Plan.
Such as: DMAIC or PDCA
To be used for:
β€’ Response to reject
β€’ Response to variation in data
β€’ Removal of non-value added time
β€’ Removal of Muda, Mura, and Muri waste

More Related Content

Similar to How I Improve and Manage a Production Area

Summer 2013 Internship Reflection
Summer 2013 Internship ReflectionSummer 2013 Internship Reflection
Summer 2013 Internship Reflection
Trevor Huggins
Β 
Toyota Kata How to Use the Key Improvement Kata Forms
Toyota Kata How to Use the Key Improvement Kata FormsToyota Kata How to Use the Key Improvement Kata Forms
Toyota Kata How to Use the Key Improvement Kata Forms
RichardCGreen
Β 
Software Management in a Lean and Agile World
Software Management in a Lean and Agile WorldSoftware Management in a Lean and Agile World
Software Management in a Lean and Agile World
IvanaTerrorBull
Β 
OPS 571 HELP Education Counseling--ops571help.com
OPS 571 HELP Education Counseling--ops571help.comOPS 571 HELP Education Counseling--ops571help.com
OPS 571 HELP Education Counseling--ops571help.com
KeatonJennings64
Β 
OPS 571 HELP Become Exceptional--ops571help.com
 OPS 571 HELP Become Exceptional--ops571help.com OPS 571 HELP Become Exceptional--ops571help.com
OPS 571 HELP Become Exceptional--ops571help.com
agathachristie127
Β 
OPS 571 HELP Lessons in Excellence / ops571help.com
OPS 571 HELP Lessons in Excellence / ops571help.comOPS 571 HELP Lessons in Excellence / ops571help.com
OPS 571 HELP Lessons in Excellence / ops571help.com
kopiko46
Β 
OPS 571 HELP Education Counseling--ops571help.com
OPS 571 HELP Education Counseling--ops571help.comOPS 571 HELP Education Counseling--ops571help.com
OPS 571 HELP Education Counseling--ops571help.com
venkat60041
Β 
Work measurement
Work measurementWork measurement
Work measurement
Huy Tẑ Ngọc
Β 
OPS 571 GENIUS Inspiring Innovation--ops571genius.com
OPS 571 GENIUS Inspiring Innovation--ops571genius.comOPS 571 GENIUS Inspiring Innovation--ops571genius.com
OPS 571 GENIUS Inspiring Innovation--ops571genius.com
kopiko111
Β 
OPS 571 GENIUS Education Counseling--ops571genius.com
OPS 571 GENIUS Education Counseling--ops571genius.comOPS 571 GENIUS Education Counseling--ops571genius.com
OPS 571 GENIUS Education Counseling--ops571genius.com
venkat60040
Β 
IRJET- Productivity Improvement in Manufacturing Industry using Lean Tools
IRJET- Productivity Improvement in Manufacturing Industry using Lean ToolsIRJET- Productivity Improvement in Manufacturing Industry using Lean Tools
IRJET- Productivity Improvement in Manufacturing Industry using Lean Tools
IRJET Journal
Β 
OPS 571 HELP Inspiring Innovation--ops571help.com
OPS 571 HELP Inspiring Innovation--ops571help.comOPS 571 HELP Inspiring Innovation--ops571help.com
OPS 571 HELP Inspiring Innovation--ops571help.com
claric77
Β 
OPS 571 HELP Education for Service--ops571help.com
 OPS 571 HELP Education for Service--ops571help.com OPS 571 HELP Education for Service--ops571help.com
OPS 571 HELP Education for Service--ops571help.com
mamata44
Β 
UOP OPS 571 Inspiring Innovation--uopops571.com
UOP OPS 571 Inspiring Innovation--uopops571.comUOP OPS 571 Inspiring Innovation--uopops571.com
UOP OPS 571 Inspiring Innovation--uopops571.com
kopiko118
Β 
In hau lee's uncertainty framework to classify supply chains
In hau lee's uncertainty framework to classify supply chainsIn hau lee's uncertainty framework to classify supply chains
In hau lee's uncertainty framework to classify supply chains
johann11371
Β 
An activity system map is which of the following
An activity system map is which of the followingAn activity system map is which of the following
An activity system map is which of the following
ramuaa126
Β 
An activity system map is which of the following
An activity system map is which of the followingAn activity system map is which of the following
An activity system map is which of the following
yearstart2
Β 
K012556370
K012556370K012556370
K012556370
vijay lahri
Β 
K012556370
K012556370K012556370
K012556370
IOSR Journals
Β 
Lead Time Reduction of Power Control Center (Pcc) Electric Panel by Lean Phil...
Lead Time Reduction of Power Control Center (Pcc) Electric Panel by Lean Phil...Lead Time Reduction of Power Control Center (Pcc) Electric Panel by Lean Phil...
Lead Time Reduction of Power Control Center (Pcc) Electric Panel by Lean Phil...
Government engineering College- Banswara,Rajasthan
Β 

Similar to How I Improve and Manage a Production Area (20)

Summer 2013 Internship Reflection
Summer 2013 Internship ReflectionSummer 2013 Internship Reflection
Summer 2013 Internship Reflection
Β 
Toyota Kata How to Use the Key Improvement Kata Forms
Toyota Kata How to Use the Key Improvement Kata FormsToyota Kata How to Use the Key Improvement Kata Forms
Toyota Kata How to Use the Key Improvement Kata Forms
Β 
Software Management in a Lean and Agile World
Software Management in a Lean and Agile WorldSoftware Management in a Lean and Agile World
Software Management in a Lean and Agile World
Β 
OPS 571 HELP Education Counseling--ops571help.com
OPS 571 HELP Education Counseling--ops571help.comOPS 571 HELP Education Counseling--ops571help.com
OPS 571 HELP Education Counseling--ops571help.com
Β 
OPS 571 HELP Become Exceptional--ops571help.com
 OPS 571 HELP Become Exceptional--ops571help.com OPS 571 HELP Become Exceptional--ops571help.com
OPS 571 HELP Become Exceptional--ops571help.com
Β 
OPS 571 HELP Lessons in Excellence / ops571help.com
OPS 571 HELP Lessons in Excellence / ops571help.comOPS 571 HELP Lessons in Excellence / ops571help.com
OPS 571 HELP Lessons in Excellence / ops571help.com
Β 
OPS 571 HELP Education Counseling--ops571help.com
OPS 571 HELP Education Counseling--ops571help.comOPS 571 HELP Education Counseling--ops571help.com
OPS 571 HELP Education Counseling--ops571help.com
Β 
Work measurement
Work measurementWork measurement
Work measurement
Β 
OPS 571 GENIUS Inspiring Innovation--ops571genius.com
OPS 571 GENIUS Inspiring Innovation--ops571genius.comOPS 571 GENIUS Inspiring Innovation--ops571genius.com
OPS 571 GENIUS Inspiring Innovation--ops571genius.com
Β 
OPS 571 GENIUS Education Counseling--ops571genius.com
OPS 571 GENIUS Education Counseling--ops571genius.comOPS 571 GENIUS Education Counseling--ops571genius.com
OPS 571 GENIUS Education Counseling--ops571genius.com
Β 
IRJET- Productivity Improvement in Manufacturing Industry using Lean Tools
IRJET- Productivity Improvement in Manufacturing Industry using Lean ToolsIRJET- Productivity Improvement in Manufacturing Industry using Lean Tools
IRJET- Productivity Improvement in Manufacturing Industry using Lean Tools
Β 
OPS 571 HELP Inspiring Innovation--ops571help.com
OPS 571 HELP Inspiring Innovation--ops571help.comOPS 571 HELP Inspiring Innovation--ops571help.com
OPS 571 HELP Inspiring Innovation--ops571help.com
Β 
OPS 571 HELP Education for Service--ops571help.com
 OPS 571 HELP Education for Service--ops571help.com OPS 571 HELP Education for Service--ops571help.com
OPS 571 HELP Education for Service--ops571help.com
Β 
UOP OPS 571 Inspiring Innovation--uopops571.com
UOP OPS 571 Inspiring Innovation--uopops571.comUOP OPS 571 Inspiring Innovation--uopops571.com
UOP OPS 571 Inspiring Innovation--uopops571.com
Β 
In hau lee's uncertainty framework to classify supply chains
In hau lee's uncertainty framework to classify supply chainsIn hau lee's uncertainty framework to classify supply chains
In hau lee's uncertainty framework to classify supply chains
Β 
An activity system map is which of the following
An activity system map is which of the followingAn activity system map is which of the following
An activity system map is which of the following
Β 
An activity system map is which of the following
An activity system map is which of the followingAn activity system map is which of the following
An activity system map is which of the following
Β 
K012556370
K012556370K012556370
K012556370
Β 
K012556370
K012556370K012556370
K012556370
Β 
Lead Time Reduction of Power Control Center (Pcc) Electric Panel by Lean Phil...
Lead Time Reduction of Power Control Center (Pcc) Electric Panel by Lean Phil...Lead Time Reduction of Power Control Center (Pcc) Electric Panel by Lean Phil...
Lead Time Reduction of Power Control Center (Pcc) Electric Panel by Lean Phil...
Β 

How I Improve and Manage a Production Area

  • 1. The short version with some examples Stephen Sikorski 2015 1
  • 2. It has occurred to me that most of the times in my career that I have been given the added responsibility of another department to run, a pattern existed between those departments I would be given : β€’ The demand on the area far exceeded the current processes capabilities. β€’ The effectiveness & efficiency of the area were seriously in question. β€’ There were no measurement metrics in place. β€’ Very few people understood the process despite the process being well documented. β€’ Change needed to come very very quickly. (Usually a matter of weeks) Stephen Sikorski 2015 The following lays out the steps that I have taken a few times over in order to quickly succeed in managing a new department. 2
  • 3. Stephen Sikorski 2015 Step 1: Create a current state value stream map (If you are not sure how, I suggest reading the book Learning to See by Mike Rother and John Shook the book is very short yet very informative) Example not actual 3
  • 4. Stephen Sikorski 2015 Step 2: Identify the area bottleneck(s) (constraint) β€’ If it is not apparent from the current state map use the following: Service or Product A B C D #1 0.5 0.6 2.0 1.5 #2 2.0 0.0 3.0 4.0 #3 0.0 3.0 4.0 2.0 Demand for week 1 #1 20 10 12 40 30 #2 15 30 0 45 60 #3 25 0 75 100 50 Total Hours Reqd: 40 87 185 140 Capacity Hours Available/Wk 40 80 160 160 Demand for week 2 #1 30 15 18 60 45 #2 30 60 0 90 120 #3 0 0 0 0 0 Total Hours Reqd: 75 18 150 165 Capacity Hours Available/Wk 40 80 160 160 (Requirements are hours per unit) Resources: Calculated resources required (week) Calculated resources required (week) Create a constraint map in excel using the cycle time data collected from the value stream map. Example not actual 4
  • 5. Stephen Sikorski 2015 Step 3: Address the constraints (For repeat bottlenecks Implement OEE and perform SMED) To implement OEE I. Brainstorm with equipment operator and maintenance personnel all of the reasons the equipment may stop. II. Create the excel sheets on the following pages. 5
  • 6. Stephen Sikorski 2015 OEE Entry Sheet Machine: # Operator: DatePart/Item Number Run/Batch/ Lot Number Start Time End Time Run Quantity Rejects Total Run Time (min) Stop Time End Stop Time Stopagge Reason Total Stop Time (min) 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 Operating Down III. Have equipment operator begin filling in the form you made. (Make sure this excel sheet auto fills to and from the excel sheets on the following pages). Watch the left side of this page for variation in run times and the right side for variation in and types of stoppages. 6
  • 7. Stephen Sikorski 2015 Number Reason Date Sum of Operating Time (min) Planned Production Time (min) Down Time Actual Down Time A 0 0 0 B C D E F G H I Categories Time(mins) Percentage J Total Operational Time 0 #DIV/0! K Total Stoppage 0 #DIV/0! L 0 #DIV/0! M 0 #DIV/0! N 0 #DIV/0! O 0 #DIV/0! P 0 #DIV/0! Q 0 #DIV/0! IV. This excel sheet should feed into and from the excel sheet and chart on the following pages. 7
  • 8. Stephen Sikorski 2015 Shift Length Hours = 0 Minutes Short Breaks Breaks @ 10 Minutes Each = 0 Minutes Total Lunch Break Breaks @ 30 Minutes Each = 0 Minutes Total Down Time Minutes Ideal Run Rate PPM(Parts Per Minute) Total Parts 0 Parts Reject Parts 0 Parts Variables Calculation Result Planned Production Time Shift Length - Breaks 10 Minutes Operating Time Planned Production Time - Down Time 0 Minutes Good Parts Total Parts - Reject Parts 0 Parts Factors Calculation My OEE% Availability Operating Time / Planned Production Time Performance (Total Parts / Operation Time) / Ideal Run Rate Quality Good Parts / Total Parts Overall OEE Availability x Performance x Quality SHIFT REPORT V. This is the third OEE excel sheet (which tells your actual OEE) 8
  • 9. Stephen Sikorski 2015 VI. Address the top 80% of your stoppage drain. (This auto fills from your second excel sheet) 100.00% 27.21% 8.55% 2.56% 11.11%10.26% 0.00%0.00% 67.52% 0.00%0.00%0.00%0.00% 0.00%0.00% 0.00%0.00%0.00% 0.00% 0.00% 0.00%0.00% 20.00% 40.00% 60.00% 80.00% 100.00% 120.00% 0 50 100 150 200 250 300 350 400 450 500 mins Categories Total Planned Production Time, Total Stoppage Time, and Subcategories of Stoppage Time Time(mins) Percentage Example not actual 9
  • 10. Stephen Sikorski 2015 SMED SETUP REDUCTION OBSERVATION FORM Stephen Sikorski Dept. Required Setup Tools: Standard Setup Time : Machine Operrator Actual Time Target Time No Task (P) (R) (L) (A) Internal External Improvement Internal External 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 ( P)- Preperation- Actions performed to support the change over. ( R)- Replacment -This includes mounting, replacing, securing, attaching tools or parts. ( L)- Locating- Calibrations, measurments, setting, aligning. ( A)- Adjusting- Actions repeted in order to attain correct machine setting. VII. You will most likely have to perform a SMED (single minute exchange of dies) in order to get your changeovers under control 10
  • 11. Stephen Sikorski 2015 VIII. Use the daily pareto chart as an operator level metric. (Teach the constraint operator to identify variations in the data as he/she fills in the form and report them immediately). IX. Congratulate and reward the operator we he/she has very low stoppage time and when he/she stops and points out variations. 11
  • 12. Stephen Sikorski 2015 Step 4: Create department level metrics I prefer the following formulas when creating my metrics: 𝑻 𝑻 βˆ’ π‘ͺ 𝑻 𝑻 𝑻 [%] Where: T/T – takt time of the value stream C/T – cycle time of the process Passive Waste (Muri) metric shows the potential overload and underutilization of employees and equipment. 𝑡𝑽𝑨 π‘ͺ 𝑻 [%] Where: NVA – non-value added activity time C/T – cycle time of a process Shows (Muda) the percentage of non-value added activities being performed. 12
  • 13. Stephen Sikorski 2015 𝑨 𝑻 βˆ’ 𝑺 𝑻 𝑨 𝑻 [%] Where: A/T - daily available time S/T - standard available time Shows (Muri) actual over and underutilization of employees or equipment. I generally use this as a check of the OEE data. 𝜎 π‘€π‘œπ‘Ÿπ‘˜π‘™π‘œπ‘Žπ‘‘ π‘₯ π‘€π‘œπ‘Ÿπ‘™π‘œπ‘Žπ‘‘ [%] Where: 𝜎 π‘€π‘œπ‘Ÿπ‘˜π‘™π‘œπ‘Žπ‘‘ βˆ’ π‘ π‘‘π‘Žπ‘›π‘‘π‘Žπ‘Ÿπ‘‘ deviation in operators cycle times within the value stream π‘₯ workload βˆ’ average operators cycle time within the value stream Passive Waste (Mura) metric shows the variation in workload between operators in a single process or a value stream. department level metrics 13
  • 14. Stephen Sikorski 2015 𝑨 𝑻 βˆ’π‘«π‘³ 𝑨 𝑻 [%] Where: A/T – available time DL – direct labor time Shows the percent of time wasted on non- production activities. 𝑫𝑳 βˆ’ 𝑺 𝑻 𝑫𝑳 [%] Where: S/T – standard time DL – direct labor time Shows the percentage of time wasted due to poor efficiency of either man or machine. department level metrics 14
  • 15. Stephen Sikorski 2015 π‘Ίπ‘Ύπ‘°π‘·βˆ’π‘Ύπ‘°π‘· 𝑺𝑾𝑰𝑷 [%] Where: SWIP – standard inventory in a process WIP – actual inventory in a process Shows how efficiently materials flow through a process. 𝑹 𝑻 𝑨 𝑻 [%] Where: R/T – time spent on rework A/T – available time Shows the percentage of time wasted on rework. department level metrics 15
  • 16. Stephen Sikorski 2015 16 Step 5: Implement an Appropriate Response Plan. Such as: DMAIC or PDCA To be used for: β€’ Response to reject β€’ Response to variation in data β€’ Removal of non-value added time β€’ Removal of Muda, Mura, and Muri waste