1. EINRIP Project Handover Road Safety
Audits Project
PHO RSA Closing Meeting, Makassar
30 April 2012
David Williamson
Road Safety Auditor
VicRoads International
2. South Sulawesi
ESS-01 : Sengkang – Impa Impa – Tarumpakkae
Construction in progress in accordance with original
design plans
Road safety audit (RSA) of detailed design plans
conducted in June 2007
Design incorporates some of the recommendations
of the RSA
Work still to be completed:
• Shoulder sealing
• Traffic islands at two major intersections
• Guardrail installation
• Pavement markings
2
12. South Sulawesi
ESS-02 : Bantaeng – Bulukumba
Construction is complete - PHO 12 March 2012
Variation order for additional road safety works
based on the RSA of the detailed design has
been prepared and is awaiting approval
12