SlideShare a Scribd company logo
Component 3 : Strategic Partnerships, Knowledge Generation, and Policy
UPG
1. Christian Aid
Knowledge Management (KM) is rated moderately satisfactory. The project has done
some visibility for the interventions. The project is in the process of producing
communication materials such as signposts in the project impact areas. The project has
started identification and documentation of case studies for lesson drawing during
implementation. The project has started compilation of compendium of beneficiary
pictures for uploading on PMU cloud system but need to develop a proper storage system
at project level.
However, on the ground, KM and visibility issues have not been mainstreamed in the
project as beneficiaries lack knowledge of project objectives probably this could be due
to the confused structure within the project, having Case workers who have not trained
the volunteers who are the direct link to the beneficiaries.
Additionally, at the time of the mission, the project did not have feedback mechanisms.
Recommendation of the mission: Facilitate intra learning in the project to crease
awareness of the project at all levels (case workers, Volunteer and Beneficiary) be done by
December 31.
2. Yamba Malawi
Knowledge Management (KM) is rated moderately satisfactory. The project is making
efforts to mainstream KM in the interventions with guidance from the organisation’s
headquarters in the USA. Project manager is responsible for project KM. The project has
produced communication materials such as launch flyers. However, facilitation of intra
learning in the project is lacking as the project team especially those interacting with
beneficiaries lack knowledge of the project concept. This calls for intensification of
awareness of the project within the project structures.
During the visit, the mission established that some materials used for training the groups
were not translated into the local language which may be difficult for beneficiaries to
grasp.
The project has started identification and documentation case studies for lesson drawing
during implementation. The project has centralized repository system where key KMC and
other project documents stored.
At the time of the mission, the project did not have feedback mechanisms.
Recommendation of the mission: Facilitate intra learning in the project to crease
awareness of the project at all levels (case workers, Volunteer and Beneficiary) be done by
December 31.
3. Concern Worldwide
Knowledge Management (KM) is rated moderately satisfactory. The project
commenced of Coaching and mentoring and at the time of the mission, 41 Case managers
were trained. However, there is no project visibility on the ground. The project has not
started identification and documentation case studies for lesson drawing during
implementation.
Issues of visibility are not clearly mainstreamed in the project. At the time of mission, the
project did not have feedback mechanisms.
Recommendations of the mission: (i) Make FARMSE visible during community
engagement and also use mass media by December 2023. (ii) Identify, document and
submit to FARMSE at least two case studies for learning in the project implementation.
(iii) Begin compiling compendium of beneficiary pictures for uploading on PMU cloud
system.
4. World Relief
Knowledge Management (KM) is rated Moderately Satisfactory. The project has
started training to create awareness among the group. There is intra learning in the project
as portrayed by understanding of project concept by project staff including those interacting with
beneficiaries demonstrated knowledge of ultra-poor graduation model, and ability to define the
interventions. However, the project need to do more on visibility at grassroots level.
At the time of the mission, the project had not completed identification and
documentation of the project cases for learning. Additionally, at the mission time, the
project did not have feedback mechanisms.
Recommendations of the mission: (i) Enhance FARMSE visibility during community
engagement by December 2023. (ii) Identify, document and submit to FARMSE at least
two case studies for learning in the project implementation. (iii) Begin compiling
compendium of beneficiary pictures for uploading on PMU cloud system.
5. AICC
Knowledge Management (KM) is rated Moderately Satisfactory. The project has
started training to create awareness among beneficiaries. Participants do not know the
existing partnership of FARMSE and AICC. At the time of the mission, the project had not
started identifying case studies for learning in the project implementation. Additionally, at
the mission time, the project did not have feedback mechanisms.
Recommendations of the mission: (i)Enhance visibility of the project by December
31December. (ii) Identification and documentation of case studies, key project lessons,
best practices, key innovations from project interventions be done by December 2023. (ii)
Begin compiling compendium of beneficiary pictures for uploading on PMU cloud system

More Related Content

Similar to FIELD REPORT-KMCO-UPG -CBFOdocumentation

Graduation project 63232
Graduation project 63232Graduation project 63232
Graduation project 63232
techprojects
 
Dial cluster nov 2012
Dial cluster nov 2012Dial cluster nov 2012
Dial cluster nov 2012
Chris Follows
 
Project manager - Consultancy
Project manager - Consultancy Project manager - Consultancy
Project manager - Consultancy
Sofía Gallego
 
Presentation of project management synopsis 1
Presentation of project management synopsis 1Presentation of project management synopsis 1
Presentation of project management synopsis 1
ferozpatowary
 
A LEADER IN ME Webinar A Project Management Final Output
A LEADER IN ME Webinar   A Project Management Final OutputA LEADER IN ME Webinar   A Project Management Final Output
A LEADER IN ME Webinar A Project Management Final Output
Justin Knight
 
Project evaluation and implementation notes and questions
Project evaluation and implementation   notes and questionsProject evaluation and implementation   notes and questions
Project evaluation and implementation notes and questions
Anirban Chakraborty
 
MANAGEMENT-OF-COMMUNITY-IMMERSION.pptx
MANAGEMENT-OF-COMMUNITY-IMMERSION.pptxMANAGEMENT-OF-COMMUNITY-IMMERSION.pptx
MANAGEMENT-OF-COMMUNITY-IMMERSION.pptx
EJINAABEGAILJASMINEA
 
Developing a City Transport Plan in an Urban Growth Area - Lessons Learnt
Developing a City Transport Plan in an Urban Growth Area - Lessons LearntDeveloping a City Transport Plan in an Urban Growth Area - Lessons Learnt
Developing a City Transport Plan in an Urban Growth Area - Lessons Learnt
JumpingJaq
 
Mobilizing Learning.
Mobilizing Learning.Mobilizing Learning.
Mobilizing Learning.
Roger Bateman
 
Kenya Ushahidi Evaluation: Uchaguzi
Kenya Ushahidi Evaluation: UchaguziKenya Ushahidi Evaluation: Uchaguzi
Kenya Ushahidi Evaluation: Uchaguzi
Ushahidi
 
EES2014_full paper_Benjamin Aisya Aug 30 2014
EES2014_full paper_Benjamin Aisya Aug 30 2014EES2014_full paper_Benjamin Aisya Aug 30 2014
EES2014_full paper_Benjamin Aisya Aug 30 2014
Benjamin Aisya
 
SHEEN Sharing Launch: Employability Resources on the Web
SHEEN Sharing Launch: Employability Resources on the WebSHEEN Sharing Launch: Employability Resources on the Web
SHEEN Sharing Launch: Employability Resources on the Web
Sarah Currier
 
Cody technology use_plan_presentation
Cody technology use_plan_presentationCody technology use_plan_presentation
Cody technology use_plan_presentation
libbyjcody
 
Young crew newsletter
Young crew newsletterYoung crew newsletter
Young crew newsletter
Oluwaseyi Sodola
 
Young Crew Newsletter
Young Crew NewsletterYoung Crew Newsletter
Young Crew Newsletter
Oluwaseyi SODOLA
 
AVO – A voyage to the open seas to study openness and a networking mode of op...
AVO – A voyage to the open seas to study openness and a networking mode of op...AVO – A voyage to the open seas to study openness and a networking mode of op...
AVO – A voyage to the open seas to study openness and a networking mode of op...
Suomen eOppimiskeskus ry
 
Young crew programs and activities 2015
Young crew programs and activities 2015Young crew programs and activities 2015
Young crew programs and activities 2015
Oluwaseyi SODOLA
 
PMDAN Young crew Programmes and Activities 2015
 PMDAN Young crew Programmes and Activities 2015 PMDAN Young crew Programmes and Activities 2015
PMDAN Young crew Programmes and Activities 2015
Oluwaseyi SODOLA
 
Social media based dissemination strategies for managers of LLP projects
Social media based dissemination strategies for managers of LLP projectsSocial media based dissemination strategies for managers of LLP projects
Social media based dissemination strategies for managers of LLP projects
Web2Learn
 
Gomez, herrera interactive activity 1
Gomez, herrera interactive activity 1Gomez, herrera interactive activity 1
Gomez, herrera interactive activity 1
gautama78
 

Similar to FIELD REPORT-KMCO-UPG -CBFOdocumentation (20)

Graduation project 63232
Graduation project 63232Graduation project 63232
Graduation project 63232
 
Dial cluster nov 2012
Dial cluster nov 2012Dial cluster nov 2012
Dial cluster nov 2012
 
Project manager - Consultancy
Project manager - Consultancy Project manager - Consultancy
Project manager - Consultancy
 
Presentation of project management synopsis 1
Presentation of project management synopsis 1Presentation of project management synopsis 1
Presentation of project management synopsis 1
 
A LEADER IN ME Webinar A Project Management Final Output
A LEADER IN ME Webinar   A Project Management Final OutputA LEADER IN ME Webinar   A Project Management Final Output
A LEADER IN ME Webinar A Project Management Final Output
 
Project evaluation and implementation notes and questions
Project evaluation and implementation   notes and questionsProject evaluation and implementation   notes and questions
Project evaluation and implementation notes and questions
 
MANAGEMENT-OF-COMMUNITY-IMMERSION.pptx
MANAGEMENT-OF-COMMUNITY-IMMERSION.pptxMANAGEMENT-OF-COMMUNITY-IMMERSION.pptx
MANAGEMENT-OF-COMMUNITY-IMMERSION.pptx
 
Developing a City Transport Plan in an Urban Growth Area - Lessons Learnt
Developing a City Transport Plan in an Urban Growth Area - Lessons LearntDeveloping a City Transport Plan in an Urban Growth Area - Lessons Learnt
Developing a City Transport Plan in an Urban Growth Area - Lessons Learnt
 
Mobilizing Learning.
Mobilizing Learning.Mobilizing Learning.
Mobilizing Learning.
 
Kenya Ushahidi Evaluation: Uchaguzi
Kenya Ushahidi Evaluation: UchaguziKenya Ushahidi Evaluation: Uchaguzi
Kenya Ushahidi Evaluation: Uchaguzi
 
EES2014_full paper_Benjamin Aisya Aug 30 2014
EES2014_full paper_Benjamin Aisya Aug 30 2014EES2014_full paper_Benjamin Aisya Aug 30 2014
EES2014_full paper_Benjamin Aisya Aug 30 2014
 
SHEEN Sharing Launch: Employability Resources on the Web
SHEEN Sharing Launch: Employability Resources on the WebSHEEN Sharing Launch: Employability Resources on the Web
SHEEN Sharing Launch: Employability Resources on the Web
 
Cody technology use_plan_presentation
Cody technology use_plan_presentationCody technology use_plan_presentation
Cody technology use_plan_presentation
 
Young crew newsletter
Young crew newsletterYoung crew newsletter
Young crew newsletter
 
Young Crew Newsletter
Young Crew NewsletterYoung Crew Newsletter
Young Crew Newsletter
 
AVO – A voyage to the open seas to study openness and a networking mode of op...
AVO – A voyage to the open seas to study openness and a networking mode of op...AVO – A voyage to the open seas to study openness and a networking mode of op...
AVO – A voyage to the open seas to study openness and a networking mode of op...
 
Young crew programs and activities 2015
Young crew programs and activities 2015Young crew programs and activities 2015
Young crew programs and activities 2015
 
PMDAN Young crew Programmes and Activities 2015
 PMDAN Young crew Programmes and Activities 2015 PMDAN Young crew Programmes and Activities 2015
PMDAN Young crew Programmes and Activities 2015
 
Social media based dissemination strategies for managers of LLP projects
Social media based dissemination strategies for managers of LLP projectsSocial media based dissemination strategies for managers of LLP projects
Social media based dissemination strategies for managers of LLP projects
 
Gomez, herrera interactive activity 1
Gomez, herrera interactive activity 1Gomez, herrera interactive activity 1
Gomez, herrera interactive activity 1
 

More from GolieNyirenda2

final for Print-MISSION FIELD PROGRAMME AND SITE PROFILES FINAL-APPROVED NPC...
final  for Print-MISSION FIELD PROGRAMME AND SITE PROFILES FINAL-APPROVED NPC...final  for Print-MISSION FIELD PROGRAMME AND SITE PROFILES FINAL-APPROVED NPC...
final for Print-MISSION FIELD PROGRAMME AND SITE PROFILES FINAL-APPROVED NPC...
GolieNyirenda2
 
Stohl - The Politics of terrorism pdfven
Stohl - The Politics of terrorism pdfvenStohl - The Politics of terrorism pdfven
Stohl - The Politics of terrorism pdfven
GolieNyirenda2
 
MIRD5102 INTRODUCTION-course content 24.
MIRD5102 INTRODUCTION-course content 24.MIRD5102 INTRODUCTION-course content 24.
MIRD5102 INTRODUCTION-course content 24.
GolieNyirenda2
 
MIRD5102 INTRODUCTION- weekend class-24.
MIRD5102 INTRODUCTION- weekend class-24.MIRD5102 INTRODUCTION- weekend class-24.
MIRD5102 INTRODUCTION- weekend class-24.
GolieNyirenda2
 
EFFECTIVE LEADERSHIP. 14-05-2024 aprilpptx.pptx
EFFECTIVE LEADERSHIP. 14-05-2024 aprilpptx.pptxEFFECTIVE LEADERSHIP. 14-05-2024 aprilpptx.pptx
EFFECTIVE LEADERSHIP. 14-05-2024 aprilpptx.pptx
GolieNyirenda2
 
Project Teams and leadership-effective .
Project Teams and leadership-effective .Project Teams and leadership-effective .
Project Teams and leadership-effective .
GolieNyirenda2
 
EFFECTIVE LEADERSHIP and projects teams.
EFFECTIVE LEADERSHIP and projects teams.EFFECTIVE LEADERSHIP and projects teams.
EFFECTIVE LEADERSHIP and projects teams.
GolieNyirenda2
 
ecdpm-peace-keeping-operations-africa-reflections-apsa-2017-171123102359.pptx
ecdpm-peace-keeping-operations-africa-reflections-apsa-2017-171123102359.pptxecdpm-peace-keeping-operations-africa-reflections-apsa-2017-171123102359.pptx
ecdpm-peace-keeping-operations-africa-reflections-apsa-2017-171123102359.pptx
GolieNyirenda2
 
MIRD6104 International security – Cyber security and Global(4).docx
MIRD6104 International security – Cyber security and Global(4).docxMIRD6104 International security – Cyber security and Global(4).docx
MIRD6104 International security – Cyber security and Global(4).docx
GolieNyirenda2
 

More from GolieNyirenda2 (9)

final for Print-MISSION FIELD PROGRAMME AND SITE PROFILES FINAL-APPROVED NPC...
final  for Print-MISSION FIELD PROGRAMME AND SITE PROFILES FINAL-APPROVED NPC...final  for Print-MISSION FIELD PROGRAMME AND SITE PROFILES FINAL-APPROVED NPC...
final for Print-MISSION FIELD PROGRAMME AND SITE PROFILES FINAL-APPROVED NPC...
 
Stohl - The Politics of terrorism pdfven
Stohl - The Politics of terrorism pdfvenStohl - The Politics of terrorism pdfven
Stohl - The Politics of terrorism pdfven
 
MIRD5102 INTRODUCTION-course content 24.
MIRD5102 INTRODUCTION-course content 24.MIRD5102 INTRODUCTION-course content 24.
MIRD5102 INTRODUCTION-course content 24.
 
MIRD5102 INTRODUCTION- weekend class-24.
MIRD5102 INTRODUCTION- weekend class-24.MIRD5102 INTRODUCTION- weekend class-24.
MIRD5102 INTRODUCTION- weekend class-24.
 
EFFECTIVE LEADERSHIP. 14-05-2024 aprilpptx.pptx
EFFECTIVE LEADERSHIP. 14-05-2024 aprilpptx.pptxEFFECTIVE LEADERSHIP. 14-05-2024 aprilpptx.pptx
EFFECTIVE LEADERSHIP. 14-05-2024 aprilpptx.pptx
 
Project Teams and leadership-effective .
Project Teams and leadership-effective .Project Teams and leadership-effective .
Project Teams and leadership-effective .
 
EFFECTIVE LEADERSHIP and projects teams.
EFFECTIVE LEADERSHIP and projects teams.EFFECTIVE LEADERSHIP and projects teams.
EFFECTIVE LEADERSHIP and projects teams.
 
ecdpm-peace-keeping-operations-africa-reflections-apsa-2017-171123102359.pptx
ecdpm-peace-keeping-operations-africa-reflections-apsa-2017-171123102359.pptxecdpm-peace-keeping-operations-africa-reflections-apsa-2017-171123102359.pptx
ecdpm-peace-keeping-operations-africa-reflections-apsa-2017-171123102359.pptx
 
MIRD6104 International security – Cyber security and Global(4).docx
MIRD6104 International security – Cyber security and Global(4).docxMIRD6104 International security – Cyber security and Global(4).docx
MIRD6104 International security – Cyber security and Global(4).docx
 

Recently uploaded

一比一原版南十字星大学毕业证(SCU毕业证书)学历如何办理
一比一原版南十字星大学毕业证(SCU毕业证书)学历如何办理一比一原版南十字星大学毕业证(SCU毕业证书)学历如何办理
一比一原版南十字星大学毕业证(SCU毕业证书)学历如何办理
slg6lamcq
 
原版一比一多伦多大学毕业证(UofT毕业证书)如何办理
原版一比一多伦多大学毕业证(UofT毕业证书)如何办理原版一比一多伦多大学毕业证(UofT毕业证书)如何办理
原版一比一多伦多大学毕业证(UofT毕业证书)如何办理
mkkikqvo
 
在线办理(英国UCA毕业证书)创意艺术大学毕业证在读证明一模一样
在线办理(英国UCA毕业证书)创意艺术大学毕业证在读证明一模一样在线办理(英国UCA毕业证书)创意艺术大学毕业证在读证明一模一样
在线办理(英国UCA毕业证书)创意艺术大学毕业证在读证明一模一样
v7oacc3l
 
一比一原版(Unimelb毕业证书)墨尔本大学毕业证如何办理
一比一原版(Unimelb毕业证书)墨尔本大学毕业证如何办理一比一原版(Unimelb毕业证书)墨尔本大学毕业证如何办理
一比一原版(Unimelb毕业证书)墨尔本大学毕业证如何办理
xclpvhuk
 
End-to-end pipeline agility - Berlin Buzzwords 2024
End-to-end pipeline agility - Berlin Buzzwords 2024End-to-end pipeline agility - Berlin Buzzwords 2024
End-to-end pipeline agility - Berlin Buzzwords 2024
Lars Albertsson
 
一比一原版(UO毕业证)渥太华大学毕业证如何办理
一比一原版(UO毕业证)渥太华大学毕业证如何办理一比一原版(UO毕业证)渥太华大学毕业证如何办理
一比一原版(UO毕业证)渥太华大学毕业证如何办理
bmucuha
 
原版制作(unimelb毕业证书)墨尔本大学毕业证Offer一模一样
原版制作(unimelb毕业证书)墨尔本大学毕业证Offer一模一样原版制作(unimelb毕业证书)墨尔本大学毕业证Offer一模一样
原版制作(unimelb毕业证书)墨尔本大学毕业证Offer一模一样
ihavuls
 
一比一原版(UCSB文凭证书)圣芭芭拉分校毕业证如何办理
一比一原版(UCSB文凭证书)圣芭芭拉分校毕业证如何办理一比一原版(UCSB文凭证书)圣芭芭拉分校毕业证如何办理
一比一原版(UCSB文凭证书)圣芭芭拉分校毕业证如何办理
nuttdpt
 
Orchestrating the Future: Navigating Today's Data Workflow Challenges with Ai...
Orchestrating the Future: Navigating Today's Data Workflow Challenges with Ai...Orchestrating the Future: Navigating Today's Data Workflow Challenges with Ai...
Orchestrating the Future: Navigating Today's Data Workflow Challenges with Ai...
Kaxil Naik
 
一比一原版(harvard毕业证书)哈佛大学毕业证如何办理
一比一原版(harvard毕业证书)哈佛大学毕业证如何办理一比一原版(harvard毕业证书)哈佛大学毕业证如何办理
一比一原版(harvard毕业证书)哈佛大学毕业证如何办理
taqyea
 
STATATHON: Unleashing the Power of Statistics in a 48-Hour Knowledge Extravag...
STATATHON: Unleashing the Power of Statistics in a 48-Hour Knowledge Extravag...STATATHON: Unleashing the Power of Statistics in a 48-Hour Knowledge Extravag...
STATATHON: Unleashing the Power of Statistics in a 48-Hour Knowledge Extravag...
sameer shah
 
Palo Alto Cortex XDR presentation .......
Palo Alto Cortex XDR presentation .......Palo Alto Cortex XDR presentation .......
Palo Alto Cortex XDR presentation .......
Sachin Paul
 
Open Source Contributions to Postgres: The Basics POSETTE 2024
Open Source Contributions to Postgres: The Basics POSETTE 2024Open Source Contributions to Postgres: The Basics POSETTE 2024
Open Source Contributions to Postgres: The Basics POSETTE 2024
ElizabethGarrettChri
 
The Ipsos - AI - Monitor 2024 Report.pdf
The  Ipsos - AI - Monitor 2024 Report.pdfThe  Ipsos - AI - Monitor 2024 Report.pdf
The Ipsos - AI - Monitor 2024 Report.pdf
Social Samosa
 
一比一原版兰加拉学院毕业证(Langara毕业证书)学历如何办理
一比一原版兰加拉学院毕业证(Langara毕业证书)学历如何办理一比一原版兰加拉学院毕业证(Langara毕业证书)学历如何办理
一比一原版兰加拉学院毕业证(Langara毕业证书)学历如何办理
hyfjgavov
 
UofT毕业证如何办理
UofT毕业证如何办理UofT毕业证如何办理
UofT毕业证如何办理
exukyp
 
"Financial Odyssey: Navigating Past Performance Through Diverse Analytical Lens"
"Financial Odyssey: Navigating Past Performance Through Diverse Analytical Lens""Financial Odyssey: Navigating Past Performance Through Diverse Analytical Lens"
"Financial Odyssey: Navigating Past Performance Through Diverse Analytical Lens"
sameer shah
 
Predictably Improve Your B2B Tech Company's Performance by Leveraging Data
Predictably Improve Your B2B Tech Company's Performance by Leveraging DataPredictably Improve Your B2B Tech Company's Performance by Leveraging Data
Predictably Improve Your B2B Tech Company's Performance by Leveraging Data
Kiwi Creative
 
Population Growth in Bataan: The effects of population growth around rural pl...
Population Growth in Bataan: The effects of population growth around rural pl...Population Growth in Bataan: The effects of population growth around rural pl...
Population Growth in Bataan: The effects of population growth around rural pl...
Bill641377
 
Monthly Management report for the Month of May 2024
Monthly Management report for the Month of May 2024Monthly Management report for the Month of May 2024
Monthly Management report for the Month of May 2024
facilitymanager11
 

Recently uploaded (20)

一比一原版南十字星大学毕业证(SCU毕业证书)学历如何办理
一比一原版南十字星大学毕业证(SCU毕业证书)学历如何办理一比一原版南十字星大学毕业证(SCU毕业证书)学历如何办理
一比一原版南十字星大学毕业证(SCU毕业证书)学历如何办理
 
原版一比一多伦多大学毕业证(UofT毕业证书)如何办理
原版一比一多伦多大学毕业证(UofT毕业证书)如何办理原版一比一多伦多大学毕业证(UofT毕业证书)如何办理
原版一比一多伦多大学毕业证(UofT毕业证书)如何办理
 
在线办理(英国UCA毕业证书)创意艺术大学毕业证在读证明一模一样
在线办理(英国UCA毕业证书)创意艺术大学毕业证在读证明一模一样在线办理(英国UCA毕业证书)创意艺术大学毕业证在读证明一模一样
在线办理(英国UCA毕业证书)创意艺术大学毕业证在读证明一模一样
 
一比一原版(Unimelb毕业证书)墨尔本大学毕业证如何办理
一比一原版(Unimelb毕业证书)墨尔本大学毕业证如何办理一比一原版(Unimelb毕业证书)墨尔本大学毕业证如何办理
一比一原版(Unimelb毕业证书)墨尔本大学毕业证如何办理
 
End-to-end pipeline agility - Berlin Buzzwords 2024
End-to-end pipeline agility - Berlin Buzzwords 2024End-to-end pipeline agility - Berlin Buzzwords 2024
End-to-end pipeline agility - Berlin Buzzwords 2024
 
一比一原版(UO毕业证)渥太华大学毕业证如何办理
一比一原版(UO毕业证)渥太华大学毕业证如何办理一比一原版(UO毕业证)渥太华大学毕业证如何办理
一比一原版(UO毕业证)渥太华大学毕业证如何办理
 
原版制作(unimelb毕业证书)墨尔本大学毕业证Offer一模一样
原版制作(unimelb毕业证书)墨尔本大学毕业证Offer一模一样原版制作(unimelb毕业证书)墨尔本大学毕业证Offer一模一样
原版制作(unimelb毕业证书)墨尔本大学毕业证Offer一模一样
 
一比一原版(UCSB文凭证书)圣芭芭拉分校毕业证如何办理
一比一原版(UCSB文凭证书)圣芭芭拉分校毕业证如何办理一比一原版(UCSB文凭证书)圣芭芭拉分校毕业证如何办理
一比一原版(UCSB文凭证书)圣芭芭拉分校毕业证如何办理
 
Orchestrating the Future: Navigating Today's Data Workflow Challenges with Ai...
Orchestrating the Future: Navigating Today's Data Workflow Challenges with Ai...Orchestrating the Future: Navigating Today's Data Workflow Challenges with Ai...
Orchestrating the Future: Navigating Today's Data Workflow Challenges with Ai...
 
一比一原版(harvard毕业证书)哈佛大学毕业证如何办理
一比一原版(harvard毕业证书)哈佛大学毕业证如何办理一比一原版(harvard毕业证书)哈佛大学毕业证如何办理
一比一原版(harvard毕业证书)哈佛大学毕业证如何办理
 
STATATHON: Unleashing the Power of Statistics in a 48-Hour Knowledge Extravag...
STATATHON: Unleashing the Power of Statistics in a 48-Hour Knowledge Extravag...STATATHON: Unleashing the Power of Statistics in a 48-Hour Knowledge Extravag...
STATATHON: Unleashing the Power of Statistics in a 48-Hour Knowledge Extravag...
 
Palo Alto Cortex XDR presentation .......
Palo Alto Cortex XDR presentation .......Palo Alto Cortex XDR presentation .......
Palo Alto Cortex XDR presentation .......
 
Open Source Contributions to Postgres: The Basics POSETTE 2024
Open Source Contributions to Postgres: The Basics POSETTE 2024Open Source Contributions to Postgres: The Basics POSETTE 2024
Open Source Contributions to Postgres: The Basics POSETTE 2024
 
The Ipsos - AI - Monitor 2024 Report.pdf
The  Ipsos - AI - Monitor 2024 Report.pdfThe  Ipsos - AI - Monitor 2024 Report.pdf
The Ipsos - AI - Monitor 2024 Report.pdf
 
一比一原版兰加拉学院毕业证(Langara毕业证书)学历如何办理
一比一原版兰加拉学院毕业证(Langara毕业证书)学历如何办理一比一原版兰加拉学院毕业证(Langara毕业证书)学历如何办理
一比一原版兰加拉学院毕业证(Langara毕业证书)学历如何办理
 
UofT毕业证如何办理
UofT毕业证如何办理UofT毕业证如何办理
UofT毕业证如何办理
 
"Financial Odyssey: Navigating Past Performance Through Diverse Analytical Lens"
"Financial Odyssey: Navigating Past Performance Through Diverse Analytical Lens""Financial Odyssey: Navigating Past Performance Through Diverse Analytical Lens"
"Financial Odyssey: Navigating Past Performance Through Diverse Analytical Lens"
 
Predictably Improve Your B2B Tech Company's Performance by Leveraging Data
Predictably Improve Your B2B Tech Company's Performance by Leveraging DataPredictably Improve Your B2B Tech Company's Performance by Leveraging Data
Predictably Improve Your B2B Tech Company's Performance by Leveraging Data
 
Population Growth in Bataan: The effects of population growth around rural pl...
Population Growth in Bataan: The effects of population growth around rural pl...Population Growth in Bataan: The effects of population growth around rural pl...
Population Growth in Bataan: The effects of population growth around rural pl...
 
Monthly Management report for the Month of May 2024
Monthly Management report for the Month of May 2024Monthly Management report for the Month of May 2024
Monthly Management report for the Month of May 2024
 

FIELD REPORT-KMCO-UPG -CBFOdocumentation

  • 1. Component 3 : Strategic Partnerships, Knowledge Generation, and Policy UPG 1. Christian Aid Knowledge Management (KM) is rated moderately satisfactory. The project has done some visibility for the interventions. The project is in the process of producing communication materials such as signposts in the project impact areas. The project has started identification and documentation of case studies for lesson drawing during implementation. The project has started compilation of compendium of beneficiary pictures for uploading on PMU cloud system but need to develop a proper storage system at project level. However, on the ground, KM and visibility issues have not been mainstreamed in the project as beneficiaries lack knowledge of project objectives probably this could be due to the confused structure within the project, having Case workers who have not trained the volunteers who are the direct link to the beneficiaries. Additionally, at the time of the mission, the project did not have feedback mechanisms. Recommendation of the mission: Facilitate intra learning in the project to crease awareness of the project at all levels (case workers, Volunteer and Beneficiary) be done by December 31. 2. Yamba Malawi Knowledge Management (KM) is rated moderately satisfactory. The project is making efforts to mainstream KM in the interventions with guidance from the organisation’s headquarters in the USA. Project manager is responsible for project KM. The project has produced communication materials such as launch flyers. However, facilitation of intra learning in the project is lacking as the project team especially those interacting with beneficiaries lack knowledge of the project concept. This calls for intensification of awareness of the project within the project structures. During the visit, the mission established that some materials used for training the groups were not translated into the local language which may be difficult for beneficiaries to grasp. The project has started identification and documentation case studies for lesson drawing during implementation. The project has centralized repository system where key KMC and other project documents stored.
  • 2. At the time of the mission, the project did not have feedback mechanisms. Recommendation of the mission: Facilitate intra learning in the project to crease awareness of the project at all levels (case workers, Volunteer and Beneficiary) be done by December 31. 3. Concern Worldwide Knowledge Management (KM) is rated moderately satisfactory. The project commenced of Coaching and mentoring and at the time of the mission, 41 Case managers were trained. However, there is no project visibility on the ground. The project has not started identification and documentation case studies for lesson drawing during implementation. Issues of visibility are not clearly mainstreamed in the project. At the time of mission, the project did not have feedback mechanisms. Recommendations of the mission: (i) Make FARMSE visible during community engagement and also use mass media by December 2023. (ii) Identify, document and submit to FARMSE at least two case studies for learning in the project implementation. (iii) Begin compiling compendium of beneficiary pictures for uploading on PMU cloud system. 4. World Relief Knowledge Management (KM) is rated Moderately Satisfactory. The project has started training to create awareness among the group. There is intra learning in the project as portrayed by understanding of project concept by project staff including those interacting with beneficiaries demonstrated knowledge of ultra-poor graduation model, and ability to define the interventions. However, the project need to do more on visibility at grassroots level. At the time of the mission, the project had not completed identification and documentation of the project cases for learning. Additionally, at the mission time, the project did not have feedback mechanisms. Recommendations of the mission: (i) Enhance FARMSE visibility during community engagement by December 2023. (ii) Identify, document and submit to FARMSE at least
  • 3. two case studies for learning in the project implementation. (iii) Begin compiling compendium of beneficiary pictures for uploading on PMU cloud system. 5. AICC Knowledge Management (KM) is rated Moderately Satisfactory. The project has started training to create awareness among beneficiaries. Participants do not know the existing partnership of FARMSE and AICC. At the time of the mission, the project had not started identifying case studies for learning in the project implementation. Additionally, at the mission time, the project did not have feedback mechanisms. Recommendations of the mission: (i)Enhance visibility of the project by December 31December. (ii) Identification and documentation of case studies, key project lessons, best practices, key innovations from project interventions be done by December 2023. (ii) Begin compiling compendium of beneficiary pictures for uploading on PMU cloud system