SlideShare a Scribd company logo
Outdoor Activity Center
Playground Improvement Project
Fariha Islam, Renee Qianye Mei, Juhi Brahmbhatt,
Rainie Wanyue Li, Katherine Beaman
1442 Richland Rd SW, Atlanta, GA 30310
Presented by:
December 4, 2016
2
Overview
● Project Scope
● Existing Conditions
● Proposed Layout
● Treehouse Design
● Site Design
○ Stormwater Planter
○ Micropool ED Pond
○ Amphitheater
○ Other Playground Equipment
● Erosion Control
● Cost Estimation
○ Treehouse
○ Site Improvements
● Conclusions
Project Scope
3
● Resolve the drainage issue currently impacting the
multi-purpose building
● Propose a renovation plan for the existing
playground, including the structural design of a
treehouse
● Perform a cost estimation on the implementation
of the treehouse and other site improvements
Existing Conditions (1)
4
Figure 1: Site Map
● Previously demolished
treehouse
● No educational treehouse
facility currently
Figure 2: Demolition of the Treehouse
Existing Conditions (2)
5
• The basement of the multi-purpose
building floods when it rains due to the
slope, causing water damage to the
materials stored in the basement
6
Figure 1: Site Map Figure 3: Location of the Basement
Existing Conditions (3)
Proposed Layout
7
Site Design (1)
8
Stormwater Planter:
Figure 1: Site Map Figure 4: Brick Raised Planter
Site Design (2)
9
● Function: Control and collect stormwater from northwest side
of site & serve as aesthetic planter
Figure 5: Dimensions of Proposed Planter
Site Design (3)
10
Micropool ED Pond:
Figure 6: Example of Micropool Pond
● Volume: 398 ft3
● Area: 435.6 ft2
Site Design (5)
11
Amphitheater:
● Seats about 20
● Limestone slabs for
seating
Figure 7: Outdoor Amphitheater
Site Design (6)
12
Other Playground Equipment:
Figure 8. Log Tunnel & Stepping Logs
Figure 9. Log Bench
Figure 10. Rubber Mulch
Erosion Control
● Phase 1:
○ Before construction activities
○ Silt fence around the lowest area of the site
● Phase 2:
○ During construction activities
○ Silt Fence around disturbed area
● Phase 3:
○ Permanent erosion control
○ Permanent vegetation on steep slope around
micropool ED and amphitheater
13
Treehouse Design (1)
Features include:
● ADA accessible ramp
● Satisfies playground regulations
● Climbing net canopy and entrance
● Octagonal platform deck
14
15Figure 11: Smaller Diameter View of
Tree
Figure 12: Larger Diameter View of Tree
5 feet
Treehouse Design (2)
9Figure 13: Three dimensional rendering of design
Treehouse
Design (3)
16
17Figure 14: South view of treehouse design with elevations
Treehouse Design (4)
18
Treehouse
Design (5)
Figure 15: Three dimensional rendering of user
perspective on ramp landing
ADA Accessibility
● 38 inch high railing
● 1:12 maximum slope ramp
● 5’-6” landings
● 5’-6” ramp width
● Total ramp length of 103’-6”
19
Playground Regulations
● Entrapment hazards
● Cedar or redwood building material
● Fall prevention
● 6 inch-thick wood chip padding
● Pressure-treated wood
● No chromated copper arsenate (CCA)
20
Framing & Decking
● 6″×6″ posts
● 2″×8″ girders and beams
● 2″×4″ knee bracing
● 2″×6″ decking
● 12″ width footing
21
Figure 16: Shear Face-Mount Joist Hanger
(Simpson Strong Tie)
Connections
● Notching and bolts
● Joist hangers
○ Shear face-mount
○ Skewed
○ Adjustable
● Deck screws
22
Figure 17: Shear Face-Mount Joist Hanger
(Simpson Strong Tie)
Alternative Design 23
Alternative Design (2) 24
Cost Estimation (1)
25
Table 1: Cost of Proposed Treehouse Design
Cost Estimation (2)
26
Component Material/Item Quantity Unit Unit Price Total Cost
Planter 2-1/4" Modular Brick 350 brick 0.74 $259.00
Mortar 2 bag 15.45 $30.90
Sand 1 ton 161.25 $161
Dirt Fill 414 cu ft 1.48 $337
Gravel Fill 138 cu ft 2.22 $307
1" Inner Diameter Soft Pipe 25 ft 1.28 $32
Grading Soil Fill-Amphitheater 10 cu yd 0.69 $7
Trail Improvements Rubber Chips 8,379 sq ft 1.24 $10427
Stepping Logs( about 14" in diameter) 17 stumps 878.00 $14926
Log Bench (about 1.3*6 ft) 2 benches 350.00 $700
log tunnel(about 2.8*4 ft) 1 tunnel 3418.00 $3418
Outdoor Theater Limestone (Cut into 3' by 1' by 6' ) 180 cu ft 1.00 $180
Sand (Lay under stone) 198 cu ft 0.17 $33
Micropool Gravel 10 cu ft 2.22 $23
Plastic Liner 51 sq ft 1.17 $60
Total Cost $55,000
Table 2: Cost of Proposed Site Design
Conclusions
● The proposed treehouse increases ADA accessibility of playground
● Implementations of the planter and pond will reduce stormwater runoff into the
building and keep the basement from flooding
● Trail improvements will enhance the usability and longevity in addition to
reducing maintenance
● Addition of the amphitheater and suggested playground equipment will
provide a cohesive space
● Net cost of $55,000 to implement all suggested improvements
27
References
Lighthouse Garage Door Services, 2016. Raised Garden Bed with Concrete Blocks.
<http://www.lighthousegaragedoors.com/10-ways-make-raised-bed-functional-aesthetic.htm/raised-garden-bed-
with-concrete-blocks>, accessed December 2016.
Simpson Strong-Tie. (2013). Deck Connection and Fastening Guide.
<https://www.iccsafe.org/BSM/Documents/PR/deck-framing-connection.pdf.>
28
QUESTIONS?
29

More Related Content

Similar to Final Presentation

CL FINAL PROJECT REPORT
CL FINAL PROJECT REPORTCL FINAL PROJECT REPORT
CL FINAL PROJECT REPORTJıa Yıı
 
Constructed Landscape
Constructed LandscapeConstructed Landscape
Constructed Landscape
Jia Xin
 
Foundation in natural and built environment
Foundation in natural and built environmentFoundation in natural and built environment
Foundation in natural and built environmentJaclyn Hwang
 
CL Final Report
CL Final ReportCL Final Report
CL Final Report
Sheau Hui Tan
 
Building construction ii report (1)
Building construction ii report  (1)Building construction ii report  (1)
Building construction ii report (1)
Chong jiayi
 
06 bridge
06 bridge06 bridge
06 bridge
Cida Feitosa
 
Rfp09498 p2 pres_t05
Rfp09498 p2 pres_t05Rfp09498 p2 pres_t05
Rfp09498 p2 pres_t05rplaughl
 
Building Construction II Report
Building Construction II ReportBuilding Construction II Report
Building Construction II Report
Bolin Loong
 
Kalorama Park & Playground ANC Presentation (December 3, 2014)
Kalorama Park & Playground ANC Presentation (December 3, 2014)Kalorama Park & Playground ANC Presentation (December 3, 2014)
Kalorama Park & Playground ANC Presentation (December 3, 2014)
DC Department of General Services
 
Lec 9 center line method
Lec 9 center line methodLec 9 center line method
Lec 9 center line method
malang1214
 
31_SHRUTIGARG_BC_GROUPREPORT.pdf
31_SHRUTIGARG_BC_GROUPREPORT.pdf31_SHRUTIGARG_BC_GROUPREPORT.pdf
31_SHRUTIGARG_BC_GROUPREPORT.pdf
ShrutiGarg261479
 
Using Porous Pavements and Other Green Technologies to Reduce Urban Runoff & ...
Using Porous Pavements and Other Green Technologies to Reduce Urban Runoff & ...Using Porous Pavements and Other Green Technologies to Reduce Urban Runoff & ...
Using Porous Pavements and Other Green Technologies to Reduce Urban Runoff & ...
Onondaga County Save the Rain
 
final presentation.pptx
final presentation.pptxfinal presentation.pptx
final presentation.pptx
KhunshanKhan1
 
final report last.pdf
final report last.pdffinal report last.pdf
final report last.pdfwzhen77
 
Parking Forest Questions from the City of Gresham
Parking Forest Questions from the City of GreshamParking Forest Questions from the City of Gresham
Parking Forest Questions from the City of Gresham
Maria Cahill
 
pilefoundation-141216072447-conversion-gate01.pdf
pilefoundation-141216072447-conversion-gate01.pdfpilefoundation-141216072447-conversion-gate01.pdf
pilefoundation-141216072447-conversion-gate01.pdf
AbdurRazzak187410
 
pilefoundation-141216072447-conversion-gate01.pdf
pilefoundation-141216072447-conversion-gate01.pdfpilefoundation-141216072447-conversion-gate01.pdf
pilefoundation-141216072447-conversion-gate01.pdf
AbdurRazzak187410
 
Lawrence Park PIC 3 slides
Lawrence Park PIC 3 slidesLawrence Park PIC 3 slides
Lawrence Park PIC 3 slides
Toronto Public Consultation Unit
 
Shallow Foundations
Shallow FoundationsShallow Foundations
Shallow FoundationsJames Smith
 

Similar to Final Presentation (20)

CL FINAL PROJECT REPORT
CL FINAL PROJECT REPORTCL FINAL PROJECT REPORT
CL FINAL PROJECT REPORT
 
Constructed Landscape
Constructed LandscapeConstructed Landscape
Constructed Landscape
 
Foundation in natural and built environment
Foundation in natural and built environmentFoundation in natural and built environment
Foundation in natural and built environment
 
CL Final Report
CL Final ReportCL Final Report
CL Final Report
 
Building construction ii report (1)
Building construction ii report  (1)Building construction ii report  (1)
Building construction ii report (1)
 
06 bridge
06 bridge06 bridge
06 bridge
 
Rfp09498 p2 pres_t05
Rfp09498 p2 pres_t05Rfp09498 p2 pres_t05
Rfp09498 p2 pres_t05
 
Building Construction II Report
Building Construction II ReportBuilding Construction II Report
Building Construction II Report
 
Kalorama Park & Playground ANC Presentation (December 3, 2014)
Kalorama Park & Playground ANC Presentation (December 3, 2014)Kalorama Park & Playground ANC Presentation (December 3, 2014)
Kalorama Park & Playground ANC Presentation (December 3, 2014)
 
Lec 9 center line method
Lec 9 center line methodLec 9 center line method
Lec 9 center line method
 
31_SHRUTIGARG_BC_GROUPREPORT.pdf
31_SHRUTIGARG_BC_GROUPREPORT.pdf31_SHRUTIGARG_BC_GROUPREPORT.pdf
31_SHRUTIGARG_BC_GROUPREPORT.pdf
 
Using Porous Pavements and Other Green Technologies to Reduce Urban Runoff & ...
Using Porous Pavements and Other Green Technologies to Reduce Urban Runoff & ...Using Porous Pavements and Other Green Technologies to Reduce Urban Runoff & ...
Using Porous Pavements and Other Green Technologies to Reduce Urban Runoff & ...
 
final presentation.pptx
final presentation.pptxfinal presentation.pptx
final presentation.pptx
 
final report last.pdf
final report last.pdffinal report last.pdf
final report last.pdf
 
Parking Forest Questions from the City of Gresham
Parking Forest Questions from the City of GreshamParking Forest Questions from the City of Gresham
Parking Forest Questions from the City of Gresham
 
pilefoundation-141216072447-conversion-gate01.pdf
pilefoundation-141216072447-conversion-gate01.pdfpilefoundation-141216072447-conversion-gate01.pdf
pilefoundation-141216072447-conversion-gate01.pdf
 
pilefoundation-141216072447-conversion-gate01.pdf
pilefoundation-141216072447-conversion-gate01.pdfpilefoundation-141216072447-conversion-gate01.pdf
pilefoundation-141216072447-conversion-gate01.pdf
 
Lawrence Park PIC 3 slides
Lawrence Park PIC 3 slidesLawrence Park PIC 3 slides
Lawrence Park PIC 3 slides
 
Shallow Foundations
Shallow FoundationsShallow Foundations
Shallow Foundations
 
CE236_Final_2007
CE236_Final_2007CE236_Final_2007
CE236_Final_2007
 

Final Presentation

  • 1. Outdoor Activity Center Playground Improvement Project Fariha Islam, Renee Qianye Mei, Juhi Brahmbhatt, Rainie Wanyue Li, Katherine Beaman 1442 Richland Rd SW, Atlanta, GA 30310 Presented by: December 4, 2016
  • 2. 2 Overview ● Project Scope ● Existing Conditions ● Proposed Layout ● Treehouse Design ● Site Design ○ Stormwater Planter ○ Micropool ED Pond ○ Amphitheater ○ Other Playground Equipment ● Erosion Control ● Cost Estimation ○ Treehouse ○ Site Improvements ● Conclusions
  • 3. Project Scope 3 ● Resolve the drainage issue currently impacting the multi-purpose building ● Propose a renovation plan for the existing playground, including the structural design of a treehouse ● Perform a cost estimation on the implementation of the treehouse and other site improvements
  • 4. Existing Conditions (1) 4 Figure 1: Site Map ● Previously demolished treehouse ● No educational treehouse facility currently Figure 2: Demolition of the Treehouse
  • 5. Existing Conditions (2) 5 • The basement of the multi-purpose building floods when it rains due to the slope, causing water damage to the materials stored in the basement
  • 6. 6 Figure 1: Site Map Figure 3: Location of the Basement Existing Conditions (3)
  • 8. Site Design (1) 8 Stormwater Planter: Figure 1: Site Map Figure 4: Brick Raised Planter
  • 9. Site Design (2) 9 ● Function: Control and collect stormwater from northwest side of site & serve as aesthetic planter Figure 5: Dimensions of Proposed Planter
  • 10. Site Design (3) 10 Micropool ED Pond: Figure 6: Example of Micropool Pond ● Volume: 398 ft3 ● Area: 435.6 ft2
  • 11. Site Design (5) 11 Amphitheater: ● Seats about 20 ● Limestone slabs for seating Figure 7: Outdoor Amphitheater
  • 12. Site Design (6) 12 Other Playground Equipment: Figure 8. Log Tunnel & Stepping Logs Figure 9. Log Bench Figure 10. Rubber Mulch
  • 13. Erosion Control ● Phase 1: ○ Before construction activities ○ Silt fence around the lowest area of the site ● Phase 2: ○ During construction activities ○ Silt Fence around disturbed area ● Phase 3: ○ Permanent erosion control ○ Permanent vegetation on steep slope around micropool ED and amphitheater 13
  • 14. Treehouse Design (1) Features include: ● ADA accessible ramp ● Satisfies playground regulations ● Climbing net canopy and entrance ● Octagonal platform deck 14
  • 15. 15Figure 11: Smaller Diameter View of Tree Figure 12: Larger Diameter View of Tree 5 feet Treehouse Design (2)
  • 16. 9Figure 13: Three dimensional rendering of design Treehouse Design (3) 16
  • 17. 17Figure 14: South view of treehouse design with elevations Treehouse Design (4)
  • 18. 18 Treehouse Design (5) Figure 15: Three dimensional rendering of user perspective on ramp landing
  • 19. ADA Accessibility ● 38 inch high railing ● 1:12 maximum slope ramp ● 5’-6” landings ● 5’-6” ramp width ● Total ramp length of 103’-6” 19
  • 20. Playground Regulations ● Entrapment hazards ● Cedar or redwood building material ● Fall prevention ● 6 inch-thick wood chip padding ● Pressure-treated wood ● No chromated copper arsenate (CCA) 20
  • 21. Framing & Decking ● 6″×6″ posts ● 2″×8″ girders and beams ● 2″×4″ knee bracing ● 2″×6″ decking ● 12″ width footing 21 Figure 16: Shear Face-Mount Joist Hanger (Simpson Strong Tie)
  • 22. Connections ● Notching and bolts ● Joist hangers ○ Shear face-mount ○ Skewed ○ Adjustable ● Deck screws 22 Figure 17: Shear Face-Mount Joist Hanger (Simpson Strong Tie)
  • 25. Cost Estimation (1) 25 Table 1: Cost of Proposed Treehouse Design
  • 26. Cost Estimation (2) 26 Component Material/Item Quantity Unit Unit Price Total Cost Planter 2-1/4" Modular Brick 350 brick 0.74 $259.00 Mortar 2 bag 15.45 $30.90 Sand 1 ton 161.25 $161 Dirt Fill 414 cu ft 1.48 $337 Gravel Fill 138 cu ft 2.22 $307 1" Inner Diameter Soft Pipe 25 ft 1.28 $32 Grading Soil Fill-Amphitheater 10 cu yd 0.69 $7 Trail Improvements Rubber Chips 8,379 sq ft 1.24 $10427 Stepping Logs( about 14" in diameter) 17 stumps 878.00 $14926 Log Bench (about 1.3*6 ft) 2 benches 350.00 $700 log tunnel(about 2.8*4 ft) 1 tunnel 3418.00 $3418 Outdoor Theater Limestone (Cut into 3' by 1' by 6' ) 180 cu ft 1.00 $180 Sand (Lay under stone) 198 cu ft 0.17 $33 Micropool Gravel 10 cu ft 2.22 $23 Plastic Liner 51 sq ft 1.17 $60 Total Cost $55,000 Table 2: Cost of Proposed Site Design
  • 27. Conclusions ● The proposed treehouse increases ADA accessibility of playground ● Implementations of the planter and pond will reduce stormwater runoff into the building and keep the basement from flooding ● Trail improvements will enhance the usability and longevity in addition to reducing maintenance ● Addition of the amphitheater and suggested playground equipment will provide a cohesive space ● Net cost of $55,000 to implement all suggested improvements 27
  • 28. References Lighthouse Garage Door Services, 2016. Raised Garden Bed with Concrete Blocks. <http://www.lighthousegaragedoors.com/10-ways-make-raised-bed-functional-aesthetic.htm/raised-garden-bed- with-concrete-blocks>, accessed December 2016. Simpson Strong-Tie. (2013). Deck Connection and Fastening Guide. <https://www.iccsafe.org/BSM/Documents/PR/deck-framing-connection.pdf.> 28