MSc Water, Energy & the
       Environment

  ENVIRONMENTAL POLICY AND
        MANAGEMENT

                       EIA
         Wind farm in the Cheshire area




Sergio Arenas Gayoso
Index




1. The need for the project

3. The likely environmental impact of this project

5. Government regulations

7. Possible project alternatives and environmental of alternatives

9. Non-technical summary/conclusions
1 – The need for the project


Fossil
fuels                         Econom

               pact
                                 y
            Im                Society
  CC


                               RE’s
 International (Kyoto Protocol) and domestic (UK Climate Change
Act) policies

• Onshore wind farm in Cheshire
• 35 wind turbines: 850 kW → 30
  MW
2 – The likely environmental impact of this project
2 – The likely environmental impact of this project
   Abiotic factors   Natural environment    Social/public
                                               welfare
   Patrimony/herit         Perceptible      Socioeconomic
         age              environment



                     Water bodies: earthmoving/machines
Installatio
                     (↓use/maintenance) → changes in water
n
                     quality
        Civil
        works
                          Sites of geological interest:
Installatio
                          earthmoving
n
                          No in the area chosen
                                                            SAC’s
                                                            SPA’s
              Aero-generators and tension cables
              buried paths modified →
              Access:
              transport
2 – The likely environmental impact of this project
   Abiotic factors      Natural environment      Social/public
                                                    welfare
   Patrimony/herit           Perceptible        Socioeconomic
         age                environment

                     Potential: affects the typical vegetation in this
Vegetation           area
                     Real: vegetation really affected by civil         •   Pine
                     works                                             •   Hazel
          Installatio                                 Conifero
                                                       •           •       Oak
Faun                                                  us           •       Willows
          n
a            Vertebrates: hares, foxes,             • Oaks
             hedgehogs,                             • Knapwee
                                                      d
             otters, minks, salmons, carps
                                                    • Buttercup
           Operation       Birds   • The IUCN Red List of Threatened
                                                      s
                                      Species
                           Bats                               • Kestrels
                                   • Data base                • Treecreeper
Wildlife           NO            ⇈attention to: bird            s
                                 migration, paths,            • Saker
corridor                                                        Falcons
                                 reproduction areas,
Directive 92/43/CEE                                             (↓population
                                 behaviour
                                                                )
The Conservation of Habitats and Species
Regulations-10
                                 Natura 2000 network
2 – The likely environmental impact of this project
     Abiotic factors   Natural environment     Social/public
                                                  welfare
    Patrimony/herit        Perceptible        Socioeconomic
          age             environment


 Vibrations        Installati   ↓ Intensity civil works, no
                   on           detonations
                       The Control of Vibration at Work
                       Regulations 2005
                                   No significant vibrations
              Operatio
                                   - wind
              n                    turbines/infrastructures -
 Electromagnetic fields                  ETSU-R-97
                                         (ETSU)
                   Operatio         Relatively ↓; city centres far
                   n                away
 Noise                          BS 6626; BS 7375; BS EN 50110
                                Parts 1-2
                 Installati                 Civil works: the usual
                 on                         noise
             Operatio               Control of Noise at Work Regulations
                                    2005
             n                          Electrical conductions:
↓ frequencies: headaches, nausea,
sleep disorders, stress and             negligible
depression                              Wind farm: 8 m/s winds ≃ 30
                                        dB(A)
2 – The likely environmental impact of this project
Abiotic factors   Natural environment   Social/public
                                           welfare
Patrimony/herit       Perceptible       Socioeconomic
      age            environment
2 – The likely environmental impact of this project
  Abiotic factors   Natural environment   Social/public
                                             welfare
  Patrimony/herit        Perceptible      Socioeconomic
        age             environment


Wind                ENTEC UK PLC : 20 points = total
farm                area
                                          5.6% = 9 wind
                                          turbines
                                          3.1% = 18 wind
                                          turbines
                                          0.64% = >3/4 wind
                                          turbines
High-tension
cables

Overhead: ⇈visual impact
2/3 use previous electrical
installation
2 – The likely environmental impact of this project
  Abiotic factors   Natural environment    Social/public
                                              welfare
  Patrimony/herit        Perceptible       Socioeconomic
        age             environment


Benefi
ts          •   £20m investment into the Cheshire and National
                economy
            •   £550,000: payment rates, rents, operation and site
                maintenance
            •   £15000/year: donated to Cheshire Hospital for the first
                5 years
            •   £20000: to the local communities and schools projects
                and trips
Acceptanc •     Energy security: supply
e                   • Annual monitoring: 2001-07
                    • 7.5/10 by the population
                    • 74% of the interviewees: better than
                      conventional energies and preferred over
                      hydraulic power stations, thermic power stations,
                      oil and nuclear power stations
2 – The likely environmental impact of this project
    Factors         Action                                    Impact
                                 Positive     Compatible          Moderate        Severe   Critical
    Abiotic       Installation                                 N,D,T,S,A,R,Rc

  Vegetation      Installation                                 N,D,T,S,Si,R,Rc
                   Operation                N,D,T,S,A,R,Rc
    Fauna         Installation              N,D,T,S,Si,R,Rc
                   Operation                N,D,T,S,A,R,Rc
                  Installation              N,D,T,S,Si,R,Rc
 Social welfare
                   Operation
                                            N,D,P,S,Si,R,Rc
   Heritage       Installation                                N,D,P,S,Si,IR,URc
 Visual Impact    Installation                                 N,D,T,S,Si,R,Rc
                   Operation                                  N,D,P,S,Sn,R,Rc
Socioeconomic     Installation              N,D,P,S,Si,R,Rc
                   Operation
 Environment       Operation

N: negative; D: direct; T: temporal; P: permanent; S: short-term; Si: simple; A: accumulative;
Sn: synergic; R: reversible; IR: irreversible; Rc: recoverable; URc: unrecoverable
3 – Government regulations

Renewable                          Kyoto
Energy                             Protocol
                          UK Climate Change Act
                          2008
                          UK Low Carbon Transition Plan
                          2009
                          Energy
                          Policy
                              Directive 2009/28/
                              EC
                                  UK Renewable Energy Strategy
                                  2009
                                  Energy White Paper
                                  2007
                     The North West Regional Assembly
                     (NWRA)
                                 Regional Spatial
                                 Strategy
                     North West Development Agency
                     (NWDA)
                                 Regional Economic
                                 Strategy
                      Regional low carbon
                      economy
Wind farm                           Feed-In Tariff
                                    scheme
EIA     Directive 97/11/    The Town and Country Planning
        CE                  Regulations 1999
4 – Possible project alternatives
                                               6


1 – Alternative “0”: not to build the
wind farm
  • Hamper local economic
                                      ↓socioeconomic
    development
                                      development
  • Hamper local welfare
  • GHG increasing
  • Hamper meet environmental and policy set targets (CC
    Act 2008)
2 – Alternative: different wind farm
location
 • Balance energetic resources/lowest environmental
   cost
 • Satisfies Planning and Energy Act 2008 and
   ↓environmental modifications and ↑energy
   efficiencies
 • The north area has been respected as it coincides
   with natural/environmental heritage (roman ruins)
4 – Possible project alternatives
                     b
3 – Access
alternatives
   A1        Impassable without ↑ environmental
   A2        modifications shady areas; longer than
             ↓↓conditions;↑
             the A1
   A3 a      Excursionists; close to natural heritage
   A4        (roman ruins)
             Impassable without ↑ environmental/village
             modifications                            d




A1             A2                A3               A4

                                              c

                             A3.a:   complex earthmovings
      Link
                             A3.b:   Excursionists
      Road
                             A3.c:   Slopes>24%
                             A3.d:   Previous path; Slope ≃
                             20%
4 – Possible project alternatives

4 – Wind turbine
alternatives
                   Criteria                       Turbine model
                                              G8X     E-80   G-58
Wind turbine power (MW)                       2       1.67   0.85
Number require                                15      18     35
Capital cost per turbine (£m)                 3.3     2.8    2
Cost installation considering wind            49.     50.4   70
turbine (£m)
Total installed capacity (MW)                 5
                                              30      30     30
Feed-In Tariff generation rate (£/kWh)        0.0     0.05   0.05
Cost MW installed (£)                         5=       =         =
Workforce (£)                                     =    =         ⇈
Civil works (installation) (£)                    ↓    ↓         ⇈
Environmental impact                              ⇈    ⇈         ↓
4 – Possible project alternatives

5 – Grid connection
alternative
  • Tension cables buried (3 km): ↑cost ↑energy loses; ↓
    visual impact
  • Tension cables overhead (2 km): ↑visual impact; ↑slopes
    (↑civil works/environmental impact); previous grid
6 – installation location
    Substation                     Transport Grid
alternative
                                                                     National
                                                                       Grid



⇈Access
             Power            Step-up                  Sub-
             station          transformer              station
Different location:
⇈ energy loses/civil works



              Home:          Step-          Industry   Distribution Step-
              230V           down                      down transformer
                             transform
                             er
5 – Summary – Conclusions


• Onshore wind farm in Cheshire; 35 wind turbines (850
  kW): 30 MW

• Compatible impact on Vegetation (operation), Fauna,
  Social welfare and Socioeconomic factor (installation)

• Moderate impact on Abiotic factors, Vegetation
  (installation), Heritage and Visual Impact

• Positive impact on Socioeconomic (operation) and the
  Environment (overall)

• Regulations: CC, Low Carbon Emissions, RE, environment
  protection, Feed-In Tariffs

• Alternatives: environment decisive factor over total cost:
  philosophy of EIA

EIA

  • 1.
    MSc Water, Energy& the Environment ENVIRONMENTAL POLICY AND MANAGEMENT EIA Wind farm in the Cheshire area Sergio Arenas Gayoso
  • 2.
    Index 1. The needfor the project 3. The likely environmental impact of this project 5. Government regulations 7. Possible project alternatives and environmental of alternatives 9. Non-technical summary/conclusions
  • 3.
    1 – Theneed for the project Fossil fuels Econom pact y Im Society CC RE’s International (Kyoto Protocol) and domestic (UK Climate Change Act) policies • Onshore wind farm in Cheshire • 35 wind turbines: 850 kW → 30 MW
  • 4.
    2 – Thelikely environmental impact of this project
  • 5.
    2 – Thelikely environmental impact of this project Abiotic factors Natural environment Social/public welfare Patrimony/herit Perceptible Socioeconomic age environment Water bodies: earthmoving/machines Installatio (↓use/maintenance) → changes in water n quality Civil works Sites of geological interest: Installatio earthmoving n No in the area chosen SAC’s SPA’s Aero-generators and tension cables buried paths modified → Access: transport
  • 6.
    2 – Thelikely environmental impact of this project Abiotic factors Natural environment Social/public welfare Patrimony/herit Perceptible Socioeconomic age environment Potential: affects the typical vegetation in this Vegetation area Real: vegetation really affected by civil • Pine works • Hazel Installatio Conifero • • Oak Faun us • Willows n a Vertebrates: hares, foxes, • Oaks hedgehogs, • Knapwee d otters, minks, salmons, carps • Buttercup Operation Birds • The IUCN Red List of Threatened s Species Bats • Kestrels • Data base • Treecreeper Wildlife NO ⇈attention to: bird s migration, paths, • Saker corridor Falcons reproduction areas, Directive 92/43/CEE (↓population behaviour ) The Conservation of Habitats and Species Regulations-10 Natura 2000 network
  • 7.
    2 – Thelikely environmental impact of this project Abiotic factors Natural environment Social/public welfare Patrimony/herit Perceptible Socioeconomic age environment Vibrations Installati ↓ Intensity civil works, no on detonations The Control of Vibration at Work Regulations 2005 No significant vibrations Operatio - wind n turbines/infrastructures - Electromagnetic fields ETSU-R-97 (ETSU) Operatio Relatively ↓; city centres far n away Noise BS 6626; BS 7375; BS EN 50110 Parts 1-2 Installati Civil works: the usual on noise Operatio Control of Noise at Work Regulations 2005 n Electrical conductions: ↓ frequencies: headaches, nausea, sleep disorders, stress and negligible depression Wind farm: 8 m/s winds ≃ 30 dB(A)
  • 8.
    2 – Thelikely environmental impact of this project Abiotic factors Natural environment Social/public welfare Patrimony/herit Perceptible Socioeconomic age environment
  • 9.
    2 – Thelikely environmental impact of this project Abiotic factors Natural environment Social/public welfare Patrimony/herit Perceptible Socioeconomic age environment Wind ENTEC UK PLC : 20 points = total farm area 5.6% = 9 wind turbines 3.1% = 18 wind turbines 0.64% = >3/4 wind turbines High-tension cables Overhead: ⇈visual impact 2/3 use previous electrical installation
  • 10.
    2 – Thelikely environmental impact of this project Abiotic factors Natural environment Social/public welfare Patrimony/herit Perceptible Socioeconomic age environment Benefi ts • £20m investment into the Cheshire and National economy • £550,000: payment rates, rents, operation and site maintenance • £15000/year: donated to Cheshire Hospital for the first 5 years • £20000: to the local communities and schools projects and trips Acceptanc • Energy security: supply e • Annual monitoring: 2001-07 • 7.5/10 by the population • 74% of the interviewees: better than conventional energies and preferred over hydraulic power stations, thermic power stations, oil and nuclear power stations
  • 11.
    2 – Thelikely environmental impact of this project Factors Action Impact Positive Compatible Moderate Severe Critical Abiotic Installation N,D,T,S,A,R,Rc Vegetation Installation N,D,T,S,Si,R,Rc Operation N,D,T,S,A,R,Rc Fauna Installation N,D,T,S,Si,R,Rc Operation N,D,T,S,A,R,Rc Installation N,D,T,S,Si,R,Rc Social welfare Operation N,D,P,S,Si,R,Rc Heritage Installation N,D,P,S,Si,IR,URc Visual Impact Installation N,D,T,S,Si,R,Rc Operation N,D,P,S,Sn,R,Rc Socioeconomic Installation N,D,P,S,Si,R,Rc Operation Environment Operation N: negative; D: direct; T: temporal; P: permanent; S: short-term; Si: simple; A: accumulative; Sn: synergic; R: reversible; IR: irreversible; Rc: recoverable; URc: unrecoverable
  • 12.
    3 – Governmentregulations Renewable Kyoto Energy Protocol UK Climate Change Act 2008 UK Low Carbon Transition Plan 2009 Energy Policy Directive 2009/28/ EC UK Renewable Energy Strategy 2009 Energy White Paper 2007 The North West Regional Assembly (NWRA) Regional Spatial Strategy North West Development Agency (NWDA) Regional Economic Strategy Regional low carbon economy Wind farm Feed-In Tariff scheme EIA Directive 97/11/ The Town and Country Planning CE Regulations 1999
  • 13.
    4 – Possibleproject alternatives 6 1 – Alternative “0”: not to build the wind farm • Hamper local economic ↓socioeconomic development development • Hamper local welfare • GHG increasing • Hamper meet environmental and policy set targets (CC Act 2008) 2 – Alternative: different wind farm location • Balance energetic resources/lowest environmental cost • Satisfies Planning and Energy Act 2008 and ↓environmental modifications and ↑energy efficiencies • The north area has been respected as it coincides with natural/environmental heritage (roman ruins)
  • 14.
    4 – Possibleproject alternatives b 3 – Access alternatives A1 Impassable without ↑ environmental A2 modifications shady areas; longer than ↓↓conditions;↑ the A1 A3 a Excursionists; close to natural heritage A4 (roman ruins) Impassable without ↑ environmental/village modifications d A1 A2 A3 A4 c A3.a: complex earthmovings Link A3.b: Excursionists Road A3.c: Slopes>24% A3.d: Previous path; Slope ≃ 20%
  • 15.
    4 – Possibleproject alternatives 4 – Wind turbine alternatives Criteria Turbine model G8X E-80 G-58 Wind turbine power (MW) 2 1.67 0.85 Number require 15 18 35 Capital cost per turbine (£m) 3.3 2.8 2 Cost installation considering wind 49. 50.4 70 turbine (£m) Total installed capacity (MW) 5 30 30 30 Feed-In Tariff generation rate (£/kWh) 0.0 0.05 0.05 Cost MW installed (£) 5= = = Workforce (£) = = ⇈ Civil works (installation) (£) ↓ ↓ ⇈ Environmental impact ⇈ ⇈ ↓
  • 16.
    4 – Possibleproject alternatives 5 – Grid connection alternative • Tension cables buried (3 km): ↑cost ↑energy loses; ↓ visual impact • Tension cables overhead (2 km): ↑visual impact; ↑slopes (↑civil works/environmental impact); previous grid 6 – installation location Substation Transport Grid alternative National Grid ⇈Access Power Step-up Sub- station transformer station Different location: ⇈ energy loses/civil works Home: Step- Industry Distribution Step- 230V down down transformer transform er
  • 17.
    5 – Summary– Conclusions • Onshore wind farm in Cheshire; 35 wind turbines (850 kW): 30 MW • Compatible impact on Vegetation (operation), Fauna, Social welfare and Socioeconomic factor (installation) • Moderate impact on Abiotic factors, Vegetation (installation), Heritage and Visual Impact • Positive impact on Socioeconomic (operation) and the Environment (overall) • Regulations: CC, Low Carbon Emissions, RE, environment protection, Feed-In Tariffs • Alternatives: environment decisive factor over total cost: philosophy of EIA